In the Court of Appeal of the Republic of Singapore
[1994] SGCA 129
CA 19/1994
Between
Gunac Enterprises (Pte) Ltd
… Appellant
And
Utraco Pte Ltd
… Respondent
grounds of decision
Contract — Discharge — Breach

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Gunac Enterprises (Pte) Ltd v Utraco Pte Ltd
[1994] SGCA 129
CA 19/1994
Karthigesu JA; L P Thean JA; Yong Pung How CJ
17 November 1994
1 This was an appeal against the measure and quantum of damages allowed on a counterclaim for breach of contract as well as against the order as to costs. We allowed the appeal at the conclusion of the hearing and now give our reasons.
2 The material facts were not in dispute and were briefly these. The respondents were awarded a contract by the Singapore Sports Council to carry out some remedial works to the National Stadium (the Stadium). By a written agreement dated 19 December 1988 (the sub-contract), the respondents engaged the appellants as sub-contractors to supply waterproofing materials and apply protective coatings of such materials over the topside and the underside of the galleries of the Stadium (the sub-contract works). The sub-contract works as described in the sub-contract included, inter alia, the following:
(a) Application of Vibalastic Flexible Waterproofing Slurry/Vibacote TW to ... [topside of the galleries] ...
(b) Application of Vibacote TW to ... [underside of the galleries] ...
3 In February 1989, the appellants commenced work on both the topside and the underside of the galleries. In May 1989, a third of the topside work had been completed when the respondents terminated the appellants` work on the topside. The ground for the termination was that the materials supplied and applied were not the Vibalastic waterproofing slurry and Vibacote TW which had been contracted for but were materials manufactured by the appellants themselves. The appellants accepted the termination. However, the respondents did not terminate the work on the underside of the galleries and the appellants continued with the work and completed it in October 1989.
4 Following the termination of the topside work, the respondents were asked by their consultant to remove the defective coating applied by the appellants on the one-third of the topside area. That the respondents did. They then imported the necessary materials directly from the Swiss company, Vibak Bautenschutz (Vibak) and hired labour by way of a sub-contract to apply the materials on the entire topside area.
5 In April 1990, the appellants commenced an action against the respondents in which they claimed the sum of $25,555.36 being the balance owing to them by the respondents in respect of the work carried out on the underside of the galleries; they also claimed damages for the work done on the topside prior to the respondents` termination and damages for the wrongful termination of the topside work. The respondents denied liability, justifying the termination on the basis of the appellants` breach of the sub-contract. In the alternative, they pleaded misrepresentation. They also counterclaimed damages for breach of the sub-contract in respect of the topside work.
6 At the conclusion of the hearing, the trial judge found that it was a condition of the sub-contract that the materials to be supplied and applied by the appellants were to be the following products, namely, `Vibalastic Art 45.35` and `Vibacote TW art 20.42` (the Vibak materials) manufactured in Switzerland by Vibak. The materials supplied and used by the appellants were materials manufactured by the appellants themselves and not the Vibak materials. The appellants therefore had committed a breach of a condition of the sub-contract. The breach of this condition, the trial judge held, entitled the respondents to terminate lawfully the sub-contract in respect of the topside work. As such, the appellants` claim for wrongful termination failed. The trial judge allowed their claim in the sum of $25,555.36 for the underside work which was admitted at the trial by the respondents to be due and owing to them. Turning to the counterclaim, the trial judge, having found that liability for breach of the sub-contract had been established, quantified damages as follows. She found that the costs of removing the defective coating applied by the appellants on the one-third area of the topside had been proved and awarded a sum of $61,363.50, which comprised the following:
(i) labour costs $40,750.50
(ii) machinery costs $9,000.00
(iii) costs of miscellaneous tools, equipment and parts $11,613.00
Total $61,363.50
7 Next, the trial judge quantified the costs incurred in coating the entire topside area with the Vibak materials and arrived at the sum of $298,324.84. Under the sub-contract, the respondents would have to pay to the appellants the sum of $378,556.66 (the contract sum) for coating the entire area, if the work were carried out by them. The trial judge set off only the costs incurred for coating the entire area against the contract sum, and observed that by terminating the sub-contract and completing the topside work themselves, the respondents had saved $80,231.82. She therefore held that the respondents had suffered no loss and that no amount was recoverable under this head. However, she did not deduct from the contract sum the amount of $61,363.50, the costs of removal of the defective coating. Accordingly, she held that only the removal costs were recoverable as damages.
8 The final decision as reached by the trial judge was judgment for the respondents on the counterclaim in the sum of $35,808.14 with interest of 5% pa from the date of the defence and counterclaim. This sum was arrived at by deducting the claim of the appellants in the sum of $25,555.36 from the full amount of counterclaim in the sum of $61,363.50. As regards costs, the trial judge awarded only one set of costs as the claim and counterclaim were closely related. She awarded 80% of the costs to the respondents.
9 Before us, counsel for the appellants accepted the quantification of the removal costs in the sum of $61,363.50 as well as the costs of coating the entire topside area in the sum of $298,324.84. His only complaint was that the costs of removal were a part of the rectification works carried out by the respondents consequent on the breach of the sub-contract by the appellants and therefore should have been added to the sum of $298,324.84, the costs of coating the entire topside area, thereby making a total sum of $359,688.34, and that sum represented the total expenditure incurred by the respondents in making good the work which the appellants had failed to carry out under the sub-contract. The difference between this total sum and the contract sum is the measure of loss suffered by the respondents. As the total sum is less than the contract sum, no loss had been suffered by the respondents; in fact, the respondents had saved $18,868.32 by terminating the sub-contract in respect of the work on the topside.
10 On the other hand, counsel for the respondents submitted that the removal costs were properly allowed as a separate head of damages in the counterclaim and such costs should not be deducted from the contract sum. His reasoning was as follows. The loss suffered by the respondents flowed from two separate and distinct breaches of the sub-contract. The first was a breach of the contractual condition to supply and apply the Vibak materials. The second was a breach of a contractual term. The trial judge found that it was a term of the sub-contract that the coating materials to be used on the topside area had to possess specified physical and chemical qualities. The appellants were in breach of this contractual term in that the materials manufactured by them did not satisfy the contractual specifications. The cost of the removal of the defective coating on the one-third of the topside area flowed solely from the appellants` breach of this contractual term, and not from the breach of the condition to supply and apply the Vibak materials. The costs incurred by the respondents in applying the Vibak materials to coat the topside area flowed from the breach of that condition, and only these costs should be set off against the contract sum; after all, the contract sum was for the supply and application of the Vibak materials to the topside area. Hence, the costs of removal of the defective coating on the one-third topside area was separate and should not be included in the amount to be deducted from the contract sum.
11 We were unable to accept such arguments advanced on behalf of the respondents. The basic position is that damages in a contractual claim are compensatory and protect the innocent party`s expectation interests. Damages are not meant to enrich the innocent party. As far as possible, the innocent party is to be put in as good a position as if the contract had been performed. The respondents had to rectify the unfortunate situation occasioned by the appellants` breach of the sub-contract. To this end, the respondents had first to remove the defective coating on the one-third of the topside area and thereafter to apply the Vibak materials on the entire topside area. The total cost for such rectifications came to $359,688.34 (ie $61,363.50 plus $298,324.84) and that was the total expenditure incurred by them. As against this total sum must be set off the contract sum, which the respondents would have paid, had the appellants carried out the entire topside work in accordance with the sub-contract. Put shortly, the measure of loss of the respondents was the costs of the rectification incurred minus the contract sum avoided and that represented the respondents` pecuniary loss. On the facts, the costs of the entire rectification required to put the respondents in as good a position as if the contract had been performed included both the costs of removing the defective coating applied by the appellants and the costs of coating the entire topside area with the Vibak materials, less the contract sum the respondents avoided paying. We therefore agreed with the appellants that the removal costs ought to have been added to the costs of coating the entire topside area to obtain the total costs of rectification and the total of these costs ought to have been deducted from the contract sum. On this basis, the respondents had not suffered any loss.
12 Next, the respondents challenged the basis adopted by the trial judge in calculating the costs of coating the entire topside area of the galleries. At the trial, the respondents contended that to coat the topside area would cost $8.89 per square metre on the basis that for each square metre of the galleries, the estimated material cost was $6.89 and the labour cost was $2. Such a method of calculation was dismissed by the trial judge as `purely theoretical`, and, in our view, rightly. The respondents were entitled to expect a sufficient supply and application of the Vibak materials on the topside area. According to their estimates, 15,722.08 kg of Vibalastic and 36,684.85 kg of Vibacryl (a material recommended and used for the rectification works) would be needed. However, in actual fact, only 14,000 kg of Vibalastic and 22,750 kg of Vibacryl were imported and used as shown by the documents produced. The trial judge`s calculation of the costs was based on the costs of materials supplied as evidenced by the invoices produced in court and the costs of the labour actually hired for the purpose. The trial judge said:
In my judgment, the way to assess whether or not the defendants [ie the respondents] suffered any loss by reason of the fact that they had to coat the topside of the entire Stadium (ie the uncompleted two-thirds plus the area done by the plaintiffs) is to calculate their cost of doing so on the basis of the documents which they produced in court in proof of the expenses incurred. Since the defendants were able to produce only three invoices from Vibak, they must be taken as having used only the material reflected in those invoices in their coating works. On that basis, the defendants` costs of materials would have amounted to $181,689.16 for the Vibak materials and another $10,000 for the sand and cement sourced locally (on the basis of 0.28 cents per kg ...) Their labour costs for the coating would have been $2 per square metre (on the basis of an invoice from the labour sub-contractor) giving a total of $106,635.68 for the 53,317.84 square metres of the stadium. The total costs incurred were therefore $298,324.84.
13 The trial judge was wholly correct in adopting this approach in the quantification of the costs of coating the topside area with the Vibak materials.
14 Accordingly, we allowed the appeal and gave judgment to the appellants in the sum of $25,555.36 with interest of 5% pa from the date of the writ. With regard to the counterclaim, as the respondents had not suffered any damage, we awarded to them nominal damages in the sum of $10. On the question of costs, having taken into account the entire course of the proceedings below and the outcome of the appeal, we ordered only one set of costs here and below to the appellants.
15 Appeal allowed.
Karthigesu JA
L P Thean JA
Yong Pung How CJ
HE Cashin and Tan Siak Hee (SH Tan & Associates) for the appellants
Muthu Kumaran and Andrew Tan (WT Woon & Co) for the respondents