SGS-Thomson Microelectronics Pte Ltd v Regional (Far East) Electronics Pte Ltd and Another
[1997] SGHC 158
Suit No 39 of 1995
C R Rajah JC
07 June 1997
Judgment:
GROUNDS OF DECISION
1. The Plaintiffs are and were at all material times the manufacturers, importers and exporters of semi conductor components. The Plaintiffs entered into a distributorship agreement with the 1st Defendants dated 1/1/92 ("the distributorship agreement") appointing them as one of the Plaintiffs’ non- exclusive distributors within the ASEAN region. The distributorship agreement provided, inter alia, as follows:-
Clause 6 (c) : Terms of payment are sixty (60) days net from shipment.
Clause 13 (c) : In the event of the breach of any of the provisions of this Agreement by one party ... such party shall be in default, and the other party at its election may terminate immediately this Agreement upon giving of written notice to the party in default.
Clause 16 : ...... . Any amendment hereto (excepting SGS-THOMSON’S Distributor Costs Price List, SGS-THOMSON’s Standard Sales Order Terms and Conditions or SGS-THOMSON’S Distributor Sales Policy), must be in writing and signed by an authorised officer or representative of SGS-THOMSON and DISTRIBUTOR.
2. The 2nd Defendant was at all material times the managing director of the 1st Defendants. The only other director was his wife, Madam Heng Kwee Choo ("Mdm. Heng"). They were the only 2 shareholders of the 1st Defendants, each having a 50% shareholding interest. In consideration for the Plaintiffs supplying goods on credit to the 1st Defendants, the 2nd Defendant had by a guarantee and indemnity in writing ("the Guarantee") agreed to be answerable and responsible to the Plaintiffs for due payment of all goods supplied by the Plaintiffs to the 1st Defendants.
3. The Plaintiffs’ claim against the 1st Defendants was for the sums of US$395,459.74 and $469,049.26 being the balance due on the price of goods sold and delivered by the Plaintiffs to the 1st Defendants for which the 1st Defendants failed to make payment. This balance was arrived at after setting-off a stock adjustment rebate of US$99,453/- and cash rebates of US$1,159.92 and $1,002/- due to the 1st Defendants. The Plaintiffs also claimed interest on their claim and costs. The Plaintiffs’ claim against the 2nd Defendant was to indemnify them under the Guarantee for the amount of their aforesaid claim against the 1st Defendants. The Plaintiffs obtained summary judgment against the 2nd Defendant and upon his failing to make payment, they made him a bankrupt.
4. The 1st Defendants originally denied liability on the Plaintiffs’ claims. At the trial, however, they admitted that they had yet to pay the price of goods sold and delivered to them amounting to US$496,054.66 and $470,051.26 as claimed by the Plaintiffs. The 1st Defendants however, said that there was more monies due to them from the Plaintiffs which should be set-off against the Plaintiffs’ claims than the US$99,453/-, US$1,159.92 and $1,002/- credited to them by the Plaintiffs. The 1st Defendants had returned the Plaintiffs some goods purchased from them. The Plaintiffs credited the 1st Defendants for the purchase price of these goods less 20%. The Defendants say they should have been credited with the full purchase price. The 20% deducted amounted to US$65,132.96 plus $37,580.59. The 1st Defendants also claimed there was monies due to them from the Plaintiffs for the 1994 calendar year under 2 incentive schemes agreed to between them and the Plaintiffs known as the stock adjustment rebate scheme ("SAR") and the budget incentive scheme ("BIS"). Although the Plaintiffs had credited the 1st Defendants with US$99,435/- under the SAR, this was less than what was due. No payment under BIS was made, although such payment was due. The 1st Defendants therefore claimed that the amount of the 20% deducted and the SAR and BIS monies due to them should be set-off against the Plaintiffs’ claims.
5. The terms of the SAR and BIS for the 1994 calendar year are set out in a letter dated 25/2/94 ("the 25/2/94 letter") prepared on the Plaintiffs’ letterhead and signed by both the Plaintiffs and the 1st Defendants in confirmation and acceptance. Under the SAR, the Plaintiffs would give the 1st Defendants a rebate each calendar year amounting to 1.5% of the total net billings by the Plaintiffs to the 1st Defendants for that year. Under the BIS, the Plaintiffs would fix a net billings target for the 1st Defendants for each calendar year. Should the Plaintiffs exceed that target, the Plaintiffs would give the Defendants an incentive payment computed on an agreed formula. The 25/2/94 letter fixed the 1st Defendants’ net billings target for 1994 at US$7 million and provided that the 1994 BIS would be computed on the following formula. If the net billings exceeded US$7 million, the 1st Defendants would be entitled to an incentive payment of 1% of the amount of all net billings between US$7 and 8 million, 2% of that between US$8 and 9 million, 3% of that between US$9 and 10 million and 4% of anything exceeding US$10 million. The SAR and BIS payments for each year would be credited to the 1st Defendants in January of the following year.
6. The 25/2/94 letter also confirmed that the Plaintiffs would provide the 1st Defendants with a credit line of up to US$1 million for their purchase of goods from the Plaintiffs. The 1st Defendants claimed that in breach of such agreement, the Plaintiffs had refused to supply goods to them on this credit line after 28/10/94. They also claimed that the Plaintiffs had failed to provide them with sales aids, data sheets and various other documentation and information as required under the distributorship agreement. They further alleged that the Plaintiffs conspired with the 2nd Defendant and others to injure the 1st Defendants by wrongfully seeking to divert the 1st Defendants’ business away from the 1st Defendants and to prevent the 1st Defendants from continuing to do business as the Plaintiffs’ distributors. By reason of all these breaches and this conspiracy the 1st Defendants claimed to have suffered damages which they said exceeded any balance monies due from them to the Plaintiffs for the goods sold and delivered. The 1st Defendants counterclaimed for these damages.
7. From the evidence in this case, I find the term in the distributorship agreement giving the 1st Defendants 60 days from date of delivery within which to pay for the goods and the credit line of US$1 million established in the 25/2/94 letter to be complementary. They show the payment arrangements agreed between the parties to be as follows. The Plaintiffs would supply the 1st Defendants with goods on 60 days payment terms provided that the total purchase price of the goods supplied did not exceed US$1 million. All these goods had to be paid for within 60 days. The US$1 million credit line was meant to apply only to goods which remained unpaid for less than 60 days from delivery. The 1st Defendants could not use this credit line to cover any outstandings in respect of goods which remained unpaid for more than 60 days. It was of course open to the Plaintiffs to allow the 1st Defendants to purchase goods on 60 days payment terms even where the US$1 million limit was exceeded. However, this was purely at the Plaintiffs’ option. The 1st Defendants only had a contractual right to require the Plaintiffs to supply on 60 days payment terms if the US$1 million credit limit was not exceeded. There was a suggestion by the 1st Defendants that the parties had agreed subsequent to the 25/2/94 letter to increase the US$1 million to US$1.2 million. This suggestion was not seriously pursued and in any event, I find that there was no such agreement.
8. By July 1994 because of correspondence received from Mdm. Heng and conversations between representatives of the Plaintiffs and the 2nd Defendant, it became apparent to the Plaintiffs that the 1st Defendants were having internal management problems because of differences between the 2nd Defendant and Mdm. Heng. However, the 1st Defendants continued to make payments for their purchases on time and the conduct of their account with the Plaintiffs remained satisfactory for at least up to August 1994.
9. On 14/10/94, the state of the Plaintiffs’ account with the 1st Defendants was as follows. US$1,564.804.12 worth of goods had been supplied and remained unpaid. Of this, US$201,374.19 plus $10,339.66 (say US$6,986.27) amounting in all to US$208,360.46 was unpaid for more than 60 days. In failing to pay for the over 60 days goods, the 1st Defendants were in breach of the distributorship agreement. The balance US$1,356,443.66 was unpaid for less than 60 days. Although this exceeded the US$1 million credit line, the credit line could not have been exceeded without the approval of the Plaintiffs. There was therefore no breach of contract by the 1st Defendants in exceeding the US$1 million credit line. So long as these goods were paid for within 60 days of delivery, the 1st Defendants would not be in breach of contract with regard to them.
10. There was a meeting on 14/10/94 between the Plaintiffs’ Director of Asia-Pacific Distribution Mr. Stephen Cheung, the Plaintiffs’ Company Secretary and Treasurer Mr. Charlie Loh Sai Way and the Plaintiffs’ Sales Manager Mr. Nino Andrin and the 2nd Defendant and Mdm. Heng over lunch at a restaurant. At this meeting the parties discussed matters relating to their business dealings. The Plaintiffs allege that in the course of these discussions the parties agreed, inter alia, on 2 matters. Firstly, that the 1st Defendants would return to the Plaintiffs some of the goods they had purchased from the Plaintiffs but which the 1st Defendants found difficult to sell on to their customers. The Plaintiffs would credit the 1st Defendants’ account with them for the price at which the 1st Defendants had purchased these goods from them less a 20% re-stocking charge. In effect this meant that the Plaintiffs would credit the 1st Defendants with only 80% of the purchase price of these goods. Secondly, until such time as the 1st Defendants could improve their financial position, all further goods would only be supplied to them on a cash on delivery ("COD") basis. After 14/10/94, the Plaintiffs were only prepared to supply goods to the 1st Defendants on a COD basis.
11. Following this meeting the 1st Defendants returned some goods to the Plaintiffs which after the 20% deduction had a value of US$260,531.84 plus $150,332.35. The Plaintiffs credited the 1st Defendants’ account with these amounts on 28/10/94. The 1st Defendants said that only some of the goods returned were slow moving. The rest were not and the 1st Defendants could have sold them for at least their purchase price. They say they would only have agreed to return the slow moving goods and even then only at the full purchase price. As for the rest, they say they were forced by the Plaintiffs to return these goods as the Plaintiffs required them to return all goods for which they did not have confirmed purchase orders from their customers. Again, they should be credited with at least 100% of the purchase price of these goods.
12. Following the return of these goods and the crediting of the 1st Defendants’ account with 80% of the purchase price thereof on 28/10/94, the 1st Defendants’ outstandings to the Plaintiffs were reduced to US$741,116.53. Of this amount, US$121,541.79 was more than 60 days overdue. At no time after 28/10/94 did the 1st Defendants’ total outstandings to the Plaintiffs exceed US$814,000/-.
13. The 1st Defendants also denied that they had agreed to make their purchases after 14/10/94 on a COD basis. They claimed that once their credit exposure to the Plaintiffs had been brought below the US$1 million ceiling, the Plaintiffs were contractually bound to supply goods to them on credit so long as their total credit exposure did not exceed US$1 million. By refusing to do so they said the Plaintiffs were in breach of the terms of the 25/2/94 letter and the 1st Defendants’ counterclaimed for damages arising from such breach.
14. I do not accept the 1st Defendants’ claim that the Plaintiffs had forced them to return the goods at only 80% of the purchase price value. I also do not accept the 1st Defendants’ claims that they could have sold some of the returned goods at not less than their purchase price. If they could, they would have done so; there was nothing stopping them. I accept that the Plaintiffs pressed them at the 14/10/94 meeting to bring their below 60 days outstandings within the US$ 1 million credit line and to pay all outstandings of more than 60 days. The 1st Defendants did not have the means to do so unless the Plaintiffs were prepared to take back some goods and set-off the value thereof against the 1st Defendants’ outstandings. The Plaintiffs were prepared to do so but only at a 20% discount on the purchase price. The 1st Defendants might not have been happy about this but they agreed. I therefore find that the Plaintiffs were entitled to credit the 1st Defendants for only 80% of the purchase price of the returned goods. The Defendants’ claim that the balance 20% should be set-off against the Plaintiffs’ claims fails.
15. The situation with regard to the COD sale issue is somewhat different. The 1st Defendants say they would never have agreed to pay for all future purchases on a COD basis as they would not have been able to carry on their distributorship business if they had to pay cash up front for all their purchases especially as they had to give some credit payment terms to their customers. Furthermore, if the Plaintiffs would only supply goods on COD terms as opposed to the 60 days payment terms provided for in the distributorship agreement, then under Clause 16 of the distributorship agreement this amendment to the payment terms from 60 days to COD had to be in writing signed by authorised representatives of both parties. No such amendment in writing was signed.
16. When they opened their case, the Plaintiffs’ position was that orders for goods exceeding the credit limit of US$1 million were not subject to the credit arrangements extended under the 25/2/94 letter and therefore the Plaintiffs were entitled to impose a COD requirement in respect of such orders. Mr.Cheung’s evidence is that when he told Mdm. Heng and the 2nd Defendant at the 14/10/94 meeting that the Plaintiffs would not extend any more credit to the 1st Defendants, what he meant was that he would not be prepared to supply any more goods on credit to the 1st Defendants until they had brought their credit exposure below the US$1 million limit. Once this was done, he said the Plaintiffs would be prepared to continue extending credit to the 1st Defendants i.e. selling goods on 60 days payment terms up to US$1 million mark.
17. This position accorded with the provisions of the distributorship agreement and the 25/2/94 letter. The Plaintiffs were entitled to require the 1st Defendants to purchase on COD terms until the 1st Defendants’ total outstandings were brought to below US$1 million. However, once the 1st Defendants did so, and they had done so by 28/10/94, the Plaintiffs were not entitled thereafter to require them to purchase only on COD terms. It is true that although the 1st Defendants’ outstandings were well below the US$1 million mark by 28/10/94 when they stood at US$741,116.53, US$121,541.79 of this amount was unpaid for more than 60 days. This meant that the 1st Defendants were in breach of the distributorship agreement as all payments had to be made within 60 days. This would have entitled the Plaintiffs to terminate the distributorship contract for this breach, if they chose to. But the Plaintiffs did not choose to do so. The distributorship agreement therefore continued to subsist and so long as it did the Plaintiffs were bound to comply with its terms. This meant they were bound to supply goods to the 1st Defendants on 60 days payment terms so long as the total amount outstanding on the 1st Defendants’ account with them did not exceed US$1 million.
18. As the hearing progressed, the Plaintiffs argued that they were entitled to demand payment on COD terms even after the 1st Defendants’ outstandings were brought below the US$1 million level. This was, they say, because the Plaintiffs had agreed to it. I find there was no such agreement. All Mr. Cheung required of the 1st Defendants at the 14/10/94 meeting was to pay for new orders on COD terms so long as the amount of their outstandings was above US$1 million. The question of the 1st Defendants having to agree to purchase on COD terms even after the total outstandings were brought to below US$1 million would not even have arisen at the 14/10/94 meeting. Any agreement by the 1st Defendants to COD terms would only have been to do so for so long as the US$1 million limit was exceeded. In any event, any amendment of payment terms from 60 days to COD would have to be in writing signed by both parties. I find there was no agreement that all purchases after 14/10/94 would be on COD terms even after the 1st Defendants’ outstandings were brought below US$1 million and even if there was, it was not binding on the parties unless made in writing and duly signed by both parties. No such amendment was agreed to in writing.
19. The Plaintiffs say that the fact that the 1st Defendants had paid for various goods delivered between 14/10/94 and 8/11/94 on a COD basis is evidence of the fact that the 1st Defendants had agreed to COD terms. As for those goods delivered between 14/10/94 to 28/10/94, the 1st Defendants could not object to the COD terms as their outstandings exceeded US$1 million credit limit. After 28/10/94, the Plaintiffs could have objected. But if they wanted the goods, as they must have, and the Plaintiffs refused to supply the same other than on COD terms, the 1st Defendants would have had to accept the COD terms to get the goods. In the circumstances, I do not consider the fact that the 1st Defendants accepted delivery of and paid for some goods between 29/10/94 and 8/11/94 on a COD basis, a period of 11 days, as being of much significance in establishing that the 1st Defendants had agreed that all goods supplied by the Plaintiffs after 14/10/94 would be paid for on a COD basis even after the 1st Defendants’ outstandings to the Plaintiffs were brought below the US$1 million mark.
20. I therefore find that the Plaintiffs were in breach of contract in refusing to supply the 1st Defendants with goods on the usual 60 days payment terms even though the 1st Defendants had brought their outstandings to below the US$1 million mark, which they did by 28/10/94. I accordingly find that the Plaintiffs were in breach of contract in this regard from 29/10/94 onwards. When I delivered my decision on this case to the parties on 2/5/97, I was asked to determine how long this breach continued so as to facilitate the assessment of damages before the Registrar. I find that this breach continued until the distributorship agreement was duly terminated by the Plaintiffs on 14/12/94 by the Plaintiffs’ notice of termination given to the 1st Defendants by the Plaintiffs’ solicitors’ letter of the same date.
21. The Plaintiffs’ solicitors’ letter of 14/12/94 determining the distributorship agreement did so on the grounds, inter alia, that some of the goods supplied to the 1st Defendants had remained unpaid for more than 60 days after delivery. The Plaintiffs contended that this amounted to, inter alia, a breach of the 60 days payment terms in Clause 6(c) of the distributorship agreement and they were therefore entitled to terminate the agreement under the provisions of Clause 13(c) of the agreement. I accept this contention and as there were goods supplied to the 1st Defendants which had remained unpaid for more than 60 days as at 14/12/94, the termination was duly made.
22. The 1st Defendants dispute that the Plaintiffs could so terminate the contract because they claim it was the Plaintiffs’ own breach in failing to supply goods on 60 days payment terms after 28/10/94 that caused the 1st Defendants to be unable to meet their financial obligations to the Plaintiffs under the distributorship agreement. I do not agree. There is no evidence that this was so. Such evidence as there is points the other way. As on 14/10/96, at which time the Plaintiffs were clearly not in breach, US$208,360.46 remained unpaid for more than 60 days. On 28/10/96, when the Plaintiffs were not yet in breach, and even if they were the effect thereof would hardly have had time to make itself felt on the 1st Defendants’ financial position, US$121,541.79 remained unpaid for more than 60 days. By 15/11/96 the unpaid amount for over 60 days goods had risen to US$271,170.05 and remained at that figure through to 14/12/96 when the Plaintiffs gave notice of termination of the distributorship agreement. Prior to this termination notice the Plaintiffs’ solicitors had sent a letter to the 1st Defendants dated 3/12/94 demanding payment of monies owing by the 1st Defendants to the Plaintiffs within 7 days. No such payment was made.
23. With regard to the 1st Defendants’ claim that the Plaintiffs breached their obligation under the distributorship agreement to provide the 1st Defendants with "sales aids, data sheets, application notes, etc.", the 1st Defendants have not satisfied me on the evidence that there was any such breach. They have also not satisfied me that the Plaintiffs breached any obligation the Plaintiffs might have under the distributorship agreement to supply the 1st Defendants with general bulletins and price schedules and to keep the 1st Defendants informed on the Plaintiffs’ "current recommended resale and Distributor Cost Price List". Any request made in relation to these matters by the 1st Defendants’ letter to the Plaintiffs dated 9/12/94, receipt of which by the Plaintiffs is date-stamped 12/12/94, was made after the Plaintiffs’ letter of demand of 3/12/94, which went unheeded, and just before the Plaintiffs terminated the distributorship agreement on 14/12/94. The 1st Defendants were themselves in breach of the distributorship agreement throughout this time and the Plaintiffs were well within their rights to ignore this request as they were in the process of terminating the distributorship agreement for such breach which they did on 14/12/94.
24. On their conspiracy counterclaim against the Plaintiffs, the 1st Defendants admit that they have no direct evidence of conspiracy and ask the Court to infer that there was a conspiracy between the Plaintiffs and the 2nd Defendant and/or others to injure the 1st Defendants from the following circumstances:-
(a) The 2nd Defendant was setting up a company of his own with a name, Regional Electronics Pte. Ltd. ("REPL"), very similar to that of the 1st Defendants and was trying to take over the distributorship for the Plaintiffs’ products from the 1st Defendants.
(b) There was a close relationship between the 2nd Defendant and Mr. Peter Lau Ai Wah ("Mr. Lau") the Plaintiffs’ Asia-Pacific Distribution Manager and perhaps other employees of the Plaintiffs.
(c) The fact that the 2nd Defendant sent Mr. Lau a draft of a letter to be sent to the Plaintiffs on REPL’s letterhead stating that from 1/7/94 onwards REPL would be taking over the 1st Defendants’ business operations.
(d) The Plaintiffs’ continued imposition of COD terms even after the 1st Defendants’ outstandings had been brought below the US$1 million mark.
(e) The Plaintiffs forcing the 1st Defendants to return saleable stock to the Plaintiffs at only 80% of the purchase price.
25. Although there was evidence that the 2nd Defendant was planning to take over the 1st Defendants’ distributorship for REPL, there was no sufficient evidence to satisfy me that the Plaintiffs or any of their officers were party to this plan. They may have known of it and may even have not stood in the way of the transfer of such a distributorship if the 2nd Defendant was able to reach some arrangement with Mdm. Heng in this regard. But I am not satisfied that the Plaintiffs or any of their employees did anything unlawful or improper in this regard. I also find no evidence that there was anything "special" in the 2nd Defendant’s relationship with Mr. Lau or any of the Plaintiffs’ other employees which would lead me to infer that any of them would go out of their way to assist the 2nd Defendant in any unlawful or improper design. I cannot therefore draw the inferences suggested by the 1st Defendants and find no conspiracy as alleged by the 1st Defendants to which the Plaintiffs or any of their employees was a party.
26. Finally, I deal with the 1st Defendants’ claim that the payment due to them under the 1994 SAR was more than the US$99,435/- credited to them by the Plaintiffs and that they were entitled to some payment under the 1994 BIS whereas the Plaintiffs said they were entitled to none. In order to determine what these SAR and BIS payments should be, it is necessary to establish what the 1st Defendants’ net billings for 1994 were.
27. Both parties agree that the 1st Defendants’ 1994 gross billings i.e. the total invoiced value of all goods purchased by the 1st Defendants from the Plaintiffs in 1994 amounted to US$7,457,390.94. As some of these goods were from time to time returned to the Plaintiffs for various reasons, and the Plaintiffs would credit the 1st Defendants’ account for the price of these returned goods, the total amount of these credits would have to be deducted from the gross billings figure to arrive at the net billings amount. Both parties agreed that 8 credit notes totalling US$300,360.58 issued by the Plaintiffs to the 1st Defendants should be deducted from the gross billings figure when computing the amount of the 1994 net billings. There is, however, a dispute between the parties as to whether 7 other credit notes issued by the Plaintiffs to the 1st Defendants in 1994 should be deducted from this gross billings figure for the purpose of determining the 1994 net billings figure.
28. 3 of these 7 disputed credit notes were issued in January 1994 ("the January credit notes") in relation to some goods sold and invoiced to the 1st Defendants in 1993 but returned to the Plaintiffs in January 1994. The Plaintiffs took these goods back at the price at which they were sold to the 1st Defendants and issued credit notes in January 1994 therefor in the sum of US$51,982/-. The Plaintiffs say this amount should be deducted from the 1994 gross billings when computing the 1994 net billings. The 1st Defendants dispute this saying that, this return was in respect of goods purchased by them in 1993 and should not therefore affect their 1994 purchase figures. I find that this figure of $51,982/- should be deducted. It was the practice of the parties to take such credit notes into account in the year the credit notes were issued. The 1st Defendants had therefore received the benefit of these goods being included in their 1993 net billings for purposes of working out their 1993 SAR and BIS payments even though they were subsequently returned. This was the system the parties had accepted and there is nothing so intrinsically wrong or unfair about it that would require a Court to intervene.
29. The remaining 4 disputed credit notes totalling US$452,617.67 were all issued in October 1994 ("the October credit notes") and comprised the credit notes issued in respect of the goods returned by the 1st Defendants to the Plaintiffs following the 14/10/94 meeting. The 1st Defendants argued that these credit notes should not be deducted because the true nature of this transaction was in effect a resale of these goods by the 1st Defendants to the Plaintiffs rather than a return of goods sold by the Plaintiffs to the 1st Defendants. I do not accept this distinction. The primary purpose of the SAR and BIS was to encourage the 1st Defendants to increase their purchase of goods from the Defendants. This purpose would not be served if the price of returned goods was not deducted from the price of goods sold when computing the figure on which to base these incentive payments. That was why these incentives were based on net billings and not gross billings. The amount of US$452,617.67 should therefore also be deducted from the gross billings figure when computing the 1st Defendants’ 1994 net billings.
30. The 1st Defendants’ net billings for 1994 therefore amount to US$6,652,129.89 which is the gross billings of US$7,457,390.94 less the 8 undisputed credit notes totalling US$300,360.58, the January credit notes totalling US$51,982.80 and the October credit notes totalling US$452,617.67. The 1994 SAR payment of 1.5% of net billings is therefore US$99,786.45. This is US$351.45 more than the set-off of US$99,435/- given by the Plaintiffs for the 1st Defendants’ SAR entitlement. The Plaintiffs’ claim must therefore be reduced by this amount. As the net billings for 1994 did not reach US$7 million there was no BIS payment due to the 1st Defendants.
31. To summarise, the Plaintiffs claim against the 1st Defendants succeeds in the amounts of US$395,108.29 and $469,049.26. The 1st Defendants’ counterclaim for damages against the Plaintiffs for breach of contract in refusing to sell the 1st Defendants’ goods on 60 days payment terms even when the total outstandings of the 1st Defendants to the Plaintiffs was less than US$1 million succeeds. These damages are to be assessed by the Registrar and in this regard, the breach commenced on 29/10/94 and continued till the distributorship agreement was duly terminated by the Plaintiffs on 14/12/94. All the other set-offs and counterclaims claimed by the Defendants are dismissed. I make no award of interest on the Plaintiffs’ claims nor should there be any element of interest awarded to the 1st Defendants in relation to their damages when such damages are assessed.
32. The parties also requested on 2/5/97 that I decide whether there should be a stay of execution of the judgment in favour of the Plaintiffs pending the assessment of the 1st Defendants’ damages. In my view, a stay of execution in respect of the enforcement of $100,000/- out of the sum adjudged to be payable by the 1st Defendants to the Plaintiffs pending the assessment of such damages will be sufficient to avoid any prejudice to the 1st Defendants in this matter and I so order. This figure should not be construed in any way as an indication of my view of what the 1st Defendants’ damages should amount to. I also informed the parties that the time for filing appeals, if any, against this judgment would not begin to run until I determined the issues of how long the Plaintiffs’ breach continued and whether there should be a stay of the judgment pending assessment of the 1st Defendants’ damages. This I have done in this judgment and time in relation to any appeals will therefore start to run from the date of this written judgment.
33. On the issue of costs, the Plaintiffs shall have their costs of this action and the 1st Defendants shall have 50% of the costs of their counterclaim.
Dated the 7th day of June 1997.
C.R. RAJAH,
JUDICIAL COMMISSIONER
Solicitors: Allen & Gledhill for the Plaintiffs
Judy Loke & Cheong for the 1st Defendants
Michael Hwang with Kenneth Pereira (Allen & Gledhill) for the plaintiffs
Cheong Aik Chye (Judy Loke & Cheong) for the 1st defendants