In the High Court of the Republic of Singapore
[1994] SGHC 13
OS 768/1993
Between
Engineering Construction Pte Ltd
… Plaintiff
And
Attorney General
… Defendant
grounds of decision
Building and Construction Law — Damages — Liquidated damages

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Engineering Construction Pte Ltd v Attorney General
[1994] SGHC 13
OS 768/1993
Lim Teong Qwee JC
20 January 1994
1 Cur Adv Vult
2 This originating summons raises an important question under standard conditions of contract applicable to contracts of engineering construction which are widely used in Singapore and elsewhere. All the material facts are agreed and I will summarize them.
(1) By a contract (`the contract`) dated 2 March 1990 incorporating the standard conditions and made between the plaintiff (`the contractor`) and the government the contractor agreed to execute and complete the reconstruction of Jalan Ahmad Ibrahim Culvert and Jurong Lake Tidegate (`the works`). The date for possession was 19 March 1990 and the date for completion was 18 December 1991. Liquidated and ascertained damages (`LAD`) were payable at the rate of $3,000 per day for delay in completion.
(2) The director of the environmental engineering division of the Ministry of the Environment (`the director`) issued two letters both dated 4 January 1992 purportedly under cll 1(d) (reserving certain rights to the director), 31(a) (payment of LAD) and 32(a) (extension of time for completion of the works). By the letter issued under cl 32(a) (`first extension of time certificate`) time was extended by five days to 23 December 1991 on the ground of `inclement weather for the period March 1990 to November 1991`.
(3) On 30 April 1992 the contractor accepted the government`s wrongful termination of the contract as a repudiatory breach and thereupon the contractor was discharged from further performance and the government was liable to the contractor in damages for breach of contract.
(4) The works were not completed at the time the contractor accepted the wrongful termination as a repudiatory breach.
(5) Disputes having arisen between the parties as to several matters including the question whether and to what extent delay in the completion of the works can be attributed to the contractor these disputes were referred to the superintending officer (`SO`) by letter dated 15 April 1992 and to the director by letter dated 24 August 1992 and finally to arbitration and the final decision of a duly appointed arbitrator.
(6) The contractor commenced proceedings by originating summons and on 17 September 1992 it was declared that:
the [SO is] not entitled by cl 31 of the said contract or otherwise to deduct from amounts due to the [contractor] under the said contract [LAD].
See Engineering Construction Pte Ltd v A-G & Anor , where I said at p 400:
The right to deduct LAD can only arise when LAD has become payable under the first part of cl 31(a). I have held that LAD is not payable and accordingly there will be a declaration.
LAD was not payable because the director`s letter dated 4 January 1992 (`first LAD certificate`) did not satisfy the requirements of cl 31(a).
(7) The director issued two further letters both dated 29 September 1992 purportedly under cll 1(d), 31(a) and 32(a). The one under cl 32(a) (`the second extension of time certificate`) reads:
Without prejudice to the validity of the letter dated 4 January 92 on the subject of extension of time under cl 32(a) of the Conditions of Contract, I hereby issue this certificate in compliance with cll 1(d) and 32(a).
3 In my opinion, you are entitled to an extension of ten days from 18 December 1991 (the contract date for completion) to 28 December 1991 by reason of inclement weather during the period March 1990 to December 1991.
It should be observed that time has now been extended by ten days to 28 December 1991 on the ground of `inclement weather during the period March 1990 to December 1991`. The letter under cl 31(a) (`the second LAD certificate`) reads:
I certify in accordance with cll 1(d) and 31 of the conditions of contract that, in my opinion, the works ought reasonably to have been completed by 28 December 1991 (the extended date for completion).
4 As you have failed to complete the works by 28 December 1991, you shall thereafter under cll 31 of the conditions of contract pay the government liquidated and ascertained damages at $3,000 per day for the period, including Sundays and public holidays, during which the said works shall remain or have remained uncompleted.
5 The first question asked in this originating summons is whether the government is entitled to deduct or recover LAD in respect of any period during which the contractor is held by the arbitrator to be in delay prior to 30 April 1992. LAD is only payable (1) if the contractor fails to complete the works by the date for completion or within any extended time under cl 32 and (2) if the SO certifies in writing that in his opinion the works ought reasonably so to have been completed under cl 31. Under cl 1(d) the right to make a fair and reasonable extension of time under cl 32 and to give the certificate under cl 31 is reserved to the director. So the substantial question is whether the director had any power to issue the second extension of time certificate and the second LAD certificate both dated 29 September 1992.
6 Mr Jeyaretnam submits that the issue of certificates by the director under cll 32(a) and 31(a) is an act of performance of the primary obligations of the contract and these obligations have been discharged upon the contractor`s acceptance of the government`s repudiation on 30 April 1992. The certificates were issued some months later. He refers to Westralian Farmers Ltd v Commonwealth Agricultural Service Engineers Ltd (in Liquidation) , where Dixon and Evatt JJ said at pp 379-380:
In general, the termination of an executory agreement out of the performance of which pecuniary demands may arise imports that, just as on the one side no further acts of performance can be required, so, on the other side, no liability can be brought into existence if it depends upon a further act of performance. If the title to rights consists of vestitive facts which would result from the further execution of the contract but which have not been brought about before the agreement terminates, the rights cannot arise. But if all the facts have occurred which entitle one party to such a right as a debt, a distinct chose in action which, for many purposes, is conceived as possessing proprietary characteristics, the fact that the right to payment is future or is contingent upon some event, not involving further performance of the contract, does not prevent it maturing into an immediately enforceable obligation.
7 He says that the director was functus officio when he purported to issue the certificates. Mr Soh submits that the fact of delay by the contractor has already occurred and the issue of certificates does not involve further performance of the contract.
8 Clauses 31(a), 32 and 40 of the conditions of contract provide:
(31) (a) If the contractor fails to complete the works by [18 December 1991] or within any extended time under cl 32 hereof, and the [SO] certifies in writing that, in his opinion, the same ought reasonably so to have been completed, the contractor shall pay or allow to the government a sum calculated at the rate [of $3,000 per day as LAD] for the period, including Sundays and public holidays, during which the said works shall remain or have remained uncompleted. ...
...
(32) (a) If, in the opinion of the [SO], the works be delayed by force majeure or by reason of any exceptionally inclement weather or by reason of directions given by the [SO] consequential upon disputes with neighbouring owners or by reason of [SO`s] instructions given in pursuance of cl 1 hereof or in consequence of the contractor not having received in due time necessary instructions from the [SO] for which he shall have specifically applied in writing, or by reason of civil commotion, local combination of workmen, strike or lock-out affecting any of the trades employed upon the works or by the works of other contractors or tradesmen engaged by the government which are not referred to in the bills of quantities and specification, then, in such case, the [SO] shall make a fair and reasonable extension of time for completion of the works. ...
(32) (b) If the contractor shall be prevented from or be materially impeded or delayed in the execution or completion of the works by reason or in consequence of any acts or omissions of the government or of the [SO] contrary to the true intent and meaning of these presents such prevention, impediment or delay shall not vitiate the contract or affect the same except that in such cases the question whether any or what compensation or allowance ought to be paid or made to the contractor in respect of such prevention, impediment or delays and in what manner such compensation or allowance ought to be paid or made shall be determined and settled by the government whose decision shall be final.
...
(40) Provided always that in case any dispute or difference except a dispute or difference as to rates of wages or conditions of employment of workmen employed by the contractor in and for the purpose of this contract including workmen employed by nominated sub-contractors and by authorized sub-contractors engaged directly by the contractor shall arise between Government or the [SO] on its behalf and the contractor, either during the progress or after completion of the works or after the determination, abandonment, or breach of the contract, as to the construction of the contract or as to any matter or thing arising thereunder, or as to the withholding by the [SO] of any certificate to which the contractor may claim to be entitled, then the [SO] shall determine such dispute or difference by a written decision given to the contractor. The said decision shall be final and binding on the parties unless the contractor, within 14 days of the receipt thereof by written notice to the [SO] disputes, the same in which case or in case the [SO] for 14 days after a written request to him by the contractor fails to give a decision as aforesaid, such dispute or difference shall be referred to the arbitration and final decision of a person nominated and appointed by agreement between the [SO] and the contractor or, in event of his death or unwillingness or inability to act, or, if the [SO] and contractor fail to agree, of an arbitrator nominated by the Minister for National Development and the award of such arbitrator shall be final and binding on the parties. Such reference, except on the question of certitifcates, shall not be commenced until after the completion or alleged completion of the works, unless with the written consent of the [SO] and the contractor. The arbitrator shall have power to review and revise any certificate, opinion, decision, requisition or notice and to determine all maters in dispute which shall be submitted to him, and of which notice shall have been given as aforesaid, in the same manner as if no such certificate, opinion, decision, requisition or notice had been given. ...
9 Under the contract the contractor agreed to execute and complete the works and the government agreed to pay the price. There are provisions for SO`s instructions to be issued in regard to several matters including variations and extras to be executed by the contractor and provisions for the price to be adjusted and finally arrived at. The contractor had to complete the works including variations and extras by the completion date. If there was any delay and such delay was due to any of the causes specified in cl 32(a) the director was required to make a fair and reasonable extension of time for completion of the works. In practice the contractor would apply for the extension required and depending on the circumstances a decision might be given after the cause of delay had as it were run its full course. In the case of variations or extras it might be possible to estimate the length of time required and to make a fair and reasonable extension of time. The contractor is entitled to be paid the agreed price but if it failed to complete the works by the completion date or within the extended time LAD would become payable by it provided that two conditions were satisfied. First the director had to issue an extension of time certificate under cl 32(a) to fix the completion time. In doing this he would be acting on behalf of the government. Then he had to issue an LAD certificate under cl 31(a). Again he would be acting on behalf of the government. Unless these further acts were performed the liability for LAD could not be brought into existence. See Engineering Construction Pte Ltd v A-G & Anor . On 30 April 1992 the contract came to an end when the contractor elected to treat the government`s breach as repudiation. The primary obligations of the government including the obligation of the director acting on its behalf to issue an extension of time certificate under cl 32(a) came to an end as well as its right to perform them. I would further say that its right in the director to issue the LAD certificate under cl 31(a) similarly came to an end since the exercise of this right depended upon the issue of an extension of time certificate under cl 32(a). The right to LAD was not merely postponed to a future date or contingent upon some event not involving further performance of the contract. Notwithstanding that the contractor had overrun the date for completion and the extension of time under the first extension of time certificate the right to LAD had not come into existence at the time the contract came to an end before completion of the works.
10 The issue of the certificates under cll 31(a) and 32(a) is not incidental to or concerned with the resolution of disputes or the determination of the consequences of the contract coming to an end before completion of the works. In a sense it is antecedent to the resolution of disputes under the contract. If the contractor is dissatisfied with the certificates it can refer the matter to the director under cl 40. The reference to the director and his determination and decision (or failure to give a decision for 14 days after a written request to do so) are conditions precedent to a reference to arbitration. The director`s power to determine any dispute and to give a decision would not be affected by the `determination, abandonment, or breach of the contract` and would survive the contract coming to an end before completion of the works but it seems to me that the issue of certificates under cll 31(a) and 32(a) stands in a different category.
11 I am unable to find any provision in the contract that can be construed to preserve the power of the director to issue certificates under cll 31(a) and 32(a) upon the contract coming to an end before completion of the works by reason of a wrongful act of the Government and in my opinion the director had no such power after 30 April 1992.
12 Where the director has not issued the final certificate or where notice of arbitration has been given, so Mr Soh`s argument proceeds, the director is not functus officio and is not precluded from issuing the two certificates. He refers to A-G of Hong Kong v Wang Chong Construction Co Ltd
13 .3 Although I have come to a decision on the question asked in this originating summons I should express my views on the further arguments that have been urged on me.
14 In A-G of Hong Kong v Wang Chong Construction Co Ltd , cl 2(4) of the contract provides:
The powers and authorities vested in the architect and the duties of the architect`s representative exercisable under the contract shall continue and be in force until the granting by the architect of the maintenance certificate referred to in cl 103 or the settling of the final payment certificate, whichever is the later.
15 The maintenance certificate was issued on 23 June 1977 and the final payment certificate was settled in May 1979.
16 Clauses 117(1) and 117(3) provide:
(1) If any dispute or difference shall arise (save only as to excepted matters as defined in cl 115) between the government or the architect and the contractor in connection with or arising out of the contract or the carrying out of the works, whether during the progress of the works or after their completion and whether before or after the termination, abandonment or breach of the contract, it shall be referred to and settled by the architect who shall state his decision in writing and shall give notice of the same to the government and to the contractor.
...
(3) If the architect shall fail to give such decision for a period of 90 days after being requested to do so or if either the government or the contractor is dissatisfied with any such decision of the Architect then and in any such case either the government or the contractor may within 90 days after receiving notice of such decision or within 90 days after the expiration of the first-named period of 90 days, as the case may be, require that the matter shall be referred to the decision of a single arbitrator in accordance with and subject to the provisions of the Arbitration Ordinance or any statutory modification thereof for the time being in force ...
17 A dispute having arisen between the government and the contractor it was referred to the architect and he stated his decision in writing on 25 February 1989, ie nearly two years after the final certificate was settled. It was held that the architect was not functus officio the settlement of a dispute under cl 117(1). This part of the judgment was not disturbed on appeal. This is clearly right but it does not follow that the architect was not functus officio the issuing of an extension of time certificate where the contract had come to an end before completion of the works.
18 Mr Soh next refers to H Fairweather Ltd v Asden Securities Ltd . Clause 30(7) provides:
Unless a written request to concur in the appointment of an arbitrator shall have been given under cl 35 of these conditions by either party before the final certificate has been issued or by the contractor within 21 days after such issue, the said certificate shall be conclusive evidence in any proceedings arising out of this contract, whether by arbitration under cl 35 of these conditions or otherwise, that the works have been properly carried out and completed in accordance with the terms of this contract, and that any necessary effect has been given to all the terms of this contract which require an adjustment to be made to the contract sum except and insofar as any sum mentioned in the said certificate is erroneous by reason of (a) fraud, dishonesty or fraudulent concealment relating to the works; (b) any defect in the works which a reasonable inspection or examination at any reasonable time during the carrying out of the works or before the issue of the certificate would not have disclosed; (c) any accidental inclusion or exclusion of any work, materials, goods or figure in any computation or any arithmetical error in any computation.
19 The works were completed on 1 December 1975 and the final certificate was issued on 28 July 1977. In 1978 the architect issued a certificate under cl 22 similar to the second LAD certificate in the case before me. The official referee said at p 53:
It seems to me that effect must be given to the earlier words, that is that `the [final certificate] shall be conclusive evidence that the works have been carried out and` - be it noted - `completed in accordance with the terms of the contract`. This, in my view, must include the provisions of cl 22 which include the giving of an architect`s certificate as a pre-requisite to the right to make a deduction. ... I think that once the architect has issued his final certificate, and provided that no notice of arbitration is given by either party within the permitted time, and provided that none of the three specific exceptions apply, the architect should be regarded as functus officio, and is precluded thereby from issuing thereafter any valid certificate under cl 22 of the conditions of the contract.
20 It was a decision on the provisions of cl 30(7). The final certificate was conclusive evidence unless notice of arbitration had been given. In the case before me there are no similar provisions. Here again it is not concerned with a contract coming to an end before completion of the works .
21 In Re An Arbitration between the Yeadon Waterworks Co and J A Binns (the Trustee of J Brigg, a Bankrupt) and Samuel Wright , the contract contained a provision entitling the employer to deduct from money due to the contractor liquidated damages in the sum of £500 and a further sum calculated at the rate of £5 per day for each day which may elapse between the date for completion or such other day to which the completion time may be extended by the engineer and the time of actual completion of the works and there was a provision for extension of time by the engineer. There was a clause entitling the employer in certain events to terminate the contract so far as respects performance by the contractor and this clause concluded with `without thereby affecting in any other respects the liabilities of the contractor`. The contractor became unable to complete the works. The employer terminated the contract in the exercise of its right to do so and entered into a contract with the contractor`s surety for the surety to complete the works on terms subjecting the surety to the contractual liabilities of the contractor. The surety completed the works after the day to which the engineer extended the completion time. It was held that the employer was entitled to deduct from money payable to the surety liquidated damages for delay on the part of the contractor before the contract was terminated as regards performance by him. I find nothing in this case that can assist the government. The surety in effect stepped into the shoes of the contractor. However, what is interesting is that Kennedy J said at p 540:
The counsel for [the surety] contend in effect that, the [employer] having exercised its powers of re-entry and put an end to [the contractor`s] performance of the contract work, the right of the [employer] to these liquidated damages under the contract was put an end to also. They further contend that [the surety] did not under the agreement of 5 December 1892 become liable to submit to any such deduction from the retention moneys. We are unable to adopt this view. If the concluding provisions of the re-entry clause had been omitted; if there had been a power simply to re-enter and terminate the contract, and the [employer] had exercised that power, then we are of opinion that, as the counsel for [the surety] argued, the [employer] could not afterwards have claimed these liquidated damages as against the contractor, nor in the settlement of accounts as against [the surety]. Having elected to dispossess the contractor and taken the performance of the contract out of his hands, they must have been taken to abandon their right to those damages. [Emphasis added.]
22 I come now to the last case referred to by Mr Soh. In Felton v Wharrie the contractor agreed to pull down certain houses and he was to be paid £75 and to have for his own use all materials pulled down. By cl 10 he was to complete the works in 42 days from the day he was admitted to the site `unless prevented by accident, weather, strikes of workmen, or other reasonable cause, in which case the surveyors of the employer shall have power to extend the time`. By cl 11 LAD at the rate of £1 per day was payable for every working day after the time or extended time for completion of the works until actual completion of the works. The contractor paid a deposit of £100 as security for the performance and was admitted to the site and did about three-quarters of the works when on 29 August 1904 the employer terminated the contract and engaged another contractor who completed the works on 22 September 1904. The court found that the works ought to have been completed by 12 August 1904 and there was consequently a delay of 36 working days. In the Court of Appeal it was held allowing the appeal that the termination was wrongful and Lord Alverstone LCJ said at pp 400-401:
That would entitle the [contractor] to 75 l, and to the 100 l deposit. As regards the unfinished balance of the contract, there would be some profit, and I am going to take 50 l for the amount of that. That would make altogether a sum of 225 l. I think it is quite plain that the [employer] would not be entitled to have any penalty, or damages in the nature of a penalty, after 29 August. I am not quite clear, in my own mind, that he may not be entitled to have some claim in respect of the delay up to that time, but that is a very small matter. We think that if a sum of 210 l were paid to the [contractor] it would be a proper judgment between the parties.
23 The report of the judgment is quite brief and it is not clear whether the allowance of £15 was for LAD or for damages at law for the loss suffered by the employer by reason of delay. Perhaps it was a very small matter and whether the sum was for LAD or for damages at law did not matter but Darling J in the court below (who had held that the contract was broken by the contractor) said at p 399:
... I hold further that the [employer] is entitled to damages for breach of contract, because the contract was broken. I fix those damages at 36 l, which is the same amount as would be due for delay if the contract had not been determined but had been completed by 22 September. I do not give them as liquidated damages, because liquidated damages contemplate that the contract continues ... [Emphasis added.]
24 In Roberts v Bury Improvement Commissioners, the contractor claimed damages for loss sustained by reason of the employers having prevented him from completing the works under a building contract. The contract was terminated before the date for completion. Clauses 24, 27 and 29 provide:
(24) Provided always that if, by reason of any additions to or enlargements of the works (which additions or enlargements the architect is hereby authorized to make), or for any other just cause arising with the [employers] or the architect, or in consequence of any unusual inclemency of weather, or for want or for alleged want or deficiency of any orders, drawings, or directions, or by reason of any difficulties, &c, or differences whatsoever and howsoever occasioned, the contractor shall in the opinion of the architect have been unduly delayed or impeded in the completion of his contract, it shall be lawful for the architect to grant from time to time, by writing under his hand, such extension of time, and to assign such other day or days for completion, as to him may seem reasonable, ...
(27) That it shall be lawful for the [employers], in case the contractor ... shall not in the opinion and according to the determination of the architect exercise due diligence and make such due progress as would enable the works to be effectually and efficiently completed at the time and in the manner aforesaid, to determine the contract ...
(29) That, in case the contractor shall fail in the due performance of his contract by and at the times hereinbefore mentioned or referred to (or at other the day or days to which the period of completion may have been extended), he shall be liable to pay to the [employers], as and for liquidated damages, the sum of 1l per cent on the amount of the accepted tender, for each and every week which may elapse between the appointed and actual time of completion and delivery hereinbefore mentioned or provided for, or the [employers] may deduct the same from any moneys in their hands due or to become due to the contractor.
25 The employers pleaded that in the opinion and according to the determination of the architect the contractor did not exercise due diligence and make due progress and that it had determined the contract under cl 27. The contractor replied that the alleged failure to exercise due diligence and to make due progress was caused by the default of the architect and the employers. The employers alleged in their rejoinder that in the opinion and according to the determination of the architect the failure to exercise due diligence and to make due progress was not caused by the default of the architect or the employers. In the Court of the Exchequer Chamber Blackburn and Mellor JJ said at pp 326-327:
The court below have thought that the parties in this case have agreed to make the architect the sole and exclusive judge of what additional time should be allowed, in case the contractor was delayed either by having additional works put upon him under the contract, or in consequence of breaches of contract on the part of the [employers], and have also made him, and him alone, the judge to determine whether there has been any breach of contract on the part of the [employers].
26 We agree that, if the parties have so contracted, the court cannot inquire whether this is a prudent engagement on the part of the contractor: but we think that, where the effect of giving such a construction to the contract would apparently be to put one party completely at the mercy of the other, we ought not to give that construction to the contract, unless the intention is pretty clearly expressed.
27 and later at p 327:
In the present case, the portion of the contract which is relied on as expressing such an intent is the 24th condition, which is as follows: [His Lordship read the condition]. It is to be observed that, in the recital with which this condition begins, no distinction is made between delays arising from additions which are authorized by the contract, delays arising from unusual inclemency of the weather (a risk which the contractor has taken on himself, though it might give rise to a claim in misericordiam), and delays arising from breaches of contract or alleged breaches of contract on the part of the [employers], for which the contractor would have a right to recover damages: in either case it is provided that `it shall be lawful` for the architect to grant an extension of time; but it is neither said that the architect must give it - which, in case the delay was from the inclemency of the weather, would not be reasonable - nor that the contractor must accept whatever extension of time the architect is pleased to give, in full satisfaction of his claim for damages, which, if the delay from the fault of the [employers] was great and the damages consequently heavy, might be very unreasonable.
28 Kelly CB said at p 331:
This raises the question whether the effect of the contract is to confer a power upon the architect to determine, and to bind the [contractor] by his determination, that the [employers] have not by their own wrongful act or default prevented the [contractor] from proceeding with the works, although in truth and in fact they have so prevented him.
29 and later at p 332:
If [the architect] had been of opinion that the [contractor] had been unduly delayed, he might have granted an extension; but then the contract must have continued in force, the [contractor] must have proceeded with the works, and the [employers] could have had no power to put an end to the contract.
30 and at p 333:
The [contractor], then, having expressly averred in his [reply] that his alleged default had been caused by the wrongful act or default of the [employers] themselves, and this averment not having been traversed by the [employers], but the rejoinders merely alleging that the [contractor`s] default had not, according to the determination of the architect, been caused by the [employers`] wrongful act or default, we are of opinion that, the architect having no power under the contract to bind the [contractor] by any such determination, the rejoinders are no answer to the [reply]; and that the rule of law relied upon by the [contractor] is applicable to this case; that the [employers] cannot take advantage of their own wrong; and that they had consequently no power to determine the contract under the 27th clause.
31 See also Amalgamated Building Contractors Ltd v Waltham Holy Cross Urban District Council where Denning LJ said at p 455:
I would also observe that on principle there is a distinction between cases where the cause of delay is due to some act or default of the building owner, such as not giving possession of the site in due time, or ordering extras, or something of that kind. When such things happen the contract time may well cease to bind the contractors, because the building owner cannot insist on a condition if it is his own fault that the condition has not been fulfilled.
32 In British Glanzstoff Manufacturing Co Ltd v General Accident, Fire and Life Assurance Corp Ltd, the employers terminated the contract by reason of the bankruptcy of the contractor as they were entitled to and engaged another contractor who completed the works. There was a resulting delay of at least six weeks between the date for completion in the contract that was terminated and actual completion under the second contract all of which was attributable to the period before the first contract was terminated. Clauses 24 and 25 of the contract provide:
(24) If the contractor fail to complete the works by [31 January 1910], or within any extended time allowed by the architect under these presents, and the architect shall certify in writing that the works could reasonably have been completed by the said date, or within the said extended time, the contractor shall pay or allow to the employer the sum of £250 sterling per week for the first four weeks, and £500 per week for all subsequent weeks as liquidated and ascertained damages for every week beyond the said date or extended time, as the case may be, during which the works shall remain unfinished, ...
25 If in the opinion of the architect the works be delayed by force majeure or by reason of [certain specified causes] the architect shall make a fair and reasonable extension of the time for completion in respect thereof. ...
33 In the court of session the Lord President said at p 598:
The contractor is gone. He has got no more power, so to speak, to stop the running of the time. He will be liable, of course, in damages, for his breach of contract, so to speak, at common law, as a contractor is in every contract if he breaks it. But this particular clause, which provides for a penalty per week for delay in completion, seems to me, upon the face of it, necessarily to apply - and to apply only - to a case where the works are finished by the original contractor.
34 Lord Mackenzie said at pp 599-600:
It appears to me, upon a sound construction of cl 24, that the [employers`] demand fails, for the clause was not intended to apply to the case when another contractor completes the work. In support of this view the provision that the architect may allow an extension of time is of importance. The contract has been so innovated upon that no application to the architect for an extension of time by the original contractor is possible. The reason is that the [employers] have exercised their rights under the 26th clause, which entitles them to enter and employ any other person to complete the works. Upon completion the architect is to certify the amount of the expenses properly incurred consequent on and incidental to the default of the original contractor, who is either to receive or pay, as the amount may be greater or less than the sum that would have been due to him if he had completed the works. This, in the circumstances, displaces the 24th clause which provides for liquidate damages.
35 The decision was affirmed on appeal to the House of Lords.
36 In the case before me the contract has been terminated by the government and terminated wrongfully. The matters in difference between the parties are before the arbitrator and one of these matters is the question whether and to what extent delay in the completion of the works can be attributed to the contractor. Under cl 40 the arbitrator has power to review and revise any certificate including the extension of time certificate dated 4 January 1992 and the second extension of time certificate and second LAD certificate both dated 29 September 1992 if they have been validly issued. Although the question referred to the arbitrator might have been better formulated there can be no doubt that any finding on this question must touch on the matters referred to in cl 32(a) and the arbitrator will have to review these certificates. In my opinion this would be a good reason to hold that the matters in difference having been referred to arbitration the director is functus officio the issuing of any extension of time certificate under cl 32(a) or any LAD certificate under cl 31(a) and I so hold.
37 Clause 32(a) enjoins the director to grant an extension of time if in his opinion the works are delayed by the happening of the events specified. One notable omission from the list of events is default by the government. Under cl 32(b) in the event of such default - by the government - the question what compensation or allowance ought to be paid or made to the contractor is determined by the government whose decision is final. Whatever else may be said of this provision I am of the opinion that the government cannot wrongfully terminate the contract and thereafter purport to exercise the power to determine what allowance ought to be made to the contractor for delay occasioned by its own default. See Roberts v Bury Improvement Commissioners . That would be taking advantage of its own wrong. I do not suggest that the government is seeking to do this in the present case. It is because the government cannot exercise its powers under cl 32(b) that it follows that where the government has wrongfully terminated the contract time will be at large. See Amalgamated Building Contractors Ltd v Waltham Holy Cross Urban District Council. , In this case there has been a reference to arbitration on the question of delay and that was before the director issued the second extension of time certificate.
38 There is a further matter as to the extension of time certificate under cl 32(a). So long as the contract continues in force the SO can issue site instructions, or the contractor may encounter exceptionally inclement weather or indeed any of the events upon the happening of which completion time may be extended may still occur. They may occur before the date for completion or within the extended time or at any time after that until the works are actually completed. Until such time no extension of time certificate can be final. I think the director recognized this when in his second extension of time certificate he allowed 10 days for inclement weather in the period to December 1991 after having allowed five days in respect of the period to November 1991. Under cl 31(a) LAD is payable in respect of the period the works remain uncompleted. The period cannot be determined until the works are in fact completed. It cannot be determined if the works can no longer be completed by the contractor by reason of the contract having come to an end. See British Glanzstoff Manufacturing Co Ltd v General Accident, Fire and Life Assurance Corp Ltd . And it does not follow that where the contractor has overrun the date for completion when the contract is terminated the period of delay cannot be shorter upon completion (if the contract had not been terminated) than at the time of termination. Take an example. Say the date for completion is 30 June. The works are not completed and will require another 15 days. The contractor proceeds with the works and on 5 July before the works are completed extras are ordered and the engineer allows an extension of 25 days. The contractor completes the original works as well as the extras on 30 July. What was potentially a 15-day period of delay has been reduced to one of only five days. If the extras are completed in 20 days on 25 July although a `fair and reasonable extension of time` is 25 days to 25 July then there would be no delay at all. In my opinion the first extension of time certificate cannot be final until the works are actually completed and since further performance has been taken out of the contractor`s hands altogether cl 32(a) can no longer operate. The director became functus officio the issuing of any certificate under cl 32(a) upon termination of the contract on 30 April 1992.
39 I come now to the question asked in this originating summons. The answer is `No`. The government is not entitled to deduct or recover LAD in respect of any period during which the contractor is held by the arbitrator to have been in delay prior to 30 April 1992. LAD cannot be deducted or recovered unless the director has issued an extension of time certificate under cl 32(a) and an LAD certificate under cl 31(a) and he was functus officio the issue of such certificates after the wrongful termination of the contract by the government on 30 April 1992. He had no power to issue the second extension of time certificate and the second LAD certificate both dated 29 September 1992 and these certificates are null and void. Of course the government may be entitled to damages at law for the contractor`s breach for delay but that will have to be claimed and proved in the ordinary way.
40 I will hear counsel on the other questions in the originating summons.
41 Order accordingly.
Lim Teong Qwee JC
Philip Jeyaretnam and Neoh Sue Lynn (Helen Yeo & Pnrs) for the plaintiff
Soh Tze Bian (Attorney General’s Chambers) for the defendant