Personal Representative of Tan Kian Seng and Chan Poh Kim v Gemtray Properties Pte Ltd formerly known as Tet Wai Realty (Pte) Ltd
[1994] SGHC 78
OS691/1992
Warren Khoo L H J
26 March 1994
1 Judgment:
2 Coram : Warren L H Khoo J
3 CAV
4 Judgment
5 By this originating summons, the plaintiffs seek the determination of their rights under an agreement with the defendants for the partition of land and for the clearance of tenants on the land.
6 Tan Kian Seng, the second plaintiff Chan Poh Kim and the defendants (then known as Tet Wai Realty Pte Ltd) were owners of the land, which was at Ang Mo Kio, as tenants in common for an estate in perpetuity. The parties were interested in developing the land. There were tenants on the land, on both sides of the proposed boundary line. There were also tenants occupying structures straddling the boundary line. Tan has since died, and his estate is represented in these proceedings by one of his children Mr Tan Ah Kiu by order of court made on 16 October 1992. I shall for convenience and simplicity generally refer to Tan or his estate and Chan as the plaintiffs and only refer to them or any of them by name only where it is necessary.
7 On 20 June 1983, an agreement was entered into between the plaintiffs of the one part and the defendants of the other part whereby the parties agreed on the partition of the land and on the clearance of tenants on it. The defendants, then known as Tet Wai Realty Pte Ltd, were to take that part of the land marked as "A" in the plan attached to the agreement. The plaintiffs were to take as tenants in common the other part of the land, marked "B". Areas "A" and "B" were equal in area, each over 20,000 sq. metres. They lay on either side of a provisional boundary line.
8 Clause 8 of the agreement provided that each party should be responsible for securing vacant possession from tenants of structures within their respective areas. In addition to clearing the tenants within their respective areas, it was necessary to clear the tenants occupying structures straddling the common boundary. It was therefore agreed that the defendants would be responsible for clearing the tenants occupying structures marked "X" on the plan annexed to the agreement, and that the plaintiffs would be responsible for clearing those occupying the structures marked "Y".
9 Cl 9 of the agreement provided as follows:
10 Compensation Agreement 9. (a) During the period of four (4) years commencing upon the date of this Agreement it is hereby agreed that < the defendants > shall negotiate with the tenants of the structure marked "X" on the plan hereto annexed (hereinafter called "structure X") and < the plaintiffs > shall negotiate with the tenants of the structure marked "Y" on the said plan (hereinafter called "structure Y"). Both parties shall use their best endeavours to procure agreements with the tenants of the said two structures for vacating the said property within the said four year period together with notices to quit to be executed by such tenants in the form set out in the Second Schedule hereto (which agreements together with their respective notices to quit are hereinafter called "the compensation agreement").
11 Compensation monies (b) Each party shall be responsible for negotiating with and obtaining vacant possession from the tenants of the respective structures referred to in sub- clause (a) hereof and also be liable for the compensation monies payable to the respective tenants thereof PROVIDED THAT < the defendants > shall contribute Dollars One Hundred Thousand ($100,000.00) (hereinafter called "the said contribution") towards such compensation monies payable by < the plaintiffs > to the tenants of the structure Y. The balance of compensation monies if any shall be paid by < the plaintiffs > .
12 Mode of Payment (c) (i) 50% of the said contribution to be paid by < the defendants > to < the plaintiffs > pursuant to the terms of sub-clause (b) hereof shall be paid within fourteen (14) days of the execution of the compensation agreement/s between < the plaintiffs > and the tenants of structure Y. >(ii) the balance 50% of the said contribution shall be paid by < the defendants > to < the plaintiffs > only upon delivery of vacant possession of structure Y within the said four (4) year period.
13 Failure to obtain vacant possession(d) (i) If < the defendants > fail to obtain possession from the tenants of structure X before the expiry of the said four (4) year period as aforesaid, < the plaintiffs > shall be at liberty to carry out the negotiations for vacant possession of structure X Provided that the compensation monies to be paid to the tenants of structure X shall be paid half by < the defendants > and half by < the plaintiffs > .
14 (ii) If < the plaintiffs > fail to obtain vacant possession from the tenants of structure Y before the expiry of the said four (4) year period as aforesaid, < the defendants > shall be at liberty to carry out the negotiations for vacant possession of structure Y. < The defendants > shall still contribute the sum of Dollars One Hundred Thousand ($100,000.00) towards such compensation monies as provided in the Proviso to clause 9(b)(i) hereof and the balance of the compensation monies payable to the tenants of structure Y shall be paid half by < the plaintiffs > and half by < the defendants > .
15 The four-year period stipulated in the agreement expired in June 1987. In September 1987, Mr Lim Chin Min was appointed by the defendants to assist in the clearing of tenants. There is dispute as to the scope of what he was to do as well as to what he did. But I do not think that anything turns on it.
16 The plaintiffs say that in September 1989, they appointed Mr Lim to assist in the negotiations with Mr Yeo and that eventually in July 1990, a settlement was reached with Mr Yeo at the sum of $500,000. A compensation agreement dated 2 July 1990 is exhibited to Mr Lim's affidavit. The defendants do not accept, without further proof, that there was such a settlement with Mr Yeo, or that the plaintiffs paid Mr Yeo.
17 It is common ground between the parties that the question before me is essentially one of the proper construction of cl 9 of the partition agreement. For that purpose, the parties have approached the matter on the supposition that it was the plaintiffs, not the defendants, who succeeded in getting the compensation agreement executed with Mr Yeo and in getting him to vacate structure Y, and that all this took place outside the four-year period stipulated in the agreement.
18 The issue before the court The plaintiffs claim that, having paid the sum of $500,000, they are entitled to be paid $300,000 by the defendants, made up of the contribution of $100,000, and half of the remaining $400,000 in accordance with cl 9 (d) (ii) of the agreement. The question that arises for consideration is, therefore, whether on a proper construction of cl 9 of the agreement, and on the assumption that the compensation agreement was executed and vacant possession of structure Y was obtained after the expiry of the four-year period stipulated in that clause, the plaintiffs are entitled to make such a claim under sub-clause (d) (ii) of that clause.
19 The plaintiffs' contentions The plaintiffs contend that at the time of the signing of the agreement the defendants were aware that Yeo was a difficult man to deal with, and that was the reason why the plaintiffs were entrusted with the task of dealing with him. It was for this reason that the parties agreed that the defendants should make a contribution of $100,000. The plaintiffs say that they used their best endeavours to settle with Yeo, but they were not successful. The plaintiffs say that on a plain reading of cl 9 (a), they were not required to actually obtain vacant possession of structure Y within 4 years; they were only required to use their best endeavours. It can be taken, they say, that they had used their best endeavours. There was the threat of government compulsory acquisition if no progress was made in clearing the tenants. It was also in the interest of the plaintiffs to clear the land as quickly as possible so as to put it to more profitable use by developing it. They say therefore that there was every reason for the plaintiffs to try their best to clear the land, including structure Y. Furthermore, to use best endeavours does not meant that the plaintiffs had to accept any demands made by the tenant Yeo, no matter how unreasonable. Yeo had in fact made an unreasonable demand of $1.2m, although at first willing to accept $500,000. The plaintiffs say that they were free to carry on negotiations with Yeo even after the four- year period. It cannot have been the intention that the plaintiffs' obligations should cease at the end of the period. The only change at the expiry of the period is that the defendants were then at liberty to carry out negotiations.
20 The plaintiffs say that on a plain reading of cl 9, they are entitled to claim the sum of $300,000 from the defendants for the following reasons: Firstly, cl 9 (d) (ii) does not limit the plaintiffs' right to recovery to the situation where the defendants carried out negotiations after the expiry of the four-year period; their right to recover does not depend on whether it was the plaintiffs or the defendants who did the negotiations after that period. That part of the clause expressly provides that after the expiry of the period, the defendants shall still contribute the $100,000 and the balance of the compensation sum should be borne equally by the parties. It was in the common interest of the parties to obtain vacant possession as soon as possible in view of the threat of acquisition and that was the reason why they agreed to share in the expenses for procuring vacant possession. That was why cl 9 (d) (ii) also provides that if the defendants failed to obtain vacant possession within the period, the plaintiffs would contribute half of the compensation sum.
21 The defendants' contentions The defendants' contention is that on a proper construction of cl 9 (d)(ii), it is only if the defendants themselves entered into and concluded negotiations with the tenant of structure Y that it would operate, and the burden of the compensation sum would be shared between the two parties in the manner stipulated.
22 The defendants say that the contract must be construed in a way that makes commercial sense. The parties were primarily concerned with the clearance of the tenants on their respective portions of the land. However, after the expiry of the period of 4 years, if the party concerned still was not successful, the other party had the liberty to step in, and only if that party did step in would cl 9(d)(ii) operate.
23 The defendants agree that it was the intention that the party originally responsible for the structure allocated to it should continue to make efforts to get vacant possession after the 4 year period. It was not the intention, however, that he should get a greater contribution just because he had taken more rather than less time to discharge his contractual responsibilities. However, the parties recognised that, should one party step in to clear a tenant who was the other party's responsibility, he was likely to do so because of the urgency of his own commercial objectives in securing vacant possession. In those circumstances he might require an increase in compensation payable to the tenant so as to induce the tenant to quit the land. Given that he was the party insisting on the payment of higher compensation it was therefore provided that it was only fair for him to share the burden of the compensation payable, as provided in cl. 9(d)(i) and (ii). The defendants say that this must be so, as otherwise the party who intervened might negotiate a ridiculous amount of compensation and require the other party to contribute.
24 To sum up, the defendants say that on a true construction of cl 9, the plaintiffs were entitled to claim against the defendants or share compensation payments with the defendants in the following amounts and in the following circumstances:
25 (a) $100,000 if the compensation agreement was signed with Mr Yeo and vacant possession was obtained within the 4 year period.
26 (b) $50,000 if the compensation agreement was signed within the period but vacant possession was obtained after the period.
27 (c) If the defendants, rather than the plaintiffs, cleared the tenants at Y after the 4 year period, the defendants would pay the compensation, but could then recover from the plaintiffs an amount represented by the total compensation sum less $100,000 divided by two.
28 The defendants say that given the fact that the compensation agreement in respect of structure Y was signed and the vacant possession was obtained outside the 4 year period, the plaintiffs could claim nothing from the defendants, and the originating summons can be disposed of on this basis without the need to inquire into and resolve the disputed facts, e.g. whether the plaintiffs had used their best endeavours during the 4-year period.
29 My views In so far as I am dealing with a question of construction, I must approach the matter by trying to ascertain the parties' mutual intention as they have expressed it in the agreement itself. I cannot take into consideration any disputed matters of fact. The reasons which have been suggested for the inclusion of this or that provision, or for the manner in which a particular provision has been worded, while helpful in understanding why a particular provision was inserted or why it was worded in a certain way, does not assist in the construction of the provision. They cannot be taken into account for the purpose of construction unless evidence of them could be admitted under well- recognised exceptions to the parole evidence rule. The task of construction is to try to ascertain the intention of the parties as it has been expressed in the words they used.
30 As I see it, the question is a fairly simple one. The meaning of cl 9 is quite clear. It essentially provided that both parties (by which I mean the defendants of the one part and the plaintiffs of the other) would use their best endeavours to clear their respective structures of tenants within 4 years from the date of the agreement. It was specially provided that in respect of the tenants at structure Y, the defendants would contribute $100,000 to the compensation money which the plaintiffs had to pay the tenants. It was further provided that $50,000 of the $100,000 would be paid within 14 days after the compensation agreement and the tenants of structure Y was signed, and the balance $50,000 would be paid when vacant possession was given "within the four year period".
31 Sub-cl (d) provided for the eventuality of either party failing to get the tenants out of their respective structures within the four year period. It was provided that either party would then be at liberty to intervene and conduct negotiations with the tenants occupying structures which fell within the responsibility of the other party. In that event, if the negotiations were successful, then the compensation money payable to the tenants would be shared between the two parties. However, in the case of structure Y, the initial $100,000 would still be borne by the defendants and the balance would be borne equally by the two parties.
32 A party was not obliged to intervene after the 4 year period and negotiate for the vacation of the structure not originally allocated as his responsibility. He might do so if he wished, but if he did so, then he would have to bear a share of the compensation sum payable according to the formula stated in that sub-clause. If he did not do so, the party originally allocated the responsibility for getting vacant possession of that structure continued to be under an obligation to get it vacated. He could not wait for the other party to come in and then get the other party to share the burden of paying the compensation to the tenant.
33 I test the validity of this view in this way. The defendants had cleared structure X. Presumably, they paid the tenant of X off, as they were obliged to do under cl 9 (b). The plaintiffs failed to get Mr Yeo to give up structure Y within the 4 years. The defendants, on the scenario postulated, did not intervene. The plaintiffs conducted and concluded negotiations with Mr Yeo, and paid him off, as they say they did. But this is what they had always been obliged to do under the partition agreement in the first place. The fact that they failed, even using all their best endeavours and with the best intentions, to get Mr Yeo to vacate within the 4 year period cannot possibly be a good reason for a substantial portion of the burden of the compensation sum to be foisted on the defendants, who had no responsibility in relation to structure Y (apart from the contribution of $100,000) in the first place. To do so would be to make the defendants bear a much greater burden than is consistent with the central idea of the division of responsibilities between the parties, i.e. X was the primary responsibility of the defendants and Y that of the plaintiffs.
34 Some argument has been directed at the point whether the plaintiffs had use their best endeavours to obtain vacant possession from Mr Yeo within the 4 year period as required by cl 9(a). In my view, this requirement does not have the significance which has been attributed to it. The words are no more than an apt expression to describe what the parties were expected to do to fulfil their central obligation of obtaining vacant possession. The use of these words was apt in a situation where neither the plaintiffs nor the defendants were in a position to accomplish the result desired without the co-operation of the rent-controlled tenant. They could only do their best. In the nature of things where the outcome is often decided by a test of will and ability to hold on or to hold out, there cannot be anything like an objective assessment whether a party has done his best.
35 I do not think that the parties' right to sharing the compensation payable under cl 9 (d)(i) or (ii) is dependent on a determination whether the best endeavours had been used to obtain vacant possession within the 4 year period. So far as structure Y is concerned, the only question that matters in this context is whether vacant possession of it was or was not obtained within the 4 year. If it was not, as it was not, the contribution of $100,000 provided in cl 9(c) was not payable, regardless of what efforts have been made. The case has then to be dealt with by reference to cl 9(d)(ii). That part of the sub- clause clearly provided for sharing of the burden of the compensation sum only if the defendants intervened. There are no provisions for sharing such burden where the plaintiffs themselves continued negotiations and obtained vacant possession after the 4 year period, as is alleged by the plaintiffs to be the case.
36 The plaintiffs' alternative claim is for the $100,000 contribution which they say they are entitled to under cl 9 (d)(ii). It follows from what I said earlier that this contribution is payable only if the vacant possession of structure Y was obtained within the 4 year period, or if the defendants chose to intervene after the 4 year period and succeeded in the negotiations.
37 I, therefore, accept the defendants' submission that the originating summons can be disposed of purely on a point of construction of cl 9. In the view I take of the matter, as set out above, I dismiss the summons with costs.
Michael Kuah and Peter Wong for the plaintiffs
Philip Jeyaretnam for the defendants