Lee Say Sugar Factory Pte Ltd v Deep-Freeze Refrigeration Pte Ltd
[1997] SGHC 149
Suit 30/1994
Christopher Lau JC
03 June 1997
Judgment:
GROUNDS OF DECISION
1. This action arises out of the supply, installation and commissioning of an airconditioning and refrigeration plant ("the plant") comprising several coldrooms and a water chiller plant at the plaintiffs’ premises at 54 Defu Lane 3, Singapore pursuant to an agreement dated 13 June 1991 entered into between the plaintiffs, suppliers of freshly slaughtered chicken, and the defendants who are manufacturers and repairers of refrigeration equipment.
Background
2. By an agreement in writing dated 13 June 1991 ("the contract"), the plaintiffs engaged the defendants to supply, install and commission the plant for the plaintiffs’ business at the plaintiffs’ Defu Lane premises. This involved the supply, installation and commissioning of two chiller rooms, one freezer room, one cutting room, one packing area, one chiller unit and related accessories and equipment for a price of approximately S$300,000.00 ("the contract sum"). The contract provided for the installation of the plant to be completed in approximately seven months, that is by about 14 January 1992.
3. By section 11 of the contract, the following schedule of payment was agreed :
10% downpayment upon the signing of the agreement;
20% downpayment upon approval from the Economic Development Board or a finance institution not later than thirty days from 13 June 1991 before delivery of the equipment to site;
30% upon delivery of the equipment to site;
20% upon complete erection of the insulation panel;
10% upon complete installation of the refrigeration equipment;
10% upon testing and commissioning of the equipment.
4. By section 12 of the contract, the defendants provided a warranty for faulty parts and workmanship provided these did not arise out of the plaintiffs’ negligent mishandling of the plant. The warranty was for a period of twelve months and it was to commence from the date of the commissioning of the plant or the completion of its installation whichever was the earlier. I refer to this period as the warranty period.
5. Section 13 of the contract provided for the defendants to provide free bi-monthly maintenance and servicing of the plant during the warranty period. Thereafter, the parties were to discuss what, if any, and the scope of the maintenance services the defendants were to provide.
6. There is no dispute between the parties that prior to the contract being signed the defendants had made a number of site visits to the plaintiffs’ Defu Lane premises and that the plaintiffs and the defendants had had a number of meetings and discussions on the plaintiffs’ requirements for such a plant. One requirement was that the plant was to provide chilled water with a temperature range of about 1 degree Celsius and in sufficient volume for the storage and production of the slaughtered poultry. It is also common ground that the plaintiffs obtained a loan from their bank to pay the contract sum and that payments due under the contract were to be made by the bank only with the plaintiffs’ approval.
7. Nothing turns on when the defendants commenced work and supplied the equipment and it is also common ground that the defendants commenced work under the contract soon after the contract was signed.
8. Where the parties’ account of events begins to differ substantially, and this determines the warranty period, is when completion of the installation and commissioning of the plant took place. The plaintiffs say that both events took place on or about 22 May 1992. The defendants say that completion took place on or about 27 December 1991, with the plant being tested to the plaintiffs’ satisfaction and commissioned on 14 January 1992 and handed over to the plaintiffs on 25 January 1992. On the plaintiffs’ case, the warranty period was to run from 22 May 1992 to 21 May 1993 whilst the defendants’ case is that the period of the warranty was from 25 January 1992 to 24 January 1993. There is also considerable variance in the parties’ account of events following the plant’s installation.
The issues
9. The issues I have to consider are essentially whether the defendants had completed the installation of the plant, whether such installation was defective, whether the defendants had been negligent in maintaining the system during the warranty period, whether there was conversion of some of the equipment in this plant by the defendants, and if the defendants were in breach, as alleged, did the loss suffered by the plaintiffs amount to S$109,309.10 as claimed and if not, what if any, was the loss. Finally I have to consider whether there is any basis for the defendants’ counterclaim for S$72,340.00.
The plaintiffs’ case
10. Essentially, the plaintiffs allege firstly that the defendants never completed the installation because there was still some outstanding work to be done as, inter alia, the defendants had omitted to install a fourth fan coil and provide to the plaintiffs a diagram for the plant’s electrical system. Secondly, the plaintiffs allege that the installation of the plant by the defendants was negligent. Thirdly, the plaintiffs allege that the installation and commissioning of the plant only took place on 21 May 1992 and accordingly that the warranty period ran from 22 May 1992 to 21 May 1993. Integral to this allegation is the further allegation by the plaintiffs that the defendants’ handover letter, purportedly handing over the plant to the plaintiffs ("the handover letter") had initially been dated 25 January 1992, but that that date had been changed by the defendants’ managing director Daniel Wong Ban Chin in his own handwriting on or about 25 January 1992 to 22 May 1992. Fourthly, the plaintiffs say that the bi-monthly maintenance of the plant by the defendants, which the plaintiffs say meant two servicings each month, during the warranty period was negligently carried out as the defendants had not serviced the plant twice each month but only once every two months and as the defendants had applied excess chemicals to the water in the plant. These breaches, the plaintiffs allege, by the defendants manifested themselves about three months after the plant’s installation when frequent electrical trippings resulting in frequent shut downs of the plant began to occur, rust began to appear in the plant’s water and subsequently in the plant’s inability to produce chilled water in the temperature of one degree Celsius and in the quantity required.
11. There is no allegation by the plaintiffs that the defendants’ design of the plant was negligent.
The defendants’ case
12. In brief, the defendants deny these allegations in their entirety. The fourth fan coil which was to have been installed in the packing room was not, the defendants allege, installed as the plaintiffs wanted to conserve floor space and as the plaintiffs instructed the defendants not to do so. The defendants’ case is that the handover of the plant took place on 25 January 1992, that the warranty period was from 25 January 1992 to 24 January 1993, that bi-monthly maintenance meant once every two months as agreed to by the plaintiffs and not twice each month, and that they did carry out bi-monthy maintenance during the warranty period from 25 January 1992 to 24 January 1993, that the problems which occurred during and after the warranty period did not affect the satisfactory operation of the plant, and that the alleged power "trippings" and rust were caused by the plaintiffs’ poor daily maintenance of the plant as well as the plant’s environment. As for the defendants’ counterclaim, the defendants claim this arises out of the plaintiffs’ instructions to them to carry out additional work outside the scope of the contract and outside the warranty period.
The plaintiffs’ evidence
13. It was the evidence of Mr Poon Teck Kee, the plaintiff company’s production manager who had charge of the running of the company’s production operation systems, which included the plant, and Mr Ng Eng Wah, a director of the plaintiff company that about three months after the plant’s installation, problems began. These, according to Mr Poon, took the form of frequent power ‘trippings’ caused by high pressure build up in the plant. The trippings occurred at least once a week and on occasions, more than once a week. These tripping problems then evolved into more serious problems when the pipes connecting the cooled water supply became corroded and damaged. The temperature of the chilled water then according to Mr Poon became erratic and unstable with the plant being unable to maintain the chilled water in a one degree Celsius range. By then, when the defendants’ technicians "managed to arrest a fault e.g. high pressure, there was another problem of oil with water". The water in the cooling tower had also begun to turn rusty. Mr Poon however did not specify the time frame within which these problems occurred. Except for the statement that these initially arose three months after installation, he did not say when complete installation of the plant took place, and the points in time when these problems metamorphosed into the chiller breaking down. Mr Poon also asserted the corrosion to the pipes was caused by excessive use by the defendants of water treatment chemicals and he sought also to establish the chiller’s breakdown by referring to alleged forced purchases of ice blocks by the plaintiffs from an ice block supplier to chill the water. He further alleged that he, together with his two assistants, had been maintaining the system to the best of their abilities, that the principal instructions given to him by the defendants on the operation of the plant comprised of switching on and switching off procedures and starting/ turning steps. The defendants, he said, had not given any specialised training, nor had the defendants ‘stationed’ a trainer or instructor at the plaintiffs’ premises to monitor or supervise his and his two assistants’ performance during or after the plant’s installation.
14. Mr Ng Eng Wah expanded on Mr Poon’s evidence. He said the problems arose when rust "started to form" and spread to the condenser and corroded the pipes. He alleged that the equipment and materials in the system were defective or faulty, that these had not been installed in a proper and workmanlike manner and that they were not fit for the plaintiffs’ purpose. He made the allegation, which another of the plaintiff company’s directors - Mr Ong Pang Teck - purported to corroborate, that the defendants did not complete the system’s installation until 21 May 1992, relying on a handover letter (two copies of which had been admitted and marked as exhibits "D-16" and "D-16A") written by the defendants and signed by the defendant company’s managing director Daniel Wong Ban Chin containing purportedly Mr Daniel Wong’s handwritten amendment of the handover letter’s date from 25 January 1992 to 22 May 1992. Mr Ong said that he had witnessed the handwritten amendment of the date by Mr Daniel Wong. Mr Ong explained that Mr Daniel Wong had initially asked him on 25 January 1992 to acknowledge in the handover letter before that letter’s date was amended that the testing and commissioning of the plant had been completed so that the defendants could then call for the final payment from the plaintiffs’ bank. He said when he then pointed out to Mr Daniel Wong that completion had not yet been completed, Mr Wong, as the defendants were in need of funds, not only assured both Mr Ng and Mr Ong that the system would be fully operational tested and commissioned by about 22 May 1992 but also amended the date of the handover letter from 5 January 1992 to 22 May 1992. Mr Ng said it was on this basis the plaintiffs, through their bank, paid or settled in full the contract sum on 28 January 1992.
15. Mr Ng alleged that the problems of tripping, rusting and the breakdown of the chiller all occurred within the warranty period which on his and Mr Ong’s evidence was from 22 May 1992 to 21 May 1993. Mr Ng’s further evidence is that it was as a result of these problems that the plaintiffs had no alternative but to appoint another firm of refrigeration specialists - Alpha Celsius Pte Ltd - to rectify the defects for a sum of S$108,209.10. He also said there can be no basis for the defendants’ counterclaim since the works or services in respect of which the counterclaim is based were either not agreed to or requested by the plaintiffs nor were these ever carried out, and that even if these were carried out, that these were part of the defendants’ contractual obligations during the warranty period. He also alleged that these invoices were all, except for two which were dated 1992, dated between February 1993 to April 1993 and impliedly, that these were fabricated to meet the plaintiffs’ claim as these were not raised until the defendants amended their Defence and Counterclaim in or about August 1994. He said the defendants had never sent these invoices to the plaintiffs. Mr Ng also said that sometime in February 1993 the defendants had taken away certain items of equipment from the plant to repair and that the defendants had since refused to return these.
The defendants’ evidence
16. The evidence of Mr Daniel Wong Ban Chin, the managing director of the defendant company, whose qualifications and experience in air-conditioning and refrigeration plant installation, repairs and maintenance are not disputed, is that he recommended and saw to the plant’s installation, that the plant as installed was sufficient for the plaintiffs’ needs had the plaintiffs properly maintained the plant and had the plaintiffs not moved the coops in which the live chickens were kept close to the cooling towers. The plant was completed, he said, satisfactorily on or about 27 December 1991, tested to the plaintiffs’ satisfaction and eventually commissioned on 14 January 1992 and it was handed over to the plaintiffs on 25 January 1992. On that date, Mr Wong also handed to the plaintiffs the defendants’ handover letter, which was dated 25 January 1992, for the plaintiffs’ acknowledgement, which although the plaintiffs signed, they however kept. The letter states :
"1) Kindly acknowledge that the above refrigeration system has been satisfactorily installed and handover for use as per our agreement dated 13 June 1991.
2) Warranty will commence from the above date for 12 months for workmanship and equipment supplied not caused by negligence or mishandling."
He was adamant he did not amend the date of the letter from 25 January 1992 to 22 May 1992.
17. It was his evidence that thereafter on 22 February 1992, the defendants applied for the release of the balance 20% of the contract sum amounting to S$72,000.00 and that on 11 March 1992, the plaintiffs’ bankers, with the plaintiffs’ approval, paid this amount to the defendants.
18. It was also Mr Wong’s evidence that bi-monthly maintenance under the contract was dutifully carried out by the defendants and that subsequently each time the system broke down, he impressed upon the plaintiffs the need for proper daily maintenance. He said that other plants employ regular maintenance staff for this purpose whereas the defendants never did. He also said that pollutants in the plaintiffs’ premises such as chicken feathers and droppings, which he says could have been avoided by daily and regular maintenance were being regularly sucked into the cooling towers and that these caused the water into the towers to become acidic and to corrode the condensers’ copper pipes, causing these to leak.
19. In summary, it was the defendants’ evidence that the problems alleged by the plaintiffs was caused by :
(a) the plaintiffs’ failure to properly maintain the plant;
(b) the plaintiffs placing the chicken coops too close to the cooling towers;
(c) the plaintiffs installing a subsidiary pipe diverting part of the chilled water to another part of the premises;
(d) the plaintiffs’ workers negligently resetting the equipment;
(e) the plaintiffs’ negligent attempts at restarting and running the compressors each time these stalled, even when the oil level had dropped to below the required level.
20. Mr Wong further denied the conversion claim saying the items of equipment that the defendants removed were done with the plaintiffs’ consent, for repairs and that these were offered back to the plaintiffs.
21. Finally, Mr Wong sought to show that the sum of S$72,340.00 was for additional work done by the defendants outside the scope of the contract, or after the expiry of the warranty period.
My findings
22. Having considered what Mr Ng, Mr Poon Teck Kee and Mr Ong Pang Teck had to say in evidence and the other evidence adduced by the plaintiffs, and their counsel’s submissions, I find the plaintiffs’ evidence far from satisfactory and in my view, fails to establish on a balance of probabilities, the plaintiffs’ claim. My reasons are :
(a) It was the view of Mr Chew Lak Swee, a director of Alpha Celsius Pte Ltd, the firm of refrigeration and airconditioning contractors that had been brought in by the plaintiffs in April 1993 to inspect and to carry out certain work on the plant that it was not the plant’s installation or its design that was the cause of the problems complained of by the plaintiffs. In essence he said the cause was poor maintenance. He agreed that the installation by the defendants of fresh water condensers in the plant was not wrong and he said that he had found the water in the system at the plaintiffs’ premises to be acidic in nature in contrast to water found elsewhere in Singapore which was not. It was also his evidence that this acidity would cause the copper fittings to corrode and the steel pipes in the plant to rust;
(b) Mr Ng Eng Wah, in cross-examination, conceded that the system worked properly when it was tested and commissioned (at page 155 letters E to F of the Notes of Evidence), and that the chiller room compressor which was an integral part of the system that produced chilled water was working until the middle of 1993 (page 197 E and page 198 A of the Notes of Evidence);
(c) The contract provided for the work to be completed in seven months ie. by January 1992 and if there was delay which, in view of the plaintiffs’ allegation of completion only being on 21 May 1992 must be the plaintiffs’ case, there is no satisfactory evidence that the plaintiffs ever protested this alleged delay in completion. Indeed Mr Ong Pang Teck admits that by January 1992, the defendants had finished all work on the plant;
(d) Mr Ong Pang Teck admitted that the handover letter was in fact not necessary in order for the bank to make the final payment and so the plaintiffs could easily have refused to sign the handover letter if in fact the plant’s installation had not been completed by on or about 25 January 1992.
(e) The plaintiffs adduced no evidence in support of their assertion that the defendants were in dire need of funds in January 1992 and indeed the undisputed evidence is that the defendants only applied for payment of the final sum of S$72,000.00 on 22 February 1992 with payment being made by the plaintiffs’ bank on 11 March 1992. If the defendants were in need of funds, why did they wait for almost a month before applying for payment ? Mr Ng sought to show this pressing need for funds by asserting and exhibiting as proof a payment made on 28 January 1992 but this he subsequently had to retract in cross-examination admitting that he had been incorrect.
(f) The evidence by the plaintiffs’ appointed handwriting expert that the date of "22.5.92" and the signature appearing against the amendment was unlikely to be that of Mr Daniel Wong.
(g) The undisputed evidence that the plaintiffs did not have a maintenance team to oversee the maintenance of the plant on a daily basis and that there was no regular water treatment of the plant apart from the application of the rust inhibitors by the defendants.
(h) Mr Poon’s own evidence in cross-examination contrary to what he had asserted in his affidavit of his evidence-in-chief was that the defendants were present almost everyday following completion of the installation of the plant, to observe the plant’s operation and that the defendants’ staff did instruct the plaintiffs on how the plant was to be operated;
(i) Mr Poon’s admission in cross-examination that in using the diverted line for chilled water flow, the supply of chilled water to the main plant had first to be switched off;
(j) Mr Poon’s further admission that he had himself noticed fine chicken feathers, that these fine chicken feathers were being drawn into the cooling towers and that when that happened, the feathers would become mixed with the water in the towers.
23. I turn next to the defendants’ evidence to consider whether on this evidence, there might be any evidence in support of the plaintiffs’ claim. I have not found any. I also prefer Mr Daniel Wong’s account of events to that of Mr Ng’s, Mr Ong’s or Mr Poon’s as I find Mr Wong both from his demeanour and from the manner in which he answered questions put to him in cross-examination in contrast to that of Mr Ng, Mr Poon and Mr Ong to be a more reliable and credible witness. I accept Mr Wong’s evidence that the plant was handed over to the plaintiffs duly tested and commissioned to the plaintiffs’ satisfaction on 25 January 1992, that he did not amend the handover letter and that the warranty period commenced on 25 January 1992 and terminated on 24 January 1993, that when the chiller compressor broke down, it was outside the warranty period and that the problems occuring at the plant including the breakdown of the chiller room compressor were not caused by the defendants but by either poor or no maintenance by the plaintiffs.
I further accept the evidence of the defendants’ expert witnesses, viz:
(a) Mr Lee Ah Kow whose view was that the problems complained of by the plaintiffs were attributable to the environmental pollution existing at the premises and that the close proximity of the chicken coops to the cooling towers resulted in fine chicken feathers and fine particles of chicken droppings in the air being sucked into the cooling towers causing in turn the water in the towers to become acidic and that the acidity in turn caused the condenser pipes to corrode, resulting in the gas in the pipes escaping, and enabling water to enter the pipes. It was his further evidence that this then resulted in water entering the compressors, and through the compressors, the refrigeration system.
(b) Miss Elisabeth Lee whose evidence was that prolonged exposure by galvanised as well as copper items to water in which chicken feathers and droppings were present resulted in these items having varying degrees of corrosion. It was also her view that condensation of acidic vapours/fumes on such items or the dripping of acidic water droplets on such items would in all probability cause corrosion albeit not instantaneously but over a prolonged period of time.
The plaintiffs further pleaded "res ipsa loquitur" but I am unable to see how this doctrine can apply in the particular circumstances of this case where the cause is ascertained or ascertainable : see Bolton v Stone [1951] 1 AER 1078 where Lord Porter (at page 1081 of his judgment) said :
"I am not assisted by any reliance on the doctrine of "res ipsa loquitur". Where the circumstances giving rise to cause of the accident are unknown, that doctrine may be of great assistance, but where, as in the present case, all the facts are known, it cannot have any application."
I turn next to the defendants’ counterclaim. Except for two invoices numbered DF/INV/92170 and DF/INV/92190 totalling S$1,540.00, all the other invoices were raised between 12 February 1993 and 22 April 1993 a period during which Mr Daniel Wong himself says the defendants undertook the work of repairing the compressors and condensers and, by implication, related works on their own account and for reasons of goodwill. As for DF/INV/92170 and DF/INV/92190, the undisputed evidence is that the fourth fan coil was never installed by the defendants and it was for this reason the defendants were prepared to set off the amounts due under these two invoices against the cost of this fourth fan coil. I fail to see for these reasons how a claim based on these two invoices and the remaining invoices can succeed.
In these circumstances, the plaintiffs’ claim against the defendants is dismissed and the defendants’ counterclaim against the plaintiffs is also dismissed.
I would add that had the plaintiffs established their claim on a balance of probabilities, and how the problems in the plant were caused by the defendants’ negligent installation and poor maintenance, I would have been prepared to accept Alpha Celsius Pte Ltd’s repair or rectification bill of S$108,209.10 as a sum properly incurred by the plaintiffs. As for the balance of the plaintiffs’ claim for the cost of the ice blocks, I would not have been prepared to accept it as there was no satisfactory evidence that their purchase was caused by the plant’s breakdown.
Similarly had I not come to the conclusion that the defendants had no basis for their counterclaim, I would have allowed the claim for all the invoices raised in 1993 totalling S$70,800.00.
I will hear parties on costs.
Dated the 3rd day of June 1997.
CHRISTOPHER LAU JC
Solicitors : M/s Toh & Co.
M/s S Gunaseelan
Toh Peng Ann for the plaintiffs
S Gunaseelan for the defendants