In the High Court of the Republic of Singapore
[1992] SGHC 213
Suit 635/1991
Between
People's Parkway Development Pte Ltd
… Plaintiff
And
Akitek Tenggara
… Defendant
grounds of decision
Limitation of Actions — When time begins to run

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
People's Parkway Development Pte Ltd v Akitek Tenggara
[1992] SGHC 213
Suit 635/1991
L P Thean J
04 August 1992
1 The plaintiffs were at all material times the developers of a parcel of land known as Lot 5474 of Mukim XXVI and Parcel 121 at Marine Parade Road/East Coast Parkway (`the site`) pursuant to a building agreement made between the plaintiffs and the President of the Republic of Singapore dated 16 December 1981, whereby the plaintiffs were granted a lease of the site for a term of 99 years for the purpose of developing a thirteen-storey building for offices and shops. The defendants were and are, at all material times, a firm of architects and were appointed on 27 May 1981 by the plaintiffs as architects for the development. In the same month, a firm of surveyors called Wang Yu Yung Associates were appointed to prepare a survey of the site showing all topographical features, including the boundary thereof. The surveyors conducted a survey of the site, and in June 1981 prepared a drawing setting out the boundary lines. On the basis of that drawing, the defendants prepared a site plan setting out the layout of the proposed thirteen-storey building. Subsequently, building approval was obtained, and piling works commenced sometime in December 1981 and were carried out. Building works commenced in June 1982 or thereabout.
2 On 7 June 1982, the plaintiffs received a letter from the Housing and Development Board (`HDB`) informing them that a survey of the site carried out on 19 May 1982 showed that `the site which was under piling had shifted towards the emporium (Block 87)`. It was then found that on the basis of the site plan drawn by the defendants (which in turn was based on the topographical survey drawing prepared by the surveyors) the building line was set beyond the true boundary of the site and encroached on HDB`s land. The defendants on behalf of the plaintiffs then wrote to HDB and the Urban Redevelopment Authority (`URA`) in an attempt to remedy the error. In that letter, the defendants requested, among other things, that the shifting of the building site to the encroached area be allowed to remain and that permission be given to the plaintiffs to carry on the works at the site. In response, URA wrote to the defendants on 6 July 1982 agreeing to the carrying on of the works but on condition that the plaintiffs were prepared to accept `any consequences that may arise from the course of action to be taken by the Land Office/HDB or the Authority`. Subsequently, by their letter of 30 April 1983 URA rejected the plaintiffs` request for a revised location of the boundary to accommodate the encroachment and required the plaintiffs to absorb the cost of the additional strip of land arising from the shift in boundary of the proposed building. If the plaintiffs did not agree to acquire the additional strip of land, the plaintiffs would unavoidably have to remove all construction works, including the pilings, on the encroached area. It was the plaintiffs` case that they had no choice but to agree to acquire the additional area. On 15 November 1984, URA forwarded to the plaintiffs a second supplemental agreement for the acquisition of the additional strip of land at the total price of $1,038,496.96. However, the supplemental agreement was executed much later, namely, on 6 December 1985. As a result of the additional area acquired or to be acquired, the plaintiffs decided to add a 14th storey to the thirteen-storey building. Accordingly, planning permission for this additional floor was applied for and obtained, but completion of the building was very much delayed. Eventually the building was completed, and the certificate of fitness for occupation was issued on 21 June 1990.
3 On 28 March 1991, the plaintiffs instituted this action against the defendants claiming damages for breach of contract and/or for negligence. The defendants on 23 May 1991 applied to strike out the plaintiffs` statement of claim under O 18 r 19 of the Rules of the Supreme Court 1970 and/or under the inherent jurisdiction of the court on the ground that (i) it is frivolous and vexatious, and/or (ii) it is an abuse of the process of the court. The application was heard before the senior assistant registrar and he struck out only that part of the claim relating to breach of contract. Against the decision of the learned senior assistant registrar, the defendant appealed, and at the conclusion of the hearing I varied the order of the learned senior assistant registrar by striking out the entire statement of claim on the ground that it was statute-barred. I now give my reasons.
4 The only issue before me was whether the cause of action in negligence was barred by the Limitation Act (Cap 163)(`the Act`). Section 6(1)(a) of the Act provides that an action founded on tort shall not be brought after the expiration of six years from the date on which the cause of action accrues. The question, therefore, is when the cause of action in negligence accrued in this case. It is accepted that the cause of action in negligence accrues when the damage caused by the negligent act or omission occurs. In this case, the negligent act - for the purpose of this appeal, I assume that the defendants were negligent in preparing the site layout plan as averred in the statement of claim - occurred during the period between June and December 1981 when the defendants prepared the site layout plan for the building. On the basis of the site layout plan the defendants approved the piling works which commenced in December 1981 and the building works which commenced in June 1982 or thereabouts. In the same month, June 1982, the error was discovered. The plaintiffs requested URA to permit the shifting of the building site to the encroached area to remain, which, in effect, involved a readjustment of the boundary to accommodate the encroachment; that, however, was not successful. The plaintiffs were then confronted with two options: first, to stop all building works on site and remove the building works, including the pilings, on the encroached strip of land, or, secondly, to proceed with the works and accept the consequences. They chose the latter. Discussions or negotiations then followed but did not yield any fruitful results to the plaintiffs. On this point, I should perhaps add that there was no direct evidence before me of any discussion or negotiation between the plaintiffs and URA after the discovery of the error. There was a complete absence of evidence as to what happened during the period between 6 July 1982, when URA gave permission to the plaintiffs to carry on with the building works, and 30 April 1983, when URA wrote to the defendants stating in no uncertain terms that whatever additional area arising from the shift in boundary would have to be absorbed by the plaintiffs. It is my inference that discussions and negotiations must have been conducted between the plaintiffs and URA exploring various possible options but no solution was found acceptable to URA; hence came the letter of 30 April from URA. Again, what precisely happened thereafter was not clear. However, it seems to me that at that time or soon thereafter, the plaintiffs agreed to acquire the additional strip of land and the additional cost involved was $1,038,496.96. On 15 November 1984, the supplemental agreement was sent to them by URA.
5 On these facts, the question is: when did the plaintiffs suffer actual damage as a result of the defendants` negligent act? This material date could be either (i) the date when acting on the erroneous layout plan drawn by the defendants the piling works were carried out and encroached on HDB`s land, ie sometime in early 1982, as on that date the plaintiffs had incurred a contingent liability which was capable of monetary assessment, or (ii) the date after the error was discovered, when the plaintiffs were confronted with the two options. In this case, it is immaterial on which of the two dates the cause of action in negligence against the defendants accrued. The action was commenced only on 28 March 1991, and the cause of action had certainly accrued long before 29 March 1985. Clearly, before that date, the plaintiffs had suffered actual loss or damage arising from the negligent act of the defendants. Indeed, the plaintiffs admitted that they had suffered loss. The loss was capable of assessment in monetary terms. The only question then was the quantification of the loss.
6 There are ample authorities bearing on the point in issue. The case of Forster v Outred & Co (a firm) 1 is of some assistance, thought not directly in point. The plaintiff at the office of the defendants, her solicitors, executed a mortgage to secure all liabilities of her son, present and future, and the mortgage was expressed to be a primary security for the son`s liabilities. Subsequently, the son became a bankrupt and was still owing money to the mortgagee. The mortgagee then threatened to foreclose the plaintiff`s property unless she paid up the total amount of her son`s liabilities. The plaintiff therefore paid to the mortgagee the sum of o70,000. Thereafter, the plaintiff sued the defendants for damages for negligence, alleging that the defendants were in breach of their duty as solicitors to explain the content of the mortgage to the plaintiff before she signed it. After the defendants had delivered the defence, the plaintiff took no further action for about three years. The defendants subsequently took out an application to strike out the action for want of prosecution. The plaintiff then issued a second writ against the defendants claiming damages for negligent advice with regard to the mortgage. The application was heard before a master who refused to strike out the first action. On appeal, the judge allowed the appeal and struck out the first action for want of prosecution on the ground of inordinate and inexcusable delay by the plaintiff to the defendants` prejudice and he thought it was only arguable that the second writ had been issued within the limitation period. The judge decided that since the defendants would not be able to raise the limitation defence if the plaintiff was allowed to proceed with the first action, justice required him to strike out the first action and let the plaintiff proceed with the second action where the defendants could raise the limitation defence. The plaintiff appealed and one of the issues before the Court of Appeal was the date when the cause of action accrued. The court held that the plaintiff suffered actual damage when in reliance on the defendants` advice she acted to her detriment by executing the mortgage and thus incurred a contingent liability which was capable of monetary assessment. Accordingly, the plaintiff`s cause of action was therefore complete when she entered into the mortgage, because the effect of her entering into the mortgage was to encumber her freehold property and subject her to a contingent liability to discharge her son`s liability to the mortgagee which might mature into financial loss and in consequence diminish her equity of redemption. Stephenson LJ said at p 98:
Although there is no more direct authority than those cases among those which have been cited to us, I would accept [counsel for the defendants`s] statement of the law and would conclude that, on the facts of this case, the plaintiff has suffered actual damage through the negligence of her solicitors by entering into the mortgage deed, the effect of which has been to encumber her interest in her freehold estate with this legal charge and subject her to a liability which may, according to matters completely outside her control, mature into financial loss, as indeed it did. It seems to me that the plaintiff did suffer actual damage in those ways, and subject to that liability and with that encumbrance on the mortgage property was then entitled to claim damages (not, I would think, an indemnity and probably not a declaration) for the alleged negligence of the solicitor which she alleges caused her that damage. In those circumstances her cause of action was complete on 8 February 1973 and the writ which she issued on 25 March 1980 was issued too late to come within the six years` period of limitation.
7 Dunn LJ, in more concise terms, said at p 99:
I approach this case on the basis that it is sufficient that it is financial loss that should be foreseen, and I would hold that in cases of financial or economic loss the damage crystallizes and the cause of action is complete at the date when the plaintiff, in reliance on negligent advice, acts to his detriment.
8 In Sykes v Midland Bank Executor and Trustee Co Ltd [1969] 2 QB 518, [1969] 2 All ER 1238 (on appeal [1971] 1 QB 113, [1970] 2 All ER 471), the damage crystallized when the plaintiff, in reliance on the negligent advice, executed the lease. It may be that at that time the plaintiff had not paid any money, but it is sufficient if he has suffered some loss capable of quantification in terms of money: see Simple Simon Catering Ltd v Binstock Miller & Co (1973) 117 SJ 529, (1973) 228 EG 527.
...
In this case, as soon as she executed the mortgage the plaintiff not only became liable under its express terms but also, and more importantly, the value of the equity of redemption of her property was reduced. Before she executed the mortgage deed she owned the property free from encumbrances; thereafter she became the owner of a property subject to a mortgage. That, in my view, was a quantifiable loss and as from that date her cause of action against her solicitor was complete, because at that date she had suffered damage. The actual quantum of damages would, of course, depend on events between that date and the date when the damages had finally to be assessed, but the cause of action was complete when she executed the mortgage, without proof of special damage. Forster [1982] 1 WLR 86[1982] 2 All ER 753 was referred to by the House of Lords in the leading case of Pirelli General Cable Works Ltd v Oscar Faber & Partners (a firm) [1983] 2 AC 1[1983] 1 All ER 65[1983] 2 WLR 6 There, a firm of consulting engineers designed an addition to the plaintiffs` factory premises which included a chimney. Owing to a wrong material used, the chimney developed cracks about one year later but the cracks were not discovered by the plaintiffs until after six years from the time the chimney was built. It was held by the House of Lords that the cause of action in negligence against the engineers accrued when the damage came into existence, ie the date when the cracks appeared, and not when the damage was discovered. Lord Fraser of Tullybelton, who delivered the main speech of the House, said at p 16:
The plaintiff`s cause of action will not accrue until damage occurs, which will commonly consist of cracks coming into existence as a result of the defect even though the cracks or the defect may be undiscovered and undiscoverable. There may perhaps be cases where the defect is so gross that the building is doomed from the start, and where the owner`s cause of action will accrue as soon as it is built, but it seems unlikely that such a defect would not be discovered within the limitation period. Such cases, if they exist, would be exceptional.
9 Later, he said at pp 18-19:
It seems to me that, except perhaps where the advice of an architect or consulting engineer leads to the erection of a building which is so defective as to be doomed from the start, the cause of action accrues only when physical damage occurs to the building. In the present case that was April 1970 when, as found by the judge, cracks must have occurred at the top of the chimney, even though that was before the date of discoverability.
10 The next case which is of some relevance is DW Moore & Co Ltd & Ors v Ferrier & Ors ;3 that was also a case of a claim against a firm of solicitors for negligence. There, two of the plaintiffs who were major shareholders of a company agreed to the company issuing shares to an employee who was a director of the company. They consulted their solicitors, the defendants, and on their instructions the solicitors then drew up an agreement containing covenants restricting the employee from setting up similar business as that carried on by the company within a certain period of time, and the agreement was executed by the parties concerned. Subsequently, the employee resigned as director and employee of the company but remained a shareholder. It was then discovered that the restrictive covenants did not take effect on the employee`s ceasing merely to be a director or employee but only on his ceasing to be a shareholder. In consequence, the plaintiffs were unable to enforce the restrictive covenants against the employee. The plaintiffs thereupon brought an action against the defendants claiming damages for negligence in drafting the restrictive covenants. The defendants pleaded that the action was statute-barred. This plea was tried as a preliminary issue, and the judge upheld the plea. The plaintiffs appealed. The Court of Appeal held that where a solicitor negligently drafted a contract, the client suffered damage at the time when the contract was executed and not when the defect was discovered since, at the time of execution, the client was entering into a contract which was of less commercial value than that if the solicitors had not been negligent. Accordingly, the limitation period for bringing an action against a solicitor for negligence began to run from the time when the contract was executed and not from the time when the defect was discovered or the financial loss was suffered. Accordingly, in that case, the plaintiffs had suffered actual damage capable of quantification at the date when they executed the agreement, even though at that date the quantification of damage would have been dependent on an assessment of the future loss due to the employee`s future behaviour. Bingham LJ in his judgment said at pp 279-280:
On the plaintiffs` case, which for purposes of this issue may be assumed to be wholly correct, the covenants against competition were intended, and said by the defendants, to be effective but were in truth wholly ineffective. It seems to me clear beyond argument that from the moment of executing each agreement the plaintiffs suffered damage because instead of receiving a potentially valuable chose in action they received one that was valueless. Indeed, the invalidity of the covenants against competition rendered the rights which the second and third plaintiffs did obtain, to Mr Fenton`s undivided services, a somewhat double-edged benefit.
11 If the quantification of the plaintiffs` damage had fallen to be considered shortly after the execution of either agreement, problems of assessment would undoubtedly have arisen. It might have appeared that Mr Fenton [the employee] was unlikely to leave, taking much of the first plaintiff`s business with him, to establish a competing business. If so, the plaintiffs` damage would have been assessed at a modest figure. But the risk of his doing so could not have been eliminated altogether, and so long as there was any risk that one of the first plaintiff`s two directors might leave, taking much of the first plaintiff`s business with him, to establish a competing business, there must necessarily have been a depressive effect on the value of the first plaintiff`s business and on that of the second and third plaintiffs` derivative interests. In making his assessment the judge would have had to attach a money value to a possible future contingency; but judges do this every day in awarding claimants damages for the risk of epilepsy, the risk of osteoarthritis, the risk of possible future operations, the risk of losing a job and so on. The valuation exercise is, of course, different, but the difference is one of subject matter, not of kind.
12 The court therefore held that the plaintiff`s cause of action had accrued more than six years before they brought their action and the action was statute-barred.
13 Both Forster 1 and DW Moore & Co Ltd 3 were referred to and followed by our Court of Appeal in Seow Teck Ming & Anor v Tan Ah Yeo & Anor and another appeal 4 where the court held, inter alia, that in that case the negligence, if any, of the solicitors was in commencing a worthless action and that damage was suffered when the solicitors commenced that action. Bell v Peter Browne & Co 5 is another case against solicitors for negligence. The plaintiff consulted his solicitors, the defendants, on the division of the matrimonial property between him and his wife. He agreed that the house would be transferred to the wife but that when it was to be sold he would receive one-sixth of the gross proceeds of sale. The plaintiff executed a transfer of the house to his wife`s name but the defendants failed to protect his one-sixth share in the proceeds of sale. The plaintiff and his wife were subsequently divorced; seven years later he was told by his wife that she had sold the matrimonial home and had spent all the proceeds, thereby depriving the plaintiff of his one-sixth interest in the proceeds of sale. The plaintiff thereupon instituted an action against the defendants claiming damages for professional negligence. The defendants applied to strike out the plaintiff`s statement of claim on the ground that the cause of action had been statute-barred. The registrar struck out the plaintiff`s action and on appeal the judge affirmed the decision. On further appeal, the Court of Appeal held, inter alia, that the cause of action in negligence did not accrue until damage was suffered and that the plaintiff suffered damage when the transfer was executed and the title to the house passed to his wife without any formal agreement to protect his one-sixth interest in the property and this actual loss remained nominal until the sale by her and therefore the claim in negligence against the defendants was statute-barred. Nicholls LJ in his judgment said at p 502:
So when did the plaintiff first sustain damage by reason of his solicitors` negligence? On this it is necessary to distinguish between (a) the solicitors` failure to see that the parties` agreement was recorded formally in a suitable declaration of trust or other instrument and (b) their failure to protect the plaintiff`s interest in the house or the proceeds of sale by lodging a caution. As to failure (a), clearly the damage, such as it may have been, was sustained when the transfer was executed and handed over. At that point the plaintiff parted with title to the house, and he became subject to the practical inconveniences which might flow from his not having his wife`s signature on a formal document. If the wife thereafter chose to deny his entitlement to one-sixth of the proceeds of sale, the plaintiff would have to rely on the correspondence between the solicitors coupled with part performance. To the extent that this was less satisfactory than a formal document recording the deal, the plaintiff suffered prejudice. He suffered that prejudice when the transaction was implemented without his having the protection of a formal document.
14 The extent of that prejudice depended on the attitude adopted thereafter by his former wife. All we know is that, according to the pleadings and the plaintiff`s affidavit evidence, when she sold the house she disposed of all the proceeds and did not account to her former husband for his agreed one- sixth share. But the uncertainty surrounding her future intentions goes only to the quantum of the loss the plaintiff sustained when the transfer was executed without him having the same degree of protection as would be provided by a formal document.
15 The learned judge held that failure (b) could be remedied at any time before the wife sold the property. But this difference was not material. In respect of both failures (a) and (b) the plaintiff did not receive the protection he ought to have received when he parted with his title to the house, though failure (b) could be put right subsequently by the plaintiff. The learned judge did not consider that the remediability of failure (b) put it `on the other side of the line from failure (a)`. Failure (b) was only remediable by the plaintiff after he became aware of it, but such a failure did not come to his notice until the house was sold and it was too late.
16 Compared with these cases, the instant case is an a fortiori situation. Assuming that the damage was not suffered by the plaintiffs at the time when the piling works encroached on HDB`s land, actual damage certainly occurred after the discovery of the encroachment when the plaintiffs were confronted with the options of either to remove all building works, including the pilings, on the encroached strip of land or to carry on with the works and accept all the consequences. The plaintiffs chose the latter, as a result of which they had no choice but to accept the requirement of URA to acquire the additional strip of land at a tremendous cost. URA indicated this in November 1984. By that time, if not earlier, damage had occurred though the amount thereof had not been quantified. The full extent of the plaintiffs` damage depends on various factors and is a matter of assessment; it depends, among other things, on the extent of the delay caused to the completion of the building, the additional costs involved in accommodating the situation and the steps or measures taken by the plaintiffs to mitigate the loss. In my judgment, in this case the cause of action in negligence had accrued more than six years before the commencement of the present action and the action was therefore statute-barred and, upon a defence of limitation being raised, was clearly unsustainable.
17 Outcome:
L P Thean J
Ruby Lee and Bernie Neo (Lee & Partners) for the plaintiffs
Foo Soon Yien (Bernard Rada & Lee) for the defendants