Hua Khian Co (Pte) Ltd v Lee Eng Kiat
[1995] SGHC 252
Suit No1156 of 1992
Lai Siu Chiu J
30 October 1995
1 Judgment:
2 Coram: Lai Siu Chiu J
3 Cur Adv Vult
4 JUDGMENT
5 The facts
6 The plaintiffs are a Singapore company and the defendant is the owner of a property known as No 6 Elliot Road, Singapore (the property). In or about December 1991 the plaintiffs were informed by a housing agent that the property was available for sale. A director of Homeland Investments Pte Ltd (Homeland) one Ong Ang Keng Hoe (Ong) who is a business associate of the plaintiffs, was authorised by the plaintiffs' director Lim Chye Him (Lim) to negotiate the purchase of the property. Ong met the defendant at Homeland's office one evening and according to Ong the defendant made the following representations:
7 a. planning approval for a pair of three storey semi-detached houses had been granted for the adjoining property known as No. 4 Elliot Road (No 4);
8 b. the property which is approximately the same size as No 4 could also be developed;
9 c. there would be no problem in the Urban Redevelopment Authority (URA) approving redevelopment of the property if the plans submitted were materially the same as the plans submitted for No 4.
10 Ong alleged that based on the above representations he agreed on the plaintiffs' behalf to a purchase price of $960,000 for the property at the meeting, which was subsequently increased to $965,000.
11 On 21 December 1991 the defendant's solicitors forwarded a draft agreement for sale and purchase to the plaintiffs' solicitors for approval. The plaintiffs' solicitors returned the draft with amendments which included inter alia the condition that the purchase was subject to planning approval for a pair of semi-detached houses of three storeys each. The agreement for sale and purchase dated 28 December 1991 (the agreement) was eventually signed with completion scheduled for thirteen (13) weeks thereafter namely on 28 March 1992. Pursuant to cl 2 thereof, the plaintiffs paid 10% of the purchase price amounting to $96,500 (the deposit) upon signing.
12 At the plaintiffs' request the defendant's solicitors informed URA on 15 February 1992 that their client had no objections to the plaintiffs' submission of plans for three storey semi-detached houses (AB76). The plaintiffs' architect (Miss Chan) submitted plans to the URA with instructions from Ong to inform the URA that the plaintiffs must know the outcome one day before completion.
13 As there was no reply from the URA by 21 March 1992, on Ong's instructions the plaintiffs' solicitors requested for an extension of two weeks for completion (AB83). The defendant's solicitors replied on 23 March 1992 to say Our client will charge the usual interest for late completion; Ong said the plaintiffs interpreted the reply to mean that an extension was granted subject to payment of usual interest for late completion.
14 The plaintiffs then received a reply from URA (AB85-87) granting provisional approval for the erection of a pair of two storey semi-detached houses. The plaintiffs were requested to resubmit their proposal to the URA within six (6) months of 24 March 1992 failing which the permission would lapse automatically. Ong instructed Miss Chan to appeal to the URA for permission to construct three storey semi- detached houses on the property. He further instructed the plaintiffs' solicitors to request for a further extension of time from the defendant to complete, pending the appeal. Accordingly the plaintiffs' solicitors wrote to the defendant's solicitors on 27 March 1992 (AB90). The request was rejected by the defendant's solicitors' letter dated 28 March 1992 (AB91); instead they gave 21 days' notice for completion expiring on 18 April 1992. The plaintiffs' solicitors responded on 30 March 1992 saying their clients reserved their rights at the same time requesting a meeting with the defendant; the defendant did not accede to the request.
15 On 7 April 1992 the plaintiffs' solicitors informed the defendant's solicitors that their clients were unable to complete, they rejected the defendant's 21 days' notice to complete, asked for the refund of the deposit and concluded by saying Please note that our clients shall not be liable for any interest. On the following day the defendant's solicitors gave notice that the defendant was not obliged to refund the deposit unless the plaintiffs produced evidence that they had complied with cl 10(b)(i) to (iv) of the agreement which state:
16 (b) the vendor shall return the sum of $96,500 stated in clause 2 herein to the purchaser subject to the following conditions:-
17 (i) the purchaser shall provide documentary evidence that his architects submitted a complete application to the relevant authorities for the said in-principle approval within fourteen (14) days from the date of this agreement;
18 (ii) the plans submitted to the authorities for the proposed one (1) pair of semi-detached houses is similar in all material respects to that submitted by Messrs James Yip & Partners on behalf of the proprietors of No 4 Elliot Road Singapore;
19 (iii) all costs of and incidental to the said in-principle approval shall be borne by the purchaser; and
20 (iv) any delay in granting of the in-principle approval by the authorities is not due to the default of the purchaser or his servants or agents.
21 On 11 April 1992 the plaintiffs' solicitors reiterated their demand for the return of the deposit giving notice that if it was not refunded within three (3) days, legal proceedings would be commenced. The defendant's solicitors responded pointing out that the plaintiffs had refused to comply with the request to show evidence of compliance with cl 10(b) of the agreement.
22 On 21 April 1992, the defendant's solicitors gave notice that the deadline for completion expired that day and requested for the return of the title deeds pursuant to cl 29(4)(a) of the Law Society's Conditions of Sale as well as removal of the plaintiffs' caveat, by 28 April 1992. They reiterated that the defendant was not obliged to refund the deposit without proof of compliance with cl 10(b) of the agreement.
23 On 23 April 1992 the plaintiffs through their solicitors offered to complete the purchase within 21 days, despite the defendant's non-compliance with cl 10 of the agreement. In a separate letter, the plaintiffs' solicitors informed the defendant's solicitors that the defendant was not ready or able to complete as he had failed to furnish evidence that he had discharged the unsatisfactory requisition queried by the plaintiffs' previous solicitors (relating to mosquito breeding). They reiterated that on a without prejudice basis the plaintiffs were willing to complete the sale and purchase and alleged for the first time, that prior to the execution of the agreement, the defendant had represented to the plaintiffs that there was existing approval for a pair of three storey semi-detached houses. The swift response from the defendant's solicitors was to ask for full particulars of the allegation and for evidence of compliance with cl 10 of the agreement. On 23 April 1992 itself the defendant had entered into a fresh contract with another purchaser Fortune Realty Pte Ltd (Fortune) to sell the property for $1m.
24 Further correspondence between the parties' solicitors still resulted in an impasse as both sides maintained their respective stands; the plaintiffs called for completion on 14 May 1992. On the defendant's part he insisted he had complied with a notice (the Notice) from the Ministry of Environment (MOE) which was the basis for the plaintiffs' contention that the reply to their requisition was unsatisfactory.
25 On 27 April 1992 the defendant's solicitors repeated their demand for the return of the title deeds. On 6 May 1992 Architects PS 100 (the architects) wrote to the plaintiffs offering on Fortune's behalf, to reimburse the plaintiffs $4,000 for the professional fees they had paid; the architects requested to be released from acting for the plaintiffs as Fortune had retained the architects to submit plans to URA.
26 The plaintiffs changed solicitors in May 1992, on 1 June 1992 the defendant indicated he was not prepared to refund the plaintiffs' deposit in full, neither did the plaintiffs remove their purchasers' caveat. The writ herein was filed on 16 June 1992. On 20 July 1992, the URA wrote to the architects to advise that the plaintiffs' application had lapsed as they had been informed by the defendant that he had withdrawn his consent, his sale to the plaintiffs being aborted.
27 On 21 October 1992 Keppel Finance Limited (Keppel) entered into a sale and purchase agreement, as mortgagees of the property, with Hern Yang Construction Pte Ltd (Hern Yang), to sell the property for $1.33m. The plaintiffs changed solicitors yet again in May 1993.
28 The claim
29 The plaintiffs amended their pleadings twice and by their re-amended statement of claim, they alleged the following:
30 1. the sale was subject to the plaintiffs' obtaining in-principle approval by 28 March 1992 for the construction of a pair of semi-detached houses on the property which condition was inserted at the request of and for the benefit of the plaintiffs. The defendant was aware of the plaintiffs' application for redevelopment as by his solicitors' letter to the URA dated 15 February 1992 he had stated he had no objections to the same;
31 2. the plaintiffs by their solicitors' letter dated 21 March 1992 requested an extension of two weeks to complete the purchase and the defendant by his solicitors' fax dated 23 March 1992 expressly or impliedly agreed to extend the date for completion by informing the plaintiffs that he would be charging the usual interest for late completion; completion was accordingly extended by consent to 11 April 1992;
32 3. on 27 March 1992 the plaintiffs' solicitors informed the defendant's solicitors that in-principle approval for the proposed development had not been granted and inquired of the defendant if he would be amenable to delay completion pending the plaintiffs' appeal. The defendant by his solicitors' fax dated 28 March 1992 to the plaintiffs' solicitors elected to treat the agreement as still subsisting and served a purported Notice to Complete thereby waiving the requirement that in-principle approval be obtained before completion;
33 4. the said Notice to Complete was invalid as:
34 a. the date for completion had been extended to 11 April 1992;
35 b. there was no basis for the defendant's contention by his solicitors that the plaintiffs were unable to complete;
36 c. the defendant was not at the time of service of the Notice ready willing and able to complete in that he had not satisfactorily shown that he had complied with a notice from the Ministry of Health affecting the property;
37 d. the Notice was not served in the manner required by the Law Society's Conditions of Sale;
38 5. the plaintiffs subsequently requested a refund of the deposit from the defendant which the defendant refused on the basis that the condition in cl 10(b) of the agreement had not been complied with;
39 6. on 23 April 1992 after the extended date for completion the plaintiffs' solicitors served a 21 days' notice to complete on the defendant's solicitors and despite repeated requests, the defendant to date has neglected to and refused to take steps to complete; the plaintiffs were at all material times ready and willing to fulfill their obligations under the agreement;
40 7. in the alternative the plaintiffs have substantively complied with cl 10(b) entitling the plaintiffs to claim the return of the deposit as the URA granted approval for two storey semi-detached houses;
41 8. alternatively the defendant has expressly or impliedly waived compliance/strict compliance with cl 10;
42 9. in the further alternative the forfeiture of the deposit is a penalty from which relief should be given on proper terms, cl 10(b) being a penalty clause;
43 10. alternatively the withholding of the deposit is unconscionable and forfeiture of the sum is out of all proportion to any damage the defendant may have suffered. The defendant subsequently made a great profit from a mortgagee sale of the property at $1.33m which sale was orchestrated by the defendant to circumvent the caveat lodged against the property by the plaintiffs. The purported sale was not bona fide but a sham;
44 11. alternatively, as a result of a change in the policy of the URA an application for a three storey semi-detached house would never be approved by URA at the material time; there was a total failure of consideration which entitled the plaintiffs to claim back the deposit and or any other restitutionary relief;
45 12. alternatively it was expressly or impliedly agreed between the parties that the agreement shall be discharged and the deposit refunded where the URA ceased to give approval for semi-detached house development that are three storeys high in the vicinity;
46 13. alternatively the agreement was frustrated, performance of the contract became impossible and the plaintiffs are entitled to a refund of the deposit;
47 14. alternatively there was a common mistake in that both parties were not aware at the date of the agreement that the URA had imposed a change in policy applicable to the vicinity in that only permission for housing developments less than three storeys high would be granted;
48 15. alternatively the defendant through his agent or himself had made the following false representations:
49 a. there was existing approval for a pair of three storey semi-detached houses at No 4;
50 b. URA would give its approval to an application for semi-detached houses with three storeys;
51 c. URA at the material time was still having a policy to give approval for applications for three storey high semi-detached or any housing development in the vicinity of the property;
52 16. the plaintiffs were induced by the false representations to enter into the agreement which the defendant well knew to be untrue whereby the plaintiffs have suffered loss and damage;
53 17. in the premises the plaintiffs are entitled to rescind the agreement and claim back the deposit and damages.
54 The plaintiffs prayed for specific performance of the agreement, alternatively rescission of the agreement with damages and refund of the deposit and in the further alternative a declaration that the agreement was void and refund of the deposit with interest thereon.
55 In the re-amended defence the defendant
56 1. denied that cl 10(b) of the agreement was only for the benefit of the plaintiffs;
57 2. alleged that when he instructed his solicitors to write to the URA on 15 February 1992 he was under the belief or was led to believe that the plaintiffs had acted in accordance with cl 10 of the agreement and he as the vendor was obliged to consent to the plaintiffs' application by the terms of the agreement;
58 3. contended that he did not at any time waive the plaintiffs' obligations under cl 10(b) of the agreement or the requirement for in-principle approval to be obtained before completion;
59 4. admitted he received the plaintiffs' letter dated 21 March 1992 and as a gesture of goodwill he agreed to serve 21 days' notice notwithstanding that the agreement would be deemed null and void if no in-principle approval was granted to the plaintiffs by the completion date -- the same was a condition precedent to completion. He denied that he had agreed to extend the completion date to 11 April 1992;
60 5. contended that apart from their solicitors' letter dated 27 March 1992 inquiring whether he would delay completion pending an appeal to the URA on the in-principle approval given, the plaintiffs never indicated that they were prepared to complete the purchase without the requisite in-principle approval. To the contrary, the plaintiffs repeatedly demanded the return of the deposit which amounted to an admission that the agreement was null and void and which is a condition precedent before the deposit can be refunded;
61 6. pointed out that the Notice to Complete from his solicitors was served when the plaintiffs were unable to complete on 28 March 1992 as scheduled. The defendant was ready willing and able to complete as he had by a letter dated 5 March 1992 informed the plaintiffs that he had complied with the Notice from the Ministry of Health months ago and an inspection of the property would have confirmed the defendant's compliance. In the alternative the plaintiffs did not raise objections that the Notice was unsatisfactory when the defendant served the Notice to Complete;
62 7. said he received the plaintiffs' solicitors' letters of 7, 11 and 14 April 1992 for refund of the deposit which demands were not made on a without prejudice basis. Alternatively the demands were an election on the plaintiffs' part to treat the agreement as null and void pursuant to cl 10 thereof;
63 8. said by his solicitors' letter dated 23 April 1992 he had also treated the agreement as null and void pursuant to cl 10 thereof and accordingly he requested for evidence of compliance with cl 10(b) in order to refund the deposit. Despite repeated requests, the plaintiffs had failed, refused and or neglected to furnish the same;
64 9. denied all the alternative claims of the plaintiffs.
65 In their reply the plaintiffs contended that both parties treated the agreement as still valid and subsisting at all material times. At this juncture I should point out that the plaintiffs and the defendant were in error in referring to the alleged non compliance by the defendant with the Notice from the Ministry of Health when the same was issued by the MOE.
66 The evidence (i) the preliminary objection
67 At the commencement of trial, counsel for the defendant applied to strike out paragraphs 18 to 22 (inclusive) in the affidavit evidence in chief of Ong for the reason that they raised a fresh allegation for the first time relating to the approved plans for No 4 which the defendant said he had and would hand to them. I granted the application and as the plaintiffs have appealed against my order I shall give my reasons.
68 Ong's affidavit was filed on 9 September 1994 pursuant to an order of court dated 5 July 1994 (the second order). Counsel for the plaintiffs said it was filed pursuant to an earlier order of court made on 13 April 1993 but that is incorrect as, that earlier order referred to the plaintiffs' amended statement of claim. It was the second order that would be relevant as the re-amended statement of claim (which reflected the state of pleadings as at trial) was filed on 5 November 1993. The relevant extracts from paras 18 to 22 of Ong's affidavit are as follows:
69 18. As to the term in the Sale and Purchase Agreement that we were to prepare the full site plans and have the same ready for submission to URA within 14 days from date of the agreement, we only consented to the same on account of the defendant's repeated assurances that he was in possession of the approved plans submitted to URA for approval for No 4 Elliot Road and that he would let us have the same immediately after signing the agreement. As 14 days would never be enough for an architect to come up with a full set of plans from scratch, we would not have agreed to such a term had it not been for the defendant's representations....;
70 19. It was on the basis of the defendant's aforesaid representation and assurances that the plaintiffs agreed to the terms under clause 10....;
71 20. Immediately after the execution of the agreement I called the defendant and asked him to hand over the plans as he had promised. The defendant told me that he had handed the plans to another property agent who was helping him to market the property and that he would hand over the same to the plaintiffs the next day. The defendant never handed over these plans to us despite numerous reminders from myself through the phone...the defendant would say that he was trying to get in touch with the estate agent holding the plans...;
72 21. Towards the end of the 14 day period, I called the defendant again and reminded him over the telephone about the plans and informed him that URA might not reply with its approval before 28 March 1992, the last day for the purchase to be completed. The defendant reassured me that even if the plaintiffs submitted the plans after 13 January 1992 the URA would still give their approval in time i e before the last day for completion. At the very least the plaintiffs were given to understand that the defendant had waived compliance of condition 10(b) of the Sale and Purchase Agreement. He advised that the plaintiffs proceed to draw their plans without relying on the approved plans used for No 4 Elliot Road as long as the plaintiffs draw their plans in accordance with the new URA guidelines issued under URA's Press Release which can also be found in the Singapore Institute of Architects' Practice News dated 2 March 1992 volume 13 No 2/92. He assured me that if the plaintiffs proceed in this manner, URA will definitely approve the plaintiffs' application...;
73 22. I immediately instructed the plaintiffs' architect one Ms Chan to proceed with the drafting of the plans and instructed her that it was imperative that the plans be completed as soon as possible....Ms Chan eventually completed the plans for a three storey semi-detached house and submitted the same to the URA on 20 February 1992.
74 In the statement of claim, Ong's new allegation was not pleaded. What was pleaded in para 23 of the re-amended statement of claim were the representations (3) which I set out earlier. It is also noteworthy that in the second letter dated 23 April 1992 (AB101) from the plaintiffs' to the defendant's solicitors the only representation the plaintiffs alleged the defendant made was prior to the signing of the agreement -- that there was existing approval for a pair of three storey semi-detached houses. Yet when pressed for particulars of that allegation by the defendant's solicitors on 24 April 1992 (see AB106), the plaintiffs did not pursue the matter.
75 I noted from para 10 of Ong's affidavit that he set out the representations (4) which the defendant purportedly made at the December 1991 meeting when the parties negotiated. By the expunged paragraphs in Ong's affidavit the plaintiffs sought to widen the scope of the defendant's alleged representations very late in the day to include an assurance that he would hand to the plaintiffs approved plans which he had, relating to No 4.
76 Counsel for the plaintiffs argued that the paragraphs in question should be allowed to stand as the defendant's counsel should have but failed to, raise his objections to the same within one (1) month of the exchange of affidavit evidence as directed by para 2 of the second order. True that counsel for the defendant was amiss in this respect but the fact remained that pleadings define the issues between parties to an action. I took into account the fact that in the plaintiffs' previous unsuccessful O 14 application (for which Ong did not file any affidavits) this allegation was not raised at all in any of the four affidavits filed by the plaintiffs' director Lim Chye Him (Lim). Indeed in Lim's second affidavit filed on 14 July 1993 his allegation of the defendant's misrepresentation was confined to
77 a. the potential redevelopment of the property;
78 b. that written permission had been granted to the owners of No 4 to construct one pair of three storey semi-detached houses, and
79 c. if plans similar to No 4's were submitted by the plaintiffs written permission was likely to be given for the property.
80 The new allegation was also not pleaded by the plaintiffs despite their extensive amendments of the statement of claim, nor in their reply. Being raised at the eleventh hour, the allegation was suspect. I did not allow paras 18 to 22 of Ong's affidavit to stand as it could have prejudiced the defendant's pleaded case and he had no opportunity to answer this fresh allegation, his affidavit evidence having been filed on the same day as Ong's.
81 (ii) the plaintiffs' testimony
82 I turn now to the evidence adduced from the two witnesses who testified for the plaintiffs. Turning first to Ong who described himself as a developer, his testimony inter alia was as follows:
83 1. the defendant had omitted all mention in his affidavit evidence, of their meeting before the draft agreement was forwarded to the plaintiffs' solicitors on 21 December 1991 and what transpired at that meeting;
84 2. the reason he asked for 14 instead of 7 days to apply for planning approval under cl 10(b)(i) of the agreement was because of time constraints -- the execution date of 28 December 1991 was a Saturday and 7 days would have expired the following Saturday (4 January 1992) with an intervening public holiday on 1 January 1992. That only gave the architects 4 days in which to prepare and submit plans whereas 14 days gave the architects 9 working days in which to do so. Even then without the plans for No 4, it was impossible for the architects to submit fresh plans from scratch within 14 days -- they required 4-6 weeks;
85 3. he disagreed with the defendant's contention that if submission had been made within 7 days similar to the plans submitted for No 4, the authorities would have been unable to refuse;
86 4. he was under the impression at the initial meeting with the defendant that the price agreed was $960,000 but when that figure was cancelled in the draft agreement and replaced by the figure $965,000 he gave the benefit of the doubt to the defendant and accepted $965,000 as the price;
87 5. because of his objections, James Yip & Partners (James Yip) who were the architects who submitted the plans for No 4, were deleted from cl 10(b)(i) as the firm who would submit plans for the plaintiffs, instead the plaintiffs used Architects PS 100;
88 6. between the date of the agreement and the submission by the architects (on 20 February 1992) the plaintiffs did not write to the defendant for the plans for No 4 as it was something 'so obvious' that it did not need to be put on record -- instead he asked Miss Chan to proceed from scratch;
89 7. although the submission by the architects was not made within 14 days (ie by 11 January 1992) of the date of the agreement the defendant waived that condition by giving his consent vide his solicitors' letter dated 15 February 1992; the defendant caused the delay by not furnishing the plans for No 4; the plaintiffs declined to use James Yip for the submission due to cost considerations and also because they were not familiar with those architects;
90 8. he requested a meeting with the defendant to ask for an extension of time to appeal to the authorities when the defendant served the plaintiffs with a 21 days' notice but the defendant refused. He then offered through the plaintiffs' solicitors to settle the matter amicably by calling off the transaction and they requested for a refund of the deposit;
91 9. he agreed that cl 10 was an automatic provision which rendered the agreement null and void in the event no in-principle approval was granted for construction of a pair of three storey semi-detached houses. Notwithstanding cl 10 however, at no time did he consider the agreement null and void;
92 10. the plaintiffs did not appeal to the authorities because of the defendant's 21 days' notice; neither did they respond to the fax of 23 March 1992 stating the defendants will charge the usual interest for late completion as it called for no reply -- the plaintiffs took it to mean time had thereby been extended to 11 April 1992. The plaintiffs asked for a further extension of time on 27 March 1992 for purposes of appealing to the authorities but this was not acceded to;
93 11. the defendant did not furnish proof as requested by the plaintiffs' solicitors, that he had complied with the Notice, even by 27 March 1992; the plaintiffs were unaware of the correspondence between the defendant's solicitors and the MOE culminating in the MOE letter dated 6 May 1992 (DB21) confirming that the Notice had been complied with. Hence the 21 days' notice to complete given by the plaintiffs' solicitors to the defendant on 23 April 1992 (AB100).
94 12. although the plaintiffs intended to complete the transaction, they no longer sought specific performance but only damages as three storey houses have since been built on the property and occupied;
95 13. he was of the view that Keppel's exercise of their power of sale as mortgagee was not genuine as there was no advertisement in the press before the sale;
96 I move next to the evidence of Lim who confirmed that Ong was authorised to negotiate on the plaintiffs' behalf for the purchase of the property notwithstanding that Ong was neither a shareholder nor director of the plaintiffs; he signed the agreement after Ong had approved the draft. Under cross-examination it emerged that Lim's knowledge of events was based on what Ong told him and he had no personal dealings with the defendant at all. His evidence therefore is of little assistance.
97 (iii) the defendant's testimony
98 I turn now to the defendant's evidence, his version of the disputed events is as follows:
99 1. he informed the plaintiffs that his neighbour at No 4 had told him that James Yip had obtained provisional permission from the authorities for the construction of one pair of three storey semi-detached houses;
100 2. when the plaintiffs' solicitors proposed to include a clause in the draft agreement that the purchase is subject to approval of all relevant authorities for the erection of a pair of semi-detached bungalows of three storeys each he objected. This was because he risked the sale being aborted if no approval was obtained and he would not be compensated in not being able to deal with the property for three months as well as for any loss if there was a downturn in the property market. Hence he counter-proposed that the price be increased from $960,000 to $965,000 and if the sale was subject to planning approval, the plaintiffs would be entitled to a refund of the deposit only if they complied with the conditions eventually incorporated in cl 10(b)(i) to (iv) of the agreement. He wanted submission to the authorities to be done within 7 days but the plaintiffs changed it to 14 days;
101 3. although the plaintiffs had not complied with cl 10(b) when they requested his consent on 12 February 1992 (which was after 14 days) to make the submission, he was advised by his solicitors to consent nonetheless as cl 10(b) would have no effect if in-principle approval was obtained even if late; he would have been in breach of the agreement otherwise. Giving his consent however did not mean that he had waived any of his rights under the agreement;
102 4. by 12 March 1992 when the plaintiffs' solicitors wrote to his solicitors for evidence of the same, he had already complied with the Notice issued in September 1991 by the MOE, within the one month deadline stipulated therein;
103 5. when the plaintiffs' solicitors requested for an extension of time on 21 March 1992, he was agreeable provided the plaintiffs paid interest for two weeks for late completion but the plaintiffs did not accept his condition. Hence the completion date was never varied but remained as 28 March 1992. In any case his proposal was superceded by the URA letter of 27 March 1992 stating in-principle approval for three storey semi-detached houses was not granted; the plaintiffs requested for an extension of time pending their appeal against URA's decision which he refused;
104 6. on 28 March 1992 his solicitors gave 21 days' notice to complete, namely by 18 April 1992. On two subsequent occasions his solicitors requested for proof that the plaintiffs had complied with cl 10(b) of the agreement which was met with a demand for the return of the deposit and the response that the defendant had not shown compliance with the Notice from MOE; it was clear that the plaintiffs considered the agreement as cancelled and without evidence they had complied with cl 10(b) thereof, he was not obliged to refund the deposit;
105 7. his solicitors requested the return of the title deeds from the plaintiffs after the extended completion date had expired but they only returned the same in June 1992 (DB23);
106 8. his agreement with Fortune Realty to sell the property had to be aborted due to the plaintiffs' refusal to remove their caveat despite his solicitors' repeated requests;
107 9. he received a demand from Keppel's solicitors on 15 September 1992 (AB134) to pay the outstanding sum of $578,836.78 on the mortgage which instalments he had not serviced since December 1990. He also received several letters of demand from Keppel's previous solicitors (DB3-6) in July and September 1991;
108 10. the plaintiffs' former solicitors wrote to Keppel on 25 November 1992 (AB147) after the mortgagee sale to Hern Yang to say they claimed an interest in the sale proceeds, they did not raise any objections to the sale itself;
109 11. in regard to the surplus funds after payment of Keppel's claim, he reached an agreement with the plaintiffs that his then solicitors would hold the sum of $96,500 as stakeholders pending the outcome of this action, the balance of the sale proceeds were released to him;
110 12. he denied that the mortgagee sale was not genuine as he was neither a party to the sale nor did he know Hern Yang, the mortgagee sale resulted from his inability to service Keppel's loan.
111 Under cross-examination, the defendant
112 1. indicated he was still prepared to refund the deposit to the plaintiffs provided they complied with the two conditions in cl 10(b) of the agreement;
113 2. said although he had no evidence that the URA rejected the plaintiffs' application due to their late submission, he was not told when URA's change in policy came into effect; had the plaintiffs' application been submitted earlier through James Yip, the result could have been different, but he agreed his surmise was mere speculation. Fortune applied for approval of 2 storey semi-detached houses but he did not endorse their plans, he merely gave his consent. In any event a pair of three storey semi-detached houses now stand on the property;
114 3. explained that at the meeting with Ong he said he wanted $965,000 as the sale price because he had paid $40,000 odd as a development charge to increase the plot ratio and in that context he told Ong that No 4 had obtained planning approval for a three storey development; in December 1991 the land was approved for a pair of terrace houses only (which would fetch a lower price), pursuant to a joint submission by him and the owner of No 4 (see DB18-19);
115 4. clarified that it was only when the plaintiffs insisted on the agreement being subject to planning approval that he inserted in cl 10(b)(ii) the condition that the plaintiffs must furnish documentary evidence of such submission which must be similar in all material aspects to that of James Yip before they are entitled to a refund of the deposit;
116 5. pointed out the only time the plaintiffs asked for the plans of No 4 was by their solicitors' letter dated 27 December 1991 (AB41) to which he did not agree and that was why there was no reference to the plans in the draft agreement prepared by his solicitors. As the plaintiffs deleted the reference to James Yip in cl 10(b)(i), he did not have to furnish copies of James Yip's plans to them which plans he himself saw only recently;
117 6. said he signed the agreement before the plaintiffs did, hence he was not aware they had deleted the reference to James Yip and changed the deadline for submission from 7 to 14 days in cl 10(b)(i) until later, that was why his initials did not appear against those amendments; however, he did not object to those changes;
118 7. agreed that the sale price to Hern Yang was $365,000 above the plaintiffs' price but pointed out he had to pay compensation to Fortune for the abortive sale which was concluded on the same day the agreement with them was signed (23 April 1992) at a price of $1m. Fortune were the intended buyers of the property before the plaintiffs and followed events very closely -- when they found out that the plaintiffs did not complete the sale, they renewed their offer after 21 April 1992 which he accepted, as he did not consider the plaintiffs' 21 days' notice to complete valid;
119 8. explained that MOE does not send written confirmation of compliance with notices issued; what the plaintiffs should have done as suggested by his counsel was to conduct a physical inspection of the property. Although the MOE on 23 March 1992 (DB20) advised that the Notice served on him was still valid that did not mean that he had not complied with it;
120 9. denied that as he found another buyer (Fortune) so quickly the only reason he had a mortgagee sale of the property was to overreach the plaintiffs' caveat - - Keppel had been kind enough to allow him to sell the property twice and when he failed, they took over the sale based on a valuation of $1.1m;
121 10. agreed that he made no reference to the abortive sale to Fortune at all in his affidavit, he thought it was irrelevant.
122 The decision
123 The only issue before the court is whether the defendant was entitled to forfeit the deposit which question in turn requires a determination of who was the party in breach of the agreement. To make that determination it is necessary to highlight the relevant events, which I now proceed to do so.
124 In the correspondence between the parties before the signing of the agreement, it was clear that the defendant did not accede to the plaintiffs' request for copies of plans for erecting three stories semi-detached bungalows in the vicinity (presumably referring to No 4) before the deposit was to be released to him, although the defendant accepted the other condition for release, namely verification of his ownership. Otherwise there would have been reference to the plans in the agreement. Therefore the issue of plans pertaining to No 4 was no longer relevant especially after the plaintiffs deleted the reference to James Yip in cl 10(b)(i) of the agreement.
125 Clause 10(b) of the agreement made the sale subject to in-principle approval being granted....by the completion date which meant the defendant was obliged to give his consent even if the plaintiffs' plans were submitted late. I agree with his counsel that it is not tantamount to a waiver by the defendant of cl 10. In any case the condition having been inserted for the plaintiffs' benefit, only the plaintiffs can waive it (Chye Seng Huat Construction Pte Ltd v Goh Chin Soon (1991) 1 MLJ 13; Heron Garage Properties Ltd v Moss (1974) 1 AER 421 followed by the Court of Appeal in Chip Thye Enterprises Pte Ltd v Development Bank of Singapore Ltd (1994) 3 SLR 613). The plaintiffs themselves hold this view as reflected in para 3B of the re-amended statement of claim as well as in Lim's affidavits filed in support of their O 14 proceedings. In Lim's second affidavit filed on 14 July 1993 he stated in para 5 ....It is clear that the clause (10) was included for the benefit of the plaintiffs as the purchasers in the event that written permission is not granted by the relevant authority.... In his third affidavit filed on 13 August 1993 Lim reiterated in para 7 ....conditions which pertain to planning approval by the authorities are included apparently for the benefit of the purchaser who would then have the concomitant right to waive such rights if and when the necessity arises....I accept that the defendant may not have been aware that the plaintiffs' plans were not submitted as at 15 February 1992 when he confirmed he had no objections to their application.
126 On 22 March 1992 when their solicitors informed the defendant's solicitors that the required planning approval was not granted, the plaintiffs could have waived cl 10 -- instead strictly on a without prejudice basis they requested for an extension of time to complete the sale and purchase pending appeal for the construction of a pair of 3-storey semi-detached.... which the defendant refused. The plaintiffs' solicitors reserved their clients' rights up to 30 March 1992 when they responded to the defendant's 21 days' notice.
127 Counsel for the plaintiffs argued that the statement in his solicitors' letter dated 23 March 1992 (AB84) that....our client will charge the usual interest for late completion meant that the defendant had waived the completion deadline and this was confirmed in the subsequent 21 days' notice which extended the completion date first to 18 and then to 21 April 1992. With respect I cannot accept that contention which I believe is due to a misunderstanding of how certain provisions in the agreement operated.
128 To elaborate, there was no clause in the agreement which made time the essence of the contract apart from the stipulation in cl 3 that completion would take place within 13 weeks from the date of this agreement. However cl 4 made the sale subject to the "Singapore Law Society's Condition of Sale 1981" so far as the same are....not....inconsistent with the Special Conditions herein. Pursuant to cl 8 of the Law Society's Conditions of Sale (the Conditions) the defendant was entitled to charge the usual interest (namely 10% per annum) for late completion -- giving notice to the plaintiffs of his entitlement cannot be considered a waiver of the completion deadline. Even if the statement is construed a waiver, the plaintiffs by their solicitors' fax dated 7 April 1992 said ....our clients shall not be liable for any interest.... a strange stance to take if I may say so, when the plaintiffs clearly did not/could not complete on 28 March 1992 -- the plaintiffs therefore never acted on the alleged waiver. The fact that on 27 March 1992 the plaintiffs' solicitors renewed their request for an extension of time for completion meant that they knew their previous request was refused.
129 The 21 days' notice to complete was given by the defendant's solicitors on 28 March 1992 presumably pursuant to cl 29 of the Conditions which state:
130 (1) This condition shall apply in every case except where the Special Conditions provide that time is to be of the essence of the contract in respect of the date fixed for completion.
131 (2) If the sale shall not be completed on the date fixed for completion either party may on that date or at any time thereafter (unless the contract shall first have been rescinded or become void) give to the other party notice in writing to complete the transaction in accordance with this condition but such notice shall only be effective if the party giving the same at the time the notice is sent is either ready, able and willing to complete or is not so ready, able and willing by reason of the default or omission of the other party to the contract.
132 (3) Upon service of an effective notice pursuant to the preceding clause it shall be an express term of the contract that the party to whom the notice is given shall complete the transaction within twenty-one days after the day of service of the notice (excluding the day of service) and in respect of such period time shall be of the essence of the contract but without prejudice to any intermediate right of rescission by either party.
133 Provided the defendant himself was not in breach, he was perfectly within his rights to give the 21 days' notice and thereby make time of the essence of the contract whereas previously time was at large; 21 days after 28 March meant the plaintiffs must complete by 18 April 1992 or risk forfeiture of the deposit. Unfortunately the defendant's notice (as his counsel conceded) was premature and therefore invalid. In Raineri v Miles (1980) 2 AER 145 the House of Lords held that to be effective a 21 day's notice can only be given after the date fixed for completion has passed, which decision was followed by our Court of Appeal in Wardley Ltd v Datin Chong Mooi Lan (1993) 2 SLR 261; the defendant's notice should have been given after, not on 28 March 1992.
134 What then is the effect of an invalid 21 days' notice? Counsel for the defendant argued that although the notice was bad, it could not/did not extend the completion date since as a matter of law (Raineri v Miles) where there is a contract in which time is not of the essence, the innocent party is required to give reasonable notice to the defaulting party before the former's right to damages accrue. In other words the invalid notice nonetheless made time of the essence of the contract and it gives the plaintiffs notice that they must complete within a reasonable period after 28 March 1992 -- I accept that submission.
135 Arguments on the validity of the defendant's 21 day's notice and whether a reasonable time for completion would have been 18 or 21 April 1992 or later are in any event academic, because of the fax from the plaintiffs' solicitors dated 7 April 1992 stating ....Please note that completion cannot take place due to the non-approval for the erection of a pair of 3 storey semi-detached....In the circumstances we are compelled to request for the full refund of monies paid to your client...hence our clients reject the twenty one days' notice served by your office. That demand can only mean that the plaintiffs considered the agreement null and void pursuant to cl 10; the plaintiffs' solicitors repeated the demand on 11 April 1992. The defendant implicitly accepted the cancellation by his request for proof of compliance by the plaintiffs with cl 10(b) although in court he said he thought the contract subsisted up to 18 April 1992.
136 To add to the confusion, the plaintiffs' solicitors on 23 April 1992 indicated that their clients wished to complete despite the defendant's .... non-compliance with cl 10.... and giving 21 days' notice to the defendant to do so. Even if the plaintiffs can be said to have waived the planning approval requirement on that day, the waiver came too late as, to be effective, it must be exercised before not after the completion date (Chye Seng Huat v Goh Chin Soon (supra) , Sandra Investments Proprietary Ltd v Booth (1983) 153 CLR 153) and certainly not after they had cancelled the contract. As was so graphically put by counsel for the defendant, quoting Lord Wilberforce (p 864) in Johnson v Agnew (1979) 1 AER 883 '....this is simply because the contract is gone, what is dead is dead....' and cannot be resurrected unilaterally. As the agreement was null and void by then, the plaintiffs' 21 days' notice was ineffectual.
137 Counsel for the defendant criticised what he said was the indiscriminate use by the plaintiffs' solicitors of the phraseology 'without prejudice/we reserve our client's rights' throughout their correspondence. Whatever their motive, he contended (citing Antaios Cia v Salen Rederierna (1983) 3 AER 777) the plaintiffs cannot prevaricate as they have done -- they must make up their mind whether they wish to continue with the agreement in which case they must abide by the terms or, consider it aborted and produce evidence to satisfy cl 10(b), before they are entitled to a refund of the deposit.
138 I turn now to the plaintiffs' arguments. Counsel submitted that the defendant himself was not ready, willing and able to complete on 28 March 1992 because he had not furnished evidence of his compliance with the Notice from MOE. This contention warrants a consideration of cl 8 of the agreement touching on requisitions which relevant extract reads:
139 (b) no reply to the requisitions shall be deemed unsatisfactory if such reply relates to any charges or notices affecting the property which are capable of being rectified, discharged or complied with by and at the vendor's expense and are so rectified, discharged or complied with by the vendor on or before the completion date;
140 The defendant had contended that he had complied with the Notice and this was subsequently confirmed by the MOE letter dated 6 May 1992; counsel for the plaintiffs argued the letter was not good enough as there was no confirmation that the defendant had complied by 28 March 1992. The counter argument of counsel for the defendant was that compliance suffices not proof; he pointed out that the letter from the plaintiffs' solicitors dated 11 February 1992 asked for confirmation, not evidence of compliance, and confirmation was duly given by the defendant's solicitors on 5 March and reiterated on 18 March, 1992.
141 It seems to me that the alleged non compliance with the Notice cannot in any event be construed to be an unsatisfactory reply to a requisition as it was capable of being and was, rectified according to the defendant; no evidence to the contrary was produced by the plaintiffs. Indeed the written confirmation (albeit late) of the MOE supports the defendant's contention that the only evidence of rectification is by an inspection of the property which was what the MOE did. Even if I am wrong on this point, I note that after the defendant's solicitors' confirmation of compliance on 5 and 18 March 1992, the issue was not raised again by the plaintiffs' solicitors before their fax of 7 April 1992 cancelling the agreement.
142 I shall now dispose of the other subsidiary issues raised by the plaintiffs the first of which alleged that forfeiture of the deposit would amount to a penalty. The short answer to that contention is that 10% of the price of a property is the standard deposit paid by purchasers in Singapore upon signing of the contract; forfeiting it cannot be said to be a penalty or unconscionable (see Indian Overseas Bank v Cheng Lai Geok (1993) 1 SLR 470 and Workers Trust v Dojap Investments Ltd ( 1993) 2 AER 370). I accept that our courts can grant relief against forfeiture (see Pacific Rim Investments Pte Ltd v Lam Seng Tiong & Anor (1995) 3 SLR 1). However ....needless to say, such jurisdiction would only be exercised in exceptional circumstances since the courts would not ordinarily countenance a departure from contractual rights and obligations. Hence in order to invoke successfully the courts' jurisdiction, the circumstances of the case must reveal elements of unconscionability and injustice (per LP Thean JA at p 23). The circumstances of this case do not warrant granting to the plaintiffs relief against forfeiture bearing in mind that they rejected the defendant's demand for interest in the event of their late completion.
143 Counsel for the plaintiffs also referred to Tian Teck Construction Pt Ltd v Exklusiv Auto Pte Ltd (1992) 2 SLR 390 to support his argument that
144 a. where time is not of the essence of the contract the plaintiffs should not be held strictly to the 14 days' deadline for submission of planning approval, and
145 b. its breach should not entitle the defendant to forfeit the deposit when he has not suffered any loss.
146 I agree that if the plaintiffs had obtained the requisite in-principle planning approval, there is no question that the defendant would not have been allowed to forfeit the deposit on the mere technicality that the plaintiffs' submission was made after the 14 days' deadline, this however was not the case. In this regard I refer to and adopt the following passage from the judgment of Yong Pung How CJ in Tian Teck Construction Pte Ltd v Exklusiv Auto Pte Ltd (at p 397)
147 ....we wish to emphasize that a stipulation of a time for the doing of an act is different from the substantive obligation to do the act, for example the obligation to convey property and to pay money for it. Whereas the promises to convey and to pay are correlative and concurrent, and breach of them involves a measurable loss, a time stipulation is a machinery aspect of a substantive obligation and breach of it merely involves a delay in performance which may involve no loss at all.
148 Having cancelled the reference to James Yip in cl 10(b)(i), the plaintiffs should have but did not, delete the requirement from cl 10(b)(ii) that their submission must be ...similar in all material respects to that submitted by Messrs James Yip & Partners on behalf of the proprietors of No 4.... According to Ong, the plaintiffs did not comply with cl 10(b)(ii) as they made a conscious decision to engage Architects PS 100 instead of James Yip to make their submission, for cost and other considerations. The burden was also on them which they failed or refused, to discharge, to show that ....any delay in granting of the in-principle approval by the authorities....was not due to their default, pursuant to cl 10(b)(iv). At the risk of repetition, the necessary planning approval related to development of a pair of three storey semi-detached houses for which the URA did not grant permission. The conditions for refund of the deposit, being inserted for the defendant's benefit, the same had to be but were not, waived by him.
149 With regard to the alternative plea that the plaintiffs had substantively complied with cl 10(b) of the agreement (approval was granted for two storey semi- detached development) I believe this was an afterthought as it was never raised in the correspondence of the plaintiffs' solicitors or in any of their 0 14 affidavits. I also reject the plea that there was a total failure of consideration which entitles the plaintiffs to a refund of the deposit. The plaintiffs' entitlement to a refund was subject to their complying with cl 10(b)(i) to (iv) which they did not. As for the contention that it was expressly or impliedly agreed that the agreement would be discharged and the deposit refunded upon URA's ceasing to give approval for development of semi-detached houses of three storeys high in the vicinity, that plea is not sustainable as there is uncontroverted evidence that a pair of three storey semi- detached houses now stand on the property. Such evidence also rebuts the allegation of misrepresentation, if there was misrepresentation by the defendant; he spoke the truth if he did indeed assure the plaintiffs that planning approval would be granted for three storey developments.
150 As for the allegation that the defendant orchestrated the mortgagee sale to circumvent and overreach the plaintiffs' caveat, there was no evidence to support this contention; not all mortgagee sales are done through public auction, some are sold by private treaty and nothing sinister can be construed from the fact that the sale to Hern Yang was by private treaty. The defendant has put forward documents which point to the same having been a genuine forced sale due to his failure to service Keppel's loan since December 1990 (see Keppel's statement at AB61); there is no evidence to suggest he knew or was in any way connected with Hern Yang.
151 I do not propose to go into the remaining alternative claims of the plaintiffs as they are devoid of merit. I am of the view that the plaintiffs were in breach of the agreement in failing to comply with cl 10(b), they are therefore not entitled to a refund of the deposit. Accordingly their claim is dismissed with costs. The deposit currently held by solicitors as stakeholders is to be returned to the defendant.
152 Lai Siu Chiu
Judge
153 30 October 1995