In the High Court of the Republic of Singapore
[1996] SGHC 227
DC Suit 292/1994, DCA 69/1995
Between
Asia Beni Steel Industries Pte Ltd
Another
… Plaintiff
And
Chua Chuan Leong Contractors Pte Ltd
… Defendant
grounds of decision
Tort — Negligence — Causation; Tort — Vicarious liability

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Asia Beni Steel Industries Pte Ltd and Another v Chua Chuan Leong Contractors Pte Ltd
[1996] SGHC 227
DC Suit 292/1994, DCA 69/1995
Goh Joon Seng J
09 October 1996
1 This was an appeal from the judgment of the court below dismissing the plaintiffs` claim for damage to their goods being 23 steel coils and 14 steel plates (the damaged goods).
2 The damaged goods were part of a consignment shipped under a bill of lading for 49 steel coils and 1491 steel plates (the cargo) on board the vessel the Atlantic Pride (the vessel) from Santos, Brazil, to Singapore. The cargo was consigned `To the order of` the second plaintiffs. Before the arrival of the cargo, the second plaintiffs sold the same to the first plaintiffs.
3 Some two days before the arrival of the vessel, the shipowner`s agent, Monson Agencies Pte Ltd (Monson), instructed Chuan Stevedoring Services to undertake the discharge of the cargo. Chuan Stevedoring Services in turn hired, from the defendants, stevedoring labourers and forklifts with drivers. By so doing the vessel was accorded priority in berthing at Berth No J6 under the defendants` special appropriated berth scheme agreement (the AB agreement) with the Jurong Town Corporation (JTC).
4 The vessel arrived on 24 January 1993 and accordingly berthed at Berth No J6 as a vessel nominated by the defendants. Discharge of the cargo began the next day and ended on 29 January 1993. The discharge was carried out by the stevedoring labourers supplied by the defendants, using the equipment hired from the defendants and Chuan Stevedoring Services` own special lifting equipment. Chua Cheng Chuan, an employee of Chuan Stevedoring Services, was in charge of the discharge operations. Other than nominating the vessel to be berthed at Berth No J6 and supplying the stevedoring labourers and the forklifts with drivers, the defendants had nothing to do with the discharge of the cargo.
5 After the cargo had been discharged from the vessel onto the wharf, it was stacked up in the open ground a short distance away from the wharf. No damage had been noted by any of the tallying clerks attending the discharge. If such damage had been noted, it would have been reported to Chua Cheng Chuan who would then have noted it in a survey report.
6 On 28 January 1993 the first plaintiffs gave notice of damage to Monson and to the insurers of the cargo. A survey was accordingly carried out by Michael Ho of Pacific-Indo Services Pte Ltd. The damaged goods were noted to have sustained damage as follows. The steel plates were noted to have buckled and or bent. The steel coils were noted to have buckled or bent or had cuts at the edges or ends. By agreement between the first plaintiffs and Michael Ho an allowance of 25% of the c & f invoice value of the damaged goods was arrived at. The insurers thus paid the first plaintiffs the sum of $29,615.83 and they were thereby subrogated to the rights of the first plaintiffs. The insurers then sought unsuccessfully to recover reimbursement of this payment from the defendants and accordingly commenced these proceedings in the subordinate courts in DC Suit No 292/94. In their statement of claim the plaintiffs alleged that the defendants as operators of Berth No J6 under the AB agreeement were responsible for the discharge, storage and delivery of the cargo and that the damaged goods sustained damage as a result of the defendants` breach of duty as bailees and/or negligence in the discharge and storage of the same.
7 To succeed in their claim against the defendants, the plaintiffs must establish the following:
8 (i) the defendants undertook the discharge of the damaged goods and or the warehousing of the same; and
9 (ii) the damage was caused by the defendants` negligent discharge of the damaged goods or breach of duty as bailees while the damaged goods were in their possession.
10 On (i), the learned judge below in finding for the defendants said:
The special appropriated berth scheme was basically a scheme giving priority in berthing. Under the scheme, the defendants had the choice of:
(a) doing the stevedoring work themselves or
(b) allowing the shipowners or the shipowners` agents to employ their own stevedores or
(c) to appoint other stevedoring companies to do the work.
In the case of the Atlantic Pride, the shipowners engaged the defendants for the purpose of obtaining priority in berthing the vessel. The vessel`s owners through their agent, Monson Agencies Pte Ltd, engaged Chuan Stevedoring Services to undertake the discharge and loading of the vessel. Chuan Stevedoring Services contracted with the defendants to supply the following:
(a) labour
(b) machinery (forklifts) and
(c) cargo gear (not dunnages).
For providing these services, the defendants billed Chuan Stevedoring Services who would then bill Monson Agencies Pte Ltd. In its request for the supply of labour, Chuan Stevedoring Services would ask for a number of gangs and machinery to be provided daily at an agreed rate for its use. The defendants` labourers would carry out the orders given by Chuan Stevedoring Services as they would be under the control and direction of Chuan Stevedoring Services or Monson Agencies Pte Ltd. Payment for these services provided by the defendants was based on a tonnage basis.
11 This finding is well supported by the evidence of the plaintiffs` own witness Chua Cheng Chuan of Chuan Stevedoring Services:
Q: Am I right that the defendants only supplied the stevedore labour, forklifts and drivers but Chuan Stevedoring Services was actually in charge of the whole operation of discharge and unloading of the goods onto the wharf?
A: Yes.
...
Q: The whole discharge operation was yours and in this case you engaged the labourers and the forklifts from the defendants?
A: Yes.
...
Q: During the operation, all these people take orders from you?
A: Yes.
Q: The defendants take no part in the discharge operation?
A:Correct.
12 In Lim Chin Yok Co Ltd v Malayan Insurance Co Inc [1975] 1 MLJ 101; [1972-1974] SLR 272, the defendants were awarded a contract for the construction of a sea wall. They hired the piling frame from another contractor and they contracted with one P Kunju for the supply of labourers to operate the piling frame. P Kunju was paid according to foot length of the piles driven. The work was carried out under the supervision of the defendants. One of the labourers supplied by P Kunju, M Sukumaran, was injured when the pulley wheel of the piling frame broke and part of it fell and hit him. In holding the defendants liable to the plaintiff, Choor Singh J said at p 103:
Counsel for the defendants submitted that the defendants were not liable as employers because they were not the plaintiff`s employers. It was contended that he was employed by Pareed Kunju who was an independent contractor.
It is true that Pareed Kunju was an independent contractor but his contract was merely for supplying labour for the piling operation which remained under the control and direction of the defendants. The defendants were in the position of being able to tell Kunju`s labourers, what to do, where to do it and how to do it. There was transfer of control from Pareed Kunju to the defendants who were under the circumstances, while the piling operation was in progress, the temporary employers of the plaintiff. Once the right of control is transferred, the temporary master takes over all the ordinary liabilities of an employer ...
13 In the matter before me the stevedoring labourers supplied by the defendants were under the control and direction of Chua Cheng Chuan who was in charge of the discharge operation on behalf of Chuan Stevedoring Services who were thus their `temporary employers`. The defendants were therefore not vicariously liable for the damage if any sustained by the damaged goods in the course of discharge.
14 Under the AB Agreement cargoes discharged from vessels berthed at Berth No J6 could be stored in Transit Warehouse No J6 (the warehouse). Chuan Stevedoring Services did not request for the use of this facility. To have the cargo stored in the warehouse a warehouse management fee would have to be paid to the defendants by Chuan Stevedoring Services who in turn would have billed Monson. This was the evidence of Alvin Lai Kam Fatt, the assistant manager (operations) of the defendants:
Can you choose not to provide warehouse management? Is it contemplated by JTC that you can exclude the provision of warehouse management?
A: If the agents choose.
Q: If they choose, how would that be shown?
A: By the bill - it would be mentioned `for warehouse management`.
Q: But the bill comes after the work is done. How would the agents specify that they do not need your warehouse management? Is it implied or understood that you would supply warehouse management in using your Appropriated Berth Scheme?
A: In this case, Chuan Stevedoring Services made clear that they did not require our warehouse management.
15 As the damaged goods were not stored in the warehouse with the defendants providing warehouse management service, the defendants were under no contractual duty of care in respect of the same. The damaged goods were not in the possession of the defendants. Accordingly the defendants were not bailees for the same. See 2 Halsbury`s Laws of England (4th Ed) para 1501 which states:
To constitute a bailment (which derives its name from the old French word Bailler, to deliver or put into the hands of), the actual or constructive possession of a specific chattel must be transferred by its owner or possessor (the bailor), or his agent duly authorised for that purpose, to another person (the bailee) in order that the latter may keep the same or perform some act in connection therewith, for which such actual or constructive possession of the chattel is necessary, thereafter returning the identical subject matter in its original or an altered form.
16 The plaintiffs` claim against the defendants for breach of duty as bailees therefore also failed.
17 On (ii), the plaintiffs contended that since the tally sheets recording the discharge of the cargo from the ship onto the wharf was headed `Discharged ... in apparent good order and condition`, the cargo must have been discharged from the vessel without any damage. This was not supported by their own evidence.
18 In his survey report Michael Ho stated:
Cause of damage
The damage sustained to the above pieces/coils, in our opinion, could be attributed to rough/improper handling and or being pierced/cut by a sharp object probably caused by the tine of a forklift truck or wire slings during transit or during loading into or discharging from the vessel and prior to acceptance by the consignee.
The jagged edges on some of the above damaged coils, in our opinion could be due to a preshipment origin and or manufacturing defects.
19 When cross-examined by counsel for the defendants on his conclusion on the cause of the damage, this was what Michael Ho said:
Q: ... By that, you mean this damage can occur:
- when the goods leave the factory to be loaded onto the lorries;
- or being loaded from the lorries into a godown for shipment;
- loaded from over the ship side;
- from the ship hold to the open space?
A: Yes.
You also said, `The jagged edges on some of the above damaged coils, in our opinion could be due to a preshipment origin and or manufacturing defects`. You mean that this damage could have occurred already in the shipper`s own premises?
A: Jagged edge damage is not buckled, it is due to the manufacturers. They have not smoothened the edges.
20 There was therefore no clear evidence that the damage to the damaged goods was sustained during and after the discharge of the same from the vessel.
21 In proceeding against the defendants the plaintiffs relied on the duties undertaken by the defendants under the AB agreement with JTC. Though the AB agreement granted priority in the use of Berth No J6 to vessels nominated by the defendants, the defendants did not have exclusive use of Berth No J6. Also vessels applying for berthing under the defendants might be directed by JTC to berth elsewhere. In return for this privilege the defendants had to ensure a minimum volume of 350,000 metric tons of cargo for loading or discharge for the period 1 October 1992 to 30 September 1993. If there was a shortfall, the defendants would have to pay JTC $2 per metric ton for the shortfall. The AB agreement also allowed the defendants or their `clients` to perform the stevedorage and wharf handling operations. By the terms of the AB agreement the defendants were inter alia made responsible for all the operations thereunder. These provisions were clearly intended by JTC to ensure a high standard in the operations of the port under its control. But the plaintiffs are not parties to the AB agreement and cannot found their claim on the duties assumed under it by the defendants vis-a-vis JTC. For the reasons given herein, I dismissed the appeal with costs.
22 Appeal dismissed.
Goh Joon Seng J
Chan Kia Pheng (Yeo-Leong & Peh) for the plaintiffs
C Arul and Lim Tanguy Yuteck (C Arul & Partners) for the defendants