In the High Court of the Republic of Singapore
[1993] SGHC 191
Suit No 2198 of 1990
Between
M K (Project Management) Ltd
… Plaintiff
And
Baker Marine Energy Pte Ltd
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
M K (Project Management) Ltd v Baker Marine Energy Pte Ltd
[1993] SGHC 191
Suit No 2198 of 1990
G P Selvam J
13 August 1993
1 Judgment:
2 CORAM: G P SELVAM, JC
3 Cur Adv Vult
4 JUDGMENT
5 In this case the plaintiffs claim agency commission. The parties entered into a written agency agreement on 16 June 1986 ("the agency agreement") by which the plaintiffs were appointed as exclusive agents of the defendants to sell the defendants' projects in the People's Republic of China and Hong Kong. The projects offered were the setting up of oil rigs.
6 The agency agreement required the plaintiffs to use their best endeavours to promote and extend sale of the defendants' projects. The plaintiffs had no authority to accept orders or to make contracts on behalf of the defendants except subject to confirmation and acceptance by the defendants. Clause 4 of the agreement, in which "BMEPL" stands for defendants, provided as follows :
7 4.1 In consideration of the services herein to be performed by the agent, BMEPL shall pay to the agent such commissions as the parties shall mutually agree in writing, on a case by case basis, such commission shall be due and payable to the agent even when the order is placed directly with BMEPL and not through the agent. In any event having regard to the non-exclusive nature of this agreement, commissions will only be due to the agent where the agent's interest in any particular contract or order has been acknowledged in writing by BMEPL and commission rate agreed.
8 4.2 The said commission shall be paid in United States Dollars within fifteen (15) days after BMEPL's receipt of payment from the buyers. Commission shall be paid in respect of only those invoices which have been paid in full by the buyers except that where payments for purchases are made in instalments the agent shall be paid a proportionate part of the commission on receipt by BMEPL of each such instalment.
9 4.3 No commission shall be paid by BMEPL in respect of bad debts or replacements made free of cost by BMEPL or on repairs.
10 4.4 No commission shall be payable to the agent in respect of any order received by BMEPL after the termination or expiry of this agreement howsoever caused notwithstanding that the agent may have been responsible for or concerned in the obtaining of that order and notwithstanding that quotations may have been submitted during the continuance in force of this agreement.
11 It would be apt to observe here that the agency agreement was made shortly after the incident on 4 June 1989 when the Chinese government used military force to quell a protest by demonstrators who demanded a more democratic system and voiced against corruption. Some 700 or more demonstrators died in or around the public square in Beijing - Tiananmen Square. There was international condemnation of the action against the demonstrators and in consequence economic sanctions were imposed against China. The evidence before the court showed that before the defendants could successfully secure any project they had to find the finance as the Chinese had no capital of their own and were either unwilling or unable to find it on their own. The imposition of economic sanctions made it extremely difficult to secure the required loan capital.
12 On 22 September 1989 the plaintiffs and the defendants entered into another agreement called the project agreement. Whereas the agency agreement was of a general nature, the project agreement related to a specified project identified as the Weizhou 11-4 and SZ 36-1 FPSU project. The project agreement provided that "Baker shall pay the agent a commission upon successful execution of the project in accordance with clauses 4.1, 4.2 and 4.3 of the agency agreement". The project agreement went on to provide further that "Baker shall pay the agent twenty (20) percentum of the agreed commission, thirty (30) days after being awarded the project. The balance shall be pro-rated in accordance with the agency agreement". The project agreement gives no elucidation of the expressions "upon execution of the project" and "after being awarded the project" which form part of it.
13 On 24 October 1989 the plaintiffs sent a fax communication to the defendants referring to the project agreement and further stated :
14 Should your quoted price need further reduction to maintain competitive we are willing to reduce the percentage on pro-data basic in accordance to your percentage reduced.
15 We look forward to secure the contract.
16 Then on 27 February 1990 the defendants signed two agreements with China National Offshore Oil Corporation ("CNOC"). One was called the Offshore Field Development Contract ("the OFD contract"). The other was the Crude Oil Repayment Contract ("the CSR Contract").
17 One of the recitals in the OFD contract stated that the defendants were willing to "provide funds to prepay for all the costs necessary for the WEI 11-4 Oil Field Development Project in such manner of sufficiency and efficiency in accordance with the terms and conditions of the CSR Contract and this Contract". Another recital declared that CNOC was willing to "sell crude oil to the defendants after production of Wei 11-4 Oil Field and repay the fund prepaid by the defendants by the crude oil sellings under the terms of this contract and CRR Contract". Further, the CSR Contract contained the following relevant provision:
18 4.6.1 30 days before this Contract is signed, the Company shall submit to the Contractor:
19 (a) Report on the WEI 11-4 oil field;
20 (b) Draft insurance policy to be taken on oilfield facilities.
21 4.6.2 30 days before this Contract is signed, the Contractor shall submit to the Company:
22 (a) Copy of the Mandate given to United Overseas Bank Limited to arrange for project financing;
23 (b) Copy of the Facility Letter by United Overseas Bank Limited for project financing.
24 It was clear from the above that CNOC was unable to procure the necessary capital by itself and the defendants had to procure it for them by way of a bank loan on terms acceptable to CNOC. The repayment of loans was by crude oil exchange.
25 The plaintiffs formed the opinion that they were entitled to 20% commission when the OFD and CSR contracts were signed. So on 6 March 1990 the plaintiffs sent the following communication to the defendants :
26 Further to our meeting yesterday, we are pleased to accept your proposal in accepting the fix commission at US$750,000 for the above captioned project.
27 Meanwhile, please forward to us by return fax/telex your confirmation of the 20% said commission - amount US$150,000.00 will be remitted to us 30 days after the official signing contract on 27.2.90 as per our contract agreement.
28 As there was no response from the defendants the plaintiffs on 27 April 1990 sent a letter which read as follows :
29 Further to our fax dated 6/3/90, we would like to have your acknowledgement and confirmation the below :
30 1) Fix commission at US$750,000.00 as agreed for the above captioned project.
31 2) The initial 20% of the commission payable after 30 day of the contract signing date. For which we have further extended 30 days is now due.
32 Your immediate response to the above would be highly appreciated.
33 This time the defendants responded as follows :
34 Yr fax 0531 dd April 27, 1990. We confirm that yr commission for the above captioned project is US$750,000 of which 20 percent will be paid in due course.
35 As explained Baker will endeavour to expedite yr payment. Presently due to the unexpected delay in our financing package, we will have to place our priority on financing the project kick-off ourselves.
36 We trust you will understand this and rest assured we will make appropriate transfer as soon as we could.
37 The plaintiffs were not pleased with the situation and expressed their dissatisfaction in a letter of 10 May 1990 which they sent to the defendants. It read as follows :
38 We are fully perturbed and concerned about the delay in Baker's finance package for captioned project.
39 As you are aware, we have taken our initiative in voluntarily reduce our commission from 1.25% to approximately 0.75%; which amounts to US$750,000. This big amount of savings for Baker clearly reflects our concern and contribution to reduce Baker's burden.
40 To follow up in this project from our end, we have incurred big expenses for the last many months. As a result, it has gone beyond our budget for this job, hence, we sincerely hope that you could remit immediately the agreed 20% of US$750,000.00 to our account as it is now 45 days overdue.
41 Your prompt attention to the above request is greatly appreciated.
42 The next important event occurred on 19 July 1990 when CNOC sent a communication to the defendants stating in effect that the defendants were responsible for providing funds for the WEI 11-4 project but they had failed to do so. The communication further stated that the defendants were also responsible for providing a bank guarantee within 30 days of the OFD contract and that they had failed to do so. The bank guarantee was in fact a performance bond required by CNOC. The communication went on to say that in view of the above it was impossible to carry out the two contracts any longer. So the contracts were terminated. On 1 August 1990 CNOC reaffirmed the termination. The plaintiffs received no commission. But the plaintiffs felt that they had a valid claim.
43 The plaintiffs in the circumstances set out above instituted this action on 30 November 1990. The plaintiffs in their statement of claim asserted that they "used their best endeavours to promote and/or procure and indeed successfully in or about the month of April or May 1990 promoted and/or procured the project." The statement of claim further asserted that the defendants by their telefax dated 27 April 1989 "duly confirmed and/or acknowledged and further agreed to the value of the commission at US$750,000 and that 20% thereof would be paid to the plaintiffs in due course". They finally said that the defendants "were breach in that they" failed, refused, and/or neglected to pay the 20% of the US$750,000 amounting to US$150,000 within 30 days from the date on which the project was awarded i.e. in or about the month of April and/or May 1990. The plaintiffs made no claim for the 80% balance of the commission because that had not fallen due.
44 The principal defence is one of denial. The plaintiffs therefore had to prove their case. Specific reference was made to the provision in the project agreement that commission would be payable "upon execution of the project". The defence further made reference to the agency agreement and stated that commission was payable "15 days after the defendant's receipt of payment from the buyers". On their letter of 27 April 1990 they said that their liability to pay any commission was subject to the terms of the agency agreement. They finally said that on or about 19 July 1990 the project was terminated and they did not any time receive any payment pursuant to or under the project.
45 The only issue raised by the pleadings was whether there was an agreement to pay a commission of US$150,000 that is 20% of US$750,000. According to the plaintiffs a project was awarded to the defendants and its value was US$100,000,000. The documents before the court did not record this figure but it can be deduced from the correspondence and in particular the letter dated 10 May 1990 in which the plaintiffs stated that they agreed to "reduce their commission from 1.25% to approximately 0.75%; which amounts to US$750,000". When reversed this gives the value of US$100,000,000. The amount of US$750,000 was not in dispute. The real issue was whether the partial amount of US$150,000 commission was due and payable as alleged by the plaintiffs.
46 The first basis of the plaintiffs' claim was that the defendants had agreed to pay the commission of US$150,000 and that this was evidenced by the plaintiffs' communications of 6 March 1990 and 27 April 1990 and the defendants' letter of 27 April 1990. It is axiomatic that for the plaintiffs to succeed on this ground they must prove the terms of the contract (the principle of certainty) and that the plaintiffs conferred some benefit to the defendants (the principle of consideration).
47 On the evidence before me, the first time a written reference to US$150,000 arose was on 6 March 1990 when the plaintiffs by a letter asked the defendants to "forward to the plaintiffs by return fax/telex your confirmation of the said commission - amount US$150,000 will be remitted to us within 30 days after the official signing contract on 27.2.90 as per our contract agreement". The defendants did not respond. This prompted the plaintiffs on 27 April 1990 to ask the defendants to confirm that commission was fixed at US$750,000 and that the interim commission of 20% was payable after 30 days of the signing of contract and which they had extended by 30 days. The defendants responded by their letter of 27 April 1990.
48 My construction of the letters is that the defendants were prepared to fix the quantum of total commission at US$750,000 but when and whether it was payable was left in a nebulous state. There was no certainty on this point. When the correspondence is read as a whole it is clear that much depended on the financial package and until that was finalised no commission would be payable. Hence the statement that "20 percent will be paid in due course" and the "concern about the delay in Baker's finance package". The words "in due course" put the matter in doubt. The very fact that the plaintiffs sought the defendants' confirmation that it was payable shows that there was no agreement. It was an attempt on the part of the plaintiffs to link the fixed commission of US$750,000 to the project agreement. In my view the true position is that there was no certainty of terms of agreement. There is no evidence, written or oral, to support the plaintiffs' contention that the defendants had agreed to pay 20% of US$750,000 within 30 days after the signed the OFD and the CSR contract on 27 February 1990. The plaintiffs' unilateral and self-serving statements made well after 27 July 1990 that the US$150,000 was due 30 days from 27 February 1990 and overdue cannot improve their position for they must show by evidence of contemporary facts that there was a clear agreement before it was breached.
49 On the question of consideration, the first point to note is that the plaintiffs failed to expressly plead the precise consideration for the alleged agreement under which commission was payable 30 days from 27 February 1990 which was based on the defendants' letter two months later. What was the consideration which moved from the plaintiffs to the defendants on 27 April 1990 to support a commitment to pay commission 30 days from 27 February 1990? I can find none. This was the major obstacle against them. It was not a technical failure for it went to the root of the problem.
50 The second ground of the plaintiffs' claim was stated in their written submission was that "the defendants were awarded the project when they signed the CSR contract and the OFD contract on 27 February 1990 and therefore the 20% agreed commission was payable 30 days thereafter i.e. after 28 March 1990".
51 But the plaintiffs in their statement of claim had taken a very different position. In paragraph 4 of their statement of claim they said that "in pursuance to project agreement dated 22 September 1989 the plaintiffs used their best endeavour to promote and/or procure and indeed successfully in or about the month of April or May 1990 promoted and/or procured the project". And in paragraph 5 they asserted that the date on which the project was awarded was "in or about the month or April or May 1990" and not on 27 February 1990. The pleadings do not say how the project was awarded in April or May 1990. The plaintiffs never explained this contradiction and the uncertainty. I was led to the inevitable conclusion that no agreement to pay US$150,000 was concluded on 27 February 1990 or in April or May 1990.
52 The defendants, on the other hand, said that the project was never awarded and that on or about 19 July 1990 the project was terminated when the defendants received a communication to that effect from CNOC. The defendants explained that the reason why the financial package could not be secured was because of the Tiananmen incident and the imposition of economic sanctions. The plaintiffs agreed to a lower commission because of the difficulty faced by the defendants in procuring the financial package. Notwithstanding the plaintiffs' willingness to accept a reduced commission the defendants were unable to procure the bank loans.
53 Furthermore I was left in no doubt that the project was never awarded to the defendants and that the word "award" in this context meant that the defendants were placed in a position to be able to work on the project. That never happened because the defendants were unable to arrange the financing package which CNOC required before the project could be awarded to the defendants.
54 The plaintiffs argued that the question of prefinance was not pleaded. Technically that was true. It is not, in my view, necessary to rely on the financial package to find the fact that the project was never awarded to the defendants in the sense I have described. The financial package was inextricably linked to the award of the project to the defendants and the defendants should not be precluded from relying on it to challenge the plaintiffs' allegation that the project was awarded to them. In fact the plaintiffs themselves found it impossible to avoid referring to it in their correspondence.
55 For the reasons set out above the plaintiffs' claim is dismissed with costs.
G P Selvam J
Lawrence Hussein (Ng Thin Wah & Partners) for the plaintiffs
James Goon Hoong Seng with Cheah Kok Lim (Low Yeap & Co) for the defendants