Mohd bin Sapri v Synthes Singapore Private Limited and Others
[1995] SGHC 248
Suit 892/1991
Judith Prakash J
26 October 1995
1 Judgment:
2 Coram: Judith Prakash J
3 GROUNDS OF DECISION
4 Introduction
5 In October 1989, the plaintiff was injured in an accident on a construction site. He instituted this action to recover damages for his injuries. By the time it came on for hearing before me, the action against the first defendants had been stayed. On the second day of the hearing, the plaintiff discontinued the action as against the third defendants. The substantive hearing therefore proceeded against the second and fourth defendants only and my decision at the end of the trial related to these parties.
6 The site at which the accident took place was located in Woodlands. It belonged to the third defendants. In February 1988, the third defendants accepted a tender from the fourth defendants, Soil Build (Pte) Ltd ("Soil Build"), for Soil Build to construct and maintain a two storey warehouse on the site for the third defendants. Pursuant to this agreement, possession of the site was given to Soil Build. Soil Build carried out the main structural works for the warehouse and employed specialist sub- contractors for certain specialist building works. The second defendants, Sprinkler Engineering Pte Ltd ("Sprinkler Engineering"), were appointed by Soil Build to supply, deliver, install, commission and maintain a fire-fighting or sprinkler system at the first and second storeys of the warehouse.
7 The plaintiff was one of the workers working on the installation of the sprinkler system at the first storey of the warehouse. He alleged that he was employed by Soil Build and that on 9 October 1989, in the course of his employment, he was instructed to touch-up the paint work on certain sprinkler pipes attached to the ceiling of the first storey. For this purpose, the plaintiff climbed a four-level mobile piece of equipment (which was at the trial variously referred to as a staging or scaffolding) and stood on the platform at its top. The plaintiff said that he had not been supplied with either a safety belt or a safety helmet and that while he was working on the pipe, he fell off the staging and injured himself.
8 The plaintiff contended that both Sprinkler Engineering and Soil Build were responsible for his injuries. He said that they were negligent and/or in breach of their duties as occupiers of the site and/or in breach of their duties as his employers. He also relied on the Factories Act and, as an alternative, alleged that the accident was caused by a breach of statutory duty on the part of Sprinkler Engineering and/or Soil Build as occupiers of the site.
9 Sprinkler Engineering denied that it had employed the plaintiff. Its story was that it had sub-contracted the work of installing the sprinkler system in the warehouse to two different sub-contractors. One of these, one Michael Chan Im Huat, was responsible for the work at the second storey and in the office which formed part of the warehouse, and the other, one Ishak Karim, was responsible for the work at the first storey. Each of these sub-contractors was given the plans of the system to be installed and supplied with pipes and sprinkler heads. They were paid on the basis of work done and were responsible for recruiting and supervising their own workers. Sprinkler Engineering contended that the plaintiff, who was Ishak Karim's brother-in- law, had been employed by Ishak Karim and was therefore not its employee.
10 Sprinkler Engineering also denied that the accident was caused by its negligence or any breach of duty on its part. It said that the accident was entirely due to the plaintiff's own negligence and/or that of his co-workers, men who had also been employed by Ishak Karim and for whom, therefore, Sprinkler Engineering was not responsible. According to Sprinkler Engineering the plaintiff was injured because he deliberately followed an unsafe and prohibited system of work in that when he had finished touching-up the pipe on which he was working, he did not climb down to the ground and push the staging to the next location at which touch-up work was supposed to be done. Instead, he stood on the top of the platform and asked his co- workers to push the staging along. As they did so, it toppled and fell over and the plaintiff was thrown off and thus injured himself.
11 Soil Build too denied liability for the accident. It said that the accident had occurred in the manner described by Sprinkler Engineering. As it had not employed either the plaintiff or his co-workers, it could not be responsible for their negligence. Further, the accident had not occurred by reason of any latent hazard existing in the site for which it, as occupier, could be made responsible. The breaches of duty under the Factories Act were also denied.
12 Apart from the plaintiff's action against the various defendants, these parties had also taken action against each other. The third defendants alleged that under the terms of the building contract between them and Soil Build, Soil Build had to indemnify them against any claim which arose out of the building works. Soil Build itself claimed an indemnity from Sprinkler Engineering on the basis of the sub-contract between the two of them.
13 Findings
14 The issues that I had to decide were narrowed towards the end of the trial when the parties were able to arrive at an agreement on quantum. On the penultimate day of the trial, I was informed that the parties had agreed on a quantum of $90,000 in total for general and special damages.
15 At the end of the hearing, I made the following findings:
16 1. the plaintiff was not employed by Sprinkler Engineering;
17 2. the accident occurred because the plaintiff while standing on the staging asked one of his fellow workers to push it and one of the wheels of the staging gave way - either because it was defective or because it hit certain pipes lying on the ground;
18 3. the staging on which the plaintiff stood had not been supplied by Soil Build. It had been taken by the plaintiff and his co-workers from somewhere on the site and they had converted it from a stationary staging into a mobile one by affixing the wheels at the base; 4. there was no ground on which Soil Build could be affixed with liability as an occupier;
19 5. none of the grounds asserted under the Factories Act had been made out;
20 6. Sprinkler Engineering was not a joint occupier of the site. Its presence on the site was that of a licensee and there was no real evidence that Sprinkler Engineering had had any exclusive control over the areas which it used for the purpose of installing the sprinkler system;
21 7. Sprinkler Engineering was, however, in breach of duty to the plaintiff. It was supposed to supply staging for the use of the sprinkler workers. It must have been aware that Ishak Karim had not taken any staging from it. Sprinkler Engineering was also aware that the workers on the sprinkler system had to use staging in order to carry out their work. It therefore had a duty to ensure that the actual staging that was used was safe for use. It did not fulfil this duty. The staging that the plaintiff used was defective in that there was something wrong with the wheels. This was clear from the evidence of one of Sprinkler Engineering's own witnesses, Michael Chan Im Huat;
22 8. whilst the negligence of Sprinkler Engineering was one cause of the accident, the negligence of the plaintiff himself contributed in greater measure to it. The plaintiff was well aware that he was not supposed to stand on the staging and have someone push it from below. Yet he did this and this must have been a major cause of the accident. As between the plaintiff and Sprinkler Engineering, the plaintiff was two-thirds responsible for the accident and Sprinkler Engineering was one-third responsible for the accident;
23 9. as between Soil Build and Sprinkler Engineering, Sprinkler Engineering owed the former a contractual duty to ensure that its sub-contract work was carried out safely and to provide proper supervision of its workers. Sprinkler Engineering was in breach of duty in that it did not supply the proper equipment and, although it was aware that Ishak Karim was rarely on site to supervise his workers, it did not provide additional supervision.
24 I therefore ordered that the plaintiff's case against Soil Build be dismissed and that Soil Build's claim for an indemnity from Sprinkler Engineering also be dismissed. I then ordered judgment for the plaintiff against Sprinkler Engineering in the agreed sum of $90,000 as reduced by the finding that the plaintiff bore two-thirds responsibility for the accident. Next, I heard arguments on costs and made the following orders:
25 1. that Sprinkler Engineering was to pay Soil Build's costs of the third party proceedings between them;
26 2. that Sprinkler Engineering was to pay the plaintiff's costs on the standard basis in full up to 31 October 1994 and half the plaintiff's costs thereafter;
27 3. that the plaintiff was to pay the costs of Soil Build on the standard basis and that Sprinkler Engineering was to pay all costs of Soil Build paid by the plaintiff up to 16 November 1994 and 50% of the costs of Soil Build incurred thereafter and paid by the plaintiff.
28 The plaintiff has now appealed against my decision that his claim against Soil Build should be dismissed with costs and Sprinkler Engineering has appealed against my decision that it was in breach of duty to the plaintiff, that the staging was defective and that it was liable for one-third of the plaintiff's damages. Sprinkler Engineering has also appealed in respect of the orders for costs which I made against it.
29 The position of Sprinkler Engineering
30 There has been no appeal against my finding that the plaintiff was not an employee of Sprinkler Engineering. The plaintiff's employment position is, therefore, no longer in issue in these proceedings. My decision with regard to Sprinkler Engineering's liability was premised on the basis that at the material time the plaintiff, contrary to the assertions that he and Ishak Karim made at the trial, was in fact employed by Ishak Karim and that Ishak Karim was acting as a sub-contractor to Sprinkler Engineering. I reached this conclusion mainly on the basis of evidence given by Sprinkler Engineering's own witnesses, in particular that of Michael Chan Im Huat ("Michael"). I also relied on Michael's evidence in connection with my findings relating to how the accident occurred and the nature of the staging involved.
31 Operations at the site
32 It appeared from Sprinkler Engineering's evidence that that company had been in the business of installing and maintaining fire-fighting systems for a considerable period of time prior to the October 1989 accident. According to Michael, he had worked for Sprinkler Engineering in one capacity or another from the end of 1979. The method by which Sprinkler Engineering usually conducted its business was that after it had successfully tendered for a sprinkler installation job, it would prepare the plans for the system, arrange for the supply of the pipes and sprinkler heads and engage labour only sub-contractors to carry out the actual installation work. Sprinkler Engineering did not have its own workers for such jobs. Instead, it employed supervisors who had to ensure that the sub-contractors did the jobs in accordance with the relevant drawings.
33 In November 1988, Sprinkler Engineering was awarded the job of installing the fire- fighting system at the Woodlands warehouse. Sprinkler pipes had to be installed in the ceilings of the first and second storeys of the warehouse and in the ceilings of the office located inside the warehouse. In about April 1989, Sprinkler Engineering engaged Michael to do the installation works at the second storey of the warehouse and at the office. Michael in turn employed his own group of workers to carry out the job. Sprinkler Engineering paid Michael on the basis of the number of sprinkler heads and lengths of sprinkler pipes which he installed. Michael paid his workers at the rates which he had agreed with them and was responsible for supervising their work. At this juncture, I should say that although Michael in fact held a work permit showing him to be an employee of Sprinkler Engineering, I accepted his evidence and that of Stanley Lui, Sprinkler Engineering's managing director, that in fact he was an independent sub-contractor. According to Michael, it was his responsibility to supply the tools which his workers needed for the job. In this case, however, as the ceiling on which they had to work was at a great height above the ground, he needed a special staging for his workers. As he could not afford this staging, he asked Sprinkler Engineering to supply the equipment and it agreed to do so and in fact did so.
34 In about September 1989, Sprinkler Engineering engaged Ishak Karim to do the sprinkler installation works at the first storey of the warehouse. Ishak Karim was employed on more or less the same terms as Michael: he had to provide his own band of workers and tools and was paid according to the work done and not on a daily basis or according to the number of workmen he employed. According to Stanley Lui, it had been agreed that Ishak Karim would supply whatever staging his men needed to do their work.
35 The supervisor appointed by Sprinkler Engineering to supervise all sprinkler installation work at the warehouse was Ong Kai Choon. He was not permanently stationed at the site. According to Stanley Lui, Ong's duty was to ensure that the sub-contractors carried out the work according to their drawings and to effect this he visited the site as often as he could, once a day or once in two days. Ong himself said that in October 1989, he attended to two or three separate work sites on Sprinkler Engineering's behalf. As far as the warehouse was concerned, he was at the Woodlands site almost every day and spent an hour or so there on each visit. Michael confirmed that Ong was at the site every day though he asserted that Ong stayed for only half an hour each time. Soil Build itself had two supervisors at the warehouse. One was Mr Henry Low. His duty, once Soil Build's main construction works had been completed, was to co- ordinate the work of the various specialist sub-contractors on the site as well as any building works which were still going on. His daily duties were to check on the progress of the work, to write reports and to check the various jobs to see that they were completed in time. He was on the site every day from 8am to 5pm.
36 As far as Sprinkler Engineering was concerned, Henry Low dealt with either Stanley Lui, Ong or Michael. He did not know Ishak Karim. He did not have any control over the workers on the sprinkler system. He stated that Ong was rarely present at the warehouse. Sometimes he was there three times a week and sometimes not at all in a week. When he informed Stanley Lui that Ong was not there, Stanley Lui told him that Michael was in charge and thereafter whenever Henry Low had anything to communicate about the sprinkler works or the supervision of these works, he spoke to Michael.
37 The other supervisor employed by Soil Build was Mr Choo Ah Kow. According to him, the main supervisor for the sprinkler installation works was Michael. Ong was seldom seen on the site. He had come across a worker named Ishak who was a sprinkler worker but had no clear recollection of the person. Mr Choo did say, however, that between himself and Henry Low, Henry Low was more involved in the supervision of the mechanical and engineering works, including the sprinkler installation works.
38 One matter upon which all Sprinkler Engineering's witnesses were agreed was thatIshak Karim himself was hardly ever at the site. According to Michael, he wouldarrive there each morning with a party of workers and would drop them off. Hewould then leave the warehouse and return only in the evening in order to take hisworkers home. He spent very little time supervising the work that was being doneand when his workers had problems as to what needed to be done, they would consultMichael. Michael also testified that Ishak Karim had told him that SprinklerEngineering was to supply the staging for his workers. However, Ishak could not bebothered to go down to Sprinkler Engineering's office to collect it and instead allowedhis workers to use various pieces of staging belonging to Soil Build and lying at thesite. Ishak Karim's explanation to Michael was that Henry Low had permitted himto do this. Henry Low, on the hand, asserted that he had not given any sprinklerworkers permission to use the Soil Build staging. He complained about this toStanley Lui. He had previously complained to Ong but nothing had been done andwhen he complained to Michael, Michael said that the sprinkler workers using thestaging were not his workmen and that Henry Low should complain to Stanley Lui. Stanley Lui did not remember receiving any such complaints.
39 Henry Low also complained about the lack of supervision of the sprinkler workers on the first floor. Stanley Lui did not remember this complaint either. The only complaint he remembered was that Soil Build had said that the sprinkler work was slow and there was not enough manpower. He stated, initially, that he was not aware that Ishak Karim was rarely at the Woodlands site and that his workers did not have any supervision. Later, however, he agreed that Michael may have mentioned to him that Ishak Karim was always away from the site. In fact, at that time Sprinkler Engineering had also employed Ishak to carry out sprinkler installation works at another work site, one located in Jurong. So Stanley Lui must have known that Ishak Karim could not give his full time and attention to the Woodlands site. At a later stage in his cross-examination, Stanley Lui admitted that he was aware that Ishak Karim was always away from the Woodlands site and that despite the warnings Sprinkler Engineering had given to Ishak Karim to be on site to supervise his workers, Ishak Karim had continued to remain away.
40 Events leading up to the accident
41 The plaintiff's testimony was that on the morning of 9 October 1989, he was instructed by a supervisor (he was unable to identify which one) to carry out some touch-up works to pipes installed at the ceiling of the first storey. In order to get to the pipes, he had to use a three and a half storey mobile staging. He climbed up this staging onto the platform at the top. This platform was made of two or three pieces of wood. In the course of his touching-up work, he fell off the platform. The plaintiff was unable to explain the exact cause of the accident. In examination-in- chief he said that maybe the wooden boards had moved and that had caused him to fall. Alternatively, he said that perhaps part of the board was not level and he could have stepped on that portion, lost his balance and fallen.
42 The plaintiff stated that he was familiar with mobile staging and had worked on it prior to the occasion of the accident. When he used the staging, he would work with a friend. One of them would be on the platform and the other on the ground and they would instruct each other to push the mobile staging in order to change its position. While the staging was being pushed, the worker who had been on top of the staging would remain on the platform. He admitted that he had been told that he should descend from the staging before it was pushed but said that whether he would do so or not depended on how high the staging in question was. On the day in question, since the staging was nearly four storeys high, he did not practise that system and did not ask anybody to push the staging while he was on the platform.
43 There were two eye witnesses to the accident itself. The first was Michael. His testimony was that the staging which the plaintiff had used had been used by him and his co-workers prior to the day of the accident. They had taken the staging, which apparently was Soil Build's, from the site and had attached four wheels to its base thus converting it into mobile staging. On the morning in question, Michael and some of his workers were threading pipes at the first storey. The plaintiff was working in the area directly in front of Michael. On the ground in the area in which the plaintiff was working, there were several steel pipes or rods. These belonged to one of the other sub-contractors working at the site. Michael watched the plaintiff at work and wondered why his co-workers did not remove the steel pipes from the vicinity of the staging. Neither Ishak Karim nor Ong was present at the warehouse at that time.
44 That morning Michael saw the plaintiff climb up the staging on two occasions. The second time was after the 10am tea break. Sometime after the plaintiff had made his second ascent, Michael saw the plaintiff ask two of his co-workers from Ishak Karim's group to push the staging along to another location so that he could continue work. The plaintiff remained on the platform. His co-workers pushed the staging without removing any of the steel rods which were lying on the floor. One of the wheels got caught on a rod and the staging toppled. As a result, the plaintiff fell off. The staging ended up in a horizontal position a short distance away from the plaintiff.
45 Michael walked over to the plaintiff to look at him. At the same time, he noticed that the wheels on the staging were not in good condition. After the ambulance had arrived and the plaintiff had been put into the ambulance, Michael asked his workmen to remove the four wheels of the staging. He knew that the safety officer employed by Soil Build would be at the site shortly in order to investigate the accident and he did not want this officer, one Mr Low Hong Teck, to see the wheels. One of these wheels did not have a rubber insulator and the others were worn out. In Michael's view, if Mr Low had seen the wheels he would have said that sprinkler workers had not followed the safety rules and he would have complained both to Sprinkler Engineering and the Ministry of Labour. When Mr Low arrived at the site at about lunch time, he noticed that the wheels were missing and asked Michael what had happened to them. Michael did not give a direct answer to that question and told him only briefly how the accident had occurred. He told Mr Low that he should ask Stanley Lui for more details if he needed them. Michael told the court that his intention in removing the wheels from the staging was to protect Sprinkler Engineering's name. He did not want the persons at the site to have a bad impression of Sprinkler Engineering.
46 The other witness who saw the accident was one Ramly bin Hussin. He was a general worker employed by Soil Build at the site in 1989. His job was to clear the debris from the warehouse. At the time the accident took place, Ramly was sweeping at the first storey. He saw two male workers, one on a staging and the other on the ground. The one above was painting some pipes while the one below was pushing the staging. Subsequently he saw both the worker on the top of the staging and the staging itself falling down. He did not, however, see exactly how the accident happened and did not know why the staging had toppled. After the plaintiff had fallen down, Ramly noticed some other workers put a safety belt around his waist. According to Ramly it was a common practice at the warehouse for one person to stand on a staging while someone else pushed it from below. Michael gave the same evidence on this point.
47 What caused the accident?
48 Counsel for Sprinkler Engineering submitted that the court should find that the accident had happened as recounted by Michael. She submitted that his evidence was clear and consistent and was supported by that of Henry Low, Chow Ah Kow and Low Hong Teck. In addition, the Notice of Accident filed with the Ministry of Labour shortly after the time of the accident stated that the plaintiff had fallen from the staging whilst it was being pushed by two other workers. I accepted this submission as to the events which led to the accident.
49 Sprinkler Engineering further submitted that the accident was caused entirely by the plaintiff's own negligence since he was well aware that at the height at which he was working that day it would be dangerous if he stayed on top of the staging whilst it was being pushed. It contended that in any event there was no employer/employee relationship between itself and the plaintiff and therefore it did not breach the standard of care required of an employer to provide a safe system of work for its employees. Whilst I accepted that Sprinkler Engineering was not the plaintiff's employer, I was unable to accept that it had no duty of care to him whatsoever.
50 It appeared to me that the accident had had three contributory factors. First, there was the dangerous practice which the plaintiff and his friends adopted - that of pushing the staging from below while the plaintiff remained on top. Secondly, there appeared to have been something wrong with the wheels on the staging as was clearly indicated by Michael's evidence. I found Michael to be a generally credible witness and, having accepted his account of how the accident happened, I did not see any reason not to accept his observations as to where the staging used had come from, who had attached the wheels to it, that those wheels were defective and that he had removed them so to protect Sprinkler Engineering. Thirdly, there was a lack of supervision of the plaintiff and his co-workers and this contributed to the accident in that there was no one to stop them from following the dangerous practice adverted to or to ensure that all obstacles were removed from the vicinity of the staging.
51 Sprinkler Engineering's duties to the plaintiff
52 In my view, although Sprinkler Engineering had employed a sub-contractor to install the sprinkler system, it had a duty to ensure that the workers of that sub-contractor were not endangered in the course of carrying out their work by hazards which could reasonably have been anticipated. Stanley Lui accepted that it was his responsibility to organise the work that Sprinkler Engineering was doing at the site. Complaints were made to him that Ishak Karim's workers were using Soil Build's staging (I accepted Henry Low's evidence in this respect). He did not do anything about it nor did he make any effort to ensure that such staging as was being used was suitable for the purpose.
53 There was some confusion in Sprinkler Engineering's evidence as to who was supposed to supply the staging for the work at the first storey. Stanley Lui said it was Ishak Karim's responsibility. Michael's evidence was to the contrary, though in re-examination he said that he didn't know about the arrangement between Ishak Karim and Sprinkler Engineering on the supply of the staging. Ong stated that he was not aware that it was Sprinkler Engineering's obligation under the main contract with Soil Build to provide the staging for the sprinkler works. He thought that Soil Build should provide the staging and when he was asked why, he said that this was because on most of Sprinkler Engineering's other projects, it had used the main contractor's staging. He was then told (in fact, wrongly) that Michael had said that the labour only sub-contractors were supposed to provide the staging. Ong changed his evidence to agree with what he thought Michael had said and continued by saying that if the staging was provided by the sub-contractor, the sub-contractor would have got it from the main contractor. He did not, surprisingly, give any sign of knowing that in this particular case the staging Michael's own workers had used had been supplied by Sprinkler Engineering itself, an act inconsistent with what he maintained was his company's normal practice of using the main contractor's equipment.
54 To my mind, his answers showed that Ong was very well aware that in this case Soil Build's staging was being used by the sprinkler workers even though he could not remember Henry Low having complained to him about such usage. It appeared to me that he, a supervisor of many years experience, in fact expected sprinkler workers to use staging provided by others whether they did so pursuant to an arrangement between themselves and Sprinkler Engineering or pursuant to an arrangement between the main contractor and Sprinkler Engineering or whether they simply borrowed it without permission as and when they needed it. Both he and Stanley Lui must have been aware that such labour only sub-contractors would have the minimum equipment with them and would have to rely on the resources of others for bulky items such as staging. I thought it was more probable than not that Sprinkler Engineering had agreed to supply Ishak Karim staging if he needed it but that its staging had not been used simply because Ishak Karim had not bothered to pick it up.
55 It was also clear from Sprinkler Engineering's evidence that the plaintiff and his co- workers received inadequate supervision and instruction because Ishak Karim was hardly ever on the site. Ong was aware that unsafe systems of work were practised at the site by the sprinkler workers. He admitted receiving complaints about this from Henry Low although he said that he could not remember the exact nature of the complaints nor how often they had been made. Ong's only response to such complaints was to tell the sub-contractor concerned to remedy the situation. There is no indication that he actually spent more time at the site to ensure that his instructions were followed. Stanley Lui's own evidence established that Ishak Karim ignored complaints about his absence from the site. This was a significant matter as the evidence which emerged from all persons at the site was that workers employed by any particular sub-contractor would only obey that sub-contractor and would not take orders from Soil Build's supervisors or safety officer or even from another sub- contractor, such as Michael. Sprinkler Engineering, by failing to take effective action to ensure that Ishak Karim spent an adequate time at the warehouse was, in fact, condoning the lack of supervision to which the plaintiff and his co-workers were subject.
56 It was my view, in the circumstances of this case where the work to be done involved some element of danger and where supervision by an experienced worker was required, that Sprinkler Engineering (quite apart from any contractual obligation to supply the staging) had a duty to the workers of its sub-contractors to ensure that the equipment that they used was adequate and not defective and that they were properly supervised so that they did not carry out their work in a dangerous or slap-dash fashion. The facts narrated above showed that in the case of the plaintiff, Sprinkler Engineering had been negligent in the way in which it carried out its duty as its supervisor was not on site with sufficient frequency to ensure that proper procedures were followed nor did it respond responsibly to various complaints made about the sprinkler workers nor, finally, did it take any steps to ensure that the workers were provided with proper equipment for the job instead of having to improvise by modifying equipment left around by Soil Build with such wheels as came to hand.
57 In my analysis of the duty which Sprinkler Engineering owed the plaintiff despite the fact that it was not his employer, I was much assisted by the case of McArdle v Andmac Roofing Co. & Ors < 1967 > 1 All ER 583. In that case the plaintiff was employed by sub-contractors (Andmac) who were laying felt and bitumen on the roof of an existing building which was being converted at Pontin's Holiday Camp at Blackpool. Other sub-contractors (Newton) were engaged to provide labour to place joists over a strip of the roof and to lay boards on the joists. Both sub-contractors were engaged by the second defendants (Pontin). On the day of the accident, the plaintiff was on the roof working. As he moved along the roof, he reached an aperture which had been left temporarily uncovered and unprotected by Newton's men. The plaintiff fell to the ground and was injured. He sued Andmac, Newton and Pontin for, inter alia, negligence. The trial judge held that each of the defendants had in the circumstances owed a duty of care to the plaintiff and were liable to him for negligence. His judgment was upheld on appeal.
58 In the course of his judgment, Davis L.J. said (at p 589):
59 "As I see it, there was here a common law duty on Pontin, who were employing these two firms of sub-contractors on a task which inevitably involved that they should work in close proximity to each other and in close proximity to this dangerous hole in the roof, to take reasonable steps, or to see that Andmac and Newton took reasonable steps, to prevent the workmen from coming to harm."
60 Another judge in the Court of Appeal, Edmund Davies L.J., was equally clear that Pontin owed its sub-contractors' workmen a duty of care. He expressed it thus:
61 "Never losing sight of the fact that Newton were independent contractors and not the servants or agents of Pontin, the roof work that the former were engaged to perform was such as could well involve danger to others who, to the knowledge of Pontin, would be working in close proximity to the joiners - danger, that is, unless proper safety precautions were taken. Had Newton's men been in the direct employment of Pontin there could be no doubt as to the liability of the latter. Having regard to all the circumstances, does the fact that Newton were independent contractors relieve Pontin of all responsibility? It does not. The duty of reasonable care owed by Pontin to the plaintiff necessitated their taking proper steps that danger was eliminated as it so easily might have been. Having given Newton no instructions, nor specifically drawn to their attention the availability of material for constructing safety devices, it is no answer to the plaintiff's claim for Pontin to say "we left it to our independent contractors to forage around the site for such safety devices as they thought desirable to use."
62 Whilst the facts of the Andmac case were different from those which arose in this claim, I thought that the principles enunciated there were equally applicable to the situation before me. Sprinkler Engineering was fully aware of all steps required to be followed in the proper installation of a fire-fighting system. It knew that the work which the plaintiff had to do required proper supervision and equipment and involved a certain amount of danger. It therefore had a duty to take steps to see that that danger was, as far as practicable, eliminated or reduced and it was no answer to the plaintiff's claim to say that everything was left to Ishak Karim, their independent contractor. It was well aware that Ishak Karim was working on more than one site at a time and that during the period when the sprinkler work was being carried out there would be various other sub-contractors and workers at the Woodlands site. Careful supervision and co-ordination was therefore required and, in view of the height at which the sprinkler workers had to work, Sprinkler Engineering should have ensured that the equipment used by them was adequate for the purpose and was used in a proper fashion. It failed lamentably to carry out this duty and I therefore found its breach of duty had contributed to the accident.
63 Nevertheless, it was my judgment that the plaintiff himself bore the greater proportion of responsibility for his injuries as he had recklessly followed a system which he knew to be dangerous. He had not taken sufficient care for his own safety. Accordingly, I apportioned the responsibility between the plaintiff and Sprinkler Engineering in the ratio of two-thirds to one-third.
64 As there has been no appeal against my finding that Sprinkler Engineering was not a joint occupier of the site, I need not deal either with my reasons for that finding nor with the plaintiff's arguments for affixing Sprinkler Engineering with liability on the basis that it was in breach of its duties as an occupier.
65 The position of Soil Build
66 As set out in his closing submissions, the plaintiff's claim against Soil Build was for:
67 1. breach of the statutory duty imposed by ss 28 and 33 of the Factories Act (Cap 104 1985 Ed) ("the Act");
68 2. breach of its duty as occupier of the warehouse to take positive steps to keep the warehouse in a safe condition; and
69 3. breach of a duty to be careful in its selection of its independent contractor. I did not find substance in any of these grounds.
70 (i) Breach of Statutory Duties
71 The first section of the Act on which the plaintiff relied was s 28. This provides that no person is to be employed at a machine which is likely to cause bodily injury unless he has been given proper training in the use of the machine and is under adequate supervision. In my view, this section was inapplicable as the staging which the plaintiff used for his work could not be classified as a "machine" within the meaning of the section. The definition of "machinery" which appears in the Act states that that term includes "machines in which mechanical movement, either linear or rotated or both, takes place". This accords with the Concise Oxford Dictionary definition of machine which is an "apparatus for applying mechanical power, having several parts each with a definite function". The staging which the plaintiff used did not fulfil this definition since it was simply a piece of equipment like a ladder which he could climb up to reach a required height. It had no movement of its own nor did any mechanical power result from its use.
72 Section 33(1)(b) of the Act requires that all places of work should, so far as it is reasonably practicable, be kept free from any obstruction and from any substance likely to cause persons to slip. The plaintiff did not specifically rely on a breach of this sub-section as his submissions were directed more towards the condition of the staging. Soil Build submitted that although Michael's evidence was that there had been some steel rods lying on the ground near where the plaintiff was working, this did not mean that those rods constituted an obstruction within the meaning of the sub- section. Counsel submitted that as it was also Michael's evidence that the rods were materials being used by other workers in the warehouse, they had not been unnecessarily left lying around so as to constitute an obstruction. Further, they had been stacked in a pile and were visible to all and could easily be avoided.
73 I agreed that the stack of rods was not an obstruction. In coming to this conclusion, I was assisted by the dictum of Lord Denning MR in Churchill v Louis Marx & Co., Ltd. < 1964 > 108 Sol. JO. 334 to the effect that "an obstruction is something that had no business to be there something ought not reasonably to be there. No formula or form of words helped greatly and it was a question of asking oneself whether the object was an obstruction in all the circumstances of the case". Applying this dictum to the facts before me, quite apart from the evidence that the rods were needed for the purpose of on-going work, I noted that there was no evidence adduced by the plaintiff establishing that it would have been difficult either to move the staging around the rods or to move the rods themselves away from the pathway of the staging. The plaintiff himself did not even remark on the presence of the rods much less blame them in any way for the accident. There was thus no basis on which to apply s 33(1)(b) to the case.
74 The other parts of s 33 which could possibly have been applicable to this case were ss(7) and ss(8). These read as follows:
75 "(7) Where a person has to work at a place from which he would be liable to fall a distance of more than three metres... a secure foothold and handhold shall be provided so far as practicable at the place for ensuring his safety.
76 (8) Where it is not practicable to provide a secure foothold and handhold as provided under sub section (7), other suitable means such as a safety belt and fencing shall be provided for ensuring the safety of every person working at such places."
77 It appeared from the evidence that the plaintiff and his co-workers had attached wooden boards to the very top of the staging in order to provide a platform on which the plaintiff could stand. There were no guardrails protruding above the platform and thus no handholds for the plaintiff. There was conflicting evidence as to the existence of a secure foothold. The testimony of the safety officer was that when he saw the toppled staging after the accident, one of the wooden boards was still tied to it. If all the boards had been so tied, they would have been secure. Michael's evidence, however, was that the boards were not tied to the platform at all. The plaintiff himself said the same thing. It appeared to me that no secure foothold existed on the staging because even if the safety officer's evidence was accepted, that meant that only one board had definitely been tied to the staging. I therefore concluded that the plaintiff had not been provided with either a secure handhold or a secure foothold.
78 There was some discussion during the trial as to whether the staging was the proper equipment to have been used for the purpose of touching up the sprinkler pipes. Some suggestion was made that a scissor-lift should have been used instead. Mr Low, the safety officer, testified that whilst the scissor-lift was a safer piece of equipment when compared with the staging used, he could not say that that staging was wrong for the work. It could be used safely provided it had been properly installed with a guardrail and a secure platform. It therefore appeared that it would have been practicable to provide, on this staging, the secure foothold and handhold which s 33(7) require. The issue was then whether the breach of s 33(7) which obviously took place in this case rendered Soil Build liable to the plaintiff.
79 The plaintiff's submission was that any breach of the Act would have the result of imposing liability on Soil Build. He argued that the Act imposed strict liability on persons subject to it. This argument was not supported by any authority and in fact ran counter to the principles laid down in several cases dealing with liability arising from a breach of the Act. In Cummings v Sir William Arrol & Co., Ltd < 1962 > 1 All ER 623, the House of Lords considered a suit involving a breach of s 26(2) of the English Factories Act 1937. That section was cast in similar terms to our s 33(7). The court held that while a breach of the section had been established, the plaintiff was not entitled to succeed as she had been unable to further establish that it was the breach of the section which had been the cause of the injury. As Viscount Simonds stated (at p 628) the law was that a causal connection must be established between the breach by an employer of his duty at common law or under a statute and the damage suffered by his employee. The importance of the chain of causation was also stressed by Viscount Kilmuir L.C. who stated (at p 627):
80 "Finally it was submitted that if the deceased's hypothetical refusal to wear a safety belt must be recognised as the effective cause of his not wearing one and hence of his death, the failure of the respondents to provide a safety belt should not be ignored as a causative factor. The answer in my view must be there are four steps of causation: (i) a duty to supply a safety belt; (ii) a breach; (iii) that if there had been a safety belt the deceased would have used it; (iv) that if there had been a safety belt the deceased would not have been killed. If the irresistible inference is that if the deceased would not have worn a safety belt had it been available, then the first two steps in the chain of causation ceased to operate."
81 Other cases such as Wigley v British Vinegars Ltd < 1962 > 3 All ER 161 and Corn v Weir's Glass (Hanley), Ltd < 1962 > 2 All ER 300 reflect the same approach that a breach of statutory duty is not sufficient to affix an employer with liability for injury; there must be a direct causal relationship between the breach and the injury.
82 In the present case there was no causal connection between the breach of the duty to provide the plaintiff with a safe handhold and a safe foothold and the injury. The injury occurred because the whole of the staging toppled when it was pushed and because the plaintiff remained on top of it when he should have come down onto the ground. The same argument applied to the contention that there was liability arising from the breach of s 33(8) because the plaintiff was not supplied with a safety belt. It was clear that the presence of such a belt would not have averted the accident since there was no hook to which the belt could have been attached in such a way so that even if the staging fell the plaintiff would not have fallen with it.
83 Quite apart from the causation issue, I did not agree that the Act had the result of imposing liability on Soil Build as the occupier of the warehouse for injury to the plaintiff who was not its employee. Soil Build had no direct relationship with the plaintiff. Its only direct relationship was with Sprinkler Engineering and, under the contract between the two companies, Sprinkler Engineering had complete control over the manner in which the sprinkler works were installed. Soil Build had no obligation to supply Sprinkler Engineering with any equipment or workers for purpose of such work. Neither did Soil Build have any control over the manner in which the plaintiff himself carried out the work which he did. In my opinion, the duties of providing the plaintiff with a secure handhold/foothold and with safety equipment imposed by the Act rested with the plaintiff's employer Ishak Karim and did not rest on Soil Build simply because it was the main contractor and occupier of the site.
84 (ii) Breach of Occupier's duty
85 Under common law, it is the duty of an occupier to use reasonable care to prevent damage to an invitee on his premises from unusual dangers which the occupier knows or ought to know about. The duty owed by the occupier to the invitee is in respect of the physical condition of the premises concerned as opposed to current operations at the site. These principles explain why I was unable to find Soil Build liable as an occupier at common law for the plaintiff's injuries. The accident did not arise from any unusual danger on the premises. Instead it was caused by the negligence of the plaintiff and his co-workers and the defective state of the staging. Although the staging wheels caught on the steel bars, the steel bars did not create any unusual danger as they were patently obvious to all users of the premises (see London Graving Dock Co. Ltd v Horton < 1951 > 2 All ER 1 and Lee Lau & Sons Realty Sdn Bhd v Tan Yah & Ors < 1983 > 2 MLJ 51).
86 Further, as an occupier who was not controlling the method of work adopted by Sprinkler Engineering and its sub-contractors, Soil Build could not be responsible for injuries sustained by the plaintiff as a result of the unsafe system of work which was adopted by him and his co-workers. This unsafe system of work must have been known to Ong and thus to Sprinkler Engineering. As it took no effective steps to put an end to the practice, it must be deemed to have adopted it. Ferguson v Welsh & Ors < 1987 > 3 All ER 777 held that an occupier would not usually be liable to an employee of a contractor employed to carry out work on the occupier's premises if the employee was injured as a result of any unsafe system of work used by his employer, the contractor, since ordinarily it would not be reasonable to expect the occupier to supervise the contractor to ensure that he would carry out the duty he owed to his employees to use a safe system of work. In this case I found no reason to expect Soil Build, the general builder, to supervise Sprinkler Engineering, the specialist sub-contractor, in the manner in which it carried out the specialist sub- contract works. On that basis, Soil Build was not liable to the plaintiff.
87 (iii) Breach of any other duty
88 I found it difficult to follow the plaintiff's contention that Soil Build should be held liable to him on the basis that it had been negligent in its selection of Sprinkler Engineering as its sub-contractor as no real argument was addressed to this issue. Counsel for the plaintiff first restated the general rule in tort that a person is not responsible for the negligence of his independent contractor. He continued that the faulty execution of any work of construction, repair or maintenance by an independent contractor employed by a main contractor will not put the main contractor in breach of a duty of care provided that:
89 (a) it was reasonable to entrust the work to an independent contractor;
90 (b) the main contractor had taken reasonable care to see that the independent contractor was competent; and
91 (c) the main contractor had taken reasonable care to check that the work was properly done.
92 He submitted that the plaintiff could recover if Soil Build's breach of duty caused his injury. Counsel did not, however, specify what breach of duty he was relying on and how that breach of duty led to the accident. He did not specify either how Soil Build had a duty to the plaintiff (rather than to the third defendants as to Soil Build's employers) to take reasonable care to see that either Sprinkler Engineering or Ishak Karim was reasonably competent to do the sprinkler installation works. Finally, counsel did not state what he thought a proper method of doing the work was or detail how Soil Build had failed to check that this proper method had been followed or how such failure led to the plaintiff's injury.
93 I did consider whether Soil Build could be made responsible for the plaintiff's accident on the same basis as I had held Sprinkler Engineering responsible. My conclusion was in the negative because of the greater distance between Soil Build and the plaintiff than existed between Sprinkler Engineering and the plaintiff. Soil Build, under the terms of the contract between it and the third defendants, had to entrust certain specialist portions of the construction work to specialist builders. One such portion was the installation of the fire protection system. Under the contract, this work had to be done by a nominated sub-contractor and could not be effected by the main contractor who had no knowledge of the expertise required for the job. In these circumstances, once Sprinkler Engineering was appointed, the work was entirely in its hands and Soil Build's role was reduced to that of a co-ordinator of the usage of the site by the various specialist sub-contractors and some general caretaking of the site. Since Soil Build had an utter lack of knowledge of what had to be done in relation to the sprinkler works, it would not have been reasonable for me to have imposed on it the same duty of care in relation to the plaintiff as I did on Sprinkler Engineering.
94 In my view, Soil Build's duty of care to the plaintiff was limited to the duties imposed on it as occupier of the warehouse. It was not in breach of such duties. It did not owe the plaintiff any duties as an employer or even as a quasi-employer as did Sprinkler Engineering. Least of all did it owe the plaintiff as a worker employed by the sub-contractor of its own sub-contractor any duty to choose a competent sprinkler sub-contractor or to supervise closely the method of work chosen by the sub-contractor and its sub-sub-contractor.
95 Soil Build v Sprinkler Engineering
96 In the event that the plaintiff is successful in his appeal against my dismissal of his claim against Soil Build, the issue will arise as to whether Soil Build's claim against Sprinkler Engineering for damages should be allowed. I dismissed that claim purely on the basis that as I was unable to find any liability to the plaintiff on Soil Build's part, it in turn had no claim against Sprinkler Engineering. However, I did make a finding that Sprinkler Engineering owed Soil Build a contractual duty to ensure that its sub-contract work was carried out safely and to provide proper supervision of its workers and that it was in breach of such duty. Thus, if I had found Soil Build liable to the plaintiff, I would have, in turn, found Sprinkler Engineering liable to Soil Build.
97 The basis of Soil Build's claim was that the contract between it and Sprinkler Engineering was contained in the tender documents and a letter of award dated 29 February 1989 from Soil Build to Sprinkler Engineering. In the tender documents, Sprinkler Engineering had represented to Soil Build that it would be employing its own workmen for the installation of the fire-fighting system as opposed to engaging sub-contractors for the job. In the letter of award sent in response to those documents, Soil Build wrote:
98 "In accepting your tender, you are reminded that:
99 i) you are responsible for informing your employees engaged in the works to conform to all statutory safety requirements;
100 ii) you are to, at all times, ensure that your men are under good supervision and the entire work is carried out in a safe and efficient manner;
101 iii) your employees working on the site should have valid work permits."
102 At the end of the letter was the following statement: "We, M/s Sprinkler Engineering Pte Ltd, hereby confirm our acceptance to the above stated herein" and Sprinkler Engineering signed below the statement in the space provided and returned a signed copy of the letter to Soil Build.
103 In my judgment, the letter of 29 February 1989 was a contractual document and the terms that I have quoted above were part of the contract between Sprinkler Engineering and Soil Build. Counsel for Sprinkler Engineering, though not denying that the letter as a whole formed part of the contract, submitted that those words were of no contractual force and simply contained a reminder to Sprinkler Engineering to follow standard procedure at construction sites. I did not agree. If the letter was a contractual document then all its terms had to be considered in that light. It was significant too that Sprinkler Engineering's further acceptance of the terms was required. The fact that the obligations were preceded by the words "you are reminded that" did not derogate from their contractual nature.
104 The reasons why I found Sprinkler Engineering to have been in breach of its duties to ensure that its workers were under good supervision and that the entire work was carried out in a safe and efficient manner are set out in detail in my discussion of Sprinkler Engineering's liability to the plaintiff. It is not necessary to repeat them here.
105 It was submitted on behalf of Sprinkler Engineering that the terms were vague and thus should be construed against Soil Build. I did not agree. As far as the phrase "your workers" was concerned, whilst it might have been intended to apply to Sprinkler Engineering's own employees as Soil Build was under the impression that the sprinkler workers on the site would be the direct employees of Sprinkler Engineering, the term was wide enough to cover any persons working on the sprinkler system at the request of Sprinkler Engineering whether such persons were employed by that company or by its sub-contractors. Secondly, the phrase "good supervision" could not be limited to mean only that the supervisor must know how the work was to be done in accordance with the drawings and specifications as counsel for Sprinkler Engineering submitted. It also meant that the supervisor would pay close attention to the way in which the men carried out the work to ensure, in particular, that they followed safe working systems. This must be so since the words "good supervision" came in the same sentence as the injunction that the work should be done in a safe manner.
106 Finally, counsel for Sprinkler Engineering submitted that Soil Build had not shown how her client had been in breach of its obligation to provide good supervision and to ensure that the work was done in a safe manner. I disagreed. The evidence of Sprinkler Engineering itself indicated that the plaintiff was not given adequate supervision let alone good supervision and that the unsafe system of work which the plaintiff had adopted was a common practice followed by the sprinkler workers which Sprinkler Engineering had not taken any steps to halt.
107 Orders for costs
108 I made two orders for costs against Sprinkler Engineering which it is dissatisfied with. The first order was that Sprinkler Engineering was to pay the plaintiff's costs on the standard basis in full up to 31 October 1994 and 50% of the plaintiff's costs thereafter.
109 On 22 October 1994, some five months after the first hearing of this case, Sprinkler Engineering made the plaintiff an offer to settle his claim by the payment of the sum of $35,000 in general damages and $12,000 costs. The plaintiff did not accept this offer and it was withdrawn on 1 November 1994 without the one clear day's notice required by O 22A r 3(2). In the event, the amount which the plaintiff recovered under the judgment which I awarded him amounted to $34,200 (inclusive of interest of 6% p.a. on the sum of $60,000 from the date of the writ to 31 October 1994). As the offer to settle was not on foot at the time of the judgment, the provisions as to costs set out in O 22A r 9 did not apply and costs remained at my discretion.
110 It appeared to me that the fairest course was to apportion the costs between Sprinkler Engineering and the plaintiff. I thought that it was right to make Sprinkler Engineering bear all the costs up to 31 October 1994 as its offer to settle had not been made until eight days prior to that date and in fact had to remain open for at least seven days. As regards the costs of the hearing thereafter, I did not think it fair to deprive the plaintiff of all his costs simply because the amount offered by Sprinkler Engineering exceeded the amount that he eventually recovered by a nominal amount of some $800. On the other hand, I had to take account of the fact that the plaintiff had failed in his attempt to prove that Sprinkler Engineering was his employer and that a substantial part of the trial dealt with this issue. In my view, the order that Sprinkler Engineering should pay only 50% of the plaintiff's costs after 31 October 1994 fairly reflected the position.
111 As regards Soil Build, since the plaintiff had failed in his claim against it, the proper order was that the plaintiff should pay Soil Build's costs. Mr Pillai submitted that I should make a bullock order so that Sprinkler Engineering should bear any costs which the plaintiff had to pay Soil Build. His contention was that the plaintiff had no choice but to commence action against Soil Build because Sprinkler Engineering had denied that it was the occupier of the site or the plaintiff's employer. Since Soil Build was the main contractor, it was reasonable to bring it in as occupier of the premises. Further, the plaintiff was not aware of the exact relationship between Soil Build and Sprinkler Engineering and whether Soil Build had any obligation to provide equipment or assistance for the sprinkler workers.
112 After hearing the arguments, I agreed that it had been reasonable for the plaintiff to sue Soil Build after Sprinkler Engineering had totally denied any relationship with the plaintiff which could possibly have founded a cause of action against it. If Sprinkler Engineering had accepted that it did owe some duties to the plaintiff even though it denied that it had been in breach of those duties or that the injury had resulted from any such breach, then the plaintiff would probably not have sued Soil Build and would have confined his efforts to building his case against Sprinkler Engineering. In these circumstances, I ordered that Sprinkler Engineering should pay all Soil Build's costs paid by the plaintiff up to 16 November 1994. On that date Soil Build had made an offer to settle by paying the plaintiff $40,000 and interest at $18,000 and costs at $12,000. The plaintiff did not accept the offer and I did not think it fair to make Sprinkler Engineering bear all Soil Build's costs thereafter when the matter could have been settled by an acceptance of the offer. I therefore ordered that only 50% of any costs payable by the plaintiff to Soil Build for the period after 16 November 1994 should be borne by Sprinkler Engineering.
113 JUDITH PRAKASH
114 JUDGE
115 SINGAPORE
116 Date : 26 October 1995
117 This does not merit reporting
Suppiah Pillai (Yong Koh & Pillai) for the plaintiff
Lie Chin Chin (Lie Kee Pong & Co) fo the 2nd defendants
Morris John and Anil Sachdev (Drew & Napier) for the 3rd defendants
Lee Yuk Lan (Goh Poh & Partners) for the 4th defendants