Hua Khian Co (Pte) Ltd v Lee Eng Kiat
[1996] SGCA 42
CA 109/1995, 185/1995
Goh Joon Seng J; Karthigesu JA; L P Thean JA
30 July 1996
1 Cur Adv Vult
2 There are two appeals before us. The main appeal, Civil Appeal No 185 of 1995, is an appeal against the decision of the trial judge dismissing the appellants` suit in which they claimed damages for breach of an agreement for the sale and purchase of the property that was not completed or the refund of the deposit paid under that agreement. The other appeal, Civil Appeal No 109 of 1995, concerns the decision of the trial judge made during the trial, in which she expunged several paragraphs of the affidavit of the primary witness for the appellants. The issues in both the appeals were argued and heard together.
3 Brief facts
4 By a sale and purchase agreement dated 28 December 1991 (the agreement) the appellants agreed to purchase the property known as No 6 Elliot Road (the property) at the price of $965,000 and on the terms and conditions therein stated. Among other things, the agreement was expressed to be subject to the Law Society`s Conditions of Sale 1981 in so far as those conditions are applicable to a sale by private treaty and are not varied by or are inconsistent with the terms of the agreement. A deposit of $96,500 representing 10% of the purchase price was paid to the respondent. By cl 3 of the agreement the completion of the sale and purchase was to take place within 13 weeks from the date of the agreement, that is, on 28 March 1992. Clause 10 of the agreement provided that the sale was subject to approval in principle by the relevant authority for the construction of one pair of three-storey semi-detached houses by the completion date, failing which the agreement would be deemed `null and void`. In such an event, the respondent was obliged to return to the appellants the deposit, subject however to certain conditions, to which we shall advert in detail shortly.
5 On 12 February 1992, the appellants` solicitors wrote to the respondent`s solicitors requesting the respondent to write to the relevant authority, namely, the Urban Redevelopment Authority (URA), stating that he had no objection to the appellants` submission of plans for the development as contemplated in the agreement. The respondent`s solicitors duly complied with the request on 15 February 1992 and wrote to the URA accordingly.
6 On 20 February 1992, the appellants through their architects, Architects PS 100, submitted an application together with the necessary plans and other documents to the URA for written permission for the construction of a pair of three-storey semi-detached houses. They also sought a prompt reply from the URA. The application was acknowledged by the URA on 24 February 1992.
7 On 21 March 1992, the appellants, not having heard further from the URA, through their solicitors wrote to the respondent`s solicitors requesting for an extension of two weeks within which to complete the purchase of the property on the ground that they were awaiting the planning permission. The respondent`s solicitors on 23 March 1992 replied saying, among other things, that their client would charge `the usual interest for late completion`.
8 On 25 March 1992, the URA responded to the appellants` application and granted provisional permission for a pair of two-storey semi-detached houses, and not, as applied for, a pair of three-storey semi-detached houses. In effect, the URA did not grant approval in principle for the construction of a pair of three-storey semi-detached houses. The URA followed its response with another letter on 26 March written to the appellants` architects explaining the reasons for restricting the permission to a two-storey building instead of a three-storey building. A copy each of this letter was sent to the appellants and the respondent respectively. The appellants` architect was instructed by the appellants to appeal. In the meantime, the appellants through their solicitors by a letter dated 27 March 1992 asked the respondent`s solicitors for an extension of time to complete the sale and purchase pending the appeal. The respondent did not agree to this request; on 28 March 1992, which was the contractual date of completion, his solicitors wrote to the appellants` solicitors purporting to give the 21 days` notice for completion, which expired on 18 April 1992. The appellants` solicitors replied on 30 March 1992, reserving their rights in the matter but also requesting a meeting with the respondent. However, the respondent declined to meet the appellants.
9 On 7 April 1992, the appellants` solicitors wrote to the respondent`s solicitors stating, among other things, that completion could not take place `due to non-approval for the erection of a pair of three-storey semi-detached` and rejected the respondent`s 21 days` notice. By that letter the appellants also sought the refund of the deposit. In response, the respondent`s solicitors informed the appellants by a letter on 8 April that he was not obliged to refund the deposit, unless the appellants produced evidence that they had complied with cl 10(b)(i) to (iv) of the agreement.
10 The appellants` solicitors on 11 April 1992 demanded once again the return of the deposit, and gave notice that if the demand was not met, legal action would be commenced. The respondent`s solicitors replied stating that the appellants had not shown any compliance with cl 10(b). On 21 April 1992, the respondent gave notice that the date of completion had passed, and requested for the return of the title deeds pursuant to cl 29(4)(a) of the Law Society`s Conditions of Sale, as well as removal of the appellants` caveat on the property. He also repeated the request to the appellants to show that they had complied with cl 10(b) of the agreement, in default of which he was not obliged to refund the deposit. The appellants` solicitors replied stating that `compliance had been made` by the appellants.
11 Notwithstanding what had transpired, the appellants still took the position that the agreement had not been terminated. Their solicitors on 23 April 1992 wrote to the respondent`s solicitors stating that they wished to proceed with the completion, that the respondent`s notice to complete was not effective, and that the matter could not be treated as abortive, and further requested the respondent to complete the sale and purchase within 21 days.
12 That very day, however, the respondent entered into an agreement with a third party for the sale of the same property at a higher price. Subsequently, the appellants still maintained that the contract should go forward and called for the completion on 14 May 1992. The parties reached an impasse: the appellants declined to remove their caveat, while the respondent refused to return the deposit. On 13 June 1992, the appellants commenced an action against the respondent claiming damages for breach of contract or the refund of the deposit.
13 On 21 October 1992, the mortgagees of the property, Keppel Finance Ltd, in exercise of their powers sold the property to Hern Yang Construction Pte Ltd, for $1.33m. As the sale was made by a prior encumbrancer, it overreached any interest which the appellants claimed in the property. The surplus from the sale proceeds was given to the respondent, less $96,500, an amount equivalent to the appellants` deposit, which was held by a firm of solicitors as stakeholders, pending the outcome of the action.
14 The decision below
15 At the commencement of the trial, the respondent`s counsel applied to the trial judge to expunge several paragraphs of the affidavit of the primary witness for the appellants, namely, Ong Ang Kheng Hoe, on the basis that they raised fresh allegations, which were not pleaded in the re-amended statement of claim. The trial judge acceded to the application and expunged those paragraphs, and the trial proceeded. At the conclusion the trial judge dismissed the claim with costs.
16 Dealing with the substantive claim, the trial judge considered that the only issue before her was whether the respondent was entitled to forfeit the deposit and the answer turned on the question: who was the party who was in breach of the agreement. To determine this issue the trial judge considered several other subsidiary issues. For our purpose, we need to concern only with her reasoning as follows.
17 The trial judge referred to the appellants` request dated 21 March 1992 made by their solicitors for an extension of time to complete and the reply of the respondent`s solicitors on 23 March 1992. She held that the respondent`s letter was not a waiver of the contractual date of completion but only notice of his entitlement to payment of interest on late completion. She regarded that the fact that on 27 March 1992, the appellants renewed their request for an extension of time meant that the appellants knew that their earlier request for an extension had been refused.
18 The trial judge held that in any event by their solicitors` letter of 7 April 1992 the appellants considered the agreement null and void pursuant to cl 10, and that was accepted by the respondent as shown by his request for proof of compliance by the appellants of cl 10(b).
19 The trial judge found that the deposit was not a penalty, and that the circumstances of the case did not warrant granting to the appellants relief against forfeiture. As regards cl 10(b)(i) and (ii), it appears that while the trial judge was of the view that time was not of the essence with respect to the 14-day period stated in cl 10(b)(i) - and therefore presumably the appellants had complied with sub-para (i) - she was of the view that the appellants had not complied with sub-para (ii). She also held that the appellants had also failed to discharge the burden that any delay in the granting of approval by the authority was not due to their fault. She rejected the further argument that the appellants had substantively complied with cl 10(b), and that there was total failure of consideration for the deposit. She accordingly held that the appellants were in breach of the agreement in failing to comply with cl 10(b) and were therefore not entitled to the refund of the deposit.
20 The appeal
21 Before us, four issues were raised, namely:
(i) whether the learned judge erred in expunging paras 18 to 22 of Ong Ang Kheng Hoe`s affidavit of evidence-in-chief and the exhibits relating to those paragraphs;
(ii) whether the appellants are entitled to damages for breach of contract;
(iii) if not, whether the appellants are entitled to the refund of their deposit of $96,500 with interest; and
(iv) whether the appellants are entitled to be relieved against forfeiture.
22 We turn to the first issue. As we have earlier related, at the commencement of the trial, counsel for the respondent applied to expunge paras 18 to 22 of the affidavit of Ong Ang Kheng Hoe affirmed and filed on 9 September 1994. Briefly, these paragraphs alleged as follows. The appellants agreed to submit plans to the URA within 14 days as provided in cl 10 because the respondent assured him that he (the respondent) would make available the approved plans of No 4 Elliot Road, which the respondent had in his possession. But for such assurance the appellants would not have agreed to the period of 14 days as stated in cl 10(b)(i), as such period was insufficient to their architects to prepare the necessary plans for submission to the URA. After the agreement was executed Ong requested for the plans of No 4 Elliot Road and the respondent promised to let him have the plans but did not do so. Ong subsequently reminded the respondent, who then told him that even if the plans were submitted after the 14 days, the URA would still give the approval. He then suggested to Ong that the appellants should proceed with the preparation of the plans without relying on those of No 4 Elliot Road, and so long as the plans fell within the guidelines of the URA, which were published in URA`s Press Release, which could be found in the Singapore Institute of Architect`s Practice News of 2 March 1992 Vol 13 No 2/92, URA would grant the approval. Ong thereupon immediately asked Ms Chan of Architects PS 100 to prepare the plans and make the submission, and accordingly the submission was made on 20 February 1992.
23 The respondent`s application to expunge these paragraphs was made on the grounds that the allegations contained therein were not pleaded, that they were fresh allegations raised for the first time at the eleventh hour and they were therefore suspect. The trial judge acceded to the application and expunged the paragraphs. In her judgment, she said:
In the statement of claim, Ong`s new allegation was not pleaded. What was pleaded in para 23 of the re-amended statement of claim were the representations (3) which I set out earlier. ...
I noted from para 10 of Ong`s affidavit that he set out the representations (4) which the defendant purportedly made at the December 1991 meeting when the parties negotiated. By the expunged paragraphs in Ong`s affidavit the plaintiffs sought to widen the scope of the defendant`s alleged representations very late in the day to include an assurance that he would hand to the plaintiffs approved plans which he had, relating to No 4.
Counsel for the plaintiffs argued that the paragraphs in question should be allowed to stand as the defendant`s counsel should have but failed to, raise his objections to the same within one (1) month of the exchange of affidavit evidence as directed by para 2 of the second order. True that counsel for the defendant was amiss [sic] in this respect but the fact remained that pleadings define the issues between parties to an action. I took into account the fact that in the plaintiffs` previous unsuccessful O 14 application (for which Ong did not file any affidavits) this allegation was not raised at all in any of the four affidavits filed by the plaintiffs` director Lim Chye Him (Lim). Indeed in Lim`s second affidavit filed on 14 July 1993 his allegation of the defendant`s misrepresentation was confined to
(a) the potential redevelopment of the property;
(b) that written permission had been granted to the owners of No 4 to construct one pair of three-storey semi-detached houses, and
(c) if plans similar to No 4`s were submitted by the plaintiffs written permission was likely to be given for the property.
The new allegation was also not pleaded by the plaintiffs despite their extensive amendments of the statement of claim, nor in their reply. Being raised at the eleventh hour, the allegation was suspect. I did not allow paras 18 to 22 of Ong`s affidavit to stand as it could have prejudiced the defendant`s pleaded case and he had no opportunity to answer this fresh allegation, his affidavit evidence having been filed on the same day as Ong`s.
24 With respect, we do not share the views of the trial judge. These allegations were not made at the eleventh hour. The affidavit containing these paragraphs was filed on 9 September 1994, and no objection to these paragraphs was taken by the respondent at any time prior to the trial. The affidavit was filed pursuant to the order of court dated 5 July 1994 under which any objection to the contents of the affidavit had to be taken within one month after it was filed. The respondent had ample time to apply to strike them out or expunge them. Alternatively, if the expunged paragraphs dealt with new matters he could have applied long before the trial for leave to file further affidavit evidence in rebuttal of paras 18 to 22. He did neither, and no explanation was forthcoming. Whether or not the allegations were suspect would have to be evaluated at the trial and tested on cross-examination of Ong and on the basis of other evidence adduced. Even if they were suspect, they should not be expunged; that is a matter of credibility and not admissibility.
25 We do not agree with the respondent`s counsel that the allegations in these paragraphs should be pleaded. The appellants were not relying on these allegations for the purpose of founding a cause of action. Nor was it their purpose to lay the foundation of the pleaded case of misrepresentation. The pleaded case relied on other alleged representations and not on those in paras 18 to 22. By these paragraphs the appellants sought to explain why the application to the URA was not made within the period of 14 days as provided in cl 10 of the agreement and also to show that the conduct of the respondent in relation to the plans of No 4 Elliot Road was such that he could not insist on strict compliance with cl 10(b) of the agreement.
26 Nor do we agree that the respondent would suffer any prejudice by the presence of these paragraphs. The respondent could have applied at the trial to adduce evidence to rebut the allegations in these paragraphs. In essence, these paragraphs are repetitions of paras 10(c) to 12 of Ong`s affidavit. In our judgment, the trial judge ought not to have expunged these paragraphs in the affidavit.
27 Damages for breach of contract
28 We now turn to the next issue: whether the appellants are entitled to damages for breach of contract. On this issue the appellants` case is founded on two premises: first, that the respondent by his solicitors` letter dated 23 March 1992 had agreed to the appellants` request for an extension of time to complete the sale and purchase; in other words, by that letter he had agreed to extend the contractual date of completion by two weeks from 28 March 1992; and secondly, that the contractual date of completion having been so extended, the respondent`s solicitors` letter of 28 March 1992 giving the 21-day notice to complete was bad and amounted to a repudiation of the contract in that the respondent had thereby evinced the intention not to be bound by the contract and that the repudiation was accepted by the appellants on 7 April 1992. The appellants accordingly are entitled to damages for breach of contract.
29 It is necessary to recapitulate here the relevant sequence of events that had transpired and examine the letters relied upon by the appellants. The appellants by their solicitors` letter dated 21 March 1992 requested for `an extension of two (2) weeks to complete` the purchase. The material part of the letter read as follows:
Purchase of No 6 Elliot Road Singapore
We refer to the above matter.
Kindly let us have an extension of two (2) weeks to complete the above matter as we are awaiting for the planning approval.
30 In response, the letter of 23 March from the respondent`s solicitors, so far as material, was this:
Purchase of No 6 Elliot Road Singapore
We refer to your letter of 21 March 1992.
Our client will charge the usual interest for late completion.
31 Counsel for the appellants relied heavily on that letter of the respondent`s solicitors contending that by that letter the respondent had agreed to the extension of time to complete as requested by the appellants` solicitors in their letter of 21 March. It was said that the respondent`s solicitors specifically replied to the appellants` request, and by saying that that the respondent would charge interest the respondent had by necessary implication agreed to the extension. We are unable to accept this contention. The respondent`s solicitors by their letter of 23 March were purely non-committal and took the stand that should the appellants complete the purchase at a date beyond the contractual date of completion, the respondent would charge interest for such delay. Indeed, by saying that their client would charge `the usual interest for late completion` the respondent`s solicitors clearly had indicated that they were not agreeable to the request for an extension of time. If they had agreed, there would be no interest chargeable.
32 It should also be borne in mind that these letters were an exchange of correspondence between the two solicitors involved in the transaction and they were fully conversant with the terms of the agreement. By cl 8 of the Law Society`s Conditions of Sale, which is a term of the agreement, the respondent was entitled to interest if there was any delay in completion which was caused solely by the appellants. The respondent by his solicitors` letter was doing no more than asserting his entitlement to interest should the appellants complete the purchase on a date beyond the contractual date of completion.
33 The appellants themselves did not consider or regard that the respondent had by the letter of 23 March agreed to an extension of two weeks to complete. This was clearly evidenced by the letter of 27 March written by the appellants` solicitors seeking an extension of time to complete. That letter stated as follows:
Purchase of No 6 Elliot Road Singapore
We refer to the above matter.
Please be informed that in principal [sic] approval for a pair of 3-storey semi-detached was not granted. As such, on a strictly without prejudice basis, our clients wish to request for an extension of time to complete the sale and purchase pending appeal for the construction of a pair of 3-storey semi-detached as agreed under the sale and purchase agreement.
Please let us hear from you.
34 We are in complete agreement with the trial judge`s conclusion that the fact that on 27 March 1992 the appellants` solicitors renewed their request for an extension of time for completion meant that they knew that their previous request had been refused.
35 In our judgment, the appellants` request for an extension of two weeks to complete the purchase had not been agreed to by the respondent. The contractual date of completion remained as originally agreed under the agreement, ie 28 March 1992.
36 We now turn to the next letter relied upon by the appellants, the letter dated 28 March 1992 from the respondent`s solicitors. The letter read as follows:
No 6 Elliot Road Singapore
We note your client is unable to complete on 28 March 1992.
Our client is ready, able and willing to complete. We hereby give notice for your clients to complete within the next twenty-one (21) days, that is, by 18 April 1992.
Please let us have seven (7) clear days` notice of the date your clients are able to complete to enable us to liase [sic] with our client`s mortgagees and to render a fresh completion account.
As requested, we enclose herewith copy of a letter dated 2 January 1991 from United Overseas Bank Limited evidencing payment of the development charge.
37 This letter was intended by the respondent`s solicitors to be a 21-day notice under condition 29(2) of the Law Society`s Conditions of Sale, which again is a term of the agreement. It was held by the trial judge, and we agree, that this letter was premature. It was given on the contractual date of completion and not thereafter. The respondent was not entitled on 28 March to give this notice which was given. Hence, as a notice under that condition it was bad and ineffective. But the appellants contended that the letter was a repudiation of the agreement in that the respondent evinced his intention not to be bound by the extended date of completion. We disagree. First, as we have held, the contractual date of completion had not been extended, and secondly, even if it had been extended, such a letter could not amount to a repudiation. The respondent did not by this letter repudiate the contract. On the contrary, he intimated that the contract was to be performed and stipulated a final date for completion, albeit he was wrong in so doing. In our judgment, the respondent had not by this letter committed a repudiatory breach of the agreement.
38 Refund of deposit
39 We now turn to the third issue: whether the appellants are entitled to the refund of the deposit. It was not in dispute that the URA did not grant approval in principle for the development of a pair of three-storey semi-detached houses by the completion date, ie 28 March 1992. Hence, cl 10 came into operation and by virtue thereof the agreement came to an end on the expiry of that date. Both parties appeared to have accepted that the agreement was so terminated. The appellants by their solicitors` letter dated 7 April 1992 stated that no approval for a pair of three storey semi-detached houses was given and sought the refund of the deposit. The respondent by his solicitors` letter dated 8 April 1992 in response asked the appellants to furnish evidence of their compliance with cl 10(b)(i)-(iv). Effectively both parties accepted that cl 10 came into operation.
40 Clause 10 provides as follows:
The property is sold subject to in-principle approval being granted by the relevant authority for the construction of one (1) pair of 3-storey semi-detached houses by the completion date stated in cl 3 stated herein, failing which the sale agreement shall be deemed null and void.
Thereupon -
(a) the purchaser shall withdraw all caveats and other encumbrances lodged against the property; and
(b) the vendor shall return the sum of $96,500 stated in cl 2 herein to the purchaser subject to the following conditions:
(i) the purchaser shall provide documentary evidence that his architects submitted a complete application for the said in-principle approval within fourteen (14) days from the date of this agreement;
(ii) the plans submitted to the authorities for the proposed one (1) pair of semi-detached houses is similar in all material respects to that submitted by Messrs James Yip & Partners on behalf of the proprietors of No 4 Elliot Road Singapore;
(iii) all costs of and incidental to the said in-principal application shall be borne by the purchaser; and
(iv) any delay in granting of the in-principle approval by the authorities is not due to the default of the purchaser or his servants or agents.
41 This clause is in two parts. The first part provides that the contract is automatically terminated upon the occurrence of an event, ie the non-approval in principle from the URA of the development of a pair of three-storey semi-detached houses. That event occurred and the agreement was accordingly terminated. The next part of the clause provides for the aftermath following such automatic termination: the appellants were to withdraw their caveat, and the respondent was to return the deposit. The withdrawal of the caveat was not in issue and we need not be concerned with it. As for the respondent`s obligation to return the deposit, it is subject to sub-paras (i) to (iv) of para (b). The events or matters specified in sub-paras (iii) and (iv) do not arise, and have no relevance to the dispute before us. We need to consider only sub-paras (i) and (ii), and the question is whether the appellants had complied with these provisions.
42 With regard to the event in sub-para (i), it was not disputed that the appellants did submit to the URA the application for written permission for the development of a pair of three storey semi-detached houses; but the application was submitted after the expiry of the 14 days as provided in cl 10(b)(i). Therefore, the only point of contention is whether by this belated submission the appellants had complied with cl 10(b)(i). It was submitted by counsel for the appellants that time was not of the essence for the purpose of this sub-para and that the appellants had complied with it. On the other hand, respondent`s counsel submitted that cl 10 is in the nature of a `break clause` and that being so the time stated there is of the essence. In referring to this terminology counsel was obviously referring to the concept of a `break clause` illustrated by Lord Diplock in United Scientific Holdings Ltd v Burnley Borough Council [1978] AC 904. There, his Lordship was referring to unilateral contracts, such as an option to purchase a property or to renew a lease where exact and strict compliance of the terms in exercising the option is required and time as stated there is of the essence, and also to the converse case of a `break clause` in a lease which gives to the tenant an option to determine prematurely the lease at the end of a stated period, where again strict observance is required and time is of the essence. His Lordship explained, at p 929:
... A more practical business explanation why stipulation as to the time by which an option to acquire an interest in property should be exercised by the grantee must be punctually observed, is that the grantor, so long as the option remains open, thereby submits to being disabled from disposing of his proprietary interest to anyone other than the grantee, and this without any guarantee that it will be disposed of to the grantee. In accepting such a fetter upon his powers of disposition of his property, the grantor needs to know with certainty the moment when it has come to an end.
... there is a practical business reason for treating time as of the essence of such a clause [ie an option to determine prematurely a lease], which is similar to that applicable to an option to acquire property. The exercise of this option by the tenant will have the effect of depriving the landlord of the existing source of income from his property and the evident purpose of the stipulation as to notice is to leave him free thereafter to enter into a contract with a new tenant for tenancy commencing at the date of surrender provided for in the break clause.
43 It should be noted that Lord Diplock in coming to this conclusion had regard to the underlying reasons for the `break clause`, and in essence what his Lordship illustrated was nothing more than this: that regard should be had to the subject matter and the surrounding circumstances.
44 In our view, clearly cl 10 is not in the nature of a `break clause` such as a clause conferring an option either to renew or to determine prematurely a lease. The first part of cl 10 may be in the nature of a `break clause` in the sense that it `breaks` the contract automatically upon the happening of the event therein specified. No time is stated here and hence there is no question of time being of the essence in respect of this part of cl 10. However, the provision of cl 10 dealing with the aftermath of that `breaking` event is quite different and is not in the nature of a `break clause`. As time is not stated in the agreement to be of the essence, it is relevant to examine the nature of the subject matter and the surrounding circumstances in order to ascertain whether time should be considered to be of the essence: see 9 Halsbury`s Laws of England (4th Ed) para 481.
45 This part of cl 10(a) was insisted upon by the respondent and the purpose of stating the period of 14 days was to provide the appellants a time frame within which the application to the URA was to be made and thus to ensure that the appellants would act with due expedition so as to be able to obtain a response from the URA by the contractual date of completion. The 14-day period was not such an event that the exact observance thereof was essential or crucial to the timely performance of the contract. There is nothing in cl 10 which says that the application to the URA cannot be made after the expiry of the 14 days; nor does it say anything of the effect of such belated application. In particular, sub-para (i) does not provide that in the event of any non-compliance of the 14-day period the appellants would be precluded from recovering the return of the deposit.
46 The appellants did not agree to engage James Yip & Partners, the architects who had previously successfully made the application to the URA for the owner of No 4 Elliot Road, to make the submission and they were at liberty to engage other architects to do so. And they did. It was contemplated that their architects would have to prepare the necessary plans afresh and make the submission. In such circumstances, it would be difficult, if not impracticable, for the appellants` architects to draw up the necessary plans and prepare the application and other documents and submit them to the URA within the period of 14 days.
47 In our judgment, both the subject matter and the surrounding circumstances ineluctably show that time is not of the essence in respect of the 14-day period as provided in cl 10(b)(i). The appellants, although they submitted their application to the URA beyond the 14-day period, had complied with this sub-paragraph.
48 We now turn to the question whether cl 10(b)(ii) had been complied with by the appellants. We find it extremely odd that the appellants could and should have agreed to this provision bearing in mind that the appellants did not have the intention of engaging James Yip & Partners as their architects, did not know the owner of No 4 Elliot Road and did not have the plans of No 4 Elliot Road. To understand the reason for the existence of this sub-paragraph it is necessary to set out and examine the factual matrix in which the parties were placed when the agreement was entered into.
49 It was in evidence that in late November 1991 the owner of No 4 Elliot Road through her architects, James Yip & Partners, obtained from the URA provisional permission for the development of a pair of three storey semi-detached houses on her property. The respondent learnt of this from the owner of No 4 Elliot Road, as he knew the owner rather well; sometime ago the respondent and the owner had made a joint application to the authority for permission to develop terrace houses on their respective properties. In the course of negotiation between the appellants and the respondent, the latter must have informed Ong that the owner of No 4 Elliot Road had obtained the permission for the development of a pair of three storey semi-detached houses, and clearly the appellants would wish to purchase the property for the purpose of a similar development. Hence, the appellants negotiated for a long date of completion and also a condition to the effect that the sale and purchase would be subject to the URA granting approval for such development by the date of completion. On the other hand, the respondent wished to be protected against the risk of a downturn in the property market over such a long period, and while agreeing to such condition he wished to ensure that the appellants would apply with all due despatch for such approval and also in a manner that would, as far as practicable, ensure that the URA would grant the permission. It is only obvious that for this reason he would like the appellants to engage James Yip & Partners as the architects to make the application, as he believed, understandably, that if James Yip & Partners were to make the application it would be likely that the URA would grant the application; after all the URA had given such approval to the owner of No 4 Elliot Road only in late November 1991. Hence, when cl 10 was finally drafted, it provided in sub-para (i) that the appellants would engage James Yip & Partners as their architects. Subsequently, the parties had further negotiated - or m ust have further negotiated - and the appellants for economic or other reasons wished to engage Architects PS 100, as Ong was acquainted with one Ms Chan of that firm. Hence, the name of James Yip & Partners was manually deleted from sub-para (i). Unfortunately, for some reason, sub-para (i) was not modified or deleted.
50 It was the evidence of Ong that the respondent agreed to furnish him with the plans of No 4 Elliot Road as he knew the owner and could obtain the plans, but that after the agreement was signed the respondent failed or was unable to do so. This was denied by the respondent. But the respondent admitted that he knew the owner of No 4 Elliot Road, and had available the plans at some stage.
51 We think that there is some truth in the evidence of Ong on this point. In all probability, the respondent did agree at or about the time of the execution of the agreement that he would obtain for Ong the plans for the development on No 4 Elliot Road. These plans were never given to Ong at any time and it was impossible for the appellants to comply with sub-para (ii) of cl 10(b). This finding is consistent with the matrix of facts at the relevant time and with the obligation of the respondent. The respondent by his pleadings conceded that he was obliged to assist the appellants in securing approval in principle from the relevant authority for the development, the basis of this obligation being an implied term under the agreement.
52 As the respondent had failed to assist the appellants in getting a set of the plans of No 4 Elliot Road, he cannot insist on a strict compliance of sub-para (ii) of cl 10(b). There was no way the appellants could possibly comply with that provision without some assistance from the respondent and there was no way they could obtain a set of the plans: they did not know the owner of No 4 Elliot Road and they did not know the architects, James Yip & Partners, and, what is more, they had decided to engage another firm of architects.
53 At any rate, as the events had turned out, whether or not the plans submitted by the appellants to the URA are `similar in all material respects` to those submitted by James Yip & Partners is wholly immaterial. The refusal of approval for a three- storey building was due essentially to a change of policy on the part of the URA and not to any matters connected with the plans submitted. It seems to us that the URA was fully conscious of its apparent inconsistent stance: in late November 1991 it granted provisional permission to the owner of No 4 Elliot Road for the development of a pair of three storey semi-detached houses and on 25 March 1992 it refused such approval and granted approval only for two-storey semi-detached houses. This accounted for the letter dated 26 March 1992 from the URA to Architects PS 100 explaining the reasons for restricting the building height to two storeys. Hence, even if the plans submitted by Architects PS 100 were similar in all material respects to those submitted by James Yip & Partners, they would have met with the same response from the URA.
54 In view of what we have decided, it is not necessary to consider the last issue whether in all the circumstances relief against forfeiture of the deposit should be granted in this case.
55 For the reasons we have given, we find that the appellants had complied with cl 10(b) and the respondent is therefore obliged to refund to the appellants the deposit of $96,500. We allow both appeals and set aside the orders made below. There will be judgment for the amount of $96,500 in favour of the appellants with interest at 6% pa from the date of the writ to the date hereof. The deposit as security for costs is to be refunded to the appellants.
56 Before we make an order as to costs here and below we would like to hear any arguments which counsel may wish to make. We invite counsel to submit their arguments within 10 days from the date hereof.
57 Appeals allowed.
Goh Joon Seng J Karthigesu JA L P Thean JA |
Davinder Singh, Ameera Ashraf (Drew & Napier) and Sham Chee Keat (Manjit, Samuel & Partners) for the appellants
Cheong Yuen Hee and Thinagaran s/o Vasudevan (Tan Kim Seng & Partners) for the respondent