grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Gunac Enterprises (Pte) Ltd v Utraco Pte Ltd
[1994] SGHC 22
Suit No 738 of 1990
Judith Prakash JC
29 January 1994
1 JUDGMENT:
2 Cur Adv Vult
3 Background
4 This claim arises out of certain remedial works which were carried out to the National Stadium ("the Stadium") in the first half of 1989 pursuant to a contract ("the main contract") which the defendant company had been awarded by the Singapore Sports Council ("the Council"). The plaintiff company was a sub- contractor employed by the defendants in relation to the project.
5 In 1988, the Stadium had a serious problem of water leakage through the gallery slabs and joints. As a result, the steel bars in the slabs had corroded and the concrete had been severely weakened resulting in a lot of spalling i.e. in places the concrete had disintegrated and pieces of concrete had fallen off. More serious than this was that the beams and columns of the Stadium were similarly affected, thereby weakening the whole structure of the Stadium. The defendants' job was to arrest the problem of corrosion and weakened concrete and to strengthen the structure of the Stadium. Apart from repairing and/or replacing corroded bars and weakened concrete and affected beams and columns, the defendants had also to apply protective coatings over the slabs and rib beams of the entire gallery and also over the underside of the gallery (the soffits). This coating work was the work which the defendants sub-contracted to the plaintiffs.
6 On 19 December 1988 the plaintiffs and the defendants signed a sub-contract agreement ("the sub-contract") whereby the plaintiffs agreed to "supply and install Waterproofing Preventive Coating to slab top and soffits, the inner and outer face of rib beams in the grand stands, the underside of concourse level, underside of staircases and other areas" ("the sub-contract works"). The Additional Conditions of the sub-contract in giving a detailed description of the sub-contract works stated, inter alia, that it comprised: "(a) Application of Vibalastic Flexible Waterproofing Slurry/Vibacote TW to top of slab and inner face of rib beam in the gallery area and ring gate steps ... (b) Application of Vibacote TW to concrete faces and soffits of unprotected concrete on underside of slab, outer face of rib beam in the gallery area, underside of concourse, level soffits, columns and staircases..." (emphasis added).
7 The plaintiffs commenced work on both the topside and the underside of the galleries in February 1989. In May 1989, by which time about a third of the topside work had been done, the defendants terminated the plaintiffs' work on the topside on the basis that the materials supplied were not the Vibalastic waterproofing slurry and Vibacote TW which had been contracted for the work but instead materials manufactured by the plaintiffs themselves. The defendants did not, however, terminate the plaintiffs' work on the underside although the material being used on the underside was, in the defendants' view, not the material which had been contracted for but a material manufactured by the plaintiffs. The plaintiffs completed the work on the underside in October 1989. In April 1990, the plaintiffs commenced this suit whereby they claimed the balance of $25,555.36 owing to them by the defendants in respect of the work on the underside, the sum of $117,086.69 for the work which they had done on the topside prior to the defendants' termination, and damages (estimated at $78,952.30) for wrongful termination of the topside work. The defendants denied liability (except as to the sum of $25,555.36) and filed a counterclaim on the following grounds: 1. it was a condition of the sub-contract that the waterproofing materials to be supplied and applied by the plaintiffs be the materials known as Vibalastic Art 45.35 and Vibacoat TW Art 20.42 ("the Vibak materials") manufactured by a Swiss company known as Vibak Bautenschutz ("Vibak"); 2. alternatively, it was also a condition of the sub-contract that the waterproofing materials to be supplied by the plaintiffs would comply with the specifications for such materials set out in the main contract between the defendants and the Council; 3. in breach of contract, the materials supplied by the plaintiffs were manufactured by themselves and not by Vibak; 4. in further breach of contract, the materials supplied did not comply with the specifications and were defective; 5. the defendants had to complete the works and put right the defective works and had suffered loss; 6. alternatively, the sub-contract had been entered into on the basis of the plaintiffs' representation that the materials to be used for the sub-contract works were the Vibak materials and this was a misrepresentation in that all along the plaintiffs had fully intended to supply their own materials.
8 In their reply to the defence and counterclaim, the plaintiffs denied that they had contracted to supply the Vibak materials and said that the contract was a sale by sample and description and the samples which had been supplied and accepted were samples of materials manufactured by the plaintiffs themselves. They denied the misrepresentation and further denied that the materials did not live up to the specifications.
9 From the above summary, it is clear that the main issues to be decided are the following: 1. whether it was a condition of the sub-contract that the materials to be supplied and applied by the plaintiffs were the Vibak materials; 2. whether the materials actually supplied complied with the specifications or were inferior or defective materials; 3. whether the defendants were entitled to terminate the plaintiffs' work on the topside while continuing to employ them to work on the underside; 4. whether there was any misrepresentation and if so whether the defendants were entitled to rescind the sub-contract; 5. if the answer to any of the above questions is in the affirmative, the quantum of the damages which the defendants are entitled to claim from the plaintiffs.
10 Issue 1 : what materials were to be supplied? This first issue is an issue of construction of the sub-contract. The point of departure must therefore be the sub-contract itself. The relevant parts of the sub-contract in this context are Parts I, III and V of the Appendix. Part I states that the "particulars and description of the works" are to "supply and install Waterproofing Preventive Coating to" followed by description of the areas to be covered. Thus Part I specifies a generic type of material only and not any particular brand. Parts III and V are, however, more specific. Part III deals with the price of the sub-contract works and states: "(a) Waterproofing by flexible slurry Vibalastic and Vibacote - topcoat @ $7.10/m2. (b) Waterproofing by flexible slurry Vibalastic/Vibacote - underside coating @ $3.50/m2." Part V contains the text of clause 20 of the sub-contract, the "Additional Conditions". The first of these conditions is entitled "Scope of Work" and sets out what is described as a "detailed work description" of the sub-contract works. Sub clause (a) deals with "Application of Vibalastic Flexible Waterproofing Slurry/Vibacote TW to top of slab and inner face of rib beam in the gallery area and ring gate steps". It spelt out that the plaintiffs were to supply supervisory staff, labour, material, equipment and tools to complete six steps of the work. Among these, under sub paragraph (a.a) the plaintiffs had to clean the surface (the substrate) to a condition suitable to receiving "Vibalastic flexible waterproofing slurry"; under sub paragraph (a.c) they had to apply "two coats of Vibalastic slurry" to the prepared surfaces; and under sub paragraph (a.d) they had to apply "one coat of finishing coat, Vibacote". Sub paragraph (b) dealt with the application of "Vibacote TW" to concrete surfaces and other areas. Here the plaintiffs had to supply supervisory staff, labour, material, equipment and tools to complete four steps of the work. Among these, under sub paragraph (b.a) the plaintiffs were to check that the substrate was suitable to receive "Vibacote TW waterproofing slurry", and under sub paragraph (b.b) they were to apply "one coat of Vibacote TW slurry" to the prepared surfaces.
11 It should be noted here, to avoid confusion, that in the documents the word "Vibacote" is sometimes spelt "Vibacoat". No issue turns on the difference in the spelling and in this judgment I will use the spelling used in the sub-contract unless quoting from a document using the alternative spelling.
12 In my opinion, the cited contractual provisions leave no doubt that the plaintiffs' obligation under the sub-contract was to provide and apply not just any generic waterproofing coating but: 1. to the topside of the gallery and other specified areas, a waterproofing coating consisting of two coats of Vibalastic slurry and one finishing coat of Vibacote TW; 2. to the underside of the gallery and other specified areas, one coat of Vibacote TW slurry. The sub-contract does not, however, expressly state that the terms "Vibalastic" and "Vibacote TW" refer to products manufactured by Vibak. These product names are technical or commercial terms and their meanings depend on the parties' intentions. In order to discover what the parties intended that they refer to, I must examine the factual background against which the sub-contract was made.
13 Prior to tendering for the main contract, the defendants were aware that one of its major requirements would be the supply and application of waterproofing and protective materials to the Stadium. They knew that the specifications for such materials required two types of coating. The first coating, a wear resistant preventive coating to be applied to the topside, had to have excellent bonding properties to concrete, remain solvent free, be flexible, be wear and weather resistant, have non-skid and good waterproofing properties but at the same time be breathable. It also had to be elastic and have a flexural strength allowing it to bridge hair-line cracks of up to 0.2mm. The second coating, that to be applied to the underside, had to have the same qualities as the topside coating except that it did not need to be wear resistant nor display non-skid properties since it would not be subject to human traffic.
14 At the time that the main contract was awarded, waterproofing of structures such as the Stadium was a new area in the construction industry. The consultant for the project had discovered that an excellent waterproofing product called Strongcoat was being manufactured in the United States. It had been used to protect several stadiums there and elsewhere from water penetration and corrosion. The consultant investigated this product and, finding it favourable, advised the defendants to use it. The main contract did not, however, specify that Strongcoat be used but instead incorporated the specifications of Strongcoat coating on the basis that any material supplied would have, as a minimum, to comply with these specifications.
15 The defendants had initially shortlisted two possible suppliers of coating material: a local company representing the Strongcoat products and another marketing a product called Barralastic which was manufactured in Switzerland. Strongcoat was, however, the favoured product. Subsequently, the defendants encountered difficulties with the Strongcoat suppliers as the latter were not willing to give a ten year guarantee for their product as required by the Council. The defendants therefore looked into other possibilities.
16 Sometime in July 1988 the defendants were approached by the marketing manager of the plaintiff company, one Danny Leong. According to the defendants, Mr Leong gave them a ring binder containing brochures produced by Vibak for its various products including "Vibalastic Art 45.35" described as a "Flexible Waterproofing Slurry" and "Vibacoat TW Art 20.42".
17 Mrs Tan (Mdm Tay Watt Moi), the defendants' administration and finance manager, studied the contents of the ring binder together with the defendants' engineer, Mr Loh. They found that in it there was a product which was technically equivalent to the other two products they were considering and Mrs Tan then instructed Mr Loh to ask the plaintiffs for a quotation. On 12 July 1988, the plaintiffs submitted their quotation to the defendants. This quotation was for the supply and application of "VIBALASTIC Flexible Waterproofing Slurry". The cover letter stated that enclosed with the quotation was, inter alia, the relevant technical brochure.
18 There was a dispute as to what documents were actually forwarded with the quotation. According to the plaintiffs, the technical brochure referred to was the document marked "PB43-44" which consisted of four sides of paper which each bore at the top the plaintiffs' name and the words "Data Spec". The first side also stated "VIBALASTIC Flexible Waterproofing Slurry". This brochure described a product known as "VIBALASTIC". It did not state specifically who the manufacturer of the product was. On the other hand, at the end of the brochure, was a note reading "The Gunac Group warrants that its products are free from manufacturers' defects...".
19 According to the defendants, PB43-44 was not the technical brochure sent to them under cover of the letter of 12 July. Instead the plaintiffs had sent them first, a folded Vibak product summary sheet headed "VIBAK" and having the words "Building Protection Products Summary" in English, German and French on the front page, secondly a two-paged product leaflet for each of "Vibalastic Art 45.35" and "Vibacoat TW Art 20.42", and thirdly a two paged data specification for "Vibacoat TW".
20 Subsequently, the plaintiffs and the defendants held negotiations on the price and the warranty. At the first meeting Mrs Tan met the plaintiffs' managing director, Mr Kong Hoe Leong, and Danny Leong. Mr Kong gave Mrs Tan his calling card. The reverse of this had the words "sole agents" followed by a list of names. Vibak was one of the listed names. According to Mrs Tan, from the beginning of their meetings, Mr Kong and Mr Leong presented the plaintiffs as the sole agent for Vibak. Throughout the negotiations they did not state specifically or even imply that they were not representing Vibak. Further, throughout the negotiations, the products discussed were Vibalastic and Vibacote from Switzerland. At no time did Mr Kong say or imply that the products were the plaintiffs' own. In fact Mr Kong kept referring to Vibak as the plaintiffs' principal and when Mrs Tan asked him whether the plaintiffs' products had the test reports which needed to be submitted to the consultant, Mr Kong replied that he would contact the principal in Switzerland for these reports.
21 On the other hand, according to Mr Kong, his initial quotation was based on a waterproofing material produced by the plaintiffs according to their own formulation. The product offered in the quotation was called "Vibalastic Flexible Waterproofing Slurry" and this was the product mentioned in PB43-44 which he had forwarded with his first quotation. He denied having sent the defendants the leaflets for Vibalastic Art 45.35 and Vibacoat TW Art 20.42. He also said that Mrs Tan was very interested in using the plaintiffs' products for the work due to the time constraints on the defendants. Using the plaintiffs' locally manufactured materials meant that work could commence almost immediately.
22 The defendants found the plaintiffs' first quotation to be far too high and told them so. On 31 August 1988 the plaintiffs sent the defendants a revised quotation in which their prices had been slashed by about 60%. Mentioned in this quotation for the first time was the supply of a finishing coat of "Vibacote" to both the topside and the underside. According to the defendants, among the documents forwarded with the revised quotation were the same Vibalastic Art 45.35 brochure that had been forwarded earlier and a set of "Data Specs" for Vibalastic Waterproofing Slurry.
23 The defendants found the new prices far more acceptable. The plaintiffs were also willing to give the 10 year guarantee required. This gave the plaintiffs an edge over the Strongcoat suppliers. The defendants therefore asked the plaintiffs to put up a mock-up of their product. According to the defendants, the purposes of the mock-up were to enable the Council to choose the colour of the coating and to obtain a demonstration of the method of application of the product. According to Mr Kong, the mock-up was required to enable the defendants and the consultants to inspect the materials and approve them.
24 The mock-up was done at the Stadium on 15 November 1988. The defendants thought that the plaintiffs applied two coats of "Vibalastic Art 45.35" and one coat of "Vibacoat TW 20.42" for the mock-up. In fact all materials used had been manufactured by the plaintiffs themselves. The site sample was approved by the Council and the next day there was a final meeting between Mr Kong and Mrs Tan on the pricing. According to Mr Kong, at this meeting not only were the prices agreed but Mrs Tan specifically requested that the plaintiffs make a one coat system called "Vibacoat slurry" for the defendants. She knew the plaintiffs could do this because all their materials were made locally.
25 On 17 November 1988 the defendants sent the plaintiffs a letter of award. By this letter they confirmed that the plaintiffs were to apply two coats of "Vibalastic Flexible Waterproofing Slurry" and one finishing coat of "Vibacote" to the topside of the Stadium at a price of S$7.10 psm. The letter specifically stated that the contract period would be for about five months beginning January 1989. According to Mrs Tan this letter was sent out after the meeting of 16 November so that the plaintiffs would have a written confirmation of the award of the works and would thus have sufficient time to place the order with Vibak for the manufacture and shipment of the materials to Singapore. Mr Kong had previously told her that since the materials had to be imported and because of the volume involved, he would need about two months from confirmation to get the goods. Because of this requirement the letter stated that work should commence sometime in January 1989. She also said that at the meeting of 16 November there had not been any negotiations on the underside coating and that was why the letter referred only to the topside coating.
26 Enough of the evidence given in this case has been stated above to make it clear that there is a direct conflict of fact between the plaintiffs and the defendants as to what each of them intended the terms "Vibalastic" and "Vibacote" to refer to. Having given all the evidence careful consideration, I have come to the conclusion that the defendants' version is the correct one and that these two terms were intended, to the knowledge of both the plaintiffs and the defendants, to refer to the products "Vibalastic Art 45.35" and "Vibacoat TW Art 20.42" manufactured in Switzerland by Vibak.
27 Some of the reasons for my conclusion are: 1. Mr Kong in his evidence admitted that "Vibalastic" was a brand name and not a generic name for waterproofing material. He agreed that this brand name belonged to Vibak and that he had no authority to use the name for his own product. 2. Mr Kong also admitted that the plaintiffs had previously had a contract under which they were supposed to waterproof a project with Vibak's Vibalastic. In the course of that project, Mr Kong found the Vibak material to be defective and he then replaced it with material of the plaintiffs' own manufacture. He did not however inform the plaintiffs' client of the change in material and allowed the client to believe that the authentic Vibalastic was still being used. 3. Mr Kong could give no good reason for calling the plaintiffs' own locally produced products by the brand names assigned to them by Vibak. He left me with the very strong impression that he was willing to trade on Vibak's name for the benefit of the plaintiffs. 4. It was clear from the plaintiffs' own documents produced in evidence by the defendants (for example Mr Kong's card and the plaintiffs' resume) that the plaintiffs had represented themselves in writing to be Vibak's sole agent in Singapore. 5. It was also clear that some, at least, of the product literature produced by Vibak itself had been sent to the defendants by the plaintiffs and that the plaintiffs had not sent the defendants only the material for their own locally produced materials. Further, the plaintiffs' own brochures did not contain any clear statement that the product "Vibalastic" had been manufactured by the plaintiffs. In the context that the plaintiffs were agents for Vibak which itself produced a material called "Vibalastic" this omission was definitely misleading. 6. At the time that the letter of award was sent out to the plaintiffs, the defendants also informed the consultant that the waterproofing material that they would be using for the Stadium would be "Vibalastic from Switzerland". In this letter the defendants were obviously referring to the Vibak materials. There was no need otherwise to inform the consultant that the materials were from Switzerland as the consultant had no preference in respect of the place of manufacture of the materials or even the manufacturer. All the consultant was concerned about was that the material eventually used would meet the specifications in the main contract. This letter clearly shows the impression under which the defendants were operating and this is an impression which could only have resulted from the behaviour of the plaintiffs and the information given to the defendants by the plaintiffs.
28 At this stage I should also state that I cannot accept the plaintiffs' contention that the sale of the material was a sale by sample. This contention runs counter to the evidence adduced. It was obvious from Mr Kong's testimony that he was aware, if not from the very beginning then from about August 1988, that the material to be used on the Stadium had to comply with certain technical specifications as laid down in the main contract. These specifications were not of qualities which could be determined from a simple physical inspection of the material. They were specifications relating to qualities which could only be ascertained from scientific testing though some of the qualities could have been inferred from an on site physical inspection carried out months after the materials had been applied and subjected to use. Thus it was ludicrous for Mr Kong to contend, as he did in court, that his materials were chosen because the samples used on the mock-up were satisfactory. On the other hand, Mrs Tan's explanation that the mock-up was to enable colour selection and to ascertain the mode of application was completely consistent with the nature of the material and the sub-contract works. Issue 2: did the materials supplied comply with the specifications? During their negotiations with the defendants, the plaintiffs were aware that the material to be applied to the Stadium had to have certain physical properties. As Mr Kong himself testified, some time in August 1988, the defendants told him that the material which was finally accepted for the project had to have test reports from an accredited laboratory evidencing these properties. In that month the defendants also gave the plaintiffs a copy of a letter dated 5 August 1988 which they had received from the consultant for the project. Mr Kong said that the plaintiffs were asked to ensure that their material for the work would conform to the technical specifications set out in that letter.
29 When the sub-contract itself was signed, it did not contain any description of the physical and mechanical properties of the waterproofing material. Under clause 6 of the sub-contract, however, the plaintiffs had to comply with those provisions of the main contract which related to the waterproofing works and which the defendants themselves were supposed to comply with. One of the documents making up the main contract was entitled "Particular Specifications". This contained two clauses dealing with the specifications for the protective materials to be applied to the topside and underside of the Stadium.
30 The relevant portions of these clauses read as follows: "3.11WEAR RESISTANCE (sic) PREVENTIVE COATING The material used shall have excellent bonding properties to concrete, remain solvent free, flexible, wear (abrasion) and weather resistant. They (sic) shall display non-skid and good waterproofing properties but "breathable" i.e. it shall allow water vapour to pass through and not blister. Its flexural strength shall allow it to bridge hairline cracks of up to 0.2mm gap... 3.12PREVENTIVE COATING The material used shall have excellent bonding properties to concrete, be solvent free, weather resistant (sic), good waterproofing properties and (sic) "breathable". It shall be elastic and have flexural strength to bridge over hairline cracks..."
31 It was common ground that the specifications in the above clauses were basically the same as those contained in the consultant's letter of 5 August 1988.
32 In the light of the above, I find that it was a term of the sub- contract that the coating material to be applied by the plaintiffs to the topside of the Stadium had to have the following physical qualities: (a) it had to bond (adhere) well to concrete; (b) it had to be flexible and have a flexural strength which would allow it to bridge hairline cracks of up to 0.2mm; (c) it had to possess good waterproofing qualities but at the same time it had to be breathable so that water vapour could pass through it without causing blisters; (d) it had to be non-skid and resistant to the weather and to wear.
33 I also find that the coating material to be applied to the underside of the Stadium had to have the same physical properties as the material for the topside except that it did not have to be wear resistant nor display non-skid properties.
34 Much of the trial was taken up with establishing whether in fact the materials applied by the plaintiffs to the topside were defective in that they did not display the qualities required by the specifications. It was common ground that these materials, consisting of two coats of cementitious flexible waterproofing slurry and one coat of a protective carbonated material, were manufactured by the plaintiffs themselves and were not the Vibak materials which the defendants thought were being applied.
35 The plaintiffs endeavoured to prove the suitability of their materials by producing the reports of various laboratory tests which had been conducted on the materials. The results of these tests purported to show that the materials complied more than satisfactorily with the contractual specifications. On the other hand, the defendants adduced evidence of the physical defects which had been detected in the area of the Stadium coated with the plaintiffs' materials. They produced a report of an investigation conducted on this area, about a year or so after the materials had been applied, by a company called Taywood Engineering Ltd ("Taywood"). The investigation covered the area of approximately 16,000 sqm treated by the plaintiffs (about one third of the total surface area of the Stadium), and the following were observed: 1. 10,885 cracks; 2. 2,616 spalls of 50mm x 50mm or less (a spall is an area where the coating has become completely detached from the underlying concrete surface and has fallen away thus exposing the substrate); 3. 2,082 spalls of 50mm x 50mm or less in fibre reinforced areas; 4. 449 locations where coating pin-holes and broken bubbles were seen; 5. of the adhesion strength tests carried out to determine whether the coating adhered strongly enough to the substrate, in 21% of the cases the coating did not have the strength of 1.5 newtons per mm2.
36 The conclusion reached by the investigators was that the plaintiffs' material was defective and not up to specifications. In this connection I was impressed by the evidence of Paul Sandeford, a lead engineer employed by Taywood. Mr Sandeford had experience both as a specialist repair contractor on coating projects and as an investigator investigating allegedly defective coatings and making recommendations for rectification.
37 In relation to the requirement that the coating must have excellent bonding properties, Taywood tested the adhesion (or bond tensile) strength of the coating by using elcometer and limpet machines. A minimum strength of 1.5 newtons per mm2 was used as a basis as, according to the plaintiffs' own "Data Spec" (PB58), its material had that adhesion strength when applied to smooth concrete. Mr Sandeford's testimony was that overall for the whole area which Taywood tested, 21% of the adhesion strength results obtained did not meet the requirement of 1.5 newtons per mm2, the failure rate rising to 32% in areas adjacent to defective coating and falling to 12% in areas where no defect was seen. He also said that in the construction industry when concrete is tested, 95% of the results must meet the specified minimum strength of the concrete for the concrete as a whole to be considered satisfactory. Applying that standard, a 21% failure rate for the coating here was unacceptably high.
38 The next quality required was that the coating had to be flexible enough to bridge hairline cracks of up to 0.2mm. According to Mr Sandeford, the fact that on a physical inspection more than 10,000 hairline cracks (typically less than 0.2mm wide) were seen in the coating, showed that it did not meet the flexibility specifications. The material should have been flexible enough to cover such cracks. Although an attempt was made to discredit the results of the physical inspection and the conclusions reached, in my view these attempts were not successful. I was satisfied from the evidence of Mr Sandeford and Mr Chu Beng Han (who actually painstakingly carried out the physical inspection of the Stadium) that that number of cracks had been detected and that they were cracks which were in 90% of cases, less than 0.2mm in width. According to Mr Sandeford these cracks could not have been caused by wear and tear on the Stadium nor by the drying of the substrate.
39 The third quality which was in question was the breathability of the coating. In this connection the investigators observed 449 pin holes and broken bubbles as well as numerous spalls on the surface of the coating. The most likely cause of the pin holing and the bubbling was that the material was not sufficiently breathable. According to the prescribed mode of application, the coating had to be applied onto a wet surface. (This clearly appears from two sets of "Data Specs" produced by the plaintiffs for Vibalastic viz those at PB38 and PB66, though Mr Kong in his oral evidence said that a waterproofing slurry material should be applied to a dry surface.) This meant that as the substrate dried, water vapour would have to pass through the coating. A breathable coating allows the transmission of water vapour without any effect on the coating. When a coating is insufficiently breathable, however, such transmission results in bubbles and pin holes. These bubbles can lead to spalls where the coating becomes entirely detached from the substrate and falls off. The investigators observed some 4705 areas of large spalling and some 18,000 small spalls. Only a few of those were clearly due to major mechanical impact. The most likely cause for the others was defective material which was not sufficiently breathable nor sufficiently resistant to the normal heavy human traffic that can be expected in a structure like the Stadium which is continually subjected to human use.
40 The plaintiffs produced a rebuttal witness, one Dr Henry Ong. I was not impressed by his evidence. He is a chemist with little experience in the coating business. Further, he did not investigate the Stadium at the same time as the Taywood people. By the time he came on the scene, the area which the plaintiffs had worked on had been redone by the defendants. Dr Ong gave various reasons for the defects observed by Taywood. These related to external factors like the climate. His points were well and succinctly rebutted by Mr Sandeford.
41 On the totality of the evidence, I was satisfied that the plaintiffs' coatings on the topside of the Stadium were defective and to a significant degree did not measure up to the contractual specifications. It must be remembered that the plaintiffs were required to give a ten year warranty for their materials. The specifications required a degree of durability and wear resistance which was not satisfied by the plaintiffs' materials. The fact that the defects were so numerous only one year after application tells against the plaintiffs. The plaintiffs' reports of tests carried out in laboratory conditions on samples which would have been thicker than the coatings applied on site, could not counter balance, much less outweigh, the evidence of how the material actually performed when it had been applied on site by the plaintiffs' workmen under the supervision of the plaintiffs.
42 Issue 3: was the defendants' termination of the plaintiffs' works on the topside valid? In April 1989 one Mr Kohler, the managing director of Vibak, visited Singapore. During this visit the defendants learned for the first time that the materials which the plaintiffs were applying to the topside and the underside of the Stadium were not the Vibak materials. As Mrs Tan tells it she then had two conversations with Mr Kong. During the first, Mrs Tan asked Mr Kong what he was going to do about the defects in the materials. His answer was that he would check with his principals in Switzerland. The next day Mrs Tan told Mr Kong that she had met the Swiss manufacturer of the Vibak materials and Mr Kong then admitted that the materials applied to the Stadium had been manufactured by the plaintiffs themselves.
43 On 17 May 1989 the defendants sent the plaintiffs a letter in which they stated that the top coating was "unacceptable due to discrepancies in the properties of the materials applied by you, as compared to the materials from Vibak of Switzerland". The letter went on to say that by reason of the foregoing the plaintiffs would immediately cease to be the defendants' sub- contractor to supply and apply Vibalastic and Vibacote to the topside of the galleries.
44 The defendants' letter did not mention anything about the coating on the underside. According to Mrs Tan, the underside coating did not form part of the discussions between the plaintiffs and the defendants at all. At the time of the defendants' discovery of the false products, the plaintiffs had already completed about 70% of the underside coating. At that time the underside coating, which was only meant to resist carbonation, seemed to perform and the defendants had not received any complaint about it. Accordingly, the defendants allowed the plaintiffs to continue with the underside works although Mrs Tan took the view that contractually she could also have rejected them on the basis that the material used on the underside was not Vibacote TW.
45 The plaintiffs contended very strongly that the defendants' action in purporting to terminate the plaintiffs' work on the topside alone was in breach of contract. They said that in order to terminate the sub-contract properly, the defendants would have had to terminate the whole of the sub-contract works and would have had to follow the procedure laid down in clause 16(a) of the sub-contract. This provided as follows: "If the Sub-Contractor shall make default in any of the following respects, viz "- (i) if without reasonable cause he wholly suspends the Sub- Contract Works before completion; (ii)if he fails to proceed with the Sub-Contract Works with reasonable diligence; (iii)if he refuses or persistently neglects after notice in writing from the Contractor to remove defective work or improper material; then, if such default shall continue for seven days after a notice by registered post specifying the default has been given to him by the Contractor, the Contractor may without prejudice to any other rights or remedies thereupon by notice by registered post determine the employment of the Sub-Contractor under this Sub-Contract; provided that notice in pursuance of this clause shall not be given unreasonably or vexatiously;". The plaintiffs contended that the defendants had not followed clause 16(a) in that they had neither given the plaintiffs written notice to remove the defective work or the improper material of which they complained nor sent them a seven day notice by registered post specifying the default. Accordingly the purported termination was wrongful and in breach of the sub- contract.
46 The defendants, on the other hand, admitted that they had not complied with clause 16(a) but contended that they were still entitled to exercise their common law rights of termination arising upon the plaintiffs' breach of a condition of a contract. In this connection the defendants relied on the statement in Chitty on Contracts, 25th Ed at paragraph 1504 to the effect that: "That fact that one party is contractually entitled to terminate the agreement in the event of a breach by the other party does not preclude that party from treating the agreement as discharged by reason of the other's repudiation or breach of condition, unless the agreement itself expressly or impliedly provides that it can only be terminated by exercise of the contractual right." The above principle was accepted and applied in a case also cited by the defendants viz Architectural Installation Services Ltd v James Gibbons Windows Ltd < 1989 > 46 BLR 91.
47 The facts of Architectural Installation decision were very similar to those of the present case. The plaintiffs in that case, acting as sub-contractors, agreed to supply specialist labour to the defendants who were main contractors. The plaintiffs sued for the balance of monies due to them and for damages for wrongful determination of the contract and relied on condition 8 of the contract (which was in language similar to that of clause 16(a) set out above) which allowed the defendants to terminate the contract by notice in writing if the plaintiffs failed to remedy defective work for seven days after being given a notice in writing of such defects.
48 Whilst in that case Judge Bowsher QC agreed with the plaintiffs' contention that condition 8 had not been complied with, the matter did not end there because he then went on to hold that condition 8 was not a comprehensive code which excluded any right to terminate under common law. The judge pointed out that in the contract under consideration there was no express provision to the effect that it could only be determined by exercise of the contractual right contained in condition 8. In dealing with the issue whether there was any implied provision to that effect he stated: "Mr Evans on behalf of the plaintiffs points to the fact that condition 8 is not prefaced by the words "without prejudice to other rights and remedies" and submits that the absence of those words tends to support the proposition that other rights and remedies are excluded. I am not impressed by that submission and would be sorry if draftsmen of contracts felt it necessary to include such legal verbiage in order to avoid unintended results of their drafting. Construction contracts are already sufficiently complicated when the draftsmen seek to state what they do mean. They should not be burdened with the additional task of stating what they do not mean. When someone has obviously gone to a great deal of trouble to draft the contract, and two commercial parties have agreed to a contract on those terms, the court should be very reluctant to step in and suggest that those two parties also agreed something which was not written down in the agreement between them. I see no reason at all for any implication of any term to the effect that condition 8 of the contract is to be the only machinery for terminating the contract, to the exclusion of common law rights of termination. Indeed, if it were the case that condition 8 provided the only means of terminating for breach, that would produce an nonsensical result in a situation which may be common but is not unknown. If the plaintiffs are right and condition 8 excludes any common law right to terminate, if the plaintiffs were to say to the defendants, "We are leaving the site and we shall not return and we shall not change our minds about this", the defendants would still have to go through the two notice procedure in order to terminate the contract. That seems to me to be contrary to any business sense. For the reasons set out earlier in this judgment, I find that the provisions of condition 8 of the contract exist side by side with the common law rights to terminate the contract."
49 In the present case the sub-contract does not expressly exclude the defendants' common law rights to terminate for breach of condition. Adopting the reasoning of Judge Bowsher QC, I hold that clause 16(a) of the sub-contract does not impliedly exclude those common law rights either but exists side by side with them. The plaintiffs cited a number of cases as authority for the proposition that termination and notice provisions in a contract have to be followed strictly otherwise a purported termination would be wrongful. Such authorities are relevant only to the situation where the parties are relying exclusively on their contractual rights of termination. If the parties are relying on their common law rights, such cases have no applicability.
50 The common law draws a distinction between those provisions of a contract which are regarded as conditions and those which are regarded as warranties. In the case of a breach of warranty, the innocent party is restricted to a claim for damages whereas if there is a breach of condition the innocent party can, in addition to claiming damages, excuse himself from further performing the contract. In the present case, the ground on which the defendants terminated the plaintiffs' work on the topside was, as stated in their letter, "discrepancies of material". By this the defendants meant, and the plaintiffs understood, that the plaintiffs had not supplied and applied the Vibak materials contracted for. The defendants would only be justified in terminating on this ground if supply of the Vibak materials was a condition rather than a warranty.
51 In my opinion, the provision as to the supply and application of the Vibak materials was a condition. As the plaintiffs well knew, the heart of the sub-contract lay in the materials which were to be supplied. The nature of those materials was of paramount importance. The defendants contracted with the plaintiffs on the basis that by doing so they would get Vibalastic Art 45.35 and Vibacote TW Art 20.42 manufactured by Vibak which they believed would comply with the specifications in the main contract. Looking at this sub-contract in the light of the surrounding circumstances, it is clear to me that this stipulation was an essential part of the contract and that the plaintiffs' failure to comply with it gave the defendants the right of termination.
52 In my view, the defendants did not prejudice their right by choosing to exercise it only in respect of the topside works. Once the plaintiffs were in breach, the defendants had, in addition to their right to terminate the sub-contract in toto, also a duty to mitigate their damages. If the defendants had terminated the plaintiffs' work on the underside as well, there would have been delays and expenses incurred in obtaining material and another contractor to complete the underside works. Since the material applied by the plaintiffs to the underside had proved suitable even though it was not a Vibak material, the defendants could justifiably reduce the damage resulting from the plaintiffs' breach of contract by continuing to employ them on the underside. If I were to hold that because the defendants did not terminate the whole of the sub-contract their termination of the work on the topside was wrong, I would in effect be penalising the defendants for acting rationally and for not incurring even greater damages. I decline to make such an irrational holding.
53 A necessary concomitant of my finding that the plaintiffs were in breach of a condition of the contract in not supplying and applying the Vibak materials is that the plaintiffs are not entitled to payment for the incorrect material which they in fact supplied and applied to the topside. Neither are the plaintiffs entitled to damages arising from the loss of the profits which they would have earned had they completed the topside work. Accordingly the plaintiffs' claim for $117,086.69 and damages for breach of contract must be dismissed.
54 Issue 4: was there any misrepresentation by the plaintiffs? This issue can be disposed of summarily. The complaint of the defendants on which it is founded is that the plaintiffs represented to them that the materials to be supplied and applied by the plaintiffs would be the Vibak materials. Acting on that representation the defendants entered the sub-contract. The representations were untrue in that the plaintiffs supplied their own materials instead.
55 A party to a contract makes a claim based on misrepresentation when he is induced to enter the contract on the basis of an untrue or misleading statement made by the other party which statement does not have contractual force. If the statement has contractual force and is not complied with, the cause of action is for breach of contract and not misrepresentation. In this case, the representation that Vibak materials would be supplied and applied became, as I have found, a part of the sub-contract. In fact, this was recognised even in the defendants' own amended particulars in support of the alleged misrepresentation where they stated "Acting on the aforesaid representations and induced thereby, the Defendants accepted the Plaintiffs' offer to supply and apply the Vibak materials." Thus their claim for damages and/or a right to rescind the sub-contract on the basis of misrepresentation was misconceived and no issue as to misrepresentation arises for decision.
56 Issue 5: what damages are the defendants entitled to? I have found that the plaintiffs were in breach of the sub- contract in two respects: first, in that they did not supply the Vibak materials and, secondly, in that the materials which they did supply and apply to the topside were defective in that the same did not meet the contractual specifications. As a result of the first breach and their termination of the plaintiffs' work on the topside, the defendants incurred expense in coating the remaining two-thirds of the Stadium. As a result of the second breach, the defendants were ordered by the consultant to remove the plaintiffs' material from the topside and incurred expenses in doing so and in re-coating the area with the Vibak materials. The defendants now claim the costs incurred in all this work less the amount which they would have had to pay the plaintiffs under the sub-contract.
57 The first objection which the plaintiffs put up to the defendants' claim was that the amounts claimed were special damages and as such had to be specifically pleaded. The defence and counterclaim ("the defence") as originally filed in March 1991 did not contain any particulars of the damages sustained by the defendants. During the course of the trial, however, the defendants became aware of this deficiency and applied for, and were given, leave to amend their pleading.
58 Paragraphs 1 to 15 of the defence contained those allegations of breach of contract in relation to the type of materials and the non-compliance with the specifications which I have dealt with above. By paragraph 16 the defendants repeated paragraphs 1 to 15 and counterclaimed so much of the monies assessed and found to be due to the defendants as would extinguish the plaintiffs' claim. Paragraph 17 of the original pleading made the alternative claim in misrepresentation and, in paragraph 18, the defendants counterclaimed damages and rescission of the sub- contract on that basis. In the amended defence, this paragraph 18 was expanded by the addition of the words "Full particulars of the damages are contained in annex I and II attached hereto and short particulars are as follows". This was followed by particulars of all the expenses incurred by the defendants and two annexes with details of how these expenses were calculated. Finally, at the end of the defence, a new paragraph was added whereby the defendants counterclaimed the sum of $198,201.20, damages, interest, costs and such other relief as the court deemed fit.
59 On the basis of the foregoing, the plaintiffs argued that the particulars of special damages given by the defendants related only to the damages which the latter had sustained as a result of the misrepresentation. They further contended that as the defendants had not expressly stated that these special damages were incurred as a result of the breach of contract, the defendants could not claim the specified sums but were restricted to a claim for general (i.e. nominal) damages in respect of any breach of contract which the court found to have taken place. I do not accept this argument.
60 Whilst the defendants' pleading could have been better drafted, it did serve the purpose of disclosing to the plaintiffs the actual costs and expenses which the defendants were claiming to have sustained by reason of the plaintiffs' actions. During the trial it was made quite clear that the sums which were particularised under paragraph 18 of the defence were incurred by the defendants because they had to take over the work of coating the uncompleted two-thirds of the topside and also had to remove the plaintiffs' coating from the other one-third and re-coat it. Further, although the defendants described these sums as damages for misrepresentation, they were, in nature, equally claimable as damages for breach of contract. The expenditure incurred by the defendants was of the type that would naturally arise out of the kind of breach of contract which the plaintiffs committed. The plaintiffs also had ample opportunity, which they utilised to the fullest, to cross-examine and test the defendants on the quantum of the amounts claimed. Since the deficiency in the defence did not prejudice the plaintiffs in the conduct of their defence to the counterclaim, it cannot preclude the defendants from recovering the loss which they were able to establish at the trial.
61 The defendants particularised their damages under three main sub- headings: (a) costs incurred to rectify the defective area (16,633 sqm); (b) costs incurred to coat the uncompleted area (36,684.84 sqm); and (c) additional administrative costs. As set out in the defence, their total claim under these three heads was for $198,201.20. In their submissions they reduced their claim to $158,288.13. I must now consider whether the various items making up this total are claimable and if so whether they have been adequately proved.
62 (a) Costs incurred to rectify the defective area Under this sub-heading, the defendants claimed the costs of removing the plaintiffs' coating from the topside and of re- coating it with the Vibak material. The plaintiffs' answer to this was to contend that in fact no such removal or re-coating work had ever taken place. I do not accept this contention. Mrs Tan's sworn testimony in court was that the work was done. She was supported in this by the testimony of an independent witness, Mr Eugene Baikoff.
63 Mr Baikoff, a professional engineer, is a director of Baikoff & Associates Consulting Engineers Pte Ltd, the company appointed by the Council as consultant in the restoration of the Stadium. It was the consultant's responsibility to approve the materials used for the coating work and to ensure that the coating once applied was up to specifications. About six weeks after the plaintiffs started the works, the consultant noticed that some defects had appeared in those works. At first, it was assumed that only isolated areas were defective and the consultant allowed the application to continue. Later on, however, it became obvious that the material was cracking and peeling off. In early May 1989 Mr Baikoff told Mrs Tan that something had to be done about the defects. Subsequently, Mr Baikoff gave instructions to the defendants to remove the whole of the work done by the plaintiffs and to re-coat the area. He informed Mrs Tan that painting over alone was unacceptable. The official notice to replace the works was given by letter dated 15 November 1989.
64 According to Mr Baikoff, the defective materials were removed. He had personal knowledge of the removal. It took three months for the defendants to remove all the plaintiffs' materials and, at regular intervals, Mr Baikoff visited the site to check the progress of the work. On those visits, the contrast between the area covered with the plaintiffs' materials and the scraped areas was absolutely obvious. He also testified that initially the defendants were using manual labour for the removal work but this resulted in a very slow rate of progress and he therefore advised them to buy machines for the work which they then did.
65 Mr Baikoff was an independent and disinterested witness. There was no reason for him to lie simply to support the defendants in their claim against the plaintiffs. His testimony, to my mind, established that the defendants did in fact do the work for which they claimed. I was not impressed by the evidence of Mr Kong that the work had not been done as Mr Kong himself was not on the site throughout the three months when the removal works were being carried out and, obviously, he had an interest in disputing the defendants' evidence on this point. Neither was I impressed by the evidence of Dr Henry Ong on this point. As I pointed out earlier, Dr Ong did not go down to the Stadium until three years after the events discussed and the knowledge on which he based his analysis came from information given to him by Mr Kong. He had no independent knowledge against which to verify Mr Kong's information.
66 The first item of claim under this sub-heading was for $13,963 being the cost of specialised equipment purchased by the defendants to remove the plaintiffs' coating. This item comprised three invoices, the first one, dated 1 December 1989, being for the sum of $2,200. The plaintiffs objected to this invoice on the basis that there was no proof that the equipment it concerned was bought in order to remove the coating. They pointed out that after receipt of the consultant's letter of 15 November 1989, the defendants had written to the plaintiffs on 18 November 1989 and again on 24 November asking the plaintiffs to remove their own coatings. Thus the defendants could not have considered removing the coating themselves until some time in December 1989 at the earliest and it was odd that they had purchased a machine for this purpose on 1 December 1989.
67 Mrs Tan who was questioned about the acquisition of this equipment was rather evasive on the issue. She could not remember when she had placed an order with the supplier of this machine. She was asked when the defendants had decided to do the removal works themselves and her reply was in December 1989. It was pointed out to her that it was odd that she had purchased the equipment before deciding to do the rectification work. She then said that the defendants had planned to do it in December and because they had planned to do it in December the machine had had to be ordered earlier. When the question was repeated as to when she made up her mind that the defendants should do the work, the answer was "that would definitely be before December, before December 1989". In this instance she was clearly changing her evidence to suit the circumstances. In my judgment the defendants have not shown on a balance of probability that the invoice for $2,200 was in respect of equipment purchased for the rectification works. This claim must be disallowed.
68 The next two invoices were dated 22 December 1990 (for $8,663) and 26 November 1990 (for $3,100). The dates of these invoices are consistent with the dates of the work. According to the evidence, the rectification work started some time in October 1990 and, at first, was done manually. Subsequently, due to slow progress, the defendants were instructed by the consultant to buy machines. The dates of these invoices fit the evidence on this point. I therefore find that the machines represented by these two invoices were purchased for the rectification work. The plaintiffs did make a valid point in that the machines would have had some residual value after the defendants had finished their work and it would not be correct to award them the full purchase prices of the machines. No evidence was given as to this residual value, the defendants insisting that once the work was finished, the machines were useless. The total claim under these invoices is for $11,763. Giving some allowance for scrap value and/or future use, I allow the claim at $9,000.
69 The next part of the claim was $11,613 for consumable tools, cleaning materials and equipment parts. The relevant invoices in support of this sum were produced and no great challenge was mounted by the plaintiffs. Accordingly, I allow this item in full.
70 The next item was $22,782 being the costs of testing services carried out by Setsco and Sisir and the Taywood inspection. In their submissions, the defendants reduced this claim to $15,642 as they had not been able to produce some of the reports of the tests carried out by Setsco Services and Sisir. As argued by the plaintiffs, there is a more fundamental objection to this claim. That is that these tests and the Taywood inspection were carried out for the purposes of litigation and did not arise from the plaintiffs' breach. As far as the Taywood inspection cost is concerned, it would more properly form an item of the defendants' bill of costs for taxation. The Setsco and Sisir costs are not in my opinion so claimable as, the materials having been rejected on the basis that they were not Vibak materials, there was really no need for the defendants to carry out further tests on them to establish their quality. The sub-claim under this heading is disallowed in full.
71 The defendants next claim $44,792.50 as the costs of labour for removal of the coating. Some of these costs were shown to be excessive. Under cross-examination Mrs Tan admitted that a sum of $1,000 paid as a bonus to one of the foremen in December 1990 was actually his bonus for the whole year. I do not think that this amount is recoverable from the plaintiffs. Secondly, bonus payments were also made to six other workers. These amounted to $3,042. Mrs Tan tried to justify the additional wages by saying that she had changed the term of payment from daily rates to payment based on quantity of work done in order to give an incentive to the workers to finish the job quickly. This does not explain why only six of the workers were given such a bonus. Surely this system should have applied to all of them. Since there was no legal obligation for the defendants to make such payments, they cannot be claimed from the plaintiffs. Accordingly, I allow the claim for labour costs at a reduced amount of $40,750.50.
72 The next item was for $29,773.07 being what was termed "increase in material costs from Vibak and labour costs". It was essentially the extra cost which the defendants incurred in re- coating the topside with Vibak materials. The defendants dropped this claim in their submissions as they could not prove it on the basis on which it had been calculated. In my opinion, however, the defendants are entitled to recover the costs of re-coating if such costs exceeded what they would have paid the plaintiffs for the work. I will consider the amount claimable under sub-heading (b) below.
73 The last item under this heading was $3,000 being a proportion of the salary of an engineer employed by the defendants whom they said had attended at the site during the rectification works. In their submissions, the defendants dropped this claim as they were not able to prove how much time the engineer had actually spent on site.
74 (b) costs incurred to coat the uncompleted area (36,684.84 sqm) After terminating the plaintiffs' work on the topside, the defendants decided that instead of employing another sub- contractor, it would be better if they imported the correct materials for the work directly from Vibak and then used sub- contract labour to apply the materials. The defendants claimed $65,665.86 as the additional expense incurred by this exercise. According to their breakdown, it cost the defendants $8.89 psm to coat the remaining area of the Stadium. If the plaintiffs had done the work they would have been paid $7.10 psm. There was therefore an additional cost of $1.79 psm which worked out to a total of $65,665.86 for the 36,684.85 sqm which remained to be done. Under cross-examination, however, it turned out that this calculation of a cost of $8.89 psm was a purely theoretical calculation. The defendants had computed it on the basis that for each square metre of the Stadium they needed 1.5 kg of Vibalastic and 1 kg of Vibacryl (which Mr Kohler had recommended be used instead of Vibacote TW). This meant that to cover the whole area the defendants would have needed 55,027.28 kg of Vibalastic and 36,684.85 kg of Vibacryl. The Vibalastic applied was obtained by mixing 1 kg of Vibalastic Art 45.35 with 2.5 kg of cement and sand. Thus the defendants needed to buy approximately 15,722.08 kg of Vibalastic Art 45.35. The defendants were able only to produce documents showing that they had imported, in total (both for the re-coating works and the uncompleted works), 14,000 kg of Vibalastic Art 45.35 and 22,750 kg of Vibacryl. The defendants were not able to prove therefore that they had spent all that they had claimed in respect of the Vibalastic and the Vibacryl.
75 In my judgment, the way to assess whether or not the defendants suffered any loss by reason of the fact that they had to coat the topside of the entire Stadium (i.e. the uncompleted two-thirds plus the area done by the plaintiffs) is to calculate their cost of doing so on the basis of the documents which they produced in court in proof of the expenses incurred. Since the defendants were able to produce only three invoices from Vibak, they must be taken as having used only the material reflected in those invoices in their coating works. On that basis, the defendants' cost of materials would have amounted to $181,689.16 for the Vibak materials and another $10,000 for the sand and cement sourced locally (on the basis of 0.28 cents per kg, a figure given by Mrs Tan and accepted by the plaintiffs). Their labour costs for the coating would have been $2 psm (on the basis of an invoice from the labour sub-contractor, Ho Hin Sin Construction) giving a total of $106,635.68 for the 53,317.84 sqm of the Stadium. The total costs incurred were therefore $298,324.84. If the plaintiffs had done the work, the defendants would have paid them $378,556.66 ($7.10 psm x 53,317.84 psm). The difference between the two figures is $80,231.82. This is the amount which the defendants saved by coating the Stadium themselves instead of employing the plaintiffs. The defendants have, therefore, not suffered a loss by reason of the coating works. Thus no amount is recoverable under this head.
76 (c) additional administrative costs Under this sub-heading, there were two items: (a) a figure of $3,000 for remobilisation and (b) a figure of $3,611.77 for staff salaries, CPF, telefax, transport, food and general expenses, repairs and maintenance, bank interest and charges. Mrs Tan explained that the remobilisation figure represented the cost to the defendants of having to set up their equipment at the Stadium for the rectification works. The administration costs were the defendants' overheads incurred in connection with these works. I am not inclined to award these sums to the defendants. First, they were not adequately proved. No breakdown of how they were arrived at was given. In relation to the administration expenses, no evidence of the defendants' administration expenses overall was adduced thus making it impossible to determine whether the proportion claimed was reasonable. Also, in relation to the remobilisation costs, it was the defendants' own decision to delay the rectification works until October 1990. If they had started in December 1989 or January 1990 i.e. just after they had finished their own work, these remobilisation costs might not have been incurred.
77 (d) amount due on the counterclaim In the result, the defendants have proved $61,363.50 of their counterclaim. As against this, they owe the plaintiffs $25,555.36 being the balance due for the underside works. The total payable to the defendants is therefore $35,808.14.
78 Conclusion In the result, the plaintiffs' claim is dismissed. There will be judgment for the defendants on the counterclaim in the sum of $35,808.14 with interest at the rate of 5% p.a. from the date of the defence and counterclaim to the date of judgment. As regards costs, I am awarding only one set of costs as the issues in the claim and counterclaim were intertwined. Further, much time was spent on the issue of misrepresentation which proved to be a red- herring. Accordingly, I am awarding the defendants 80% of their costs as taxed.
Judith Prakash JC
Tan Siak Hee (S H Tan & Associates) for the plaintiffs
Ramalingam Kasi with W T Woon (W T Woon & Co) for the defendants