grounds of decision
Land — Sale of land — Contract

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Huang Ching Hwee v Heng Kay Pay and Another
[1992] SGCA 79
CA 128/1990
Chao Hick Tin J; Chua F A J; Warren Khoo L H J
13 November 1992
1 Cur Adv Vult
2 This is an appeal from the judgment of Goh Joon Seng JC (as he then was) whereby he dismissed the appellant`s application by a vendor and purchaser summons for a declaration that the respondents were not entitled to rescind a contract for the purchase of a property and that the appellant was entitled to forfeit the deposit paid by the respondents and for other reliefs.
3 The facts are fully set out in the learned judge`s judgment, reported in [1991] 2 MLJ 15 . We can be brief. The appellant was the owner of a property known as No 4 Joan Road, a two-storey bungalow. On 11 May 1990, the appellant granted an option to the respondents to purchase the property at the price of $2.5m. The respondents exercised the option on 1 June 1990, thereby bringing into being, a binding contract for the sale of the property. Completion date was set for 24 August 1990. The sale was subject to the Singapore Law Society`s Conditions of Sale 1981 and to the special terms and conditions set out in the option to purchase.
4 After the exercise of the option, the respondents discovered that the appellant had, after he became owner of the property in October 1989, just over seven months before the present contract, carried out certain demolition works and substantial additions and alterations to the property. In their solicitors` letter to the appellant`s solicitors dated 21 August 1990, they told the appellant that their inquiries had revealed that the following works had been carried out without the necessary planning permission:
(1) the roof over the patio;
(2) the mono-pitch roof to the main entrance;
(3) the demolition of the garage and servant`s room including the toilets;
(4) the metal structure where the garage servant`s room and toilets stood;
(5) the demolition of the covered roofing structure at the rear;
(6) the railing at rear flat terrace over lounge;
(7) the timber fence;
(8) the tinted aluminium glass panes at lounge area;
(9) the toilet in the servant`s room;
(10) the treatment of window surrounds;
(11) the new roofing to external of dining and kitchen area.
5 By the same letter of 21 August, the respondents` solicitors gave notice to the appellant`s solicitors purporting to rescind the contract on the ground that there had been a `serious misrepresentation as to quality of a fundamental character`. They demanded the return of the $250,000 deposit paid by the respondents. The appellant did not agree with the respondents` stand, and took out the originating summons by which he sought the remedies mentioned above.
6 There is no dispute that these works were carried out, although the appellant`s description of them differs somewhat in detail from the above description.
7 It is also not in dispute that at the time of the making of the contract, the fact that these works had been carried out was not disclosed to the respondents. Indeed, as the judgment shows, the appellant was not very forthcoming in disclosing the information in the requisitions.
8 Before the learned judge, the respondents did not pursue their original contention (in the correspondence) that the appellant was guilty of `misrepresentation as to the quality of a fundamental character`. Neither did they pursue their contention (also in correspondence) that the works were in contravention of the planning laws. They relied on the fact that no approval for the works had been obtained under the Building Control Act (Cap 29)(`the Act`), and contended that this constituted a latent defect of title.
9 The issues which developed before the learned judge were, therefore, firstly, whether the works required the approval of the building authority under the Act; and, secondly, if they required such approval, whether, approval not having been obtained, such unauthorized works constituted a defect of title.
10 The judge answered both questions in the affirmative, and dismissed the appellant`s application.
11 On appeal, only the second issue was canvassed before us, ie whether the unauthorized works constituted a latent defect of title at law and as such were subject to disclosure at the date of the contract.
12 The relevant statutory provisions are as follows. Section 5 of the Act prohibits the commencement or carrying out of any building works unless the building authority has approved all the plans of the building works. `Building works` is defined in s 2 as including the alteration, addition or repair of a building. Section 13(1) of the Act, so far as relevant, provides that where any building works have been carried out in contravention of the provisions of the Act or the building regulations, the building authority may by order in writing require:
...
(b) the demolition of the building; or
(c) such work or alteration to the building or building works to be carried out as may be necessary to cause the same to comply with the provisions of this Act and the building regulations or otherwise to put an end to the contravention thereof ...
13 Section 13(3) provides that in the event of non-compliance with an order issued under sub-s (1) the building authority may demolish remove or alter such building or building works and recover all expenses incurred. Subsection (4) provides in the event of non-compliance with an order under sub-s (1) for a fine not exceeding $10,000 or imprisonment not exceeding 6 months or both, and in the case of a continuing offence a further fine not exceeding $500 for every day during the continuance of the offence after conviction.
14 Section 20 of the Act also provides that no building or part of a building where any building works have been carried out shall be occupied in any way without a certificate of statutory completion in respect of that building or that part of the building. It is also provided that any person who contravenes these provisions shall be guilty of an offence and liable to a fine not exceeding $20,000 or to imprisonment not exceeding 6 months or to both, and in the case of a continuing offence, to a further fine not exceeding $1,000 for every day during the continuance of the offence after conviction.
15 The learned judge approached the matter as follows. He found that as no plans had been submitted to the building authorities for approval, the purchasers would not, in the normal course of inquiries by requisitions, be able to discover the existence of the unauthorized works. He held therefore that the defect was a latent defect. He then posed the question whether the latent defect amounted to a latent defect of title. He referred to a series of authorities from New Zealand and Australia and came down in favour of the view that the defects did amount to a latent defect of title and that the appellant should have disclosed them. The learned judge dismissed the appellant`s application.
16 General principles
17 The principles governing the vendor`s duty of disclosure of defects are reasonably well established. Broadly, the position is as follows. The law draws a distinction between defects of quality and defects of title. It also draws a distinction between patent and latent defects. There is no duty to call attention to patent defects, whether of title or quality. As to latent defects, prima facie the rule `caveat emptor` applies to latent defects of quality or other matters (as opposed to defects of title) which affect the value of the property sold, and the vendor, even if he is aware of any such matters, is under no obligation to disclose them. However, the vendor is under a duty to disclose latent defects of title. See 42 Halsbury`s Laws of England (4th Ed) paras 51ff.
18 The learned editors of Emmet on Title state (citations of authorities omitted):
The general rule of contract is that a vendor is under no duty to disclose material facts to a prospective purchaser, and this applies to contracts for sale of land ... However, there is a term implied into a contract for the sale of land that a good title should be shown by the vendor, ie that he is selling the fee simple free from incumbrances. The implication of such a term does not arise if the purchaser has knowledge, actual or constructive, at the time of the contract of any irremediable defect in the vendor`s title. Consequently, it may be said that a prospective vendor of land has a duty of disclosure to the extent necessary to prevent the implied term arising. In other words, a vendor should disclose to prospective purchasers any defects in his title which are latent and not patent.
19 The learned editors of 42 Halsbury`s Laws of England (4th Ed) at para 61 say:
Since a vendor`s title to land is exclusively within his own knowledge, he is bound to disclose all latent defects in his title to an intending purchaser. If a purchaser subsequently becomes aware of an irremovable defect of title which the vendor did not disclose to him before entering into the contract, he may rescind the contract or resist its specific performance on that ground.
20 At para 62, the learned editors express the view that the duty to disclose is absolute, and the vendor`s ignorance of the defect is no excuse. They cite the case of Re Brewer and Hankins` Contract .1
21 Unauthorized alterations to buildings: whether defect of title
22 There are several authorities from Australia and New Zealand dealing with the application of these principles to the cases of alterations or additions to dwellings in contravention of building laws and regulations. The cases cited were Vukelic v Sadil-Quinlan & Associates ;2 Maxwell & Anor v Pinheiro & Anor [1979] 46 LGRA 310 Borthwick v Walsh [1980] 1 BPR 9259 Watkin v Wilson [1985] 1 NZLR 666 and McInnes v Edwards [1986] VR 161
23 These cases were well analysed by the learned judge, and it is not necessary for us to repeat what he has done. In broad terms, in all these cases, the building laws, like our Act, made it an offence to make unauthorized alterations and additions and empowered the authorities to require rectification, demolition or removal of the offending works and provided for other sanctions. These authorities, apart from McInnes v Edwards ,6 all held that works such as extensions and additions to a building without the necessary permission under building laws constitute a defect of title. In all these cases except McInnes ,6 the court did not consider that it mattered that the authorities had not taken any action to require compliance; the mere potential for such enforcement action was enough to constitute a defect of title.
24 The learned judges in these cases gave a variety of reasons for holding such a view. Connor J in Vukelic 2said:
All such consequences (provided for in the Building Ordinance) could flow to the purchaser if he chose to park his car in the garage. Moreover, ... the building controller was empowered to direct the owner of the land to demolish a building which had been erected without a permit, as this garage was. These provisions impose on the purchaser a liability of uncertain amount at some future time and constituted in my view a defect in the title of the premises: cf Carlish v Salt [1906] 1 Ch 335 at 340.
25 Powell J in Maxwell 3said:
Quite untutored by authority I would have thought that the fact that, in consequence of work having been unlawfully carried out, a council might lawfully require the demolition or rectification of a building on land the subject of a contract for sale and might itself enter the subject land to carry out the work of demolition or rectification was, unless the purchaser knew, or had reason to suspect that fact at the time of entering into the contract, a latent defect in title, which defect the purchaser was entitled to have removed either by having the work rectified by the vendor at the vendor`s expense or having the vendor obtain a certificate under s 317A of the Act. The authorities (see Carlish v Salt; Fletcher v Manton) would seem to demonstrate that this is certainly so in a case in which a council had proceeded to issue a notice under s 317B(1A) of the Act.
26 McLelland J in Borthwick v Walsh [1980] 1 BPR 9259 expressing himself as following the decision of Powell J in Maxwell [1979] 46 LGRA 310 said:
In my opinion, the existence as at the date of a contract for the sale of real property of a state of affairs which renders the powers conferred on a council by s 317B (provision for demolition) available to be exercised in respect of that property constitutes a defect in the vendors` title. I respectfully agree with the decision of Powell J to that effect in Maxwell v Pinheiro. Any right exercisable against, or restriction affecting, the property or its owner to its or his detriment is a defect in title unless it arises solely by reason of the existence of a law of general application.
27 Henry J in Watkin v Wilson 5 said:
The (common law) rule puts a vendor under a duty to make good title to the estate or property he has contracted to sell. The contract here embraced land and buildings. As it transpired, good title to the building was not given because a portion of it had been erected without a permit and did not comply with the relevant byelaws. I find as a fact that such was the position, and I am also satisfied on the evidence that the Council can require demolition of the addition in question. It seems to me that there is here a latent defect in title in respect of part of the subject matter of the contract.
28 Henry J said that a similar conclusion was reached in Vukelic ,2 Maxwell 3and Borthwick .4
29 Authorities in favour of opposite view
30 The appellants relied on Fletcher v Manton ,7 a decision of the High Court of Australia, and McInnes v Edwards [1986] VR 161 a decision of the Supreme Court of Victoria. In Fletcher v Manton [1940] 64 CLR 37 the facts are briefly as follows. On 21 March 1940, the parties entered into a contract for the sale of certain land together with a terrace of houses built thereon. Unknown to the parties, the Housing Commission, acting under s 8 of the Slum Reclamation and Housing Act 1938 had on 8 March declared the terrace of houses unfit for human habitation and directed its demolition. The notice of the declaration was not received by the vendor until 3 April. In answer to requisitions after conclusion of contract, the vendor disclosed the receipt of the notice, and pursuant to the notice received by him he demolished the terrace. The purchasers refused to complete and demanded rescission of the contract and return of the deposit paid. Fletcher v Manton 7 was fought on the issue whether the matter was governed by the rule in equity, that the risk of loss or destruction of the property contracted to be sold passes to the purchaser upon conclusion of the contract, but it incidentally also resolved a point which is of direct relevance to the point at issue in the instant case. The property contracted to be sold was slum property liable at any time to be declared unfit for human habitation. However, the majority of the court were of the opinion that the obligation to demolish the terrace did not attach until the service of the notice of the declaration. Since this did not occur until after the conclusion of the contract, the purchaser must bear the loss.
31 Starke J said:
The Act empowers the authority under the Act to declare a house unfit for habitation but that imposes no duty upon the owner to demolish the house unless notice of the declaration be served and also notice requiring its demolition. McInnes v Edwards, as stated above, was an unauthorized building works case. Kaye J in the Supreme Court of Victoria took the view that such works did not constitute a defect of title. In doing so, he consciously departed from the decisions in Vukelic [1976] 13 ACTR 3 Maxwell [1979] 46 LGRA 310 and Borthwick [1980] 1 BPR 9259 He was of the view that these cases, all decided at the Supreme Court level, had been decided per incuriam as the decision of the High Court of Australia in Fletcher v Manton [1940] 64 CLR 37 had not been considered. Referring to the unauthorized alterations, which in this case included extensions to the roof, Kaye J said:
That state of affairs per se did not and does not create an encumbrance, charge or burden upon the property. It gives rise merely to a potential situation out of which a statutory liability might be created or imposed by the Council exercising its powers under regs 3.2(1) and 3.2(3) of service of both a show cause notice upon the owner of the property and in the event of non-compliance, a notice to alter, demolish or remove the building. However, although the power to serve a show cause summons is mandatory, it is within the council`s discretion to serve a notice to alter, demolish or remove. Thus, for any one of a number of reasons the Council might decide not to exercise those powers which create the necessary statutory liability. But those powers, not having been exercised by the Council, there is not a latent defect in the title to the property agreed to be sold.
32 Textbook writers` views
33 The learned editors of Megarry and Wade: The Law of Real Property (5th Ed) at p 611 state:
A good title means a title free from incumbrances. The term `incumbrances` covers all subsisting third party rights such as leases, rent charges, mortgages, easements and restrictive covenants. It also includes statutory liabilities, if they are not merely potential or imposed on all property generally.
34 In Voumard`s The Sale of Land (4th Ed, 1986) at p 218, there is a strong criticism of the decisions in Vukelic 2 and Borthwick [1980] 1 BPR 9259 The learned author cites part of the above passage from Megarry and Wade
35 and says that these two cases were wrongly decided. He says:
In neither Vukelic v Sadil-Quinlanor Borthwick v Walsh had the failure to comply with the building regulations in fact imposed on the vendors a statutory liability in the sense that encumbrances had been imposed on their respective properties, in each case the liability of the vendors was still contingent, since no action had been taken by the relevant local authorities. The relevant local authorities were first required to exercise their statutory powers in the normal course of events before liability could be imposed upon the vendors. In neither case had any notices been served or orders been made by the relevant local authorities.
36 The author concludes that a failure to comply with the building regulations without more amounts merely to a defect in the quality of the building, and not a defect of title.
37 The views of the learned author were apparently cited to Kaye J in McInnes v Edwards [1986] VR 161 and appear generally to have been accepted by Kaye J ( Voumard p 220 fn 51).
38 Other cases of statutory liability
39 In Abbot v Bull [1884] 14 VLR 996 the purchaser refused to complete the sale of land unless the vendor discharged a claim made by the City Council for a sum of money in respect of the formation of a private street under the Public Health Amendment Statute of 1883. Section 131 of the statute empowered the local council to require owners of premises fronting any street to make up streets, in default of which the local council might do so and charge the apportioned cost to owners of properties fronting the street. Section 145 provided that where any lands or premises were unoccupied and any such expenses incurred by the local council remained unpaid for three years, the local board might take possession of such land or premises, and may hold the same against any person interested therein. The vendor contended that the purchaser was liable to pay this claim, as it was made after the contract had been entered into, although the street works had been substantially completed before that date. It was held by the full court of three judges of Victoria that the liability under s 145 of the statute did not create a present charge or encumbrance on the land at the time the expenses were incurred by the local board, but a contingent future charge or encumbrance in the event of the person liable to pay not fulfilling his liability for a period of three years. As the contingent liability would only form a charge on the land if the money was unpaid and the land was found to be unoccupied at the end of three years, the learned judges of the full court were of the view that it was not a charge or encumbrance on the land.
40 In Dormer v Solo Investments Pty Ltd [1974] 1 NSWLR 428 the purchaser of land discovered after exchanging contract, that the subject land might be affected by proposals for the establishment of a natural gas pipeline by the gas authorities. Inquiries revealed that the tentative route of the pipeline passed across the land. The purchaser claimed that the vendor was aware of the proposals and failed to disclose them to him at the time the parties entered into the contract. The vendor admitted that he was aware of a real possibility that the gas authorities would acquire an interest in the land and was aware of correspondence between the former owner and the authorities. It was held by Holland J in the Supreme Court of New South Wales that this possibility did not amount to a defect of title, as it was subject to a number of contingencies, such as the possibility that the final route might not pass across the land, the possibility of the Minister`s refusal of the necessary licence for the authorities to construct the pipeline, etc.
41 In Tsekos v Finance Corporation of Australia Ltd [1982] 2 NSWLR 347 separate agreements for the sale of three adjoining properties with dwellings thereon were entered into on 2 June 1977. Two months before that, in a letter dated 7 April 1977 the council made an offer to acquire the properties in the sum of $70,000, failing acceptance of which the council would proceed to apply to the Governor for powers to resume the properties. There followed some inconclusive discussions first about the council acquiring the properties, and then about the plaintiff vendors restoring the properties. On 7 June 1977, after the conclusion of the contract for the purchase of the properties, the council made another offer to acquire the properties at an increased price, failing acceptance of which the council would take action to resume. The offer not being accepted, the council on 21 June finally served a notice of their proposal to resume the properties. The ultimate decision rested with the Governor under the relevant legislation, and there was no certainty of resumption until his approval was obtained.
42 The purchasers relied upon the notice of proposal to resume, and purported to rescind the contracts of sale of the properties.
43 Rath J in the Supreme Court of New South Wales held that the threat of resumption, as it existed at the date of the contracts, did not constitute a defect of title. He held therefore that the purchasers were not entitled to rescind.
44 Rath J referred to Carlish v Salt [1906] 1 Ch 335 He said the threat of resumption was different in kind from the party wall notice and the award in that case. It is to be noted that at the date of the contract, there was only a threat of applying for powers to resume. The formal notice of proposal to do so was not served until after the date of contract.
45 Last but not least, we must refer to Carlish v Salt [1906] 1 Ch 335
46 In this case, a property in Lincoln`s Inn Fields in London was contracted to be sold. The property was in a tumble down condition and the party wall with the adjoining property had been condemned by the district surveyor. Before the contract for the sale of the property was concluded, the owners had in fact been served with a notice under the London Building Act by the owner of the adjoining property of his intention to execute works to the party wall. In pursuance of the notice, the surveyors appointed had also made an award requiring the cost of the works to be shared between the owners of the two properties. However, the vendor did not disclose the notice or the award.
47 After the conclusion of the contract, in consequence of the condemnation of the premises by the district surveyor, a dangerous structure notice under the Act was served on the vendors, requiring them to take down forthwith certain portions of the property and to shore up the structure immediately. The purchaser was then informed of this notice and the previous party wall notice and award. Thereupon, the purchaser claimed rescission of the contract. It was held by Joyce J that he was entitled to do so. He said:
I hold that the party wall notice and the award constituted a material fact affecting the price to be paid, and in so far as they imposed a liability of uncertain amount at some future time on the owner of the premises, I am of opinion that they constituted a latent defect not in the quality of, but in the title to the property, and ought to have been disclosed.
48 Carlish v Salt in application
49 Carlish v Salt [1906] 1 Ch 335 is the authority commonly referred to in the cases which have been referred to, but different courts have drawn different conclusions from it. What has probably given rise to these differing conclusions is that while Joyce J in Carlish [1906] 1 Ch 335 did decide that the notice and award in that case constituted a title defect, he did not, nor was it necessary for him to, decide whether a potential liability under the London Building Act would do so where no notice had been served or award made.
50 In Vukelic [1976] 13 ACTR 3 Connor J referred to the various provisions of the Building Ordinance and the consequences to the owner arising from the unauthorized garage. He then, using the words Joyce J used in Carlish [1906] 1 Ch 335 held that there was a liability of uncertain amount at some future time and that there was thus a title defect. He did not refer to the notice and award in the Carlish case.11
51 Powell J in Maxwell [1979] 46 LGRA 310 recognized the limit of what Joyce J had decided when he said that Carlish 11showed that it would certainly be a title defect where the authorities had issued a notice. See the passage from his judgment set out above.
52 McLelland J in Borthwick [1980] 1 BPR 9259 followed the decision in Maxwell 3in arriving at his conclusion that there was a defect of title. He added that any right exercisable against, or restriction affecting, the property or its owner to its or his detriment is a defect of title unless it arises solely by reason of the existence of a law of general application.
53 Henry J in Watkin v Wilson [1985] 1 NZLR 666 relied on the Vukelic
54 line of cases for the conclusion he came to, that there was a defect of title.
55 Our views
56 In our view, the essential element of the Carlish case11 was the party wall notice that had been served and the award that had been made before the conclusion of the contract for the sale of the property. Joyce J there in terms specifically referred to the notice and the award, and held that in so far as they imposed a liability of uncertain amount at some future time on the owner of the premises, they constituted a latent defect of title.
57 As stated above, Connor J in the Carlish case11 did not refer to the notice of the award. The cases following Vukelic [1976] 13 ACTR 3 similarly did not do so. Had greater emphasis been placed on the significance of this feature of the Carlish case,11 the Vukelic line of cases might well have been decided differently. Also, as pointed out by Kaye J in McInnes [1986] VR 161 the Australian High Court case of Fletcher v Manton [1940] 64 CLR 37 was not considered in any of those cases.
58 It seems to us that the better view is that represented in Kaye J`s persuasive analysis in McInnes [1986] VR 161 It seems to us that McInnes [1986] VR 161 is entirely consistent not only with such previous authorities as there were (except of course the Vukelic line of cases), it is also consistent with academic and professional opinion and assumptions. In this connection, it is noteworthy that in giving a list of examples of encumbrances on title, the learned editors of 42 Halsbury`s Laws of England (4th Ed) at para 63, mentioned the party wall notice and award in Carlish [1906] 1 Ch 335 as the only examples of encumbrances arising from a liability under a statute among the more readily recognizable encumbrances, such as easements, unusual covenants in a lease, etc.
59 It is difficult to lay down any precise rules, but we think that the Carlish case11 provides a useful guide for deciding when a potential or inchoate statutory liability becomes an encumbrance and a blot on title. The mere fact that a state of affairs exist which might bring into operation the provisions of a law imposing a liability or burden is not enough to constitute a defect of title. Any intention to invoke the provisions of the law should have been manifested and brought to the notice of those concerned before the conclusion of the contract, before any question of a defect of title can arise.
60 The instant case
61 Under our Building Control Act, although the building authority has power to take any of a number of actions prescribed by the Act in case of any infringement, it does not follow that it will necessarily do so. It might for any of a number of reasons decide not to take action in any particular case. Even in a country where laws are enforced more rigorously than perhaps in some others, there is surely always an element of decision-making, of judgment and exercise of discretion before action is taken.
62 There is no evidence in the instant case that the authorities had threatened to take action against the infringement. All that has been shown is that the approval for the works was not obtained, not that the works were of such a character that they actually contravened the requirements of any building regulations. We assume that it is always open to the owners for the time being to apply to regularize the position, and where no questions of safety is involved, there is no reason to believe that approval to retain the works must necessarily be ruled out.
63 Indeed, s 14 of the Act allows applications to be made for the waiver or modification of any requirements of the building regulations, although the section contemplates such applications being made before works are carried out.
64 Therefore, although the potential for enforcement action by the building authority was always there, there was never any certainty or inevitability about it.
65 It would give rise to great uncertainty and unnecessary disputes in conveyancing practice if the mere potential of enforcement action by the authorities were to be treated as something going to title.
66 It is noteworthy that the common requisitions made by solicitors to the Building Control Division, so far as contraventions of building laws are concerned, are all addressed to questions whether any order or notice has been served or not. This can be seen from the ones the appellant produced in this case in support of his argument based on special condition 7 (of which more below).
67 Does the vendor`s knowledge matter?
68 In arriving at his decision, the learned judge below appears to have relied partly on the following passage in the judgment of Dixon J in Fletcher v Manton :7
Again, if the vendor had known that the making of an order was even under consideration and had failed to disclose his knowledge to the purchasers, the contract might have been voidable and, at all events, could hardly have been enforced specifically.
69 The learned judge appears to have based his decision on the fact that since it was the appellant himself who carried out the illegal alterations, he obviously knew of them, and on the basis of the above statement of Dixon J, the appellant as the vendor should have disclosed the alterations. On this point we would respectfully differ from the learned judge below.
70 The rule allowing a purchaser to rescind in the case of a defective title is based on an express or implied term in the contract of sale that the vendor has to show a good title, that he is selling the property contracted to be sold free of encumbrances. It is a contractual obligation, the performance of which is not dependent on knowledge. Knowledge of any latent defect of title on the part of the vendor no doubt facilitates his disclosure to the purchaser, so as to prevent the purchaser from subsequently objecting to title on the basis of the defect. On the other hand, ignorance of it does not excuse the performance of the contractual obligation to deduce a good title even though the vendor is not in a position to disclose what he does not know. In this instance, it is meaningless to speak of disclosure or of what the vendor ought to know. The vendor would have failed to discharge his contractual obligation all the same. It is this failure of performance that provides the basis for the right of the purchaser to rescind.
71 As the learned editors of 42 Halsbury`s Laws of England (4th Ed) at para 62 say, the vendor`s duty to disclose a defect of title is absolute, and his ignorance of the defect is no excuse.
72 Where, as in the instant case, as we hold, the subject matter of the non-disclosure is not a matter of title, but of quality, there is in general no duty to disclose, and knowledge is generally not material in the absence of misrepresentation or warranty or other special circumstances. As stated above, the responrelied solely on the ground that the unauthorized works constituted a latent defect of title.
73 Whether such knowledge on the part of the vendor would prevent him from resorting to the equitable remedy of specific performance is a topic which we need not have to discuss as the appellant has elected not to proceed with his claim for this remedy.
74 Condition 7
75 We have to deal with condition 7 of the special terms and conditions of the contract which the appellant relied on. Condition 7, in essence, provided that the sale was subject to satisfactory replies to the purchasers` requisitions to various governmental authorities. There is a proviso to condition 7 which reads:
Provided that the answers from the ... Building Control Division shall not be deemed unsatisfactory unless the same disclose that the property is affected by any notice or order which has not been complied with and which is incapable of being complied with by the vendor before completion.
76 The appellant relied on this proviso.
77 He produced answers from the Building Control Division showing that no notices had been served under the Building Control Act. He argued that therefore the requisitions to the Building Control Division were not to be deemed unsatisfactory pursuant to the proviso.
78 The learned judge did not in terms deal with this submission. He did, however, say that as no building plans had been submitted in respect of the works complained of, no requisitions to the Building Control Division would have revealed their existence. We assume that he did not think that this proviso was applicable.
79 On the view which we take, it does not matter that the Building Control Division was not aware of the unauthorized works at the time it gave the reply. The result of the view we take is that even if the works were unauthorized, they are not a title defect until a notice or order has been served.
80 Other points in the case
81 Before we conclude, we need to deal with two points that have been raised.
82 A point was made in the court below about the appellant not being forthcoming with his replies to the respondents` inquiries about the unauthorized works. As there was no duty to disclose, it does not matter that the appellant was not forthcoming.
83 There was also mention in the judgment of the learned judge the fact that in a letter to the Chief Assessor of the Property Tax Department dated 14 August 1990, the appellant`s solicitors, in answer to a request to submit a return, told the Chief Assessor, falsely it is said, that he had not carried out any of the `actions listed in the said return` (presumably relating to the unauthorized works the respondents complained of).
84 On the view which we take of the issues raised in this case, we are of the view that this misrepresentation, if it was that, is of no relevance. If anything, it is a matter for the attention of the Chief Assessor.
85 Conclusion
86 For the reasons which we have set out above, we allow this appeal. We make a declaration that the respondents were not entitled to rescind the contract and that the appellant is entitled to forfeit the deposit of $250,000. We order that the amount of $225,000, held by the appellant`s solicitors as stakeholders, being part of the deposit of $250,000, be released to the appellant forthwith.
87 The appellant also asked for damages for wrongful rescission and interest on the damages. We direct an inquiry as to what damages, if any, have been sustained by the appellant in consequence of the wrongful rescission of the contract and we order that the respondents pay the appellant the amount of the damages, if any, so ascertained, giving credit to the deposit forfeited. In the event that the amount of damages is less than the deposit, the vendor shall nevertheless retain the entire amount of the deposit. The appellant shall have interest on the amount of the net damages, if any, after giving credit for the deposit, at the rate of 8%. The date from which the interest is to run is reserved for determination at the inquiry. The appellant and his advisors will no doubt decide for themselves whether any loss has been sustained and whether there is any need to pursue their damages claim.
88 As the appellant elected not to proceed with his claim for specific performance in the court below, we do not need to consider it.
89 The respondents shall pay the appellant`s costs here and below. [lt ]6[gt ] Appeal allowed.
Chao Hick Tin J
Chua F A J
Warren Khoo L H J
Foo Soon Yien (Bernard Rada & Lee) for the appellant
Berny Johns (Johns & Co) for the respondents