In the High Court of the Republic of Singapore
[1984] SGHC 17
Suit 1082/1982
Between
Jusuf Kaliman
Another
… Plaintiff
And
Outram Realty (Pte) Ltd
… Defendant
grounds of decision
Contract — Remedies — Liquidated damages; Land — Conveyance

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Jusuf Kaliman and Another v Outram Realty (Pte) Ltd
[1984] SGHC 17
Suit 1082/1982
Wee Chong Jin CJ
18 June 1984
1 The plaintiffs, in an O 81 application, claim, inter alia, the sum of $130,351.50 as liquidated damages as specified in two contracts of sale of two shop units 65 and 67 situated on the ground floor of Pearl Centre. The plaintiffs are the purchasers and the defendants are the vendors of these two shop units. The relevant clause of the sale agreements is cl 12 which reads:
The sale and purchase shall be completed at the Office of the Vendor`s Solicitors M/s Lee Kim Siang & Co of No 17-B, Upper Circular Road, Singapore 1, fourteen (14) days after the receipt by the Purchaser or his Solicitors of the Notice to Complete of the Vendor or its Solicitors such Notice to be accompanied by the certificate of the Vendor`s Architect that the said premises and road drainage and sewerage works have been completed in accordance with the relevant approved plans and that sewerage water and electricity and/or gas services have been duly connected to the said Premises and that the said approval of the Competent Authority for separate disposal has been obtained, and, after receipt by the Purchaser or his Solicitors of the notice from the Vendor`s Solicitors that the Subsidiary Strata Certificate or Title has been issued for the said Premises. The said Notice to Complete shall be given by the Vendor on or before 31 December 1976 or such other subsequent date or dates as may after the date hereof be appointed by the Controller of Housing. If the Vendor shall fail to give the said Notice to Complete on the appointed date the Vendor shall pay to the Purchaser liquidated damages calculated from day to day in respect of the period commencing from the appointed date up to the date when the said Notice to Complete shall have actually been given at the rate of nine per centum (9%) per annum on the purchase price such interest to be paid and deducted from the balance of the purchase price payable on completion. On completion, the Vendor shall make and execute to the Purchaser a transfer of the said Premises sold, such transfer to be prepared by and at the expense of the Purchaser.
2 The defendants contend that the plaintiffs have expressly waived their right to liquidated damages. They rely on the fact that the plaintiffs had taken possession of the shop units on 19 March 1977 and on a document dated 19 March 1977 alleged to be executed by the plaintiffs which, so far as relevant reads:
Re: Undertaking and indemnity
Unit/Units G5 & G7
Pearls Centre
In consideration of M/s Outram Realty Pte Ltd (hereinafter referred to as `the Company`) agreeing at my/our request to give me/us vacant possession of the above property, without their having obtained the Temporary Occupation Licence/Certificate of Fitness for Occupation in respect thereof, I/We do hereby freely and without coercion agree and undertake the following -
3 ...
13 In consideration of my/our taking over the above unit/units to-day, I/We am/are fully aware of my/our rights as per cl 12/14(2) of the sales agreement and I/We on my/our own free will do hereby waive my/our rights in the aforesaid cl 12/14(2).
4 The plaintiffs` answer to this contention is r 16 of the Housing Developers Rules 1965 made under the Housing Developers (Control and Licensing) Act 1965 which reads:
(1) A housing developer shall not, without the prior consent in writing of the Controller, seek from a purchaser -
(a) any waiver of the purchaser`s rights under an agreement for sale of any housing accommodation sold by the housing developer; or
(b) any release from the performance of the housing developer`s duties and obligations under the aforesaid agreement.
(2) Any undertaking given by a purchaser of any housing accommodation to a housing developer which seeks to waive the purchaser`s rights or claims against the housing developer for a breach of, or to release a housing developer from the performance of the housing developer`s duties and obligations under, an agreement for the sale of any housing accommodation by the housing developer shall be unenforceable unless the prior consent in writing of the Controller has been obtained therefor.
5 It is undisputed that the defendants failed to give notice of completion on 31 December 1976 which was the date appointed by the Controller of Housing on or before which the notice to complete should be given by the vendor under cl 12 of the sale agreements. The defendants gave notice to complete the sale and purchase on 11 March 1981.
6 I am satisfied that on these facts that there is no defence or no fairly arguable point to argue on behalf of the defendants and that the plaintiffs are entitled to enter judgment for the sum claimed.
7 Judgment for the plaintiffs
Wee Chong Jin CJ
Dennis Tan Jui Kwang (Char Pee & Co) for the plaintiffs
Lee Kim Siang (Lee Kim Siang & Co) for the defendants