Re Mechanised Construction Pte Ltd
[1989] SGHC 44
CWU 786/1986
Chao Hick Tin JC
27 April 1989
1 Cur Adv Vult
2 These winding-up proceedings were first initiated by Haller (Far East) Pte Ltd on 22 November 1986 on the ground that the debtor company, Mechanised Construction Pte Ltd, owed Haller a sum of $64,297.96. The petition of Haller was based on neglect by the company to pay up the sum demanded within three weeks of the issue of the statutory notice. On 17 November 1987, by an order of court, Haller was given leave to withdraw its petition and in its place, Boustead Services Pte Ltd (Boustead) was granted leave to be substituted as the petitioning creditor. The substituted petition was filed on 22 December 1987. The ground upon which the substituted petitioner sought to rely to wind up the company was that the latter neglected to pay or satisfy a statutory notice of demand dated 20 January 1987 for a sum of $141,036.79.
3 The sum of $141,036.79 was alleged to be due from the company to Boustead under a sale contract dated 30 June 1985 whereby Boustead agreed to supply, fabricate and install structural steelworks of an estimated total weight of 201 metric tones at the rate of $1,490 per tone, making an estimated total of $299,490. These materials and services were required in connection with the Katong Convent Secondary School Project, in which the company was a sub-contractor. Under the contract the time for completing the works was to be `four to five months from confirmation of order and on condition that the site is available to (Boustead) within two weeks after confirmation of order`. Payment was to be made by `monthly progressive at 30 days upon invoicing`. On 5 July 1985, in accepting the offer from Boustead, the company stated that it agreed and accepted `the sales contract for a total lump sum price of $299,490 subject to final quantity`. The site was only made available to Boustead on 10 August 1985.
4 The company alleged that the progress of work undertaken by Boustead `was extremely slow`. The company asserted that the original completion date should have been 10 January 1986 (five months from 10 August 1985). On 8 November 1985, Boustead submitted a revised programme to the company to complete the works by 7 April 1986. The company indicated that, without prejudice to its rights, it agreed to the revised programme. Thereafter, the progress of the work still appeared to be slow, so much so that on 3 March 1986, the company reminded Boustead that their delay had caused delay to other works relating to `roof tile installation and subsequent windows plastering, screwing and ceiling below the roofs`. In their reply of 5 March 1986, Boustead admitted that `the rate of progress at the site prior to the beginning of this year (was) unfortunately slow` but added that `efforts (had) been made since to speed up the work both at site and in our workshop`. Boustead also said that `this rate of progress will be difficult to maintain if progressive payment due to us is not forthcoming`.
5 Thereafter works would appear to remain slow as the company alleged that by April 1986, only about 35 tones of trusses had been installed and that by 26 April 1986, the company had paid $60,000 to Boustead, more than what was due to Boustead. That sum was said to be equivalent to payment for 40 tones of installed trusses. The minutes of a site meeting on 18 April 1986 recorded that `there are presently 40 trusses yet to be laid in order that the entire roofing might be finished on time`. On 19 May 1986, Boustead was warned by the company to complete the works by 15 June 1986, failing which the company would terminate the contract for `breaching the time frame and (would) continue the remaining work on (its) own` so that the school project would not be jeopardized. The company ceased to make any payment to Boustead since May 1986. The entire works were not completed until 26 August 1986, a delay of four months and 20 days counting from the date on which the works should have been completed in accordance with the revised programme.
6 I would also set out the following events subsequent to the date of completion of the works on 26 August 1986:
27 August 1986:
Boustead wrote to the company to say that it had completed all the works and demanded payment for the sum of $175,832.26.
5 September 1986:
The company replied to say that the claim was not acceptable and said that `since 20 June 1986, we have continued your remaining works with our own men and machineries to complete your contractual work on 26 August 1986 due to the absence of your workforce on site. We are unable to calculate the cost incurred and suffered by us due to your long delay and absence of manpower until the whole project is completed and handed over to the employer`.
16 September 1986:
Boustead wrote to dispute that their workforce was not present to undertake the works except in one instance - `the exception is frames TRC-1 and TRC-5 in drawing R4-1 which you had revised and decided to carry out supply, fabrications and installations yourself.` Boustead suggested a meeting to resolve their dispute.
24 October 1986:
A meeting was held between the parties.
12 November 1986:
Boustead wrote to say that following the meeting and their examination of the claims raised by the company, Boustead would reduce their invoiced claim of $175,832.26 by $30,443.50.
22 November 1986:
Haller filed the original petition to wind up the company.
12 December 1986:
Boustead sent a reminder to the company to pay up the sum of $141,036.79 within seven days failing which Boustead `will be compelled to take appropriate action for recovery` of the amount due. The sum was arrived at as follows:
Total value of work done $256,480.29
Less: Due to company for various
claims as proposed by Boustead $30,443.50
$226,036.79
Less: Payments made $85,000.00
Balance due to Boustead: $141,036.79
20 January 1987:
Boustead, through their solicitors, issued the statutory notice of demand.
7 The company alleged that in view of the delay in completion by Boustead, it had incurred additional expenses in the sum of $78,125 in respect of certain preliminary items. Boustead did not deny the delay but was only prepared to bear a very much lesser amount. As stated above, the contract was subject to final quantity. The company contended that the actual structural steelworks fabricated and installed had to be measured and calculated by the quantity surveyor of the project before the final amount could be ascertained. This final measurement by the quantity surveyor was not completed until January 1988 and it showed that the total steelworks undertaken were only 166.171 tones. In other words, two areas of dispute were raised by the company to the balanced amount of $141,036.79 claimed by Boustead - first, the damages claimed by the company against Boustead on account of the delay; and second, at the time the statutory notice was issued, final measurement by a quantity surveyor had yet to be undertaken.
8 The response of Boustead to these two points was essentially as follows:
(i) the site was to be made available to Boustead within two weeks of 5 July 1985. It was not made available until 10 August 1985. In view of this non-compliance by the company, the time-frame of five months specified in the contract was no longer applicable. Accordingly, Boustead was only required to complete the works within a reasonable time. The amount claimed by the company as additional expenses were excessive and unreasonable.
(ii) The company was informed of the final amount due to Boustead under the contract through Boustead`s letter of 27 August 1986. Boustead should not have to wait nor were they bound by the final measurement made by the quantity surveyor. It was not necessary that a measurement be carried out by a quantity surveyor.
9 In the alternative, Boustead contended that even if it be assumed that the claim for additional expenses of $78,125 were correct, and even taking into consideration the adjustment that needed to be made to the amount claimed based on the final measurement carried out by the quantity surveyor, there was still an amount of $58,676.29 which was indisputably due from the company to Boustead, computed as follows:
Particulars
Value of works in accordance with
measurement of quantity surveyor $ 247,594.79
Less previous payments $85,000.00
$162,594.79
Less company`s allowable deductions which
were denied
(1) Payment to sub-contractors $19,520.00
(2) Test charges $ 3,857.50
(3) Generator sets $1,686.00
(4) Supply of diesel $730.00
(5) 5 months of preliminary expenses $78,125.00
$58,676.29
10 On the foregoing it seemed to me quite clear that the amount of $141,036.79 claimed by Boustead against the company was seriously disputed. On the facts, both the points of dispute raised were not without some basis. The first point of dispute clearly raised questions of fact and of law which ought to have been thrashed out at a trial. For example, in view of the three-week delay in giving site to Boustead, when should Boustead have finished the works? Were they bound by the five-month period? What consequences flowed from the delay by Boustead in completing the works? As regards the second point, while the contract did not provide that the measurement must be done by a surveyor, this obviously would have to be so unless the parties could, among themselves, agree on the quantity. This was a question of fact. Considering all the circumstances, the proper course would be for Boustead to commence an action to establish the debt due rather than a winding-up petition.
11 It is a well established principle that a winding-up petition is not a legitimate means of seeking to enforce payment of a debt which is bona fide disputed: see Stonegate Securities v Gregory [1980] 1 All ER 241 at p 243. It is an abuse of the process of the court to petition to wind up a company upon the basis of a debt which is so bona fide disputed: see judgment of Ungoed-Thomas J in Mann v Goldstein [1968] 1 WLR 1091 at pp 1098-1099. This substituted petition was presented on the basis of neglect on the part of the company to pay the amount claimed in the statutory notice. But there could not be neglect to pay if the sum demanded was bona fide disputed. As Jessel MR stated in Re London & Paris Banking Corp (1874) LR 19 Eq 444 at p 446:
Negligence is a term which is well known to the law. Negligence in paying a debt on demand, as I understand it, is omitting to pay without reasonable excuse. Mere omission by itself does not amount to negligence. Therefore, I should hold, upon the words of the statute, that where a debt is bona fide disputed by the debtor, and the debtor alleges, for example, that the demand for goods sold and delivered is excessive, and says that he, the debtor, is willing to pay such sum as he is either advised by competent valuers to pay, or as he himself considers a fair sum for the goods, then in that case he has not neglected to pay and is not within the wording of the statute.
12 As regards the alternative ground, counsel for the substituted petitioner argued that even if the two points of dispute raised by the company were valid, there was nevertheless outstanding the sum of $58,626.29 which was indisputably due from the company and failure so to pay that sum constituted `neglect to pay` within the meaning of s 254(2)(a) of the Companies Act. During the hearing before me, counsel for the company stated that if $58,626.29 was all that Boustead were asking, the company was prepared to pay that sum. In this regard, it is pertinent to refer to the case Re A Company [1984] 3 All ER 78. There the petition was founded on a statutory demand dated 1 July 1982 in the sum of £12,435.75 which sum related to some muck and soil removal work done by the petitioners for the company. The petitioners submitted an invoice for £12,435.75. In April 1980, the company wrote disputing the rate charged. The rate specified in the contract was for the spoil to be taken to Elstow Tip, not Wentworth Drive, which was much nearer. Having received no reply, the company suggested that the sum payable to the petitioners was £2,230.38 and was prepared to pay that sum, if the petitioners would agree. Then in September 1980, the petitioners wrote to say that they would be taking professional advice on the comments made by the company on the invoice. The next letter was the statutory demand dated 1 July 1982 from the petitioners` solicitor. The statutory notice was not complied with and the petition was presented on 2 August 1982. On 17 September 1982, the company by a motion sought to have the petition dismissed. A week later on 24 September 1982, the company paid the petitioner £2,234.38 and said that in consequence it no longer owed the petitioners any money. One of the submissions made by the petitioners was that when this statutory demand was issued it was apparent that some sum exceeding the statutory minimum of £200 was owing, ie £2,234.38, and that nonpayment of that sum within 21 days was sufficient neglect within s 223(a) of the English Companies Act. Mervyn Davies J referred to the well-known passage of Lord Chelmford LC in Cardiff Preserved Coal and Coke Co v Norton (1867) LR 2 Ch App 405 at p 410 where it was held that even though the notice demanded a larger sum but if a smaller sum (exceeding the statutory minimum) was indisputably due and known to the company, and the company nevertheless failed to pay up the smaller sum, then there was neglect to pay on the part of the company within the meaning of s 68(1) of the English Companies Act 1856. Merryn Davies J distinguished the case before him from Cardiff Preserved Coal in this way (at p 82):
When the demand was made, the amount due to the petitioners was not known to the company. It is still not known. At the time of the demand the company knew there was a dispute and were willing to pay £2,234.38 but that is not to say that they knew that the sum due was £2,234.38. They knew that the petitioners were alleging the sum due to be £12,435.75. As to the petitioners, they knew that the company were disputing liability in that sum. In these circumstances I do not see how the petitioners were in any position to make a genuine demand for a specified sum. Section 223(a) contemplates a creditor being able to point to a debt of a specified sum that cannot be seriously questioned either as to existence or quantum. It follows that the petitioners were not at liberty to make use of s 223(a). The position is no doubt otherwise when a petitioner can, without serious argument, allege a debt of a specified sum but by inadvertence specifies the sum wrongly in a statutory demand.
13 In the instant case, as stated above, the company was seriously disputing the claim for $141,036.79. The crucial date to determine whether the sum of $58,626.29 was indisputably due was the date on which the statutory notice was issued, ie 20 January 1987. On that date there was clearly a dispute between the parties on the question of damages that were due from Boustead to the company for the delay in completing the works. Similarly on that date, the final measurement of the works had yet to be carried out by the parties or, in the absence of agreement, by a quantity surveyor. Having regard to all the circumstances and on the authority of Re A Company [1984] 3 All ER 78, all the more so I did not see how one could say that the company clearly knew that the sum due to the petitioners was $58,626.29 and that since they did not pay that sum, there was neglect to pay within s 254(a) of the Companies Act.
14 For the above reasons, I did not think, in the light of the dispute between the parties on the sum claimed by Boustead, that a filing of a winding-up petition was a proper course to pursue. An action should have been instituted to establish the amount due from the company to Boustead. Accordingly, I dismissed this substituted petition and fixed costs at $2,500.
15 Order accordingly.
Chao Hick Tin JC
DA Mitchell (Donaldson & Burkinshaw) for the petitioning creditor
Kelvin Lim (Tan Lee & Choo) for the company