Teknikal dan Kejuruteraan Pte Ltd v Resources Development Corp (Pte) Ltd
[1994] SGCA 80
CA 202/1992, 3/1993
Warren Khoo L H J; Rajendran S J; L P Thean JA
26 May 1994
1 Cur Adv Vult
2 These appeals arise from a claim by the appellants against the respondents for wrongful termination of a contract to work a granite quarry on Pulau Ubin. One is on the substantive claim, and the other on a procedural matter.
3 There was a building boom in Singapore in the late 1970s and early 1980s This resulted in an increased demand for granite products for use in building construction. The respondents, Resources Development Corp (Pte) Ltd (RDC), who were suppliers of granite products, wished to expand their operations. They had quarries in various parts of Singapore, including one on Pulau Ubin. They were given a lease of another quarry site there by the government, and they contracted to buy a new crusher plant from a Japanese supplier for the purpose of turning granite blocks to be quarried from this quarry into granite products.
4 RDC had to look for experienced quarry contractors to develop the quarry site and then to extract the granite. Sykt Teknikal dan Kejuruteraan Sdn Bhd (hereinafter `STDK`), a company incorporated in Malaysia, had such experience in Malaysia. They were operating a quarry in Rawang at the time. By a letter of acceptance dated 8 May 1981, their tender was accepted by the RDC. The appellants, `TDK`, were incorporated in Singapore for the purpose of carrying out the contract. By a novation agreement dated 31 July, TDK were effectively substituted as the contractors.
5 The contract entailed heavy investments by TDK and their shareholders. The principal sum for the leasing of equipment from RDC by TDK alone was about $6.6m and interest payments were nearly as much. The leasing arrangements were secured by a debenture over 70% of the net worth of the company. Shareholders had to provide additional collaterals. In the end, because of the difficulties to which we shall refer, the contract was terminated almost a year to the day it was awarded, and the company was wound up and the shareholders also lost everything they had put into this venture.
6 The site, of about 35 acres, was a hill covered with rubber trees and thick undergrowth. The rock formation from which the granite was to be quarried lay under this cover, which is known in the trade as the overburden. The overburden would include boulders as well as earth and vegetation. The boulders, although of granite, are to be distinguished from the underlying rock formation which would form the quarry proper.
7 In order to get at the granite it was necessary for the overburden to be removed. The overburden had to be removed to create a bench - a working surface upon which operations could be carried out. It appears that the creation of a bench with sufficient proximity in depth to the granite was important for the drilling and blasting operations to remove the granite. The bench also facilitated the movement of men and machinery for these operations as well as the transportation of the granite out of the quarry to the crusher plant. Hence the location of granite deposits in terms of proximity to the surface was vital to the production of granite from the quarry.
8 Tenderers were offered two alternatives in respect of the removal of overburden. Alternative A provided for RDC to clear an initial area of 10 acres of overburden, and for the contractor to clear the remaining contract area as quarrying progressed. Alternative B provided for RDC to clear the initial area as well as the remaining area. Under either alternative, RDC were responsible for clearing the earth to within 1m of the rock surface as far as possible. It appears to be common ground that because of the undulating surface of the underlying rock, it was not expected that the overburden would be cropped to a uniform depth of 1m as that might hinder rather than help the establishment of benches. But on average, the depth should be about 1m. Hence the words `as far as possible`.
9 The contract area was referred to at the trial, and is referred to in this judgment, as area A. The initial area was and is referred to as such.
10 STDK opted for alternative A. That alternative, which was contained in cl 4 of the specification, provided as follows:
Alternative A
RDC will clear an initial area of overburden as shown in the drawing RDC/QO-PU/1A. As quarrying proceeds, TDK shall be responsible for the continual removal of overburden to a minimum distance of 10m back from the quarry face and form slopes of 1:1. The rock surfaces shall be kept bare and this condition must be maintained and kept well ahead of any rock extraction of the quarry face. TDK is also responsible to remove any boulders that may be encountered in the overburden removal. This condition of the overburden to be removed within 10m from the quarry face shall be maintained up to the end of the contract.
11 In the initial removal of overburden by RDC, RDC will clear the earth to within 1m of the rock surface as far as possible. TDK shall be responsible for the removal of whatever [is] left over and shall allow for the cost of such expenditure in his tender rate.
12 Other relevant provisions of the contract
13 The contract provided that TDK would carry out and be responsible for the following works:
(i) Development of quarry face.
(ii) The continual removal of overburden.
(iii) The quarrying of granite and transportation to the crusher plant.
(iv) The operation and maintenance of the 500 tonnes per hour granite crusher plant (including supply of spare parts).
(v) Stockpiling of the products as and when required by the company.
14 The duration of the contract was expressed to be for a term of three years from 1 June 1981 to 31 May 1984. The date for possession of the site was expressed to be from 1 June 1981.
15 The contract stated that the plant was expected to be commissioned in August 1981. It provided that before the plant was operational TDK should carry out preparations such as developing the quarry face, the roadway and the stockpiling of granite blocks. It provided that after the commissioning of the plant, the minimum production of the granite products, described as 20-6mm chips and -5mm granite dust, should be as follows:
First month: 30,000 tonnes per month
Second month: 50,000 tonnes per month
Third month: 70,000 tonnes per month
From fourth month onwards: 100,000 tonnes per month
16 The contract was expressed to be a rated contract; TDK were to be paid $8.40 per tonne of the product. The contract provided for the imposition of liquidated damages at the rate of $8 per tonne `for production volume of less than 100,000 tonnes`. The contract reserved to RDC the right to increase or reduce the quantity of granite produced, by giving to TDK one month`s advance notice.
17 Some relevant events
18 In March 1981, RDC awarded to Chuan Joo Pte Ltd a contract for the removal of the overburden in the initial area. Chuan Joo were to commence the work on 12 April and to complete it within 18 weeks. That would take it to about the middle of August. In June, TDK moved some equipment and men on site to do preparatory work. At this time, Chuan Joo`s sub-contractors were still doing their overburden removal work in the initial area. They remained there until September.
19 Soon after TDK moved on site, they complained about the state of the excessive amount of overburden left by the earth contractors and about the problem this had created for them in terms of planning of work. In their letter to RDC dated 17 August 1981, TDK said:
Stripping of overburden
We have noted that the stripping operations have not been completed to date and in view of the differences in depth of overburden indicated by seismic survey presented to us during time of tendering and actual depth encountered while stripping and tested by our drilling machines, we have found it very difficult to plan our quarry benching operations to date.
20 We feel we actually have to reorientate our initial extraction area to work in with levels established by the earthwork contractor in order to save time and to avoid causing hindrance to earthwork operation.
21 We also note with dismay by our drilling tests that overburden depths given by seismic indications are totally out and much greater depths have to be stripped before rock formation is encountered. This will definitely delay rock output production and much higher operating costs. We hope RDC will view this problem of ours with sympathy and due consideration for assistance.
22 It is clear from the contents of this letter and its date that TDK were referring to the overburden in the initial area.
23 Later in a letter dated 19 November 1981 to RDC, TDK elaborated on the matter further as follows:
It was a condition of the contract that initial stripping of overburden within an area indicated on the plan would cover approximately 10 acres to a depth of about 1m from rock surface.
24 This operation commenced in early June and when stopped in late September we were left with not an area of rock hill to work on but an area clustered and scattered with boulders of approximately 40ft in height and narrow. We need an average of three to four months to clear this area full of boulders whose total tonnage is estimated at 60,000 tonnes. The existence of these unusually huge and narrow boulders which we have never encountered anywhere in our quarry operations before, have completely upset our development plan for the area.
25 Also when the stripping operations stopped at the level indicated by seismic survey given to us during tender period, we were left with an area which needed a further stripping of overburden to be carried out to over 40ft within the stripped and also surrounding areas as tested by our random drilling to ascertain rock level.
26 Hence the contract condition of stripping the overburden to within 3ft of rock surface for us has never been fulfilled by RDC. We are in no position to strip this extra and excessive overburden.
27 We are now concentrating on blasting off the boulders which are now lying all over the initial area.
28 We shall refer further to these letters in due course.
29 At this point, we should say something about the seismic survey referred to in these letters. This had been done by a newly-established specialist firm as part of the feasibility study. Its purpose was to show the depths of the overburden in area A and to enable an estimate to be made of the amount of rock available underneath. With the help of the results of this survey, RDC`s consultant, one Mr Parton, made estimates of the amount of rock available and proposals for the development and operation of the quarry. It was not part of the documents supplied to tenderers, but TDK had obtained a copy of it from Mr Parton after they submitted the tender.
30 The importance of the seismic survey in the context of the overburden problem is that it appears from a letter dated 18 August 1981 from Chuan Joo to RDC, which we shall refer to further later on, that on one view of the contract between RDC and Chuan Joo, Chuan Joo were to remove the overburden to depths determined by the seismic survey. If the seismic survey levels were inaccurate in that the underlying granite formation was deeper than indicated by the seismic survey, there would correspondingly be that much more overburden left unremoved by Chuan Joo proceeding according to the seismic survey.
31 TDK say that as a result of these problems, RDC offered another site, known as area B, to TDK, in addition to area A. TDK accepted this and moved to area B on 11 August 1981, while continuing to try to work area A.
32 In September, RDC were interested in another granite product, referred to as crusher run, of a different specification (3"-6") from those of the products in the original contract. TDK agreed to do this work at a separately negotiated rate, and to do it for a period of six months from October 1981 to March 1982. This is evidenced in minutes of a site meeting on 17 September 1981. It was also agreed at that meeting that the production targets for TDK would be as follows:
September 1981 - 10,000 tonnes
October 1981 - 35,000 tonnes
November 1981 - 60,000 tonnes
December 1981 - 85,000 tonnes
January 1982 - 120,000 tonnes
33 We have to add at this point that in RDC`s subsequent letter of 6 May 1982 threatening termination of contract, it was said that the production quantities required were as follows:
October 1981 - 30,000 tonnes
November 1981 - 50,000 tonnes
December 1981 - 40,000 tonnes
January - (not stated)
February onwards - 100,000 tonnes
34 It is not known how these figures came about.
35 There is dispute as to whether the crusher plant was properly commissioned. However, it is not disputed that some test runs were undertaken, and the plant was handed over to TDK around the beginning of September. Small amounts of granite were produced in September and October.
36 On 7 November 1981, there was a blasting incident in which a rock fragment from a boulder in the initial area landed on a house nearby. The authorities would not allow TDK to continue blasting in this area unless a 30-ft high fence was built around the house. In the event, TDK did not build such a fence, or buy up the house as they hoped to, and work in area A effectively stopped from the date of the incident and was never resumed. TDK continued to work area B, and in the following months before the contract was terminated such granite production as there was came from blasting boulders in that area.
37 The production targets, either as stipulated in the contract or as varied by the agreement stated in the site minutes of 17 September 1981, were never reached. Production stopped altogether at the beginning of May 1982.
38 At site meetings, TDK were warned of the imposition of liquidated damages and the termination of the contract if the production figures did not improve. On 6 May 1982, RDC wrote a formal letter referring to TDK`s consistent low production and gave notice pursuant to cl 35 of the specification that if TDK continued to be in default, RDC would exercise their right to terminate the contract.
39 This was followed by several other letters, all calling upon TDK to improve the position and reminding TDK of the consequences of their failing to do so. On 12 May 1982, TDK wrote to RDC. In their letter, TDK referred to RDC`s breach of their obligation to remove the overburden in the initial area to within 1m of the rock surface. TDK said that as a result of this, RDC were in breach of their obligation to hand over the contract area in accordance with the contract, and that this breach went to the root of the contract. They also gave notice of their intention to rescind the contract unless possession of the site in accordance with the contract was given to them within 30 days.
40 On 18 May 1982, RDC replied to TDK`s letter, denying liability. We shall refer to this reply in due course. There followed some more letters from RDC complaining about TDK having stopped production. Finally, by letter dated 28 May 1982, RDC gave notice of termination of the contract with immediate effect, and required TDK to vacate the site. On 11 August 1982, TDK commenced action.
41 The overburden problem
42 There were several issues raised before us. It seems to us that it is necessary to deal with only one, that is whether RDC had fulfilled their obligation in relation to the removal of the overburden in the initial area. This is an important issue and it is necessary to deal with the evidence at some length.
43 As stated earlier, in March 1981, RDC had awarded to Chuan Joo Pte Ltd a contract for the removal of the overburden in the initial area. It was for a lump sum of $1.93m. The contract expressly required the contractor to expose all granite formation. However, the estimated quantity of the overburden to be removed was stated to be 495,000m3, which was stated to be a rough estimate based on the seismic survey. The contract provided that the amount of work could be increased or reduced on the direction of the superintending officer and it provided for the contract sum to be adjusted in accordance with a schedule of rates annexed. The contract required Chuan Joo to remove any boulders encountered.
44 From the evidence of RDC`s witnesses, it appears that more than one view was taken by them as to how much work Chuan Joo were required to do for the lump sum of $1.93m. The first view was that they were to do as much work as was necessary to expose all the granite formation in the initial area regardless of the amount of overburden that had to be removed. The second view was that they were to do only the estimated quantity of 495,000m3 regardless of whether any or all of the rock surface was exposed. The third view was that they were to excavate only down to the level as shown in the seismic survey regardless of whether the estimated quantity of 495,000m3 was achieved and regardless of whether the rock bed was exposed.
45 RDC appear to have taken the second view. Mr Lam, their quarry manager at the time, said that the contract was to remove about 500,000m3 of overburden for the lump sum of $1.93m. He told the court that as the amount of the overburden removed by Chuan Joo fell short of the 495,000m3 provided in the contract, Chuan Joo were required to make up the balance of the work by excavating another small area nearby outside area A.
46 Chuan Joo seem to have taken the third view. This is shown as follows. On 18 August 1981, when work had been done to a certain level, Chuan Joo wrote to RDC informing them that the excavation work had been carried out and that the major part of the work had exceeded the seismic level. Chuan Joo also requested RDC to let them know whether they were required to dig any further. Chuan Joo said :
Please note that for excavation work exceeding seismic level, a new rate shall apply. This is because excavation work exceeding seismic level is no longer considered as bulk excavation but is trench excavation.
47 Chuan Joo`s view, as shown in this letter, however, was not one shared by the sub-contractor engaged by them to perform the contract. Mr Loh Teck Lok, the sub-contractor, said that, as he saw it, the contract required him to remove all the overburden to expose the rock surface in the initial area. He added, for good measure, that no matter how much had to be removed, even if he had to remove twice the estimated quantity of 495,000m3, it would still be part of his job. So he appears to have subscribed to the first view. But he later retracted and agreed with counsel that the contract required him only to remove about 495,000m3.
48 Just as there was confusion as to scope of the overburden removal contract, there were confusion, ambiguities and contradictions in RDC`s evidence as to how much overburden had in fact been removed and how much was left in the initial area. Mr Lam in examination-in-chief said that, after Chuan Joo had finished work in the initial area, about 50-60% of the area had the rock surface exposed. In an apparent reference to TDK`s Mr Ong`s evidence (of which more later) that when Chuan Joo purportedly completed their work, there was a lot of burden left, in some places more than 40ft deep, Mr Lam added, somewhat equivocally:
If the remaining area still had overburden of many metres, it would not interfere with blasting of exposed area ... .
49 Apart from this, Mr Lam said nothing specific about the state of the remaining 40-50% of the initial area. It was only at the very end of his evidence, in answer to questions of the court, that he said:
About half the initial had exposed rock, ie little or no overburden. The other half had 1m or less of overburden. So for the first half we can see the rock but I cannot say that there was totally no earth. For the second half, excavation had reached rock, and depth of overburden was less than 1m.
50 Mr Lam did not give any reason for his evidence regarding the depth of the remaining overburden in the `second half` of the initial area; he did not explain the basis for his statement that it was less than 1m deep.
51 Mr Loh Teck Lok, Chuan Joo`s subcontractor, testified that he had done what the contract required Chuan Joo to do, ie to expose the rock surface of the entire initial area. He said:
We spent less than four months doing work in the contract area. At end of period, we saw jagged rocks. The whole area became exposed rock surface.
52 Chuan Joo`s letter of 18 August 1981 to RDC, referred to a moment ago, shows that there was still a substantial amount of overburden to be excavated even though the excavation had reached or even exceeded the seismic level. No one from Chuan Joo gave evidence, although Chuan Joo had been served with a subpoena. Mr Lam, when referred to this letter, said that RDC accepted that Chuan Joo had done what the contract required them to do in the initial area, and they were told not to excavate any more in that area.
53 The plaintiffs` evidence
54 Mr Ong Teng Leong, the managing director of TDK at the time, gave evidence for TDK. He told the court that only part of the initial area had been stripped by Chuan Joo. Of the part that had been stripped, TDK`s drilling tests showed that there were places where the overburden was so deep that the 40-ft drill which was used could not reach rock. In those places where the drills did reach rock, the depth was more than 1m. He produced a plan (exh P-2) which he had prepared in February 1986 based on data in TDK files of drillings done in September 1981 soon after Chuan Joo left the site. This plan was annexed to the further and better particulars of TDK`s statement of claim filed in June 1986.
55 Mr Ong also gave evidence that Chuan Joo left a lot of boulders which they should have blasted and removed. He told the court that because this should have been done by Chuan Joo and not TDK, RDC agreed to pay TDK separately for this work at the rate of $40 per m3. This evidence is supported by minutes of a site meeting held on 10 September 1981.
56 Mr Ong testified that because of the problem with the presence of this excessive overburden, progress in the development of the quarry was slow. Up to July, there was no bench anywhere which was 1m from rock. In August, he was still complaining about difficulty in planning the benching operations. Because of this RDC requested TDK to move to area B, which they did on 11 August, as stated above.
57 But area B was three times as far as area A from the crusher plant, resulting in increased haulage cost. It was also a very small area, no more than 5 acres, compared to area A`s 35 acres. There was also overburden there of unknown depths, including boulders; no seismic survey had ever been done there.
58 Mr Ong said that after the move to area B, most of TDK`s work was concentrated there, although some work appears to have continued in area A. However, TDK never reached the rock formation underneath in either area. Such granite as they were able to produce until they gave up the contract in May 1982 all came from blasting boulders, instead of from the rock formation below as contemplated by the contract.
59 Mr Ong`s evidence was no afterthought. He was the writer of the two letters, dated 17 August 1981 and 19 November 1981, referred to earlier in this judgment.
60 RDC did not respond to TDK`s letters. Mr Lam explained that he was busy, being on the site every day, and that there were regular site meetings at which such problems would have been dealt with. However, a perusal of the site meetings minutes shows that there is no record of anything said about TDK`s complaints. Although TDK`s letters raised doubts about the correctness of the seismic survey, Mr Lam told the court that RDC decided that it was not necessary to refer them to the specialist firm which RDC had engaged to do the survey.
61 It was only when the dispute came to a head that RDC attempted to provide some answer to TDK`s allegations about the excessive overburden. In a letter dated 18 May 1982, RDC referred to STDK`s letter dated 2 April 1981 submitting the tender in which STDK had stated:
Overburden removal
We undertake to execute the work of removal of overburden and will take over this operation as soon as our machinery for stripping of overburden arrives at worksite - ie within four months from date of acceptance of our offer.
62 On the basis of that, RDC took the position that it was not their obligation, but TDK`s, to remove any overburden in the initial area. In their letter of 18 May 1982, RDC said:
Notwithstanding that and in order to assist you ... we removed approximately 500,000m3 of overburden and exposed about 10,000m2 of quarry face to facilitate your production of rock.
63 At the trial, RDC conceded in evidence that the part of the TDK letter dated 2 April 1981 set out above did not form part of the contract. The learned judicial commissioner on his part held that this part of the letter did not dispense with RDC`s obligation under the contract to remove the overburden to within 1m of the rock surface.
64 As to the reason for the move to area B, RDC in the same letter of 18 May 1982 said that the move was because of the blasting incident. This is demonstrably untrue, as the accident took place on 7 November, whereas the move to area B had taken place on 11 August.
65 How overburden issue was dealt with
66 The learned judicial commissioner dealt with the evidence in regard to the overburden issue as follows. Firstly, he said that TDK relied heavily on exh P-2. He said that Mr Ong had prepared this plan on the basis of information given to him by Mr Wong Sin Fu, the former general manager of TDK, and Mr Wong`s information was based on data from TDK`s records. This made the information contained in P-2 hearsay evidence, and in the absence of Mr Wong as a witness he was not prepared to place much reliance on it even if it was admissible. He also said that he was entitled to draw an adverse inference against TDK for failing to call Mr Wong as a witness.
67 Secondly, he was doubtful of Mr Ong`s personal knowledge of the matter. He relied on the evidence of Mr Lam and Mr Fong, another witness for RDC, that they hardly saw Ong on the island.
68 Thirdly, he found RDC`s witnesses` evidence more persuasive. He relied particularly on the evidence of Loh, describing him as obviously a candid, if reluctant, witness. He found that Mr Loh had completed the clearance of the overburden to within 1m of the rock surface. He referred to photographs produced by RDC and found that they showed `relatively large` areas of exposed rock available for quarrying in October 1981.
69 The learned judicial commissioner concluded that TDK were not able to prove their allegation that the initial area had not been substantially cleared of overburden to the required depth. He held that RDC were not liable for breach of their contractual obligations.
70 Our views
71 The issue turns on a finding of fact whether RDC had caused to be removed the overburden in the initial area to the extent required by the contract between TDK and RDC.
72 The principles governing the review by an appellate court of findings of fact of the trial court are well established. The issues before us concern to an extent the evaluation of the quality of the evidence given by RDC`s witnesses. The evaluation involves testing a witness`s evidence against inherent probabilities or against uncontroverted facts, including the conduct of the parties at the relevant time. We are in this instance in as good a position as the court of first instance, although we must, where appropriate, give due allowance to the fact that we have not had the advantage of seeing the witnesses that the trial court had. Proceeding on this basis, we would make the following observations.
73 Firstly, it seems to us that Loh`s evidence that he had removed all the overburden in the initial area to the extent of exposing the underlying rock formation over the entire initial area was obviously highly exaggerated. Apart from the fact that he contradicted himself, his evidence did not square with other evidence that had been produced. It went against the evidence, prevaricating though it was, of Mr Lam. It did not square with Chuan Joo`s letter of 18 August indicating that the excavation had only been carried out to about the level indicated by the seismic survey. It also did not tally with the fact that, as late as September, Loh was still on site, blasting boulders and also the fact that TDK was also blasting boulders on a separately negotiated rate with RDC.
74 Secondly, in regard to Lam, there was an obvious shift of position between what he said in examination-in-chief and what he said at the very end of his evidence in answer to questions of the court. If it was true that the overburden in the initial area had been stripped to rock surface or within 1m of it, it is somewhat strange why Lam should have been so tentative about this point when first giving evidence.
75 Thirdly, and generally, it seems to us that the evidence of the witnesses should be weighed and tested against indisputable facts and contemporary documentary evidence, and against inherent probabilities. An important fact in this connection is the move to area B. It seems to us that if either Mr Loh`s or Mr Lam`s evidence is correct as regards the extent of the overburden removal, there would hardly have been any reason for this move. RDC`s answer on this point was that TDK did not have enough men and equipment and production was too low, and that the move was to help TDK increase its production. This explanation does not make sense. Area B was a virgin area, covered with overburden of unknown depths. It would have taken time to remove it. Furthermore, area B was three times as far from the crusher plant as area A, and it was also a very small area, compared to area A. If indeed TDK were short of manpower and equipment, surely it would have been more sensible to carry on in area A, if area A had indeed been cleared of overburden to the extent contended by RDC.
76 In RDC`s letter of 18 May 1982, RDC gave the explanation for the move to area B that it was due to the blasting incident. As pointed out earlier, this is patently untrue.
77 There can be very little doubt, it seems to us, that the move to area B was solely necessitated by the fact that the overburden in the initial area had not been cleared to anything like what the contract required. The fact that RDC had to agree to pay TDK for blasting boulders in the initial area as late as September also provides support to TDK`s case that the overburden had not been cleared to the extent required by the contract.
78 The conduct of RDC throughout hardly adds credit to their position. They did not answer the letters of TDK of 17 August and 19 November 1981. When they did deal with the matter in their letter of 18 May 1982 they took a rather incredible position that they had had 500,000m3 of overburden removed to assist TDK. It is hard to imagine why RDC`s management would have agreed to spend nearly $2m to assist TDK without any apparent quid pro quo.
79 In any event, the position that RDC had no contractual obligation to remove any overburden in the initial area, although maintained for a time into the trial, was abandoned in favour of the position that RDC had a contractual obligation but they had fulfilled it. Mr Lam, whose evidence on the point at first was tentative, took a position at the end of his evidence consistent with this new case.
80 A final point to be made about RDC`s position is this. Since it was their position at the time that they were under no such contractual obligation, it is more likely than not that they did not make any attempt to fulfil it.
81 In contrast, the evidence of Mr Ong appears to have been quite straightforward and consistent throughout. Quite apart from exh P-2, which the learned judicial commissioner rejected as hearsay, Mr Ong gave his own oral evidence about the presence of the overburden in the initial area and the difficulties this posed to TDK in the planning and execution of the works. Mr Ong was a mechanical engineer with substantial experience with granite quarries in Malaysia. Presumably, he was knowledgeable enough to testify on this point. His evidence is consistent with, and explains, the move to area B. It is corroborated by his contemporary letters detailing TDK`s complaints about the overburden problem. It is corroborated by Chuan Joo`s letter of 18 August 1981, and what took place between RDC and Chuan Joo following this letter. It is corroborated by the fact that, even as late as September, the earth sub-contractor Loh was still on site and there was still boulders to be blasted, and by the unchallenged evidence that all the granite which TDK had been able to produce until they gave up the contract had come from blasting boulders rather than working the underlying granite formation.
82 It seems to us that once the oral evidence adduced on behalf of both parties is weighed and tested in this manner, RDC`s contention that they had removed the overburden to the extent required by the contract cannot stand. The irresistible conclusion is, and, we say with respect, should have been, that RDC left such a large amount of overburden in the initial area as to make it impossible for TDK to do any meaningful quarry development work.
83 The consequences
84 As stated above, the contract required TDK to commence production in August, after the commissioning of the crusher plant. Within the first month of operation, that is to say in September, TDK was required to deliver 30,000 tonnes of the product, and thereafter in progressively larger quantities until the target of 100,000 tonnes a month was reached. The obligations were reinforced by the provision for the payment of liquidated damages for any shortfall in performance. As stated above, the contract provided for possession of site on 1 June. It is clear that it required RDC to prepare the initial area in the manner stated in alternative A so that TDK could commence development work and in due course produce the tonnages required.
85 In speaking about possession of site in a building contract, Vaughan Williams LJ in Wells v Army and Navy Co-operative Society , said:
If in the contract one finds that the time is limited within which the builder is to do the work, that means, not only that he is to do it within that time, but it means also that he is to have that time within which to do it.
86 What was said in that case aptly applies to the case at hand.
87 There is a general obligation on the part of the employer not to prevent the performance of the contract by the contractor. The obligation to give possession of the site at the time provided by the contract is part of this general obligation. Conversely, the contractor has the right to carry out his work in the order he chooses. A failure to give possession of the site in accordance with the contract may amount to an interference with this right.
88 In this case, the purpose of the provision for the overburden in the initial area to be removed to the required extent by RDC was to give TDK on the date for possession a sufficient degree of possession of site to enable them to carry out the benching operations and other preparatory work so as to put them in a position to extract granite blocks from the rock formation (as opposed to the boulders) below in time to feed the crusher plant when it was handed over to them after commissioning in August.
89 If one discounts the evidence of Lam and Loh in regard to the state of the site for reasons which have been referred to, what remains is Mr Ong`s clear evidence that when Chuan Joo purportedly completed the overburden removal, there was still overburden left, in some places over 40ft deep, and in all places more than a metre deep, with boulders lying all over the place.
90 Mr Ong complained, almost from day one, that this made it impossible for TDK to plan their quarry benching operations and to proceed with the quarry development work.
91 The suggestion by Mr Lam that TDK should start work on the 50-60% of the initial area that was workable is tantamount to a suggestion that TDK should work the site in the order dictated by the state of the site left by RDC`s earth contractor, rather than in the order chosen by TDK. As the contract provided for the handing over of the whole of the initial area on 1 June, a handing over of the site which complied with the requirement of the contract to the extent of only 50 to 60% of the area would not be sufficient compliance unless it can be shown that that was sufficient possession to enable TDK to proceed with the work in such a way as to enable them to fulfil the obligations placed upon them by the contract. That is a burden which cannot be discharged by Mr Lam simply saying that TDK could have carried out blasting operations in the 50-60% of the site. Similarly, the finding of the learned judicial commissioner that as of 1 October, there were `relatively large` areas of exposed rock which could be quarried, with respect, also misses the point.
92 As pointed out above, RDC`s contractors, Chuan Joo (or the sub-contractor), were still on site in September blasting boulders, and TDK themselves also had to blast boulders that should have been cleared by RDC`s contractors. Thereafter, all that TDK were able to do was to blast boulders, which were part of the overburden in the initial area, and produce granite from the boulders rather than quarry the granite from the rock formation below. TDK were never able to perform the contract to develop and work the granite quarry in the way contemplated by the contract.
93 RDC`s other response
94 Apart from their contention that they had fulfilled their contractual obligation in regard to the provision of site, RDC`s case is that the low production was due to TDK`s own fault, including their poor planning, lack of equipment, manpower and financial resources, and lack of application to the project. Counsel for the RDC said that TDK had bitten off more than it could chew. To support his argument, counsel for RDC referred to letters exchanged between the parties in the period after the award of contract. He also referred to minutes of site meetings. Most of the correspondence and the minutes had not been put to TDK`s witnesses, or even referred to in evidence. So it is not safe to rely on them as substantive evidence in regard to the shortcomings alleged against TDK. However, we would make some brief references to counsel`s submissions. As far as equipment is concerned, Mr Ong referred to a list of 23 items of equipment, all except two of which had been delivered to site between June and 1 September 1981; most of them by the middle of August. This was not challenged. It was not suggested that all the equipment must be on site when TDK moved on site. Nor was it shown by RDC what equipment should have been available that was not. There was some general allegation in Mr Lam`s evidence that some equipment brought by TDK was old and frequently broke down, but no details were given.
95 As far as manpower was concerned, RDC made the point at the trial that the contract called for the deployment of 83 workers. Mr Ong`s response, which seems reasonable, was that there was no point in having so many men there when there was not enough for them to do.
96 It seems to us that since RDC had breached their contractual obligation to make the site available to TDK they were hardly in a position to make criticisms about the shortage of equipment or manpower. The same goes for the point they made at trial and before us about the cash flow problem encountered by TDK. Mr Ong admitted that TDK did begin to have a cash flow problem from October, and the problem became very acute in February when TDK had to make rental payments under the equipment leasing agreements. It seems to us that as TDK were not able to produce the amount of granite contemplated because of the site constraints left by RDC, it is not surprising that they should experience cash flow problems. Again, it seems that it does not lie with RDC to make such a point.
97 We need to say a special word about the blasting incident that took place on 7 November 1981. RDC have made the point that TDK could not fulfil their production obligations because they were not allowed to carry on blasting in area A.
98 The evidence is not very clear whether the boulder that was blasted was within the initial area. If it was, then this was something which RDC should have cleared in accordance with the contract. The primary cause of TDK`s failure to comply with their production obligations under the contract would still be RDC`s failure to provide site in accordance with the contract. Although it was no doubt incumbent on TDK when undertaking the blasting of boulders to exercise care to prevent the sort of accident that happened, the blasting incident would not have broken the chain of causation so far as TDK`s failure to produce according to the contract is concerned. It is more an indication of the difficulty that RDC had created for TDK as a result of RDC`s breach of their obligation to provide proper site in accordance with the contract.
99 TDK tried to cope with the situation created by RDC`s breaches by accepting the move to area B, and by working the overburden in that area as well as area A until the blasting incident, rather than the underlying rock formation. However, despite months of work, they were never able to perform the contract in the way it had been envisaged. RDC had no right to expect TDK to continue to carry on work, and to do so at a loss. TDK in our view did not lose their right to tell RDC that enough is enough, and they were not going to have any more to do with the contract. This is what they did in May 1982.
100 The termination of contract: The procedural appeal
101 As stated above, on the basis that TDK had failed to produce the tonnages allegedly required by the contract, RDC purported to terminate the contract by invoking cl 35 of the specification. That clause in terms provided for termination in the event, inter alia, of TDK`s failure to produce the contracted quantities. That was the case pleaded by RDC. The hearing of the suit concluded on 25 February 1992, and the learned judicial commissioner reserved judgment. On 12 August 1992, some six months later, the learned judicial commissioner invited RDC to make an application to amend their pleadings to raise an alternative ground that TDK had repudiated their contract by abandoning the work and their obligations under the contract and RDC had accepted the repudiation.
102 Against TDK`s objection, amendments were allowed to the effect that TDK had repudiated the contract by abandoning work and their obligations under the contract on or about 6 May 1982 and that RDC had accepted the repudiation by their letter of 28 May 1982. The learned judicial commissioner held in favour of RDC on this alternative basis. There is an appeal against the decision of the learned judicial commissioner to allow these amendments, and we now have to deal with it.
103 As stated above, RDC`s letter of 28 May 1982 was the last of the series of letters beginning with the one on 6 May 1982. The letter of 6 May specifically invoked cl 35 of the specification as the provision under which RDC would terminate the contract if TDK continued to be in default. Several letters followed intimating RDC`s intention to terminate according to the terms and conditions of the contract and the letter of 6 May. On 14 May, a letter headed `final notice` referred to the notice of 6 May as having been issued under cl 35 of the specification. The actual notice of termination, which is the letter of 28 May, stated as follows:
We refer to our notice dated 6 May 1982 and to our final notice dated 14 May 1982 issued by us to you in pursuant to cl 35 of the above quarry contract made between you and Resources Development Corp (Pte) Ltd.
104 We now inform you that as there had been no improvement of the situation referred to in the aforesaid notices, we hereby terminate the aforesaid contract with immediate effect.
105 You are requested to vacate the site within seven days from the date of this letter.
106 Referring to the letters of 6 and 14 May, the learned judicial commissioner said that the letter of 28 May did not in terms purport to terminate the contract pursuant to cl 35. What it did, he said, was to refer, by way of introduction, to the previous notices of 6 and 14 May which had been issued pursuant to cl 35. He said that the previous notices of 6 and 14 May although purporting to be notices under cl 35, also made it plain that the complaint was about the stoppage of work and dismissal of workers. He also took the view that the letter of 28 May could be treated as an exercise of RDC`s common law right to terminate by acceptance of TDK`s repudiation.
107 We need only make two comments. Firstly, it is reasonably clear from the wording of the letters that if any termination was to be effected it would be on the basis of cl 35. The letter of 28 May, on a reasonable reading of it, must also be understood to be a termination in pursuance of cl 35. With respect, we do not think that it could reasonably be understood to be an acceptance of any repudiation by TDK.
108 Secondly, on our view of the facts, as shown above, RDC were in no position to rely on the low production of TDK or on TDK`s abandoning work as the ground for any proper termination on their part, as these had resulted substantially from RDC`s own breach of contract in regard to the matter of removal of the overburden.
109 What the amendments amounted to is that RDC were allowed to plead a case that on the facts was not open to them. On our view of the matter, the amendments should, with respect, not have been invited or allowed.
110 Conclusion
111 In the result both appeals are allowed. TDK is entitled to damages resulting from RDC`s breach of their contractual obligation to remove the overburden in the initial area according to the provisions of alternative A. The damages are to be assessed by the registrar. The appellants shall have the costs here and below. Costs in the assessment of damages are reserved for determination by the registrar. There is the usual order in regard to the payment out of the security deposit for the appeal.
112 Appeals allowed.
Warren Khoo L H J Rajendran S J L P Thean JA |
G Sri Ram, Manjit Singh and Anil Sachdev (Manjit Singh and Pnrs) for the appellants
Davinder Singh and Bonnie Lo (Drew & Napier) and John Ng (Tan Lee & Pnrs) for the respondents