In the High Court of the Republic of Singapore
[1994] SGHC 182
Suit 2557/1987
Between
Mahtani
… Plaintiff
And
Kiaw Aik Hang Land Pte Ltd
… Defendant
grounds of decision
Building and Construction Law — Construction torts; Building and Construction Law — Construction torts

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Mahtani and Others v Kiaw Aik Hang Land Pte Ltd
[1994] SGHC 182
Suit 2557/1987
Judith Prakash JC
11 July 1994
1 Cur Adv Vult
2 The defendants carry on the business of property developers. In the 1970s and early 1980s, they were engaged in developing the condominium project known as Amber Gardens located near the corner of Mountbatten Road and Tanjong Katong Road. They constructed five blocks of flats in two phases. Blocks A and B were built during the first phase and Blocks C, D, and E were built during the second phase. This action arises out of the sale by the defendants to the plaintiffs of a flat located on the seventh storey of Block E and now known as 1 Amber Gardens, #07-03 Block E, Maryland Park, Singapore (the flat).
3 In December 1980, the plaintiffs were granted an option to buy the flat for the sum of $465,900. The option was exercised on 9 February 1981, and an agreement for sale was thereupon entered into. In this agreement the defendants described the flat as being estimated to contain a floor area of 181.5 sq m and they also undertook, by cl 8, to construct the flat itself, the building project, and the common property, in a good and workmanlike manner.
4 The plaintiffs are three brothers residing in Indonesia. The purchase was handled by the first plaintiff, Mahtani Lakhmichand Gobindram (Lakhmichand), who, during a visit to Singapore in December 1980, had seen the project under construction. When Lakhmichand made enquiries at the defendants` office about the availability of flats in the project, he was told that the defendants had a sister company, Kiaw Aik Hang Finance Co Ltd (the mortgagee), which could finance a purchase at a better rate than a bank. He was also told that the defendants` lawyer was one Dr Phang and that if the plaintiffs used Dr Phang in the purchase as well, then their legal costs would be reduced by half. In the result, the plaintiffs decided to take a loan of $370,000 from the mortgagee to finance their purchase of the flat and they also appointed Dr Phang as their lawyer. Dr Phang thereafter acted for the defendants as vendors, the plaintiffs as purchasers and mortgagors, and the mortgagee as lender. The loan was secured by a mortgage of the property.
5 In March 1982, the subsidiary strata certificate of title in respect of the flat was issued. This showed its floor area to be 152 sq m and not 181.5 sq m. The certificate was received by the plaintiffs` solicitor and sent thereafter to the mortgagee. According to Lakhmichand, the plaintiffs were never given a copy of it and did not become aware until much later that there was a shortfall in the floor area. In the meantime, the sale of the property was completed in April 1982.
6 On 18 February 1987, the Development and Building Control Division of the Public Works Department served a notice on the Management Corp of Maryland Park stating that the Building Authority was of the opinion that Blocks C and E were dangerous. The Management Corporation was ordered to submit its professional engineer`s report and investigation on the buildings and to thereafter make the buildings safe. Subsequently, various engineers were appointed to investigate and make recommendations. In the result, the Management Corp accepted the reports of Dr YS Lau submitted in March 1989, October 1989 and March 1990, and appointed him to supervise certain remedial works to Blocks C, D and E. These were completed in August 1991.
7 In the meantime, the plaintiffs had defaulted in punctual payment of the instalments due to the mortgagee. In fact, all the instalments falling due from January 1986 onwards were not paid. The mortgagee therefore took action in July 1987 to enforce the mortgage. The flat was put up for sale by auction. At the auction, which was conducted on 20 August 1987, the flat was sold for a price of $295,000.
8 On 24 September 1987, the plaintiffs issued the writ in this action claiming damages against the defendants for their breaches of contract in relation to the shortfall in the area of the flat and their failure to construct the flat and the building in which it was contained in a good and workmanlike manner. Initially the defendants denied both claims. When this action first came on for trial in July 1993, however, the defendants conceded liability on the shortfall claim in the amount of $75,724.73 as claimed in the statement of claim. The defendants continued to dispute liability on the second claim.
9 The trial therefore proceeded on the basis that the plaintiffs had to establish the failure of the defendants to comply with their contractual obligations in relation to the construction of Block E and that, as a result thereof, they had sustained damage. Both these issues were hotly contested by the defendants. It should be noted that the defendants did not deny their duty to build the block and the flat in a good and workmanlike manner. What they denied was that they were in breach of this obligation.
10 Issue 1: were the defendants in breach of their obligation as builders?
11 In their re-amended statement of claim, the plaintiffs gave the following particulars of the alleged breach on the part of the defendants:
Particulars
The defendants used defective concrete which was insufficiently dense, weak, porous and unduly variable and contained insufficient cement in the construction of the concrete structures. This has necessitated the use of jackets to the columns which have shown signs of distress. Over the years moisture in the atmosphere and water from the wet areas seeps into the concrete and corrodes the main reinforcement of the structures through the porous concrete which has lost its alkalinity and is unable to protect the steel reinforcement from corrosion. Once the steel reinforcement begins to corrode, rust forms around the bar and, as this rust has a volume up to three times as great as that of the original steel, it generates considerable internal pressure which is greater than the tensile strength of concrete. This results in cracking and spalling of the structure and will eventually lead to a loss of strength which affects the achievement of design loads and the maintenance of safety factors.
12 The plaintiffs` main witness in connection with this part of the claim was Dr YS Lau, the engineer who had been brought in by the Management Corp as a consultant to investigate the alleged defects and advise them on what, if any, remedial action was required. In rebuttal, the defendants called Dr CK Murthy, another consultant engineer. Dr Murthy, however, laboured under the considerable disadvantage of not having carried out an investigation or even an inspection of the site at the material time. He therefore had to work from the reports of various investigators, including Dr Lau, who had themselves carried out the physical inspections.
13 The evidence before the court on this issue consisted of the four reports which Dr Lau gave to the Management Corp (three relating to his investigations and recommendations and the fourth being a report issued after the remedial works had been completed), Dr Murthy`s `Opinion Report on Alleged Defective Concrete in Blocks C, D and E at Maryland Park`, Dr Lau`s commentary on that report and the oral testimony of both experts. Thus a wealth of documentation and opinion was introduced. For the purpose of this judgment, it is not necessary to dwell on all the technical points raised. Instead I will summarize the main points that emerged.
14 (i) Differential settlement
15 Dr Lau found that the columns of Blocks C, D, and E (the buildings) had settled differentially and that there was a difference of 70-80mm in the levels of different columns. The differential settlement did not result in tilting or in cracks in the original structure other than in beams and slabs at two locations at the second storey floor of Block D. By the time Dr Lau came on the scene, the settlement had stabilized and had not affected the buildings.
16 Dr Murthy commented that the large differential settlement observed in the buildings should have given rise to severe damage. The fact that Dr Lau had observed cracks only in plaster and found the structural members to be free from cracks except at two locations showed that the quality of the concrete must have been good since it had sustained such a big differential settlement.
17 In response, Dr Lau pointed out that various cracks which had arisen from the differential settlement had been observed both by himself and by previous investigators. For example, there was wall cracking in Block C; vertical cracking of external columns and some columns inside the building in levels 3 and 5 of Block C; cracking or spalling of concrete in certain columns/walls in Blocks C, D, and E; diagonal cracks across slabs of very short spans which appeared to radiate from columns at the balconies and/or those surrounding the lifts shafts on many levels of the buildings and numerous shear cracks on beams at the first storey ceiling of all the buildings. He also pointed to maps and photographs of numerous cracks and other defects in columns, beams and slabs observed by his engineers. Dr Lau stated that the fact that structural cracks wider than 0.15mm were found at two locations meant that the cracking was well distributed by reinforcement and did not rule out the existence of narrower cracks or cracks which may have been repaired or covered with plaster. According to Dr Lau, his site records showed that at the end of the strengthening/repair contract, more than 900 metres of cracks in the concrete structures had to be grouted. Many of these cracks had, at the start, been hidden under hairline cracks in the plaster and were only discovered when the plaster was removed for the purpose of the rectification works.
18 (ii) Low concrete strength
19 The structural design of the columns was adequate but there was a serious deviation from the design which directly affected the load carrying capacities of the columns. This deviation was the use of concrete which was low and variable in strength. This resulted in columns with strength that was low and variable. According to Dr Lau, weakness in a single column cannot be compensated for by strength of other columns. Every column has to be good enough. Some of the columns were unacceptably weak in that they did not meet the minimum specifications. The margins of safety were unacceptably low and there were signs of distress in the columns. In fact, five columns in the flat itself were substandard and had to be strengthened.
20 Low concrete strength arose from incorrect and variable concrete mix proportions. This meant that the standard of control of the quality of the material and workmanship at the site had been low, especially during the early stages of the super structure construction.
21 At some stage during the construction, it had been realized that some of the columns were not strong enough for their purpose. Thus, in order to strengthen them, someone had put jackets around these columns. Dr Lau pointed out that in the original design the columns had not been jacketed. Dr Murthy testified that he had been told by the defendants that the jackets had been erected to conceal drain pipes. In Dr Lau`s opinion, this information could not have been correct because firstly, expensive reinforced grout had been used in the jacketing and, secondly, if the purpose of the jacketing had been merely to conceal the pipes, only one side of the columns would have been covered. Instead the jackets went all round the columns. Dr Lau pointed out that because the columns were weak and the jackets were strong, load had been transferred to the jackets which, on inspection, showed signs of distress. There were many cracks in the interfaces between the columns and the jackets.
22 Dr Murthy stated that owners of units in the buildings had raised their balcony floors and this had added up to 15% extra load to the columns. Further, Dr Lau had not observed any symptoms of creep movements in the structure. He said that concrete could not be weak if it did not crack and crumble when overstressed by a combination of large differential settlement and overloading by users of the building. Further, the columns should have crept because of the overloading. They should have developed micro-cracks which would have enlarged with time and joined together to form macro-cracks. The absence of these symptoms indicated that the concrete in the structure was not weak.
23 In response to these criticisms, Dr Lau pointed out that the structural design of the buildings was adequate and they would not have been significantly overstressed on account of an up to 15% overload from the raised balconies if the concrete used had been grade 20 or better. He also pointed out that there might be some confusion between strength of concrete and strength of the structure . The latter depends not only on concrete strength but also on the quantity and distribution of the steel reinforcement, to which load on the concrete would be transferred, if the concrete is weak. Concrete strength is important to the structural strength to the extent that the strength of the structure depends on it and not on the steel reinforcement. Concrete which is heavily reinforced does not crack and crumble under overload but transfers the load on it to the reinforcement. Jackets and adjacent brick walls also take up excessive loads on the concrete in the columns.
24 Dr Lau also testified that the absence of symptoms of creep movement does not mean that the concrete is not weak. That theory is only valid for non-reinforced or lightly reinforced concrete where the contribution to the strength of the structural element is predominantly from the concrete. In the case of the buildings, heavy reinforcement, grout/brick jackets and adjacent brick walls took up the excessive load on the concrete, and there was no visible creep movement because of restraint and load transfer. The effects of load transfer stresses were in fact observed in the cracks at the columns/jacket interfaces and in the jackets themselves.
25 (iii) Cement content in the concrete
26 Dr Lau carried out tests on the concrete and testified that these tests indicated that much of the concrete in the buildings was weak, insufficiently dense, porous, variable, lacking in durability and defective in many respects. Fifty percent of the concrete tested for strength did not meet grade 20, the lowest structural grade acceptable for reinforced concrete. In tests carried out in Block D, the concrete of certain columns disintegrated when attempts were made to core them.
27 (iv) Wet areas (kitchens, bathrooms, exposed balconies)
28 Carbonation was observed to have taken place in these areas. The concrete had been attacked by the atmosphere and its alkalinity had been reduced thus lessening its ability to protect the steel rods which had subsequently corroded. The corroded steel expanded leading to spalling of the concrete. In Dr Lau`s opinion, the carbonation arose from the poor quality of the concrete and not from the proximity of the buildings to the sea. He said that deep carbonation within a few years from construction must mean weak permeable concrete. A porous or permeable concrete is a low density concrete. Further, tests carried out on the concrete of the buildings showed that its density was low. Dr Lau also stated that the low density of the concrete was consistent with there having been insufficient cement used to fill the voids between the aggregate particles and/or with there being inadequate compaction of the concrete.
29 In respect of the flat itself, the evidence was that the floor slabs of bathroom B2 leaked into the bathroom directly below in unit #06-03. There were also rust stains on the false ceiling of bathroom B1 of the flat and this indicated corrosion in the slab above. Dr Lau stated that if the concrete had been of good quality, it would have been dense enough to be impermeable even without waterproofing and the bathrooms would not have leaked.
30 The above is only a summary of the more important points raised during the hearing. Having considered all the evidence, I am satisfied that Dr Lau`s opinion is correct and should be accepted. Dr Lau was commissioned to investigate the defects. He did extensive investigations and scrutinized the reports of the previous consultants in order to arrive at the conclusions he presented, first to the Management Corp and later in court. His results and the British Standards which he used in his investigations were accepted by the Building Authority and rectification works were undertaken on the buildings in accordance with Dr Lau`s recommendations. In my judgment, the defence was not able to establish that Dr Lau`s opinion was incorrect in any material aspect. Accordingly, I find that the plaintiffs have proved their case in relation to the allegation of structural defects in Block E and the flat. I therefore find that the defendants were in breach of their obligation to build the block and the flat in a good and workmanlike manner.
31 Issue 2: have the plaintiffs sustained damage as a result of the breach?
32 It appears from Emden`s Construction Law that whilst there are four alternative bases on which the damage sustained by a party who has been injured by the failure of a developer or builder to build or complete a structurally sound and defect free building may be assessed, the general rule is that the correct basis is the cost of rectifying or completing the work. Such cost is assessed at the time it was reasonable for such party to carry out the rectification work. The plaintiffs contend that that basis is inapplicable in the present circumstances. If it were used, they would recover nothing since the flat was sold before any rectification works were commenced. The plaintiffs say that their loss should instead be assessed on the basis of the diminution in the value of the flat by reason of the defects.
33 Measuring damages by having regard to the adverse effect which the defects have had on the value of the property concerned is an appropriate basis of assessment in a situation where it is unreasonable to require the defects to be remedied. For example, where the building is so defective as to be incapable of economic repair, the court will award the market value of that building as it would have been had it been sound. This principle was laid down by the English Court of Appeal in .1 There the defendants had in 1957 sold a house in the course of erection to the plaintiff. In 1965 it was discovered that the house was unsaleable, irreparable and dangerous. In the plaintiff`s action against the defendants for not building the house in accordance with the plans and specifications, the trial judge held that the cause of action arose in 1957 and, as at that time the building was worth £1,900, the correct award was for that amount plus interest from 1957 onwards. On appeal, the award was increased to £2,900 being the value of the house in 1965. As explained by Lord Denning MR (at p 414), the right method of assessing the damage was as follows:
If the defects had not been so serious, and the house could have been repaired at a reasonable cost, the damages would be the cost of repair at the date when in 1965 the breach was discovered. ... But in 1965 it was not a economical proposition to repair the house. It would have cost too much to underpin it. The only thing was to pull it down. In these circumstances, it seems to me that we should apply the general principle that the party injured by the breach should be put into as good a position, as far as money can do it, as he would have been if there had been no breach. If this house had been properly built, it would have been worth £2,900 in 1965 when the breach was discovered. That is the proper figure of damage.
34 Megaw LJ arrived at the same conclusions but by a slightly different route. He said (at p 417):
In relation to the question of damages and the question of interest, I think that the principle laid down in the Sale of Goods Act 1893 for remedy for breach of warranty provides guidance although this is a case of sale of goods. In s 53 of the Sale of Goods Act 1893 this general principle is laid down:
(2) The measure of damages for breach of warranty is the estimated loss directly and naturally resulting in the ordinary course of events, from the breach of warranty.
(3) In the case of a breach of warranty of quality such loss is prima facie the difference between the value of the goods at the time of delivery to the buyer and the value they would have had if they answered to the warranty.
So, if that is applied by analogy here, the prima facie rule would be that one looks, in assessing the damage, to the time of delivery. That would be the time of the building of the house in 1958. But it cannot be too much stressed that that is a prima facie rule and is so expressed. Where, as here, the plaintiff is unable to take his action to recover his remedy for breach of contract at the time of delivery because of the fraudulent concealment by the defendant, the prima facie rule in my view is displaced: the time of delivery ceases to be relevant and the time that becomes relevant instead is the time when with reasonable diligence the cause of action is discovered. In this case that was 1965. Accordingly, in my view, the measure of damages here for this breach of contract, which has to be treated as a breach of warranty, was that which naturally resulted in the ordinary course of events from the breach, having regard to events as they were when it was first discovered by the plaintiff in June 1965. On that basis the correct solution of this problem appears to me to be that one should look at the loss as it was at that date. If there had not been the fraudulent concealment of the breach of contract, the plaintiff would have been entitled in 1958, soon after the breach occurred, to damages of £1,900, being the then cost of reinstatement, or the value, of the building. I have no doubt that Mr Brooke is right in his submission that one must take into account in those circumstances that fact that the plaintiff could and almost certainly would have used that £1,900 at that date to buy another house, which, it must be assumed, would not have had defective foundations; and the value of that other house, as a result of what happened between 1958 and 1965 would have been £2,900 in 1965.
35 In the present case repairs were economically feasible and were in fact carried out. The plaintiffs did not incur those costs because they were no longer the owners of the flat at the time the repairs were done. The plaintiffs` contention is that nevertheless they are entitled to claim the diminution in the value of the flat since the fact it was sold before repairs were effected does not mean that they did not suffer loss by reason of the defendants` breach. They relied on , where the defendants had contracted to install a damp proof course in a house in 1964. The work was defective and when the plaintiffs in that case tried to sell the house in 1968 for £8,000, there were no takers. Subsequently, the defendants did some remedial work and gave a guarantee that the problem was solved. A year later the plaintiffs put the house on the market again but, as the court found, the history of the matter had rather spoiled the market for the sale of the house and, as a result, the price the plaintiffs eventually obtained, £7,350, reflected a discount for the risk that the defendants` guaranteed damp proofing system would not work. It was held that the correct measure of damages was the difference between the price the plaintiffs wanted and the discounted price they actually received.
36 I accept that in the present circumstances it would not be correct for me to measure damages by using the cost of repair basis and that the diminution of value basis is the appropriate basis. The defendants cannot insist that, in order to entitle themselves to claim damages, the plaintiffs must hold on to ownership of the house whatever the other pressures on them may be. The case shows that even when the sale is entirely voluntary, the injured plaintiff may be entitled to have his damages assessed on this basis. Here the sale was effected by the mortgagee. That fact should not affect the plaintiffs` right to claim compensation for the diminution in value of the flat, if any, which arose by reason of the defendants` breach.
37 The defendants` response to this position is that even using diminution in value as the basis of assessment, the plaintiffs have not sustained any actual damage and are entitled only to nominal damages. Their point is that the flat was auctioned in August 1987 at a time when the structural defects to the buildings were not common knowledge and the $295,000 auction price reflected the market value of a structurally sound flat in a structurally sound building. Thus, their breach has not caused actual loss to the plaintiffs. Accordingly, the defendants imply that the plaintiffs` damages have to be assessed as of the date of sale of the flat .
38 The plaintiffs, however, take a different tack. They contend that the proper measure of damages is the difference at the time of purchase of the flat between its value in its assumed good condition and its value in its actual bad condition. On this basis they assess their damages at $69,900 being the difference between the purchase price of $465,900 and the figure of $396,000 which their valuer gave as the value of the structurally defective flat in February 1981, on the basis of a 15% drop in value.
39 Before discussing which date is the correct date I should determine the value of the flat in August 1987. The plaintiffs` valuer who, on their instructions given in July 1993, examined the state of the property market in relation to the flat in 1987, gave it as his opinion that the fair market value of the flat in August 1987 in its structurally defective state was $360,000. To counter this evidence the defendants called Ms Lydia Wong who had actually carried out a valuation of the flat in July 1987 on the instructions of the mortgagee. Ms Wong`s report issued on 17 July 1987 put the then fair market value of the flat at $295,000. According to Ms Wong, at the time she carried out the valuation the defects in the structure of Block E and the flat were not common knowledge and she had been unaware of them. Accordingly, her valuation had been arrived at on the assumption of a structurally sound unit. Having considered the evidence of both the plaintiffs` valuer Mr Teo, and that of Ms Wong, I accept Ms Wong`s valuation as reflecting the true market value of the flat in August 1987 on the basis that both the flat and Block E were free from serious defects. Brief reasons for my finding are:
(1) The plaintiffs failed to adduce any evidence that at the time of the auction the value of flats in Maryland Park had been affected by the defects. Mr Teo said he knew about the defects at around that time but he was talking six years after the event. It was clear from the newspaper reports produced that the public announcement of the defects was not made until October 1988. Ms Wong who had actually valued the flat at that time had not heard about the defects. It is therefore probable that Mr Teo only learnt of the defects in 1988 but, after a lapse of five years, believed that he had known of them earlier. Further, Mr Teo confirmed under cross-examination that sales data given by him in App 1 of his report were sales figures achieved before there was a percentage dip in price due to knowledge of the defects. This Appendix disclosed that there had been sales of units in Block E in November and December 1987 at prices ranging between $340,000 and $375,000. Thus Mr Teo`s opinion that $360,000 represented, on 20 August 1987, the value of a defective flat is difficult to support.
(2) Mr Teo`s analysis of the assumed dip in property prices was done by comparing figures in App 1 and App 2 of his report. Appendix 1 dealt with sales in November and December 1987 whereas App 2 dealt with sales between April 1988 and April 1989. He drew his conclusions from the gross sales figures and did not make any adjustments for material considerations such as orientation, time, height and age of the flats concerned. His analysis was thus not supported by detailed reasoning.
(3) Mr Teo agreed that after October 1987 there was a fall in property prices generally due to the stock market crash on 20 October 1987. His calculation that there was a 15% drop in the value of flats at Maryland Park caused by the disclosure of the defects includes the percentage drop caused by that stock market crash. Although he said that two-thirds of that 15% was attributable to the disclosure and the other one-third was attributable to the stock market crash, he could not substantiate these proportions.
(4) On the other hand, Ms Wong did her valuation at the material time and had the advantage of the feel of the ground. She relied on data of sales effected prior to July 1987 and made adjustments for market movements during the second quarter of 1987. She also made careful adjustments for considerations such as orientation, height and age of block. I found her to be an impressive witness who was not shaken in cross-examination.
40 Since the flat was sold for $295,000, its fair market value in a sound condition in August 1987, if the plaintiffs` damages had to be assessed as that date it would appear that they have not suffered any loss by reason of the defendants` breach. On the other hand, both valuers agreed that once the structural defects in the flat came to the knowledge of the public, its market value would decrease. Mr Teo estimated that the price adjustment would be 15% whereas Ms Wong gave two actual examples of how prices of flats in Maryland Park had been affected by the disclosure of the defects. In one case the price fell by 20% and in the other there was a 10% fall in price. So if the date and method of calculating damages put forward by the plaintiffs is correct, the award would be a sum representing between 10-20% to the price of the flat to reflect its actual value in its defective state as against the market value of a sound flat at that time as shown by the purchase price.
41 Reverting to the issue of the relevant date, in this connection, the plaintiffs rely on three English Court of Appeal decisions viz , and . The defendants rely on case.
42 The trio of cases cited by the plaintiffs involved suits by purchasers of houses against surveyors for negligent survey. What had happened in each case was that the plaintiff had, prior to purchasing a property, asked the defendant surveyor for a report on the condition of the building concerned. In each case the report had been favourable and the plaintiff had gone ahead to pay the price asked for by the vendor. Subsequently substantial defects were discovered in those houses. In the ensuing litigation the main issue in respect of damages was whether the plaintiff should be awarded the cost of repairing the defects which the surveyor had overlooked or whether the award should be for the diminution in the value of the house. It was held that, in these circumstances, the proper award would be the difference in money at the date of purchase of the house between the value of the property in the condition described and its condition as it should have been described. In two of the cases the cost of repairs exceeded the loss in value and in the third case the house was sold at a profit with only minor repairs having been effected.
43 In , the earliest of the cases, the applicable principle enunciated by Denning LJ at p 473 was:
I take it to be clear law that the proper measure of damage is the amount of money which will put Mr Philips into as good a position as if the surveying contract had been properly fulfilled: see , per Lord Haldane LC. Now, if Mr Ward had carried out his contract, he would have reported the bad state of the timbers. On receiving that report, Mr Philips would either have refused to have anything to do with the house - in which case he would have suffered no damage - or he would have bought it for a sum which represented its fair value in its bad condition - in which case he would pay so much less on that account. The proper measure of damages is therefore the difference between the value in its assumed good condition and the value in the bad condition which should have been reported to the client.
44 Later in his judgment (at p 474) Denning LJ said that it was right to assess the damages as at the date on which the house was purchased following the general principle of English law which is that damages must be assessed as at the date when the damage occurs, which is usually the same day as the cause of action arises but which may be later.
45 In , Bingham LJ gave this rationale of the principle established in the ` case3 (at p 118):
The restitutory or compensatory principle which underlies the award of damages in contract is not open to question. Since it is ultimately a question of fact what sum of money is necessary to put a particular plaintiff in a position he would have been in if the particular defendant had properly performed the contract in question, I would accept Mr Naughton`s contention that the measure of damages cannot be governed by an inflexible rule of law to be applied in all cases irrespective of the particular facts and regardless of whether or not such measure gives effect to the underlying principle. ... In the present field, by which I mean the purchase of houses by private buyers in reliance on a negligent survey of structure or condition, has been generally thought to lay down and in my view did lay down a prima facie rule for measuring damages. The crucial question is whether that prima facie rule was, as the judge held, inapplicable to the facts of the present case.
46 I do not think so. In , as in the present case, the cost of repairs exceeded the diminution in value. The Court of Appeal there pointed out that if the plaintiff received the house (for which he had paid £25,000) and £7,000 (the cost of repairs) he would in effect have obtained the house for £18,000. But the value of the house in the defective state in which it had actually been was £21,000, and had the defendant properly performed his contract the plaintiff could not have bought at any lower price. An award of £7,000 would not therefore have put him in the same position as if the defendant had properly performed his contract. It would have improved his position to the extent of £3,000 and thus put him in an advantageous position he could never have enjoyed had the defendant properly performed.
47 The same simple approach applies here. The plaintiffs paid £177,500, the value of the house as it was represented to be. The value of the house in its actual condition was £162,500, a difference of £15,000. The actual cost of repairs was (in rounded up figures) £34,000. If the plaintiff were to end up with the house and an award of £34,000 damages he would have obtained the house for £143,500. But even if the defendant had properly performed his contract this bargain was never on offer. The effect of the award is not to put the plaintiffs in the same position as if the defendant had properly performed but in a much better one.
48 The defendants contended that the above cases are distinguishable as I am not here concerned with a purchase made in reliance on a negligent survey report. They say that I should be guided instead by which is directly in point in that it deals with the liability of a builder who has breached his obligation to build a sound building. It would be recalled that in the loss was assessed as at the date of discovery of the breach and not as at the date of the breach itself. I do not think that it is sufficient to distinguish et al on the basis that these cases related to surveyors` negligence. Instead one must examine the basic principle behind both sets of decisions which led to two different dates being applied.
49 As is clear from the extracts quoted above, both categories of cases proceeded on the basis that the principle governing the award of damages was to put the plaintiff in the position in which he would have been had the breach not occurred. It was also a prime concern of all the judges involved in the line of cases that the plaintiff should not be better off by the award than he would have been if no breach had occurred.
50 It would be recalled that in , Denning LJ said that damages must be assessed at the date when they arise which is generally the date of the breach of contract but which may be later. In , Megaw LJ pointed out that in sales of goods cases damages arising by reason of defects in quality were to be assessed at the time of delivery. Thus, the prima facie rule is to assess damages at the date of the breach unless there is a good reason to postpone assessment to a later date. In the survey cases there was no reason to move from that prima facie date as the defects were discovered shortly after the breach. Also, the negligent reports meant that the plaintiffs concerned lost the opportunity to buy their homes at their true values and had to pay inflated prices so that the date of purchase was the true date of the loss.
51 On the other hand in , there was a good reason for postponing the date of assessment, namely, that the plaintiff did not and could not discover the defects until a later date. As Megaw LJ stated, the prima facie rule could be displaced if the plaintiff was unable to discover the breach at the time of delivery and the relevant time then became when the cause of action was discovered. In that case too, as both Megaw and Denning LJJ emphasized, assessing damages at the date of the breach would not have put the plaintiff into the position he would have been in had no breach occurred.
52 In the present instance the plaintiffs did not and could not have discovered the breach at the time or shortly after they purchased the flat. The defects were latent rather than patent and it took time for them to appear. Not having the ability to become aware of the defects, the plaintiffs were not in 1981 in a position to negotiate for reduction of the price. Wanting the flat, they had to pay the asking price which, presumably, was in line with the then prevailing market conditions. That is one reason why the prima facie rule should be displaced here as well.
53 Also, whilst the flat would have been worth (assuming its area was the 181.5 sq m estimated in the contract) between 10% to 20% less than the asking price had the defects been known, the plaintiffs could, since the defects would not have been detected by any potential buyer, have resold the flat at that time as a sound flat for a price close to the purchase price. In that event no damage would have been sustained. I cannot accept the plaintiffs` contention that if the relevant date for assessment is the date of purchase the way to assess damages would be by estimating the then value of the flat in its defective condition and awarding the difference between that figure and the purchase price. Assessing damages in that way presupposes knowledge of the defects which knowledge was completely absent. Even if damages were assessed as at date of purchase therefore, I would have to say that no damage were sustained. The fact that damage were not sustained then does not mean, however, that the plaintiffs would never suffer any by reason of the breach. Once the plaintiffs discovered the defects there would, at the least, be damage to the extent that expenditure on repair would be incurred or reasonably anticipated. The second reason why the prima facie rule should be displaced, therefore, is that if it was invoked the defendants would be able to escape from having to compensate the plaintiffs for loss arising naturally from their breach of contract. Such a result is, in principle, wrong.
54 A further reason for not assessing the damages at the date and in the way which the plaintiffs argued for, is that doing so would give the plaintiffs a profit which they would not have obtained had there been no defects. Unfortunately for the plaintiffs, as the evidence showed, property prices of condominium units peaked in 1981, then declined slightly till about 1982, then picked up again so that they almost reached 1981 levels in 1983 and then slid right down, bottoming out in 1986. In 1987 the prices picked up somewhat but were nowhere near the highs achieved in 1981 and 1983. So in August 1987 the plaintiffs had a flat which the market valued at $295,000 and which in 1981 they should have paid $390,175.27 (ie the amount which a flat of 152 sq m in area was worth then) for. They had therefore lost approximately $95,000. But this loss was caused not by the defects in the flat but by the unforeseen decline in the property market generally, a matter which was completely outside the control of the defendants. If the plaintiffs had paid $390,000 for another flat in the vicinity of Amber Gardens in 1981, they would, in 1987 have still faced the situation of a loss in value of some $95,000 in respect of that other flat. For me to ignore this position and say that nevertheless because the flat itself was defective the plaintiffs are entitled to recover 10% to 20% of the price they paid for it would, to paraphrase Bingham LJ in the case, be to put the plaintiffs in an advantageous position which they would never have enjoyed had the defendants properly performed. This would run completely counter to the compensatory or restitutionary nature of a damages award.
55 I therefore conclude that in the present case the date at which damages should be assessed is the date when the plaintiffs became aware of the defects. That was in February 1987. No evidence was adduced as to the market value of the flat at that date. But since the defects were not publicly known then the flat would, if sold, have fetched the prevailing market price for a sound flat, as it in fact did when it was auctioned six months later. It is therefore clear that, very fortunately for the defendants, the plaintiffs suffered no actual damage as a result of their breach of contract and can only recover nominal damages, which I assess as $10, for that breach.
56 Issue 3: what interest are the plaintiffs entitled to?
57 The defendants` submission is that interest on the sum of $75,724.73 damages agreed for the shortfall claim should be awarded to the plaintiffs only for the periods 9 September 1987 to 29 December 1987 and from 18 August 1992 up to date. The defendants state that the date of the loss has to be taken as 18 March 1982, the date on which the subsidiary strata certificate of title, which showed the area of the flat, was issued. Although legal completion took place on 30 April 1982, on which day the shortfall in the area came to the plaintiffs` notice (at least constructively as that was the day on which their solicitor would have seen the certificate), a period of five years and four months elapsed before the plaintiffs sent, on 9 September 1987, a letter from their solicitors alleging the shortfall and demanding reparation. This long delay between knowledge of the shortfall and the making of the claim led the defendants to believe, reasonably, that no action would be taken. Further, the agreement for sale did not mention a specific area but only gave the estimated area of the flat. At that time the defendants` legal liability was unclear and the legal position was only ascertained after judgment was delivered in September 1987 in the case of . Therefore, interest should not start to run till 9 September 1987 at the earliest.
58 Secondly, this action was commenced on 24 September 1987 and shortly thereafter an application for summary judgment was filed. The plaintiffs withdrew that application on 29 December 1987, however, and did nothing for the next two years and one month. On 19 January 1990, the plaintiffs` present solicitors filed a notice of intention to proceed but no further step was in fact taken until two years and seven months later when, on 18 August 1992, a further notice of intention to proceed was filed. So interest should stop accruing on 29 December 1987 and not run again until 18 August 1992.
59 In reply, the plaintiffs say that interest should run from the date of the sale and purchase agreement, ie 9 February 1981, to the date of judgment. They have been kept out of their money since then and the defendants having had the benefit of this money should not be allowed to retain it since they are the party in breach. As regards the second period of delay their response is it was caused by the complexity of the case. There were legal and technical difficulties encountered especially with regard to the point taken by the defendants that the plaintiffs had no right to institute proceedings against them because they had assigned all their rights, title and interest in and to the sale and purchase agreement to the mortgagee. The defendants only dropped this point just prior to the commencement of the trial.
60 I cannot accept the defendants` argument that because they were not notified of the claim until 9 September 1987 and further that because prior thereto the legal basis of their liability for the shortfall claim was not clear to them, interest should not be awarded for any period before September 1987. That argument overlooks the fact that the defendants have had the use of money to which they were not in law entitled. They cannot make a profit out of their own breach of contract. In a case like this where money has been paid to which a party is not entitled, the interest should run from the date of payment. This conclusion is supported by , another case involving the sale of a flat the actual area of which turned out to be less than the estimated area in the agreement for sale. In that case the buyer had paid the full balance of the purchase price on completion under protest although he wanted to withhold a sum of $70,023.80 in compensation for the shortfall. He was awarded interest on this sum at 6% pa from the date of completion up to the date of judgment.
61 On the other hand I do not agree with the plaintiffs that interest on the whole amount has to be calculated as from the date of the agreement for sale. The plaintiffs were not out of pocket for the whole amount on that date. The agreement provided for payment of the purchase price by instalments. Bearing in mind that the flat`s actual area was approximately 16.25% less than the estimated area, this means that each instalment payment made by the plaintiffs contained an overpayment of 16.25%. Accordingly, the plaintiffs are entitled to interest on 16.25% of each such instalment from the date on which it was paid. In the case of any money paid before the date of the agreement, interest should run as from the date of the agreement.
62 The next question is whether interest should run up to date of judgment or whether, as the defendants submit, the period 29 December 1987 to 18 August 1992 should be interest free due to the plaintiffs` dilatoriness in prosecuting the action. Whilst the case may have presented certain legal difficulties especially in connection with the issue of title to sue, this is really no excuse for a four and a half year delay. I note, however, that in January 1990 the plaintiffs changed solicitors. A change of lawyers often involves some delay and, as long as the period is not unduly prolonged, the plaintiffs should not be deprived of interest on that account. I think that six months would be more than a reasonable time for the new solicitors to acquaint themselves with the facts and law. Accordingly, I hold that the applicable periods for the calculation of interest due to the plaintiffs should be from the respective payment dates up to 19 July 1988 (being six months after the new solicitors were appointed) and from 18 August 1992 up to the date of judgment.
63 Finally, at what rate should interest be calculated? The plaintiffs` position is that the court should, in exercise of its wide discretion under s 9 of the Civil Law Act (Cap 43), award interest at the rate they were charged under their contract with the mortgagee. They say that justice and fairness require that the plaintiffs be compensated by an award at this rate which varied between 16.5% pa and 9.5% pa. They urge me to bear in mind the following:
(a) Lakhmichand`s evidence that the defendants told him that the mortgagee, their sister company, could finance the purchase of the flat at a better rate than a bank. The defendants therefore knew at the time of the agreement for sale that the plaintiffs would need financing in order to meet the purchase price.
(b) The defendants and the mortgagee have common directors and a common managing director. Managementwise, the mortgagee and the defendants constitute a single unit.
(c) The plaintiffs borrowed money from the mortgagee to finance the purchase at $465,900 when in fact after taking into account the shortfall in area the true value of the flat was $390,175.27.
64 The defendants` response is that the usual rates awarded by the court should be taken and the maximum award should be the 8% pa carried by judgment debts. They say that if the plaintiffs are awarded interest on the basis of what they paid the mortgagee they would in fact be recovering special damages and that this is not permissible since there was no pleading particularizing such special damages.
65 In this instance I think that since the defendants were well aware from the outset that the plaintiffs would be borrowing to finance their purchase of the flat and in fact took the opportunity to send the business in the direction of their `sister` company, and since the court awards interest as compensation for monetary loss, it would be correct to allow the plaintiffs to recover interest at the mortgage rate, at least for part of their claim. I would like to emphasize that by mortgage rate I mean the normal mortgage and not the rate charged on default of punctual payment. The defendants should not have to bear any additional interest incurred by the plaintiffs by reason of the latter`s failure to pay their mortgage instalments punctually. Secondly, it would not be fair to award interest at the mortgage rate after the date on which the flat was sold as the plaintiffs should have mitigated their loss by repaying the outstanding loan amount.
66 The plaintiffs borrowed $370,000 from the mortgagee. That was 79.4% of the purchase price. Accordingly, only 79.4% of each overpayment made by the plaintiffs should carry interest at the mortgage rate from the date of payment up to 20 August 1987. In respect of the remaining 20.6% of each overpayment, I award interest at 8% pa from the date of payment up to 20 August 1987. As from 21 August 1987 to the date of judgment (excluding of course the period 20 July 1988 till 17 August 1992), the interest should be calculated at the rate of 6% pa as during this period interest rates had fallen substantially.
67 Issue 4: Costs
68 Relying on the principle established in and , the defendants submitted that if in this action the plaintiffs recovered only nominal damages they should not be regarded as successful plaintiffs and I should treat the defendants as having succeeded and award them the costs of the action. The policy behind this principle is, of course, to discourage frivolous litigation since not every breach of contract will actually cause loss to the innocent party.
69 Whilst I accept the above principle, the circumstances of the present case are such that it would be wrong to apply its full rigour to the plaintiffs. In the first place, I think that the plaintiffs must have their costs up to the time the trial started as it was not till then that the defendants conceded the shortfall claim and dropped the title to sue point. As regards the costs of the trial itself, the trial was unduly prolonged by the defendants` insistence that they had not breached their duty to construct the flat in a good and workmanlike manner. In support of their defence, the defendants did not call anyone who was actually involved in the construction. Instead they relied solely on the evidence of a consultant engineer who was engaged only in 1993 and then for the purpose of criticizing Dr Lau`s report. The defendants thus put up a negative rather than a positive defence. In fact it was an academic defence and as such had little chance of success. Accordingly, I think that the defendants should get only 50% of the costs of the trial.
70 Conclusion
71 For the foregoing reasons, there will be judgment for the plaintiffs by consent in the sum of $75,724.73 and further judgment for them for damages of $10. In addition the plaintiffs are entitled to interest on $75,724.73 up to date at the rates and in the manner specified above. I do not know the dates on which instalments were paid by the plaintiffs or the amounts of such instalments and I will therefore see the parties in chambers on the exact form which the order for interest should take. The plaintiffs are awarded the costs of the action up to the commencement of the trial and the defendants are awarded 50% of their costs incurred in the trial itself.
72 Order accordingly.
Judith Prakash JC
Shantini Ramachandra (Wee Ramayah & Pnrs) for the plaintiffs
Sim Eu Jin (Peter Yap & Co) for the defendants