Engineering Construction (Pte) Ltd v Ohbayashi-Gumi Ltd
[1985] SGHC 12
Suit 3297/1979
Lai Kew Chai J
23 April 1985
1 In this case, the plaintiffs, who had acted as the building sub-contractors of the defendants, are claiming that the termination of their employment on 17 October 1979 by the defendants was wrongful and accordingly they are claiming the price of work done and materials supplied, the refund of the retention monies, damages and other consequential reliefs. The defendants for their part relied on the unsatisfactory performance of the plaintiffs and contended that they had accepted such repudiation by their notice of termination. In the result, the defendants are counterclaiming the sum of $689,893.60 as damages for the work left undone by the plaintiffs in respect of the Stage III works. They also claim the repayment of a loan of $210,000 with interest.
2 In the course of the resumed hearing of the case, learned counsel for the defendants informed me that the defendants were relying solely on the lack of progress in respect of the remaining aluminium works for Stage III to justify the termination. This stand has since its adoption considerably reduced the scope of the disputes relating to the ground of the termination.
3 The matter arose in this way. In 1976 the Ministry of Environment (MOE) of the Government of Singapore had invited tenders for the execution of the Kim Chuan Sewage Treatment Works Stages II and III (the said works). Stage III of the said works involved modifications of the treatment plant and although it was described as `Stage III`, this stage of the said works, which included some extensive road works (the roadworks), had to be completed and commissioned before the commencement of the Stage II works. The plaintiffs, not being eligible to tender for the said works, towards the end of 1976 offered to act as the sub-contractor of the defendants and to prepare quotations, which included the provisional bills of quantities, for submission by the defendants. Much groundwork was done by both parties and in January 1977 the defendants submitted their tender based substantially on the quotations of the plaintiffs.
4 On 6 May 1977 the defendants were awarded the contract by the MOE at the price of $14,319,877.45 subject, of course, to final measurements upon the practical completion of the said works. In turn, the parties proceeded as if the said works would be sub-contracted to the plaintiffs, save and except the prime cost items, and on the basis that the plaintiffs would carry out the sub-contract works at 6.5% less than the main contract sum. It was agreed that parties would later enter into a written sub-contract. On 4 July 1977 the plaintiffs commenced their work, although no written sub-contract was ever signed by the plaintiffs. As a result, the plaintiffs have maintained throughout that no concluded sub-contract was entered into.
5 On this aspect of the case, what had happened was this. On 1 October 1977 the defendants sent to the plaintiffs the draft sub-contract. After some three months, the plaintiffs wrote to the defendants suggesting five amendments, viz (1) there should be no requirement for a performance bond, (2) monthly progress and final payments should be made within 14 days of submission of claims, (3) the limit of the retention fund should be 2% of the sub-contract sum, (4) profit for prime cost sum in respect of item 441/1 in the bills of quantities should be increased from 0.5% to 0.568182% and (5) six specified items of work should not be subject to the deduction of 6.5%. According to the defendants` Project Manager, S Kimishima, whose evidence on this and what followed I accept without hesitation, he informed the plaintiffs` director, KH Ng, that modifications (1), (4) and (5) were accepted by the defendants. Ng has agreed to this. On 14 March 1979 the defendants sent the duly amended sub-contract to the plaintiffs for their signature. It was signed by the defendants and it was back-dated to 15 December 1977. Although it was not signed and returned by the plaintiffs, I also accept Kimishima`s evidence that Ng had orally confirmed that the terms of the sub-contract were in order. I find that at that stage, the plaintiffs had intended to agree and has in March 1977 agreed to be bound by the terms of the sub-contract.
6 On the pleadings and the evidence elicited at the early stages of the trial, there was considerable controversy on the general performance and progress of the sub-contract works. In view of the fact that the issue has been narrowed to the progress of aluminium works between June 1979 and October 1979, particularly in October 1979, I am spared the need to make any findings on the general performance of the plaintiffs.
7 By June 1979 the MOE had started to claim against the defendants liquidated damages for delays from 23 June 1979. By 25 July 1979 the claim for liquidated damages was $115,500. In July 1979 the plaintiffs were asking to be released from carrying out the whole of the Stage II works. By August 1979 all the Tanks in Stage III were ready to be commissioned. But the aluminium works of Stage III, in so far as they related to the installation of handrails and aluminium meshes, were not progressing satisfactorily. The sub-contractors for the aluminium works were United Central Engineering Works (S) Pte Ltd (UCE). They were delaying because they were not paid by the plaintiffs who claimed that the defendants were wrongfully withholding payments from June 1979 onwards. On the other hand, the defendants claimed that they had overpaid the plaintiffs by some $283,564.78 and they presented through their consultant quantity surveyors, Messrs Elim ABH, the approximate interim final accounts as at 16 August 1979. At this stage, the outstanding items under the sub-contract which were still uncompleted were the aluminium works of Stage III, namely the installation of the balance of the handrails and the aluminium meshes, the roadworks of Stage III and the entire Stage II works which also involved aluminium works. The aluminium works in Stage III and the aluminium works in Stage II had been sub-contracted by the plaintiffs to UCE.
8 This was the background when the parties met on 29 August 1979 about releasing the plaintiffs from the remaining parts of the said Works. They concluded an agreement in writing which appeared in ABVI, p 56-58. I bear in mind the entire document but I need to set out only cl 7 which has to be construed. Clause 7 provided:
EC (the plaintiffs) will assign to OG (the defendants) Messrs United Central Engineering Works (S) Pte Ltd for the aluminium works which span both Stage III (New Treatment) Works and Stage II (Modification) Works of the project, on terms that United Central Engineering Pte Ltd`s price for that portion of the Works relating to New Treatment Works will remain EC`s responsibility. OG shall release EC from any further liability relating thereto. As regards the price for that portion of the works that relate to Stage II (Modification) Works, this will be OG`s responsibility.
9 The question for my determination is whether the plaintiffs were released from all responsibilities to complete the remaining aluminium works for Stage III except as to the price thereof. If the answer is in the affirmative, obviously they could not be held responsible for any lack of progress in those works and the defendants could not therefore terminate their employment to complete the roadworks. I am of the view that the plaintiffs were on the true and natural construction of cl 7 released from seeing to the progress of the remaining aluminium works for Stage III. Except for the pricing with regard to Stage III aluminium works for which the plaintiffs had to continue to be responsible, the aluminium works to be assigned to UCE were `the aluminium works which span both Stage III (New Treatment) Works and Stage II (Modification) Works`. I cannot ignore these words and am constrained to give effect to them.
10 Accordingly, the defendants were wrong to have purported to terminate the contract by serving two notices on 3 October 1979 and 17 October 1979 which were based or grounded on the unsatisfactory progress of the remaining Stage III aluminium works.
11 If I am wrong in my interpretation of cl 7, I go on to find that the progress of the balance of the aluminium works for Stage III was so unsatisfactory as to warrant a termination of the sub-contract.
12 I now come to the reliefs claimed by the plaintiffs. Parties have agreed before me that assessment of the quantum and damages will be referred to arbitration. I declare that the defendants` purported termination of the sub-contract for the roadworks in Stage III unlawful. There will be judgment for the plaintiffs for work done and materials supplied up to the date of the wrongful termination and damages, if any, for the unlawful termination of the roadworks sub-contract. The plaintiffs are entitled to the refund of the retention moneys said to be $259,471.33 which must be subject to assessment, if necessary, by the arbitrators. The defendants are, of course, entitled to set off the claims of the plaintiffs against the loan of $210,000 plus interest thereon at 9% per annum from the date of its disbursement. The defendants will have to pay the plaintiffs the costs of these proceedings.
13 (Court: Plaintiffs to be paid 60% of the taxed costs. Liberty to apply.)
14 Order accordingly
Cheng Tim Pin (Yap & Yap) for the plaintiffs
CS Wu (Donaldson & Burkinshaw) for the defendants