Engineering Construction Pte Ltd v The Attorney-General and Another
[1997] SGHC 174
OS No 527 of 1992
C R Rajah JC
25 June 1997
Judgment:
The Background
1. The Plaintiffs are building contractors. By a contract in writing dated 2/3/90, The Government of the Republic of Singapore ("the Government") awarded the Plaintiffs a contract for the Reconstruction of Jalan Ahmad Ibrahim Culvert and Jurong Tidegate ("the Contract") for a total contract sum of $12,070,282.08. The commencement date of the Contract was 19/3/90 i.e. the date the Plaintiffs were to and did take possession of the Contract site ("the Site") and the completion date was 21 months later on 18/12/91. The proceedings herein by the Plaintiffs against the Government were instituted against the 1st Defendant, the Attorney-General, under the provisions of the Government Proceedings Act (Cap. 121) as representing the Government. The 2nd Defendants who were in the business of providing professional engineering services were the 1st Defendant’s consultants for the Contract and were the Superintending Officer ("SO") for the Contract. As such they were responsible for administering and supervising the Contract.
2. Clause 31 of the Contract provided for liquidated and ascertained damages ("LAD") to be payable by the Plaintiffs to the Government for delay beyond the completion date of 18/12/91 or such extended completion date as allowed by the SO. The SO had extended the contract period by 5 days to 23/12/91 on grounds of inclement weather during the Contract period up to 30/11/91. LAD was payable at $3,000/- for each day of delay until completion of the Contract.
3. Clauses 1(d) and 34(a) of the Contract provided as follows:-
"1(d) Notwithstanding any provision to the contrary in these Conditions contained, it is hereby agreed that the right to take action and/or initiate proceedings on behalf of the Government under Clauses 31, 32, 34, 35 or 40 hereof is expressly reserved to the Permanent Secretary/Director Environmental Engineering Ministry of the Environment."
"34(a) Default - If the Contractor shall make default in any of the following respects, namely:-
(i) without reasonable cause wholly suspends the Works before completion;
(ii) fails to proceed with the Works with reasonable diligence;
(iii) refuses or to a substantial degree persistently neglects after notice in writing from the Superintending Officer to remove defective work or improper materials.
then, if any such default shall continue for seven days after a notice sent by registered post to the Contractor from the Superintending Officer specifying the same, the Superintending Officer may (without prejudice to any other rights herein contained) thereupon by notice sent by registered post determine the employment of the Contractor; provided that notice hereunder shall not be given unreasonably or vexatiously and such notice shall be void if Government is at the time of the notice in breach of this Contract."
4. Clause 34(a) therefore provided two-notice system for the Government to terminate the Contract on any of the defaults (i), (ii) and (iii) set out therein. The Government would have to send a 1st notice specifying which of the 3 defaults it was relying on and if the default continued for 7 days after the 1st notice was sent, the Government could then send a 2nd notice terminating the Contract. No notice should be given unreasonably or vexatiously and any notice would be void if the Government was in breach of the Contract at the time of the notice.
5. In the course of the Contract, the Director, Environmental Engineering Department, Ministry of the Environment ("the Director") sent the Plaintiffs 3 1st notices dated 20/7/91, 1/4/92 and 18/4/92 respectively under Clause 34(a)(ii) on the grounds that the Plaintiffs had failed to proceed with the works under the Contract ("the Works") with reasonable diligence. The Director did not proceed to issue any 2nd notices i.e. notices of termination in respect of the first 2 1st notices but did so in respect of the third 1st notice of 18/4/92. This 2nd notice, which was dated 25/4/92, was posted under A.R. Registered cover to the Plaintiffs on the same day and was therefore sent 1 day before the required 7 days from the sending of the 1st notice of 18/4/92 had elapsed. A copy of the 2nd notice was given by hand to the Plaintiffs on 27/4/92 and the notice sent by A.R. Registered Post was received by the Plaintiffs on 28/4/92. The Plaintiffs treated the Government’s purported termination as an unlawful repudiation of the Contract and accepted the repudiation on 30/4/92 thereby terminating the Contract.
6. The Plaintiffs commenced the present proceedings on 9/6/92 seeking, inter alia, the following declarations:-
(a) that the Government’s 2nd notice of 25/4/92 was not issued in accordance with the provisions of Clause 34 of the Contract and was therefore null and void and the Government’s purported termination of the Contract was an unlawful repudiation and breach of contract;
(b) that the Government is liable to the Plaintiffs in damages by reason of its said unlawful repudiation and breach of contract;
(c) that the 2nd Defendants as SO are not entitled by Clause 31 of the Contract or otherwise to deduct LAD from amounts due to the Plaintiffs under the said Contract;
and the following order:-
(d) that the damages under (b) be assessed by the Registrar;
7. The 1st Defendant admitted that the 2nd notice of 25/4/92 was sent 1 day too early and therefore invalid and consented to declarations (a) and (b) and order (d) at a hearing before Judicial Commissioner Lim Teong Quee on 17/8/92. Declaration (c) was disputed. After hearing arguments, Lim JC held that LAD should not be deducted from the amounts payable to the Plaintiffs under the Contract. The learned Judicial Commissioner found that Clause 32 of the Contract provided that LAD would only be payable if 2 conditions were satisfied. The first was that the Contract remained uncompleted at the date due for completion, in this case 23/12/91. This condition was satisfied. The second was that the SO must have certified in writing that in his opinion the Works ought reasonably so to have been completed. No such certificate was given. The second condition was not met and therefore no LAD arose. The fact the SO subsequently issued such certificates on 2/9/92 did not help the Government’s case because although Clause 34 required the SO to issue these certificates, by virtue of Clause 1(d) the certificates had to be issued by the Permanent Secretary or the Director. Therefore even if ex post facto certificates issued after LAD was imposed and after the Contract was terminated could satisfy the second condition, on which issue the Court reserved its opinion, the SO was not competent to do so. Under the terms of the Contract only the Permanent Secretary or the Director were competent and they had not done so. The Court therefore granted the declaration (c) sought by the Plaintiffs.
8. Lim JC’s judgment which was delivered on 17/9/92 is reported in Engineering Construction Pte. Ltd. vs. Attorney-General [1993] 1 SLR 390. His analysis of the role, duties and obligations of the SO under the Contract set out in pg. 398 and reproduced below is relevant to the issues I will be dealing with later in this judgment:-
"The SO has many functions under the contract. Those under cl 34 have been noted. Throughout he acts as the agent of the government by whom he is appointed with responsibility expressly for the supervision and administration of the contract. The SO is not party to the contract. The parties are the government as employer and EC as contractor. In the exercise of many of his functions the SO has to form an opinion or make a decision which will determine the amount the contractor is entitled to be paid or the quality of the completed works that the employer has contracted for. In all these matters the parties enter into the contract on the understanding that the SO is the agent of the government but nevertheless will act fairly."
9. Following this judgment, the parties agreed to refer their other disputes arising out of the Contract for arbitration and agreed to appoint Dr. A. Vijiaratnam as arbitrator. They also agreed to defer the assessment of damages by the Registrar until after the arbitration. There was no dispute that as at 30/4/92 when the Plaintiffs accepted the Government’s repudiation and terminated the Contract, the Works were far from being completed. One of the issues referred to the arbitrator was the question of who was responsible for the delay in the Works insofar as it was relevant to the assessment of damages ordered. The parties also agreed to be bound by the arbitrator’s award in this regard subject to any right of appeal under section 28 of the Arbitration Act (Cap. 10).
10. In their points of claim in the arbitration the Plaintiffs set out a list of the reasons as to why the Works were delayed by events beyond their control. They claimed that for these reasons they should have been granted as at 30/4/93 an extension of time until 30/3/93 to complete the Works or, alternatively, that the time for completion of the Works was set at large.
11. The arbitrator’s award was made in writing and dated 12/10/94. His award, after considering the various claims made by the Plaintiffs for an extension of time for the completion of the Works, refused to allow any such extension. He also stated in page 55 of his award, where the Plaintiffs are referred to as "the Claimants", as follows:-
"Having considered the contentions, arguments and evidences (sic) given by both parties I am satisfied that the progress of the works was delayed by the Claimants’ default ........."
and later in page 56:-
"I therefore rule that as the delay was caused by the Claimants’ own default they must take full responsibility for carrying out the rectification works and to bear the full costs of such rectification."
The only exception was the rectification works for the de-watering chamber where the Government was ordered to pay the Plaintiffs $14,687/-.
12. Among the reasons which the arbitrator found contributed to the Plaintiffs’ delay in completing the Works were the Plaintiffs’ financial problems which the arbitrator found resulted in the unsatisfactory performance of the Plaintiffs’ sub-contractors and suppliers of materials. In this regard, it is relevant to note that the Plaintiffs were put into judicial management on 10/7/91, approximately 17 months into the Contract period of 21 months (extensions excepted). The Plaintiffs were still under judicial management when they terminated the Contract. The arbitrator also found that as at 30/4/92 when the Contract was terminated, the Plaintiffs had only completed 21% of the Works.
13. During the course of the arbitration which took place over 22 days between 26/7/93 and 3/3/94, a question of law was referred to the High Court. The Director had on 29/9/92 issued 2 letters. One extended the completion date of the Contract pursuant to Clause 32 thereof for a further 5 days to 28/12/91 by reason of inclement weather in December 1991. The other was a LAD certificate stating that in his opinion the Works ought reasonably to have been completed by 28/12/91, the extended date for completion. The Government claimed that they had by the second of these letters complied with the second condition which Lim JC’s judgment had found must be satisfied before LAD could arise. The arbitrator should therefore deduct the LAD from whatever monies he might find payable to the Plaintiffs for work done under the Contract. The Plaintiffs argued that as the Contract was terminated on 30/4/92, the Director was functus officio after that date insofar as the Contract was concerned and therefore no certificate issued by him thereafter had any effect.
14. This point of law was argued, again before Judicial Commissioner Lim Teong Qwee, and his judgment thereon is reported in Engineering Construction Pte. Ltd. vs. Attorney-General [1994] 1 SLR pg. 687. He accepted the Plaintiffs’ argument and held (at pg. 699D) that:-
"The government is not entitled to deduct or recover LAD in respect of any period during which the contractor is held by the arbitrator to have been in delay prior to 30 April 1992."
He also made (at pg. 699F) the following observation on the Government’s rights to damages in this matter which is also of some relevance to the issues considered later in this judgment:-
"Of course the government may be entitled to damages at law for the contractor’s breach for delay but that will have to be claimed and proved in the ordinary way."
15. The arbitrator’s award also valued the work done by the Plaintiffs under the Contract as at 30/4/92 to be $2,848,332.60, the materials on site to be $470,276.65, the variations to be $49,067.00 and fluctuations in a negative amount of $13,002.41 making a total of $3,354,673.84 payable to the Plaintiffs by the Defendants for work done under the Contract. This was of course, without any deduction being made for LAD or any set-off for damages as may be claimable by the Plaintiffs. As the Plaintiffs had already paid $2,807,000/- under the Contract, the arbitrator awarded the Plaintiffs the balance sum of $547,673.84 and found that each party should pay its own costs of the arbitration and that the arbitrator’s fees, the costs of preparing the award and the tape-recording and transcription costs be borne equally by the parties.
16. Following the publication of the arbitrator’s award, the parties filed various affidavits for purposes of the assessment of damages which was to be heard by a Judge in Chambers. The Government then applied for a preliminary issue be heard prior to the assessment of damages. The issue they raised was that as the arbitrator had found that the Plaintiffs were responsible for the delay of the Works and as the parties had agreed to be bound by the arbitrator’s findings in this issue, the Plaintiffs would not be entitled to anything more than nominal damages.
17. The preliminary issue raised by the Government arises from the decision of the English Court of Appeal in Maredelanto Compania Naviera S.A. v. Bergbau - Handel GmbH; The Mihalis Angelos [1971] 1 QB 164. In this case the charterers of a vessel chartered it for the purpose of carrying mineral ore from Haiphong to a port in North Europe. The charterparty provided that if the vessel was not ready to load on or before 20/7/65, the charterers had the option to cancel the charterparty. On 17/7/65, whilst the vessel was still in Hong Kong, the charterers sought to cancel the charterparty on the grounds of force majeure, claiming there was no ore available in Haiphong because of war in North Vietnam. The owners treated this as an unlawful repudiation of the charterparty, accepted the repudiation and terminated the charterparty. The owners claim for damages was referred to arbitration. The arbitrators found, inter alia, that although the charterers were not entitled to terminate the charterparty on grounds of force majeure, even if the ship had proceeded to Haiphong, she could not have been ready to load until after 20/7/65 and there was no doubt that the charterers would have exercised their option to cancel the charterparty. They accordingly held that the owners were only entitled to nominal damages. This matter was referred to the English High Court by a special case stated and reached the Court of Appeal by way of appeal therefrom. The Court of Appeal held that the charterers were in fact entitled to terminate the charterparty albeit not on the grounds of force majeure but on the breach of another condition of the charterparty by the owners. The Court of Appeal then went on to hold (and I quote from the headnote) as follows:-
"Assuming that the charterers committed an anticipatory repudiation of the contract by their purported cancellation on July 17, 1965, the owners would be entitled to damages; but because the charterers would have cancelled the contract when the vessel arrived at Haiphong, the owners would have suffered no loss from the repudiation and would only have been entitled to nominal damages."
18. In particular the Government relied on the following dictum from the judgment of Megaw L.J. in The Mihalis Angelos at pages. 209H to 210B:-
"In my view, where there is an anticipatory breach of contract, the breach is the repudiation once it has been accepted, the other party is entitled to recover by way of damages the true value of the contractual rights which he has thereby lost subject to his duty to mitigate. If the contractual rights which he has lost were capable by the terms of the contract of being rendered either less valuable or valueless in certain events, and if it can be shown that these events were, at the date of acceptance of the repudiation, predestined to happen, then the damages which he can recover are not more than the true value, if any, of the rights which he has lost, having regard to those predestined events."
19. The Government also referred to decision of the Supreme Court of New South Wales in TCN Channel 9 Pty. Ltd. vs. Hayden Enterprises Pty. Ltd. [1989] 1 NSWLR 130 which accepted the principle that where a defendant in proceedings to recover damages for breach of contract had a right under the contract to alternative methods of performance, the Court should assume that the defendant would have performed the contract in the way least advantageous to the plaintiff and most advantageous to the defendant. In making this assumption, however, the Supreme Court held that regard must be given to the facts and relevant circumstances as to avoid the assessment of damages based on a fiction that a defendant would have adopted one method of performance when the facts belie that possibility.
20. The Government maintained that in the light and circumstances of the present case and the findings of the arbitrator and on the basis of The Mihalis Angelos and the TCN Case, it can be assumed that the Government would have sent a fresh 1st notice in due form immediately after the termination on 30/4/92, i.e. later on 30/4/92 itself or so soon thereafter as possible, that the Plaintiffs were failing to proceed with the Works with reasonable diligence. It was inevitable and predestined that this default would continue for another 7 days. It could also be assumed that the Government would then duly issue as soon as possible a 2nd notice terminating the Contract. Any damages the Plaintiffs would suffer would therefore be nominal.
21. The Government also claimed that they were justified in sending the 1st notice of 18/4/92 and would have been similarly justified in terminating the Contract 7 days thereafter by a 2nd notice. However, because of an error in the method of termination, the error being that the 2nd notice was not sent after 7 days but one day earlier, the Government, which is in fact the innocent party in this matter, had inadvertently put itself in breach of the Contract. The Plaintiffs were the real guilty party. It was they who had breached the Contract by causing it to be so delayed that the Contract period of 21 months was exceeded by some 3 months although only some 21% of the Works had been completed. The Plaintiffs then took advantage of the Government’s inadvertent breach by accepting the Government’s erroneous repudiation and terminating the Contract. The guilty party was now suing the innocent party for damages for breach of contract. For this reason too the Plaintiffs should not be entitled to more than nominal damages as had the Government’s 2nd notice been sent just 1 day later, the Government’s termination would have been lawful.
22. The Plaintiffs disputed the Government’s allegations. Their first point was that the Government’s 1st notice could only be properly given if the Plaintiffs were not proceeding with the Works with reasonable diligence at the time the 1st notice was given. However slow and delayed the Plaintiffs’ performance might have been prior to the 1st notice being given, unless the Plaintiffs were not working with reasonable diligence at the time the 1st notice was given, the 1st notice was bad. In other words, past delays did not count and should be put out of mind. What mattered was whether the level of the Plaintiffs’ performance of the Contract at the time the 1st notice was given was such that the Plaintiffs were at that time proceeding with the Works with reasonable diligence or not. The Plaintiffs denied they were not proceeding with reasonable diligence when the 1st notice of 18/4/92 was given. They also disputed that they would not have been proceeding with reasonable diligence on 30/4/92 or so soon thereafter as the Government was able to issue a fresh 1st notice.
23. The Plaintiffs’ second point was that even if the Plaintiffs were not performing with reasonable diligence as at 18/4/92 or when a fresh 1st notice was issued on say 30/5/92, all this meant was that the 1st notice was properly given. It did not mean that the Government was entitled to terminate the Contract as a matter of course 7 days later. The Government could only do so if at the expiry of the 7 days the Plaintiffs were still in default i.e. still not proceeding with the Works with reasonable diligence. To be so proceeding the Plaintiffs did not have to catch up on all the past delays within the 7 days. So long as the level at which the Plaintiffs were working at the end of the 7th day was that of a contractor proceeding with reasonable diligence on the Contract, the Government could not properly issue a 2nd notice. The Plaintiffs say that they were proceeding with reasonable diligence throughout the 7 day period after the 1st notice of 18/4/92 was sent and even if they were not, they would have been doing so by the 7th day after the 1st notice of 18/4/92. The same would apply in respect of any fresh 1st notice issued on 30/4/92 or so soon thereafter as the Government was able to. They disputed that it was inevitable or predestined that the Plaintiffs would still be in default 7 days after the fresh 1st notice was sent.
24. The Plaintiffs’ third point was that it could not be assumed that the 1st notice or the 2nd notice would be issued properly. A notice might be issued too early as in the case of the present 2nd notice of 25/4/92 or even possibly too late i.e. after the 7 day default period is "spent". A 1st notice might also specify a target for the Plaintiffs to achieve by the end of the 7 day period as a measure of whether the Plaintiffs had proceeded with reasonable diligence during that period. The 1st notice of 18/4/92 did set such a target. If the target set was unreasonable, and the Plaintiffs claimed the target set in the 1st notice of 18/4/92 was unreasonable, then the 1st notice would have been given "unreasonably or vexatiously" and therefore void.
25. The Plaintiffs’ fourth point was that the Plaintiffs were not quite the innocent party they claimed to be. They were, apart from their unlawful repudiation by the 2nd notice of 25/4/92, already separately in breach of the Contract on 3 occasions. Firstly, they had refused to pay the Plaintiffs the cost of the rectification works for the de-watering chamber amounting to $14,687/- until the arbitrator held them liable therefor. This breach subsisted as at April 1992. Secondly and thirdly, the Government had delayed payment by 6 days on 2 payment certificates. Although the arbitrator had held that the amount of interest accrued for the 6 days was insignificant and not sufficient to render time for completion of the Contract at large, the Government had nevertheless not remedied their late payment by any payment of interest, even if such interest amount was insignificant. This breach too was current at April 1992. As Clause 34 expressly provided that any notice issued by the Government thereunder would be void if the Government was in breach of the Contract at the time of the notice, the 1st notice of 18/4/92 and any subsequent 1st and 2nd notices under Clause 34 would be void so long as these breaches subsisted. These breaches subsisted even up to the date of the arbitrator’s award on 12/10/94 and beyond.
26. The Plaintiffs’ fifth point was that the Government had waived any rights they may have had to rely on the Plaintiffs’ past delays as a ground for termination under Clause 34 (although not for the purposes of liquidated damages) when they accepted the Plaintiffs’ 5th revised programme for the construction of the Works submitted on 18/2/92. Under this 5th revised programme, the Plaintiffs targeted completion of the Works for 31/12/92. By accepting this revised programme the Government encouraged the Plaintiffs to commit resources into achieving this revised programme. It was therefore no longer open to the Government to rely on any delays prior to their accepting the 5th revised programme as a basis for terminating the Contract under Clause 34 or at all. If the Government wished to terminate the Contract on the basis of past delays, they should have done so prior to requiring the Plaintiffs to continue with the Works and commit additional resources in seeking to achieve the target of the 5th revised programme.
27. After hearing the parties, I found as follows:-
(a) The fact and extent of the delay in the performance of the Contract and the arbitrator’s findings that the Plaintiffs were responsible for the delay raised a prima facie case that the Plaintiffs were not proceeding with the Works with reasonable diligence as at 30/4/92;
(b) The Plaintiffs, however, had not had the opportunity to show that despite their being responsible for the delay, they were nevertheless proceeding with the Works with reasonable diligence as at 30/4/92 as this issue was not specifically dealt with by the arbitrator;
(c) Under the principles of The Mihalis Angelos, the Court could assume for the purpose of assessing damages that the Defendants would have duly given a fresh 1st notice in due form and in compliance with any required procedure as soon as was reasonably possible after the Plaintiffs’ termination of the Contract on 30/4/92 and could further assume that if the Plaintiffs continued to fail to proceed with the Works with reasonable diligence for a further 7 days thereafter, that the Defendants would duly terminate the Contract forthwith by a 2nd notice duly given in due form and in compliance with any required procedure;
(d) The fact and extent of the Plaintiffs’ delay in performing the Contract raised a prima facie case that the Plaintiffs would not be able to proceed with the Works with reasonable diligence within 7 days after being duly given the aforesaid fresh 1st notice;
(e) The Plaintiffs, however, had not had the opportunity to show that they could and would have been proceeding with the Works with reasonable diligence within 7 days of the aforesaid fresh 1st notice being duly given;
(f) The issue of whether the Government had at any time waived their right to rely on any or all of the Plaintiffs’ delay prior to 30/4/92 in performing the Contract as a basis for terminating the Contract under Clause 34 had not been determined by the arbitrator and required to be determined by the Court before it could decide whether any fresh 1st notice or 2nd Notice under (c) above could be properly effected;
(g) The Plaintiffs had not had the opportunity to adduce evidence on this issue of waiver.
28. Having made those findings, I made no order on the Government’s application for a preliminary issue to be determined and ordered instead that the Court would hear evidence on the issues referred to in (b), (e) and (g) above and also on the issue of whether the 1st notice dated 18/4/92 was duly given and whether the Plaintiffs would have been able to comply with its terms within 7 days thereof and that the Court would make its determination on those issues before deciding whether to proceed with the assessment of damages.
29. To summarise, albeit in a different order from that set out above, the issues to be determined by the Court after taking evidence were as follow:-
(a) whether the 1st notice of 18/4/92 was given in due form and in compliance with the required procedure ("the 1st issue").
(b) whether the Plaintiffs could have complied with the 18/4/92 notice within the relevant 7 day period ("the 2nd issue").
(c) whether the Government could have properly issued a fresh 1st notice immediately after the Plaintiffs’ termination of the Contract on 30/4/92 ("the 3rd issue").
(d) whether the Plaintiffs could have complied with such a fresh 1st notice within the relevant 7 days ("the 4th issue").
(e) whether the Government had at any time waived their rights to rely on any or all of the Plaintiffs’ delays prior to 30/4/92 when issuing a 1st or 2nd notice under Clause 34(a) ("the waiver issue").
30. These issues were fixed for hearing before me. The Plaintiffs’ director Mr. Ng Kim Hoe ("PW1"), one of its founder directors, testified on behalf of the Plaintiffs. He held a Professional Diploma in Building from the Singapore Polytechnic obtained in 1964 and had thereafter always worked in the construction industry. He was the Plaintiffs’ only witness. The Defendants had 2 witnesses testifying on their behalf. One was Mr. T. Gangatharan ("DW1") who was the Chief Engineer (Construction Section) of the Drainage Department of the Ministry of Environment and supervised the involvement of the Ministry of Environment ("ENV") who represented the Government in the Contract. The other was Mr. Leong Kwok Thye ("DW2") who was the managing director of the 2nd Defendants and a professional engineer and was in charge of the 2nd Defendants’ involvement in the Contract. After considering all their testimony and the documents in this case, I have found the facts to be and reached the findings as set out below.
Facts and Findings
31. The Plaintiffs through its Judicial Manager Mr. Chan Ket Teck ("the JM") presented a 5th revised programme for the completion of the Works to the Government on 18/2/92 at a meeting between officials from the ENV, the SO and the Plaintiffs. Under this revised programme the Works were targeted to be completed by 31/12/92. The Government, represented by ENV officials, selected from this programme the 1st stage of the excavation works in Sector C of the Site ("the said excavation works") as a critical activity by which to measure the Plaintiffs’ ability to work to this 5th revised programme. Under this revised programme the Plaintiffs maintained they would complete the said excavation works by 31/3/92. ENV informed the JM at this meeting that if the Plaintiffs did not complete such excavation works by 31/3/92, the Government would terminate the Contract. The JM, representing the Plaintiffs, accepted that this was reasonable.
32. On 19/3/92 the Plaintiffs submitted their revised work programme for the period 16/3/92 to 6/4/92 ("the 19/3/92 programme") to the Government. The 19/3/92 programme showed that the level of the said excavation works was then at RL 95.2. For the 3 days from 17/3/92 to 19/3/92, the Plaintiffs would be installing a 3rd level of struts and walers at RL 95.5, a level 0.3 metres above RL 95.2. These struts and walers had to be installed to support the excavation and prevent it from collapsing before further excavation could be proceeded with. The struts would extend from one side of the excavation to the other, spanning the excavation pit. There were already 2 levels of struts and walers at upper levels of the excavation. Whilst the struts and walers were being installed at each level, no excavation works should be carried out. Apart from it being dangerous to excavate deeper without the struts and walers being properly in place to support the existing excavation, the workmen and machinery involved in installing the struts and walers would impede the safe and efficient progress of any excavation works. After the Plaintiffs had completed installation of each level of struts and walers, it had to be checked and passed as having been properly installed. The party responsible for doing so in this case was an engineering company called A L Technologies (S) Pte. Ltd.
33. After the 3rd level supports were installed and passed, the 19/3/92 programme showed that the Plaintiffs would take 3 days to excavate 1.5 metres from RL 95.2 down to RL 93.7. They would then take another 3 days installing the 4th level struts and walers at RL 94.0 and a further 2 days excavating another 1.55 metres down to RL 92.15. The Plaintiffs’ own 19/3/92 programme therefore showed they needed 5 days to excavate a depth of 3.05 metres from RL 95.2 to RL 92.15 i.e. some 0.61 metres a day and 3 days to install the 4th level supports, making 8 days in all.
34. None of the excavation works after the installing of the 3rd level supports should have been proceeded with without the SO approving the Plaintiffs’ structural engineer’s design for the temporary works with regard to this excavation. The Plaintiffs had submitted this design to the SO. The SO required some amendments to the design before they would approve it but the Plaintiffs’ structural engineer refused to amend his design as required. This impasse was finally resolved only on 14/4/96. Although the Plaintiffs should not have proceeded with any further excavation works until after this approval, they did in fact excavate from RL 95.2 down to RL 94.5 before stopping work to wait for the SO’s approval of the design for the temporary works.
35. On 26/2/92, the SO wrote to the Plaintiffs reminding them of the target they were required to meet by 31/3/92. The Plaintiffs replied on 30/3/92 asking for an extension of time of 15 days to complete the said excavation works because they claimed that there were 7 days of inclement weather and that they were required to excavate deeper than had been planned and that their design for the temporary works had not been approved by the SO. The SO advised the Government against giving any such extension as there were only 5 hours of inclement weather on 1 day in the relevant period, and that the additional excavation depth involved was brought about by the Plaintiffs’ own change of mind on a design because of cost considerations. As for the design for the temporary works not being approved, the SO advised that this was caused by the Plaintiffs’ refusal to amend their design to conform with the SO’s requirements. [At the arbitration the arbitrator held that the SO was justified in not accepting the Plaintiffs’ professional engineer’s designs relating to the temporary works and that the Plaintiffs were not entitled to any extension of time for any delay in this regard.] The SO was against giving any extension because the Plaintiffs were continuing to fall further behind schedule. The SO’s opinion was that the Plaintiffs did not have the capacity or resources to complete the Works satisfactorily and they advised the Government to terminate the Contract pursuant to Clause 34(a)(ii).
36. The Director issued a 1st notice dated 1/4/92 stipulating that if the Plaintiffs failed to complete the said excavation works within 7 days from the date of the notice, they would be deemed to be not proceeding with reasonable diligence and the Government would determine the Contract. The Plaintiffs responded by their letter of 3/4/92 to the Director alleging that the 1st notice of 1/4/92 was unreasonable and/or vexatious and of no legal effect. The Plaintiffs maintained they were entitled to an extension of time for the reasons set out in their 30/3/92 letter. They now also referred to the problems arising from the cracking of bored piles used in the Works which they claimed was due to faulty or defective design by the 2nd Defendants. [This issue too was considered by the arbitrator. He found that the design of the bored piles was adequate and that responsibility for their cracking lay with the Plaintiffs who should therefore bear the full cost of the compensating piles and make good all other damage in this regard.]
37. On 8/4/92, the SO wrote to the Director in relation to the Plaintiffs’ letter of 3/4/92. The SO was still of the view that the Plaintiffs were not proceeding with reasonable diligence and that a 2nd notice should be sent terminating the Contract. The SO also enclosed details of the deployment of labour on site by the Plaintiffs for the days immediately prior to and after the 1st notice of 1/4/92 was sent. These figures showed no increase in the labour being deployed at the Site after the 1st notice was sent.
38. On 10/4/92, ENV had another meeting with the JM. Following that meeting the Director sent a letter of the same date giving the Plaintiffs another 7 days grace period to complete the required excavation works. The JM replied on 13/4/92 stating that he never requested for any grace period of 7 days. He said that what he did say at the meeting was to remind ENV of the serious delays caused by the design fault to the bored piles and the other matters raised in his letter of 3/4/92. He also rejected any imposition of a grace period and maintained that any determination of the Contract by the Government would be a breach by them and the Plaintiffs reserved their right to claim damages in such event.
39. The SO replied to the Plaintiffs on behalf of ENV by their letter of 15/4/92. They reminded the Plaintiffs that it was agreed by all those present at the meeting of 18/2/92, including the JM, that failure by the Plaintiffs to complete the said excavation works would be a sufficient reason for the Government to terminate the Contract. This target date was derived from the Plaintiffs’ own 5th revised programme submitted on that day. The SO further reminded the Plaintiffs that they had until 16/4/92 to complete the said excavation works and if they did not do so the Plaintiffs would serve a 2nd notice terminating the Contract. The SO also maintained that there was no design fault in the bored piles and informed the Plaintiffs that they had no valid basis for their claim for an extension of time.
40. The Plaintiffs failed to complete the said excavation works by 16/4/92. The Government, however, did not send a 2nd notice terminating the Contract. Instead they sent another 1st notice dated 18/4/92. All parties are agreed that by this notice the Government required the Plaintiffs to complete the said excavation works within 7 days from the date of the notice failing which the Government would deem the Plaintiffs not to be proceeding with reasonable diligence and would thereafter terminate the Contract under Clause 34(a). All parties are also agreed that when this notice was sent, the excavation level stood at RL 94.5 and for the Plaintiffs to complete the said excavation works, they would have had to complete installation of the 4th level supports at RL 94.0 and complete excavation down to a level of RL 92.3, a depth of 2.2 metres.
41. From the progress of work on the Site and the level of resources deployed, the SO remained of the view on 24/4/92 that the Plaintiffs would not be able to meet the target set. The SO’s view was that the 4th level supports had still not been fully and properly installed and that 30% of the excavation was only at RL 94.00 and 70% was at RL 93.50. The SO accordingly advised the Government by their letter of 24/4/92 to send a 2nd notice and terminate the Contract.
42. This time the Plaintiffs did so. They sent the 2nd notice dated 25/4/97 by A.R. Registered post. This letter was posted on 25/4/97 before 1:00 p.m. DW1 also asked one of the other ENV engineers involved in the Contract, Mr. Anselm Gonsalves, to contact the JM by telephone and ask him to attend at the Site at 10:00 a.m. on Monday 27/4/97 for a meeting. ENV also sent a fax to the JM at about 8:50 a.m. on 27/4/97 asking him to attend a meeting at the Site at 9:30 a.m. that same morning.
43. DW1 was at the Site from about 9:00 a.m. on 27/4/97. There was activity at the Site. He saw welders working and believed they were working to get the struts ready to allow further excavation to be carried out. He also saw other workers working or preparing to work. The JM arrived at the Site for the meeting which commenced at about 10:00 a.m. on 27/4/92. DW1 believed that he was the first person to inform the JM that the Government was terminating the Contract and he did so at that meeting and handed the JM a copy of the 2nd notice of 25/4/92. He had no reason to believe that JM knew about the termination prior to that.
44. PW1 testified that he had heard from the JM on 24/4/92 that the Contract was to be terminated on 25/4/92. The Plaintiffs did not call the JM to testify on this or any of the other issues on which the JM’s testimony might have lent support to the Plaintiffs’ case. In the light of DW1’s testimony, which I accept, I find that the Plaintiffs first learnt of the Government’s termination of the Contract at or about 10:00 a.m. on 27/4/92. The Plaintiffs only received the 2nd notice sent by A.R. Registered Post on 28/4/92.
45. DW1 also testified that when he informed the JM that the Government was terminating the Contract the JM never disputed the Government’s claim that Plaintiffs had failed to meet the target set in the 1st notice of 18/4/92. I accept this evidence which is also supported by the minutes of the meeting of 27/4/92 which has no record of any objection by the JM to this claim. Such an objection would have been expected if the Plaintiffs believed they had met the target. Nor does the Plaintiffs’ letter of 30/4/92, which terminates the Contract by accepting the Government’s wrongful repudiation, claim that the Plaintiffs had met the target.
46. The Plaintiffs say that the 1st notice of 18/4/92 was not in due form because it required the Plaintiffs to comply with its requirements within 7 days from the date of the notice when under the provisions of Clause 34, they should have been given 7 days from date of receipt of the notice within which to comply. In Re Arbitration between Stewardson Stubbs & Collett Pty. Ltd. and Bankstown Muncipal Council [1965] NSWR 161, the Supreme Court of New South Wales construed clause 19(a) of a building contract which is pari materia with the present Clause 34(a) except that the period between the 2 notices there was 14 days whereas in the present case it is 7 days. The provision in clause 19(a) relating to the period of notice is as follows:-
"......... and if he shall continue such default for 14 days after a notice by registered post specifying the default has been given to him ........ ."
47. The Court considered the question of when the period between the 1st and 2nd notices commenced. Was it the date of posting, the date of receipt, the day after the date of posting or the day after the date of receipt? The Court found that the period commenced on the day after posting and Moffit J. in his judgment said (on pg. 1676) as follows:-
"The requirement of registered post is a strong factor in favour of an interpretation that time runs from the date of posting. The operative word is "given" not "received". The words "after", "by registered post" and "given" lead to the conclusion that the first day of the period for the continuance of default is the day which follows the date of posting of the notice."
48. The relevant provisions of Clause 34(a) of the Contract are materially no different from those of the clause 19(a) construed by Moffit J. but where Clause 34(a) uses the word "sent", clause 19(a) uses "given". If anything, "sent" lends even stronger support for Moffit J.’s interpretation than does "given". I accept and apply Moffit J.’s reasoning to this issue and find that the 7 day period commences on the day after posting. As the notice was posted on 18/4/92, the period of 7 days would commence on 19/4/92 and end on 25/4/92. A period of "7 days from the date of the notice" as specified in the 1st notice of 18/4/92 would also end on 25/4/92. I therefore do not accept the Plaintiffs’ contention that the 1st notice of 18/4/92 was bad simply because it required the Plaintiffs to achieve the target within 7 days of the date of the notice.
49. The Plaintiffs also say that Clause 34 was not properly invoked by the 1st notice of 18/4/92 because the target set thereunder as a measure of reasonable diligence, i.e. the completion of the said excavation works, was not achievable even by a reasonably diligent contractor. I do not agree. The reasonableness of this target has to considered in the context of the relevant facts and circumstances. They are as follow:-
(a) The Plaintiffs had by their own 5th revised programme of 18/2/92 stated this target would be met by 31/3/9.
(b) By 31/3/92, however, the Plaintiffs still had 2.2 metres to excavate and the 4th level of struts and walers to install. They could not proceed with the work because their design for the temporary works had not been approved. But it was the Plaintiffs’ own fault that the design was not approved.
(c) The design was finally approved on 14/4/92. The Plaintiffs could thereupon have proceeded with the said excavation works immediately. They did not.
(d) When the Plaintiffs issued the 1st notice of 18/4/92, the 4th level of struts and walers and 2.2 metres of excavation remained to be done to complete the said excavation works. The Plaintiffs’ own 19/3/92 programme showed they could complete installation of the 4th level supports in 3 days and excavate 3.05 metres in 5 days which is a rate of 0.61 metres a day. At this rate the Plaintiffs should be able to excavate 2.2 metres in 3.6 days. By their own timetable the Plaintiffs should have been able to complete the said excavation works in 6.6 days which was less than the 7 days given.
50. In Re Stewardson Stubbs Moffit J. also considered the meaning of "proceeding with the work with reasonable diligence" and what was meant by the provision that the contractor must "continue to default" during the period between the 2 notices. He also considered the issues by the following questions: Did proceeding with reasonable diligence require the contractor to catch up or rectify all past consequences of lack of reasonable diligence? Or could a contractor simply by ensuring he was proceeding with reasonable diligence on the last day of the notice period frustrate the employer’s threatened dismissal and thereafter revert to his previous lack of diligence? He concluded as follows (at pg. 1674):-
"....... the substantial question would be whether the builder had in the 14-day period, in a substantial and commercial sense, and not in a nominal or colourable way ...... proceeded with the contract with reasonable diligence and competence."
51. I accept this practical test. Whether or not a contractor is performing with reasonable diligence is a matter which a Court has to determine in accordance with the facts and circumstances of each case. On the facts and circumstances of this case the target of completion of the said excavation works set by the Government to measure whether the Plaintiffs were proceeding with reasonable diligence or not, is not at all unreasonable. The Plaintiffs failed to meet the target. Unless they can show that their failure was caused by the unreasonable conduct of the Government or the Government’s agents, and they have not so shown, their failure shows they were not proceeding with the work with reasonable diligence. What I do find unreasonable was the Plaintiffs’ conduct. Instead of concentrating their efforts and resources on meeting the target, they responded to the Government’s requirements with petulance and non-cooperation. Their whole attitude towards the discharge of their responsibilities and obligations under the Contract was disappointing.
52. From the evidence before me of the Plaintiffs’ performance of the Contract until it was terminated, I also find that if the Government issued a fresh 1st notice under Clause 34(a)(ii) as soon as possible after the Plaintiffs terminated the Contract on 30/4/92, the Plaintiffs would not have been able to comply with such notice and be proceeding with the Works with reasonable diligence within 7 days of such notice being sent.
53. Also in issue was the question whether the Plaintiffs could have worked on Sundays and Public holidays and on double shifts if they wished to do so. The Government’s position was that the Contract provided that the Plaintiffs could not do so without the SO’s permission. Because the Government had decided to terminate the Contract owing to the Plaintiffs’ poor performance and sent a 1st notice as a first step towards such end, the Government argued that the SO would never agree to allow the Plaintiffs any extra working time during the notice period. To do so would only help the Plaintiffs achieve the target and frustrate the Government’s intention to terminate the Contract. The Government claimed that on the authority of the TCN Case the SO was entitled to refuse such permission.
54. The Plaintiffs’ position was that although the SO was the Government’s agent to administer the Contract the SO had a duty to act fairly. Simply to deny the Plaintiffs’ request to work on holidays and double shifts on no other grounds than to frustrate any chance of the Plaintiffs’ achieving the target would not be acting fairly. This would be especially so where the evidence showed that the SO was aware that the Plaintiffs had in the past worked on Sundays and had not objected to it. Also where the JM had evinced an intention to work double shifts the SO had again raised no objection although aware of this intention. It could not therefore be assumed that the SO would not have granted such Petition. DW1 had also confirmed that the Government encouraged the idea of the Plaintiffs working longer hours to hasten the completion of the Works. As for the TCN Case, the Plaintiffs maintained that although it did support the fiction that a defendant would perform the contract most advantageously to himself and least advantageously to the plaintiff, it did warn the Court to avoid a finding based on this fiction when the actual facts and circumstances belied this fiction.
55. I accept the Plaintiffs’ argument and find on the evidence that the SO would not have objected to the Plaintiffs working on Sundays and double shifts. I find therefore that the Plaintiffs may have worked on Sundays and double shifts to achieve the target set in a 1st notice. However, I also find no reason to believe that the Plaintiffs would have worked any double shifts to comply with a 1st notice in general and the 1st notice of 18/4/92 in particular . They only worked a partial double shift once, when they were pouring of concrete in an earlier stage of the Contract which had nothing to do with the said excavation works. Even then they stopped work before mid-night. They never worked any double shifts to comply with the 1st notice of 18/4/92 nor indeed with respect to any works at all in Sector C of the Site.
56. There was also a dispute between the parties as to how much was left to be excavated when the Government took possession of the Site from the Defendants on 27/4/92. The Plaintiffs had a firm of licensed surveyors, Wang Surveyors, to survey the excavation depth on 28/4/92. This survey ("the Wang Survey") was not a joint survey in that it was not done with the consent or knowledge of the Government or the SO. According to the Wang Survey there was an average depth of 0.494 metres still to be excavated to reach the target depth of RL 92.3. At the arbitration the Government agreed that the arbitrator could adopt the figures shown in the Wang Survey for the purpose of assessing the value of work done by the Plaintiffs. The Government, however, maintained before me that this did not mean they agreed these figures were correct.
57. The Government relied on a survey done by another surveyor. This survey, which was referred to as "the Ohin Survey", was made on or about 17/9/92 by which time the excavation area had long been flooded with water in order to maintain its stability and to help prevent it from collapsing. The Ohin Survey showed that the average depth left to be excavated was 1.35 metres. The Government claimed that the Ohin Survey showed the amount of excavation still to be done to achieve the target of RL 92.3. The Ohin Survey was not brought to the arbitrator’s attention during the arbitration. In the circumstances and considering in particular the fact that the Government accepted the levels set out in the Wang Survey at the arbitration and did not press or even suggest to the arbitrator that the correct level was as shown in the Ohin Survey, I find that the remaining depth to be excavated was 0.494 metres as shown in the Wang Survey.
58. The parties also dispute the extent to which the installation of the 4th level struts and walers had been completed. The Plaintiffs claim that these 4th level supports had been more or less completed and that all that was outstanding was some finishing touches which involved some "wedging and filling-up gaps". The Government, however, disputed this. They referred to the letter of 24/4/92 from the SO to the Government in which the SO states that as at that date, part of the 4th level supports at RL 94.00 had yet to be installed. More tellingly, they refer to a letter dated 10/7/92 from the JM on behalf of the Plaintiffs to the Government which states:-
"As you knew when you required us to leave the Site, the 4th level of walers had not been completed or fully strutted. Also the timbering at the gaps in the sheet piles where services pass through had not been completed."
59. Although DW2 signed the SO’s letter of 24/4/92, he had no personal knowledge of the state of the 4th level supports and had relied on the report of the resident engineer at the Site with regard thereto. The Plaintiffs’ evidence that the installation of the 4th level struts and walers was more or less completed was given by PW1 who claimed to have been at the Site and had personal knowledge on this issue. However, PW1’s evidence was at odds with the contents of the JM’s letter of 10/7/92. This letter is a previous statement by the Plaintiffs themselves made much closer to the date when the events took place. It was incumbent on the Plaintiffs to explain the apparent contradiction if they wished to persuade the Court that PW1’s evidence on this issue was to be preferred to what was stated in the JM’s aforesaid letter. They have not cleared up this contradiction to my satisfaction. In the circumstances I find that the description of the state of completion of the 4th level supports as set out in the JM’s letter is the best evidence of the actual state of installation of the 4th level struts and walers as at 27/4/92. On this description I find that although some substantial work may have been done with regard thereto, there was much more than just some minor finishing touches left to be done as maintained by the Plaintiffs.
60. I also do not accept the Plaintiff’s argument that the fact the excavation pit did not collapse during the 5 months or so after 27/4/92 that it was left unworked proves that the 4th level supports were for all practical purposes completely installed. Firstly, I accept DW1’s and DW2’s evidence that the flooding of the excavation pit would have provided substantial additional support for the excavation. This additional support, coupled with that of the support that such 4th level supports as completed by the Plaintiffs no doubt also gave, was sufficient to prevent the excavation pit from collapsing. However, for purposes of proceeding with the excavation in the scenario as at in late April 1992, the excavation would have to be fully supported by the struts and walers without the additional support flooding provided. For this the 4th level struts and walers would have had to be completely installed and passed by AL Technologies (S) Pte. Ltd. before any further excavation could safely be carried on. Secondly, all such supports are usually designed and constructed to provide an additional safety margin of support. In incomplete installation might still support the excavation but without this safety margin. Simply because the excavation pit did not collapse does not necessarily mean therefore that the 4th level supports had been completely installed.
61. Summarising some of my findings so far, the 1st notice of 18/4/92 was good notice. The target it set of completion of the said excavation works as a measure of whether the Plaintiffs were proceeding with the Works with reasonable diligence was a fair target. In order to achieve this target the Plaintiffs had to complete the said excavation works by 25/6/92 which was a Saturday. Although the Plaintiffs terminated the Contract prematurely when they posted the 2nd notice on 25/6/92, the termination would have been proper if the target had not been met by the end of 25/6/92 and the 2nd notice was posted on 26/6/92 or within a reasonable period thereafter. Although the Government posted the 2nd notice on 25/6/92, the Plaintiffs only learnt on 27/4/92 that the Contract had been terminated. Their performance of the Contract in the period 24 to 26/4/92 could not therefore have been affected by the Government’s posting of the 2nd notice on 25/4/92. The fact that installation of the 4th level supports was not completed and there was another 0.494 metres to go before the target of RL 92.3 was reached shows that if the Government had not sent the 2nd notice prematurely on 25/4/92 but on say 26/4/92 i.e. 7 days after the 1st notice was sent, the Plaintiffs would still not have achieved the target.
62. When the Government took possession of the Site on 27/4/92, installation of the 4th level supports had not been completed . The 4th level supports had also not been inspected and passed by AL Technologies (S) Pte. Ltd. The Plaintiffs therefore should not have been excavating below RL 93.5. On the basis of the Wang Survey, the average excavation level was now RL (92.3 + 0.494) i.e. RL 92.794. This shows that the Plaintiffs had in fact excavated some 0.706 metres below RL 93.5 without the 4th level supports being completely installed or checked. This shows that the Plaintiffs were not working in the safe and responsible manner as would be expected of a reasonably competent contractor proceeding with reasonable diligence. Even if the Plaintiffs had achieved the target but did so only by working in an unsafe manner, it is doubtful whether they can be said to have been proceeding with the Works with reasonable diligence.
63. I also find that even if the Plaintiffs worked another full day they would not have been able to reach the target. In the period from 19/4/92 to 27/4/92 they had not completed installation of the 4th level supports and only excavated some 0.706 metres leaving another 0.494 metres to be done. I find that they would not be able to complete the installation of the 4th level supports, get the installation passed by AL Technologies (S) Pte. Ltd. and complete 0.494 metres of excavation within 1 day.
64. On the issue of waiver, when the Plaintiffs submitted their 5th revised programme to the Government on 18/2/92 and the Government told them that if they failed to complete the said excavation works by 31/3/92, as proposed in the programme, the Government would terminate the Contract, the Government was simply adopting a wait and see approach to what was yet another revision by the Plaintiffs of their timetable for completion. I find nothing in what the Government did, said or wrote to justify the Plaintiffs’ claim that in so doing the Government had waived any rights they had to proceed against the Plaintiffs for past delays. All the Government were doing was to indicate to the Plaintiffs what they had to do if they wished to carry on under the Contract. If the Plaintiffs failed to meet this target, which they had set for themselves, I see no reason why the Government should not be free to proceed to exercise all their rights in the matter including all rights they had prior to 18/2/92.
65. On the issue that the Government were themselves in breach of contract in April 1992 and continued to be so at all material times thereafter and could not therefore under the provisions of Clause 34(a) give any valid 1st or 2nd notice, I find as follows. The first alleged breach was the failure to pay the $14,687/- in respect of rectification works for the de-watering chamber. The Government had not paid this amount because the SO had not certified such works for payment. The arbitrator held that the works should have been certified for payment. The Government thereafter made payment.
66. In Lubenham Fidelities and Investment Co. Ltd. vs. South Pembrokeshire District Council & Another (1986) The Times L.R. 171 the English Court of Appeal held that where an employer had not interfered in the issue of certificates for payment and the contract contained general provisions for the reference of disputes to arbitration, as does the Contract, the employers were entitled to be guided by the certificates issued by the competent authority, in this case the SO. I therefore find that the Government’s failure to pay $14,687/- until after the arbitrator’s award was not a breach of the Contract.
67. As for the second and third alleged breaches of late payment on 2 certificates, these payments were made only 6 days late. They had been made prior to April 1992. Once they were paid the Government was no longer in breach. The fact that the Plaintiffs may have had a claim for interest for late payment did not mean that the Government continued to be in breach of the Contract until the interest was paid. In any event the arbitrator did not award the Plaintiffs any interest in this regard. In the circumstances, I find that the 1st or 2nd notices issued by the Government under Clause 34(a) would not be void by reason of the Government being in breach of the Contract.
68. The answers to the 5 issues raised are therefore as follow:-
(a) On the 1st issue, the answer is: Yes, the 1st notice of 18/4/92 was given in due form and in compliance with the required procedure.
(b) On the 2nd issue, the answer is: No, the Plaintiffs could not have complied with the 18/4/92 notice within the relevant 7 day period.
(c) On the 3rd issue, the answer is: Yes, the Government could have properly issued a fresh 1st notice immediately after the Plaintiffs’ termination of the Contract on 30/4/92.
(d) On the 4th issue, the answer is: No, the Plaintiffs could not have complied with a fresh 1st notice issued immediately after the Plaintiffs’ termination of the Contract on 30/4/92 within 7 days of the notice being sent.
(e) On the waiver issue, the answer is: No, the Government had not waived its rights to rely on any or all of the Plaintiffs’ delays prior to 30/4/92 when issuing a 1st or 2nd notice under Clause 34(a).
69. In the circumstances, I find that the Plaintiffs will only be entitled to nominal damages in this matter. There is therefore no point in proceeding with the Plaintiffs’ assessment of damages and I so order. On the matter of costs, I order that each party bears its own costs in respect of the hearing before me culminating in the order of Court herein dated 1/12/95. As for the costs of this hearing on the 5 issues, the Plaintiffs shall pay the Defendants 60% of their costs to be taxed.
Dated the 25th day of June 1997.
C.R. RAJAH,
JUDICIAL COMMISSIONER
Solicitors: Helen Yeo & Partners for the Plaintiffs
The Attorney-General for the Defendants
Philip Jeyaretnam with Neoh Sue Lynn (Helen Yeo & Partners) for the plaintiffs
Soh Tze Bian (The Attorney-General) for the defendants