Hiap Hong & Co Pte Ltd v Hong Huat Co (Pte) Ltd
[1985] SGHC 16
Suit 95/1984
Wee Chong Jin CJ
24 May 1985
1 This is an appeal against the decision of the Assistant Registrar granting the defendants` application to stay further proceedings in the action pursuant to s 7 of the Arbitration Act (Cap 16). The plaintiffs (hereinafter referred to as the contractor) claimed against the defendants (hereinafter referred to as the Employer) the sum of $572,729.91 being money due on a payment certificate stated to be a `Penultimate Certificate of Payment` dated 6 December 1983 issued by the employer`s architects pursuant to a building contract dated 27 January 1979, (the contract) made between the contractor and the employer whereby the employer agreed in consideration of the contractor erecting and completing a proposed 6/5 storey shopping centre , inter alia, to payto the contractor within 30 days from the date of the Certificates issued by the employer`s architects thereunder such sums as should be certified as being due to the contractor thereon.
2 Under cl 30 of the contract the architects have to issue monthly an Interim Certificate of Payment and the employer must pay the amount certified within 30 days and when the requirements of cl 30(6) have been complied with the architects have to issue the Final Certificate. There is no express provision for the issue of a `penultimate` Certificate of Payment. The crucial question in this appeal is whether or not the certificate issued by the Architects dated 6 December 1983 is an Interim Certificate within the meaning of cl 30 of the contract. It is contended on behalf of the contractor that it is in fact an Interim Certificate and the amount certified therein fell due and payable by the employer under cl 30(1) which reads:
At the period of Interim Certificates named in the appendix to these Conditions the Architect shall issue a certificate stating the amount due to the Contractor from the Employer and the Contractor shall, on presenting any such certificate to the Employer, be entitled to payment therefore within the Period for Honouring Certificates named in the appendix to these Conditions.
Interim valuations shall be made whenever the Architect considers them to be necessary for the purpose of ascertaining the amount to be stated as due in an Interim Certificate."
3 The employer contends that the penultimate certificate is in fact a Final Certificate though in the form of an Interim Certificate.
4 Mr Wu on behalf of the contractor submits that the term `penultimate` should be given its ordinary grammatical meaning of `last but one` and since the last payment certificate is the Final Certificate referred to in cll 30(6) and (7), the `penultimate` payment certificate is necessarily an interim payment certificate governed by cl 30(1). He says that the term `penultimate payment certificate` is commonly used by architects and engineers to mean the interim payment certificate next preceding the Final Certificate to be issued in order to place the employer and contractor on notice that his next certificate will be the Final Certificate. In this way, the employer will have the opportunity to serve his notice of reference prior to the issuance of the Final Certificate if he has outstanding claims against the Contractor as cl 30(7) precludes him from issuing a notice of reference after the Final Certificate is issued. On the contractor`s part, he will know that the next certificate to be issued will be the Final Certificate.
5 Mr Karthigesu on behalf of the employer submits that the penultimate payment certificate dated 6 December 1983 whatever else it might be, is clearly not an interim payment certificate governed by cl 30(1). The penultimate payment certificate of the architects states, so far as material, as follows:
PENULTIMATE
Certificate of Payment
Date of Contract: 27 January 1979
Original Value of Contract: $10,243,091.26
We hereby certify that under the Terms of the Building Contract
the sum of Dollars Five Hundred and Seventy Two Thousand
Seven Hundred and Twenty Nine and cents Ninety One $572,729.91
is now due to Hiap Hong Co Pte Ltd for work done and materials
supplied up to
Value of work and materials on site by this Contractor $11,288,727.77
Retention money withheld
Net value of works and materials to date $11,288,727.77
Less Payments previously certified $10,715,997.86
Amount payable by this Certificate $572,729.91
Please make payment direct to Contractor.
6 Mr Karthigesu submits that the certification of `the value of work and materials of site` at $11,288,727.77 and of `Net value of works and materials to date` at the same amount ie$11,288,727.77 is a clear indication and therefore a certification that the works undertaken by this building contract have been completed and is valued at $11,288,727.77. He further submits that the sum of $572,729.91 certified as payable by the penultimate payment certificate is the difference between `net value of works and materials to date` and the total amount paid to the contractor under previous interim payment certificates and that the penultimate payment certificate can be nothing less than and is in fact a Final Certificate, though in the form of an interim certificate of payment and that it is called a Penultimate Certificate patently to avoid the implications of cl 30(7) and the arbitration clause, cl 34.
7 I cannot accept Mr Karthigesu`s submissions. It is plain that a payment certificate cannot be a Final Certificate unless the architect intends it to be the Final Certificate and the architects` letter of 1 December 1983 stating, inter alia , that `We have decided that a penultimate certificate be issued` clearly shows that the architects did not intend the penultimate certificate of 6 December 1983 to be the Final Certificate under the contract.
8 Another submission advanced by Mr Karthigesu is that the employer challenges that `even the $572,929.91 is due` and asserts that the whole of the final measurement and valuation is in dispute. The only basis to support the assertion that there is a dispute is the employer`s contention that the project quantity surveyor, who is the employer`s own quantity surveyor, had over measured or that the employer`s own architects had over certified. No evidence has been produced, nor any explanation offered, to substantiate that contention and I am of the opinion that there is no real basis for that contention to warrant a stay of proceedings.
9 I accept Mr Wu`s submission that the term `penultimate` used by the architects in the Certificate of Payment dated 6 December 1983 means the last but one certificate under the contract and that the certificate dated 6 December 1983 is an interim payment certificate governed by cl 30(1) of the building contract. Accordingly, I allow the appeal and dismiss the employer`s application for stay of these proceedings with costs in any event.
10 Appeal allowed.
WE Jansen (Donaldson & Burkinshaw) for the plaintiffs
M Karthigesu (Cooma Lau, Loh & Karthigesu) and Richard Sam (Gupta & Sam) for the defendants