This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

In the High Court of the Republic of Singapore
[1997] SGHC 216
Suit 146/1995, 1564/1995, 1565/1995
Between
D & C Property Pte Ltd
NCM Properties Pte Ltd
… Plaintiff
And
Four Seas Construction Co Pte Ltd
Stephen Tan Guan Seng
Derek Lew Guan Seng
Four Seas Realty Holdings Pte Ltd
So Sioe Kim
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
D & C Property Pte Ltd and Another v Four Seas Construction Co Pte Ltd and Others
[1997] SGHC 216
Suit 146/1995, 1564/1995, 1565/1995
Tan Lee Meng J
20 August 1997
JUDGMENT:
Cur Adv Vult
GROUNDS OF JUDGMENT
1. For the purpose of this trial, three suits were consolidated. Suit No. 146 of 1995, the main action, was consolidated with Suit No. 1564 of 1995, which was instituted by the first defendants in the main action against the first plaintiffs in the main action, and with Suit No. 1565 of 1995, which was instituted by the first defendants in the main action against the second plaintiffs in the main action.
2. The first plaintiffs in the main action were the developers of a building project in Swiss Club Road. Their related company, the second plaintiffs, were the developers of a building project in Cornwall Gardens. The first defendants in this action, Four Seas Construction Co. Pte. Ltd., were the main contractors for the first and second plaintiffs' building projects and the second defendant, Steven Tan, is the first and fourth defendants' director. The third defendant, Derek Lew, was the managing director of the first and second plaintiffs until he resigned on 21 July 1994. He also held 20% of the shares in these two companies. The fourth defendants, Four Seas Realty Holdings, are a related company of the first defendants. Finally, the fifth defendant, Madam So Sioe Kim, who is the second defendant's mother, is a director of the first and fourth defendant companies. During the trial, the plaintiffs withdrew their claims against Madam So Sioe Kim. As for Derek Lew, the third defendant, his whereabouts are unknown and the plaintiffs obtained judgment in default of appearance against him.
3. The first and second plaintiffs are suing the first defendants, the main contractor for their two building projects, in contract for failing to complete the projects. They also alleged that while investigating the activities of their former managing director, Derek Lew, they unearthed sufficient evidence to justify a finding by the court that he conspired with the first, second and fourth defendants to siphon money from them. The first defendants, who contended that they were entitled to withdraw from the two building projects on the ground of the first and second plaintiffs' breach of contract, filed two actions against them. The first, Suit No. 1564 of 1995, is with respect to the alleged breach by the first plaintiffs of the construction contract for the Swiss Club project and a contract to build and connect the said project's minor sewer line. The second, Suit No. 1565 of 1995, is with respect to the alleged breach by the second plaintiffs of the construction contract for the Cornwall Gardens project. As the first defendants' actions concerned the same subject matter as the main action, all three suits were consolidated.
A. THE ALLEGATION OF CONSPIRACY
4. The first and second plaintiffs' case is that they were badly served by their former managing director, Derek Lew, who conspired with the first and fourth defendant companies and their director, the second defendant, Steven Tan, against their interests. They accepted that they did not have direct evidence of the alleged conspiracy. However, they submitted that the circumstantial evidence surrounding this case is so voluminous and unusual that a reasonable man would conclude that there was a conspiracy against their interests. Various instances of alleged impropriety by Derek Lew were recounted. They included the following:
(a) opting to run the minor sewer line for the Swiss Club project through an inappropriate site and on conditions which were disadvantageous to the first plaintiffs in that they were required to appoint the first defendants as the main contractor for this project as well as the second plaintiffs' building project in Cornwall Gardens without the benefit of a competitive tender exercise.
(b) allowing the first defendants to inflate the contract price of the Swiss Club project to around $6.48 million to the detriment of the first plaintiffs.
(c) providing large advance payments to the first defendants without consulting the architect.
(d) giving a bribe of $100,000 to the second defendant after misrepresenting the purpose of the payment to the first plaintiffs.
(e) diverting to the second and fourth defendants a valuable corporate opportunity open to the second plaintiffs to acquire five properties at Tessensohn Road, after having protracted negotiations with the owner of the properties.
(f) receiving secret commissions and illegal compensation by way of purported commissions and consultancy fees from the second and fourth defendants.
5. As most of the alleged instances of impropriety concern the first plaintiffs' Swiss Club project, the background of this project should first be discussed. Sometime prior to 1992, Derek Lew persuaded the first plaintiffs' present managing director, Michael Ng, to take an interest in the purchase of a large plot of land in Swiss Club Road. Michael Ng, who was not knowledgeable about property development, agreed to a joint venture with Derek Lew for the purpose of purchasing and developing the said Swiss Club property. The vehicle for the joint venture was D & C Property Pte. Ltd., the first plaintiffs, in which Michael Ng held 80% of the shares. Derek Lew held the remaining 20% of the shares in the company. The land at Swiss Club Road was purchased by the first plaintiffs for $12,067,770 and Derek Lew was put in charge of the Swiss Club building project. In the first plaintiffs' view, he did not act in their interest from the very start.
6. The first instance of alleged impropriety in the Swiss Club Road project relates to Derek Lew's handling of its minor sewer line. The first plaintiffs' property did not have any discharge point for sewerage and drainage. As such, a minor sewer line had to be connected from the first plaintiffs' property to a suitable discharge point in a neighbouring property. Derek Lew decided to have the minor sewer line run across No. 23, Swiss Club Road, which is owned by the second defendant's mother. This might not have raised eyebrows except that the second defendant's mother drove a very hard bargain. She imposed seven conditions on the first plaintiffs before agreeing to allow the plaintiffs to run the minor sewer line through her property. One of them required the first plaintiffs to arrange for the appointment of the first defendants, Four Seas Construction, as the designated main contractor at a mutually agreed price for not only the Swiss Club project, but also for the Cornwall Gardens project, which was to be developed by the second plaintiffs. Such a condition was unusual in the context of an agreement to allow a neighbour to connect a sewer line.
7. The first plaintiffs' expert witness, Raymond Kuah, an architect, said that no reasonable architect would have advised the first plaintiffs to give up their right to call for open tenders for their building project in exchange for the right to run the minor sewer line across the second defendant's mother's property when there were other better options, which were not properly explored. For instance, the minor sewer line could have been connected to a neighbouring plot of land, owned by Park Court. The first plaintiffs' architect, Kok Siew Weng, said that this option was not pursued because the architects for Park Court, were rather difficult to deal with. He added that a large sum had to be paid as compensation for running the minor sewer line across the Park Court property. However, it appears that the architects for Park Court were rather helpful and had invited the first plaintiffs to discuss the minor sewer without making any demand for compensation. As there were other better options available, it remains a mystery why Derek Lew decided to connect the minor sewer line through the second defendant's mother's property when this resulted in the first and second plaintiffs losing their right to call for a competitive tender for their building projects in Swiss Club Road and Cornwall Gardens.
8. Another alleged wrongdoing concerning the minor sewer connection needs to be considered. According to the first plaintiffs' records, $100,000 in cash was paid by Derek Lew out of their bank account to the second defendant on 16 February 1993. It was stated in the payment voucher that this payment was for 'compensation for minor sewer works'. The first plaintiffs contended that the $100,000 was a bribe given to the second defendant to induce him to persuade his mother to allow her property to be used for the connection of the minor sewer. They pointed out that after receiving the alleged bribe, the second defendant informed his mother that it had been agreed 'in principle' that Four Seas Construction, the first defendants, would be appointed as the main contractors for the Swiss Club and Cornwall Gardens projects if she allowed the first plaintiffs to run their minor sewer line across her property. As a director of the first defendants, the second defendant's mother readily gave her consent. In the first plaintiffs' view, the second defendant's mother's letter to the first plaintiffs dated 22 February 1993, in which she insisted on seven conditions for her consent, was a cover-up for the conspiracy since it was clear that by then, she had already agreed to have the first plaintiffs' minor sewer line run across her property. After all, on 17 February 1993, the day after the $100,000 was allegedly paid to the second defendant, and four days before the second defendant's mother's letter to the first plaintiffs was written, the first plaintiffs' architect had written to the first defendants regarding the minor sewer line on the basis that the required consent had been obtained.
9. The next allegation of Derek Lew's impropriety relates to the cost of building the bungalows at Swiss Club Road. At the planning stage, the estimated cost of building each bungalow was $1 million. This was the figure submitted to the Urban Redevelopment Authority as well as to financial institutions, from whom the first plaintiffs intended to borrow money for the building project. Notwithstanding these projections, on 16 September 1993, the first defendants offered in a letter to the first plaintiffs' architect to build three bungalows for $6,480,191.61. On 23 November 1993, the architect confirmed on behalf of the first plaintiffs the award of the construction contract to the first defendants for $6,480,191.61. As a result, the construction cost of each bungalow was around $2.16 million. As each bungalow was to be sold at around $4 million, and the cost of the land on which each bungalow stood was around $2 million, this meant that the first plaintiffs would be selling their bungalows at a loss.
10. The first plaintiffs' main shareholder, Michael Ng, queried Derek Lew about the construction costs. Within a month of the first award, there was a revised award of the construction contract. On 20 December 1993, the first plaintiffs' architect wrote to the first defendants as follows:
On behalf of D & C Property Pte Ltd, we are pleased to award the above contract to you at the Revised Lump Sum Contract of $3,450,000.00.
The revised award, which reduced the contract sum from $6,480,191.61 to $3.45 million, specifically provided that the 'revised and adjusted Contract Sum shall be fixed lump sum and firm, and no provisions shall be allowed for fluctuations whatsoever'. Notwithstanding the drastic cut in the contract price, no revisions were made in the revised award to the size of the bungalows. The changes in the revised award were mainly concerned with the downgrading of some of the architectural finishes. By no stretch of imagination could the savings from this cost-cutting exercise amount to $3,000,000. The first plaintiffs pointed out that it was surprising that the first defendants, who, as experienced contractors, were aware of their legal rights, accepted the revised award at $3.45 million when they should have protested loudly after the contract sum was drastically reduced without a corresponding reduction in the scale of construction work. In view of this, the first plaintiffs submitted that the original tender sum of $6,480,191.61 must have been a highly inflated figure agreed upon between Derek Lew and the second defendant for the purpose of siphoning money from them.
11. The first plaintiffs also pointed out that it was strange that the architect, Kok Siew Weng, and the quantity surveyor, Lee Boon Cheang, called for comparative quotes from other contractors after the first defendants had already been awarded the first building contract for $6,480,191.61. Both the architect and quantity surveyor were unable to provide satisfactory answers as to why the comparative quotes were obtained. In fact, the architect admitted that he erred when he declared in his affidavit of evidence-in-chief that the comparative quotes were obtained before the first building contract had been awarded to the first defendants. The first plaintiffs concluded that it was obvious that the architect and quantity surveyor knew that the contract sum of $6,480,191.61 was an inflated sum and that the comparative quotes were required to support their claim that the inflated sum was a reasonable contract sum.
12. The first plaintiffs also attacked the first contract sum of $6,480,191.61 on yet another ground. They pointed out that the first defendants had agreed to build in the Cornwall Gardens project one bungalow with similar specifications for $1.5 million. If the Cornwall Gardens bungalow, which had a slightly larger built-up area than the Swiss Club bungalows, could be built for $1.5 million, there was no reason why three Swiss Club bungalows should cost $6,480,191.61.
13. The first plaintiffs also relied on the large advance payments requested by the second defendant and Derek Lew's swift and favourable response as evidence of the alleged conspiracy. In the case of the Swiss Club properties, the second defendant wrote to Derek Lew on 22 December 1993 for an advance of 30% of the contract sum of $3.45 million, which amounted to $1,035,000. On the very next day, Derek Lew paid the amount requested. As for the Cornwall Gardens project, the second defendant asked for an advance of 30% of the contract sum, which amounted to $450,000 on 23 May 1994. Instead of paying 30% as requested, Derek Lew gave an advance of $500,000 on 1 June 1994. The first plaintiffs' expert witness, Raymond Kuah, had no doubt that these large advance payments were 'extraordinarily unusual' and were not the norm in the construction industry. He added that there were no special circumstances to warrant the requests.
14. The second defendant, who insisted that his requests were not unusual, was unable to provide evidence that his company had received large advance payments from other developers. Most of the advance payments which he claimed to have received in the past were not really advance payments. With respect to the construction contract for Villa Azura, which involved an advance payment, the amount paid in advance was only 3%, ten times less the advance payments in the Swiss Club and Cornwall Garden projects.
15. The next allegedly unexplainable sequence of events involving both Derek Lew and the second defendant concerns the purchase by the fourth defendants of five properties at Tessensohn Road and the subsequent purchase by the second plaintiffs of one of these properties from the fourth defendants, of which the second defendant is a director. It is because of the Tessensohn Road properties that the fourth defendants are involved in this action, which primarily concerns the first and second defendants.
16. The facts with respect to the Tessensohn Road properties are as follows. In 1993, Derek Lew took an interest in the sale of five houses in Tessensohn Road by the vendors, Corplan Pte. Ltd. He discussed the sale of these properties in his office in the second plaintiffs' premises with the vendors' representative, Jeanette Chan, who pointed out that the vendors wanted $4.5 million for the properties. The second plaintiffs contended that Derek Lew negotiated with the vendors on their behalf and that the vendors agreed to sell them the properties for $4.2 million. They added that after the successful negotiations with the vendors, Derek Lew diverted the option to purchase the properties to the second defendant, who purchased the properties on behalf of the fourth defendants in October 1993. The fourth defendants thus had the opportunity to purchase the five Tessensohn Road properties for $840,000 each.
17. In May 1994, the second defendant arranged to have the fourth defendants' properties at Tessensohn Road sold at a public auction. Derek Lew attended the auction and purchased one of the properties, No. 35 Tessensohn Road, on behalf of the second plaintiffs for $1.48 million. What further irked the second plaintiffs was that Derek Lew was retained by the second defendant as a consultant for the development of the Tessensohn Road properties and was to be paid $90,000 for his services. To date, he had received half of this sum. Furthermore, Derek Lew was paid a commission of $36,000 by the fourth defendants for assisting in the sale of two of the properties. The second plaintiffs submitted that the consultancy fees and commissions were in fact bribes or 'kick-backs' to Derek Lew for his services to the first and second defendants in the Swiss Club and Cornwall Gardens projects.
B. WHETHER THERE WAS A CONSPIRACY
18. There are two types of conspiracy. The first type involves the use of lawful means to injure the victim while the second type involves the use of unlawful means to injure the victim. The first and second plaintiffs alleged that the defendants used both lawful and unlawful means. In Lonrho Plc. v. Fayed [1992] A.C. 448, where the House of Lords reiterated that there is a distinction between the two types of conspiracy, Lord Bridge explained:
Where conspirators act with the predominant purpose of injuring the plaintiff and in fact inflict damage on him, but do nothing which would have been actionable if done by an individual acting alone, it is the fact of their concerted action for that illegitimate purpose that the law, however anomalous it may now seem, finds a sufficient ground to condemn their action as illegal and tortious. But when conspirators intentionally injure the plaintiff and use unlawful means to do so, it is no defence for them to show that their primary purpose was to further or protect their own interests; it is sufficient to make their action tortious that the means used were unlawful.
It must thus be borne in mind that when considering the lawful means which are part of the alleged conspiracy, it must be shown that the conspirators' predominant purpose was to injure the plaintiffs but in the case of the defendants' allegedly unlawful acts, there is no such requirement.
19. Regardless of the type of conspiracy alleged, the question of a conspiracy does not arise unless there was a combination of efforts to injure the plaintiffs. In other words, the first, second, third and fourth defendants must have had an agreement or some sort of arrangement to siphon money from the first and second plaintiffs to themselves. In Seagate Technology Pte. Ltd. v. Goh Han Kim [1995] 1 S.L.R. 17, 23, L.P. Thean J.A., who delivered the judgment of the Court of Appeal, explained:
The essence of conspiracy is an agreement, and the question is whether the appellants had proved that there was in existence an agreement or at least some arrangement ... to defraud the first appellants; and a high degree of proof is required.
20. The first, second and fourth defendants deny that they had any arrangement with Derek Lew to injure the plaintiffs. They stressed that in all their transactions with Derek Lew, they acted in their own commercial interest. They saw no reason why they should be tainted by Derek Lew's breach, if any, of his fiduciary duties to the first and second plaintiffs.
21. There can be no doubt that the second defendant, an astute and experienced building contractor, sensed that he and his companies had much to gain from working with Derek Lew, who was relatively inexperienced in property development. To enhance their business ties, the second defendant even went to China with Derek Lew in search of business opportunities there. He sized up Derek Lew, knew his weaknesses, and got the better of the latter in their deals. As far as the Swiss Club and Cornwall Gardens projects are concerned, there appears to be more than meets the eye on a number of occasions and the position is exacerbated by the fact that business arrangements between Derek Lew and the second defendant were conducted with the minimum of documentation and formality. However, whatever faults and wrongs one may attribute to the second defendant, it is difficult to accept that the circumstantial evidence led to the conclusion that he and his companies acted in concert with Derek Lew to siphon money from the first and second plaintiffs to themselves. As such, the main ingredient of a conspiracy, namely a combination by two or more persons to injure the plaintiffs, was absent.
22. The agreement to construct the minor sewer connection through the second defendant's mother's property was one of the main threads in the alleged conspiracy. No matter how much one may suspect the second defendant's motives and actions in relation to the minor sewer line, in regard to the lawful acts undertaken in furtherance of the alleged conspiracy, he acted to further his own business interests and he did not have the predominant purpose of injuring the first plaintiffs.
23. As for unlawful acts such as the alleged bribe of $100,000 to the second defendant for facilitating the construction of the minor sewer line across his mother's property, there is no requirement that there be a predominant purpose of harming the first plaintiffs' interest. The second defendant claimed that this amount was paid to him in cash in November 1993, and not in February 1993, as claimed by Derek Lew, and for a different purpose, namely to compensate the first defendants for building three bungalows instead of a larger number, as had originally promised by Derek Lew. He suggested that his name might have been used by Derek Lew to make false claims. As the first plaintiffs were suspicious of other monetary claims by Derek Lew, this suggestion is not to be lightly dismissed. However, the first plaintiffs pointed out that even if Derek Lew made a false claim in February 1993, they saw no reason why he would not have recovered another $100,000 from his company if he really had to compensate the second defendant in November 1993 for building less bungalows than had originally been promised. The first plaintiffs also noted that the second defendant only informed his company of the payment in January 1994. The second defendant pointed out that he informed his brother, a director of the company, immediately after receiving the cash payment and that there was nothing sinister about the fact that the sum was not paid into the first defendants' account because contractors require large sums of cash for payments to suppliers and sub-contractors. Furthermore, the cash payment was reflected in the company's audited accounts. The second defendant did not make his position very clear and he contradicted himself. All the same, in the absence of clearer evidence and considering the high standard of proof required, it has not been established that the cash payment of $100,000 was an illicit bribe to the second defendant.
24. As for the cost of construction of the Swiss Club bungalows, it has also not been established that Derek Lew conspired with the first and second defendants to inflate the contract price for the purpose of siphoning money from the first plaintiffs. As good class bungalows did not, as a rule of thumb, cost more than $200 per square foot at the relevant time, the first defendants' quote of $6,480,191.61 for three bungalows was certainly rather high. However, the first defendants pointed out that Derek Lew opted for specifications which raised the cost of construction significantly. Samples of the superior architectural finishes were shown to prospective purchasers of the Swiss Club bungalows. The quote of $6,480,191.61 was checked by the project quantity surveyor, Lee Boon Cheang, who found it reasonable, subject to a possible reduction in the cost of some items.
25. The best way to determine whether or not the first defendants' quote of $6,480,191.61 was a grossly inflated sum is to have an independent quantity surveyor study the specifications for the Swiss Club bungalows to see if the bungalows could have been built for a very much smaller sum. However, this was not done. Instead, the first plaintiffs invited me to infer that as a contract sum of $6,480,191.61 cannot be reduced to $3.45 million by merely changing a number of relatively inexpensive specifications, the first defendants' quote must have been a fraudulent and exorbitant sum agreed to by Derek Lew without taking into account their interests. As for the defendants, they took the line that the question of an inflated contract sum did not arise because they did not agree to have the contract sum reduced to $3.45 million. They contended that the contract sum was in fact $6,480,191.61, subject to the proviso that it would be reduced to the extent that savings could be made as a result of a cost-cutting exercise.
26. What was the actual contract sum for the Swiss Club contract will be discussed later in relation to the first plaintiffs' claim in contract. All that needs to be said here is that if $6,480,191.61 was a fraudulently exaggerated sum, arrived at for the purpose of allowing Derek Lew and the second defendant to siphon money from the first plaintiffs, the project architect, Kok Siew Weng, who signed the letter of award for this sum, and the quantity surveyor, Lee Boon Cheang, who checked the reasonableness of the quote, were either co-conspirators or were so incompetent that they could not see that the quote was some $3,000,000 off the mark. The evidence of the architect and quantity surveyor left much to be desired on a number of occasions. However, while the first plaintiffs and their counsel have questioned the competence of the architect and quantity surveyor, it has not been pleaded that they were parties to the alleged conspiracy. Furthermore, while the comparative quotes from a number of other contractors may have been incomplete and not totally reliable, they did indicate that the first defendants' quote was not so far off the mark as to be fraudulent. There is no suggestion that all the contractors involved in this exercise were in cahoots with the alleged conspirators. As such, although there remain many unanswered questions, the very serious allegation that a fraudulently inflated contract price was part of the conspiracy has not been proven.
27. Turning now to the advance payments, there is no doubt that the large advance payments of 30% of the contract price requested by the second defendant were unusual in the construction industry. However, the first and second defendants emphasized that these payments were not part of a scheme to siphon money from the plaintiffs. They pointed out that in the Swiss Club project, the advance payment was taken into account by them when interim certificates for progress payments due to them were issued by the architects. They added that if they intended to siphon money from the first plaintiffs, they would have submitted claims for progress payments when the first three interim certificates for progress payments were issued. Admittedly, all that can be said is that the first defendants had the use of 30% of the contract sum ahead of schedule but this by itself, cannot, in the circumstances of this case, be taken to mean that money was being siphoned to the first defendants as a result of a conspiracy.
28. As for the five Tessensohn Road properties, they will be discussed in greater detail later in connection with the second plaintiffs' allegation of a diversion of a corporate opportunity. All that needs to be said here is that it has not been established that the purchase of these five properties by the fourth defendants and the subsequent purchase of one of the five properties by the second plaintiffs reveal that the second and fourth defendants combined with Derek Lew to injure the second plaintiffs. After learning that these properties were up for sale, the second defendant could easily have contacted the vendors himself. Probably, the second defendant was prepared to have Derek Lew negotiate on behalf of the fourth defendants because Derek Lew claimed to be entitled to a 1% commission from the vendors if he sold the properties. Whether or not this was the case, Derek Lew sued the vendors in June 1994 to recover the 1% commission. As for the consultancy fees, the second defendant said that he agreed to pay Derek Lew a consultancy fee of $18,000 for each of the five Tessensohn Road properties, or $90,000 for all the five properties, and that half of this sum was paid in advance. At a meeting with the plaintiffs on 15 August 1994, he explained that the consultancy fee was for 'the purchase of the Tessensohn Road properties'. In his affidavit, he said that the consultancy fee was for the 'advice given for the most suitable method of redevelopment of the properties'. When cross-examined, he said that Derek Lew was paid a consultancy fee for his advice on how to maximise profits by redeveloping the properties as a conservation project. Derek Lew had advised him to obtain approval to add another storey so as to increase the floor area of each property from 2,000 square feet to close to 3,000 square feet. He also gave some advice on marketing strategy. The second defendant, who stressed that he was 'not giving away the money without the input from others', added :
As I say, he already put in his effort as giving me advice for how to do it and on marketing. If for me, I felt the price, I think, is reasonable, OK, I agree. Normally architects will be charging you know, 4 to 5% as consultancy or even including other consultants, it could come up to more than 10%.
As for the sales commission of $18,000 for each property sold, the plaintiffs questioned why Derek Lew was paid $36,000 for introducing two purchasers when he introduced only one purchaser to the fourth defendants and it was that purchaser who introduced his brother-in-law, the second purchaser, to the fourth defendants. Needless to say, the second defendant took the view that Derek Lew was entitled to the commission. He also made it clear that there was no need for him to give a 'kickback' or a bribe to Derek Lew. In truth, the position has not been totally clarified. All the same, the payment of the commission and consultancy fees do not, without more, establish that there was a combination of efforts to injure the plaintiffs.
29. While the first and second plaintiffs may have reason to be aggrieved by the events relating to the Swiss Club and Cornwall Garden projects, the cumulative effect of the evidence presented by them is that there is merely a suspicion as to whether all was always above board. However, the allegation of a conspiracy must be established to a standard which is commensurate with the seriousness of the charge. (See, for instance, the decision of the Court of Appeal in Ching Mun Fong. v. Peng Ann Realty Pte. Ltd. [1995] 2 S.L.R. 541, 554.) As such, the allegation of conspiracy has not been proven, if only because of the understandably high standard of proof required for such an allegation.
C. DIVERSION OF A CORPORATE OPPORTUNITY
30. In relation to the Tessensohn properties, apart from submitting that the circumstances relating to the purchase of these properties by the fourth defendants and the subsequent purchase by the second plaintiffs of No. 35, Tessensohn Road from the fourth defendants support their allegation of conspiracy, the second plaintiffs also contended that Derek Lew, who could have purchased all the Tessensohn Road properties on their behalf for $4.2 million, was guilty of diverting a corporate opportunity from them to the fourth defendants at the request of the second defendant. They submitted that the second defendant knew or ought to have known that Derek Lew was their managing director and that he was negotiating with the vendors on their behalf. They added that alternatively, given that Derek Lew was their managing director, the second defendant ought to have known that he was acting in breach of his fiduciary duties towards his company when he negotiated on behalf of the second and fourth defendants in the purchase of the properties. As such, the second plaintiffs sought the following:
(a) a declaration that the Tessensohn Road properties are held on a constructive trust for their benefit.
(b) an order that the fourth defendants transfer the Tessensohn Road properties to them for the sum of $4,200,000 less $1,480,000 previously paid to them for No. 35 Tessensohn Road.
(c) An account of all profits made from the sale of any and/or all the Tessensohn Road properties.
(d) An order for the payment to the second plaintiffs of the monies due on the taking of the account.
31. A director who has not been authorised to do so is not entitled to divert a corporate opportunity from his company to himself or to a third party. If he does so, he is in breach of his fiduciary duty to his company and a third party who assists in such a breach may be liable to the errant director's company. It is clear from Lord Selborne L.C.'s judgment in Barnes v. Addy (1874) L.R. 9 Ch. App. 244, 252, that third parties may be made constructive trustees if they receive and become chargeable with some part of the trust property, or assist with knowledge in a dishonest and fraudulent design on the part of the trustees. In Royal Brunei Airlines Sdn. Bhd. v. Tan Kok Ming [1995] 3 M.L.J. 74, 77, Lord Nicholls of Birkenhead explained what Lord Selborne L.C. had in mind when he said:
In the conventional shorthand, the first of these two circumstances in which third parties (non-trustee) may become liable to account in equity is 'knowing receipt', as distinct from the second where liability arises from 'knowing assistance'. Stated even more shortly, the first limb of Lord Selborne L.C.'s formulation is concerned with the liability of a person as a recipient of trust property or its traceable proceeds. The second limb is concerned with what, for want of a better compendious description, can be called the liability of an accessory to a trustee's breach of trust. Liability as an accessory is not dependent upon the receipt of trust property. It arises even though no trust property has reached the hands of the accessory. It is a form of secondary liability in the sense that it only arises where there has been a breach of trust.
32. In this case, even if Derek Lew breached his fiduciary duty to his company and deprived his company of an opportunity to consider whether the Tessensohn properties should be acquired, it does not follow that the second plaintiffs are entitled to the reliefs sought. While strangers, such as the fourth defendants, may, in appropriate cases, be made constructive trustees, the 'knowledge required to hold a stranger liable as constructive trustee in a dishonest and fraudulent design, is knowledge of circumstances which would indicate to an honest, reasonable man that such a design was being committed or would put him on inquiry, which the stranger failed to make, whether it was being committed'. (per Ungoed-Thomas J, in Selangor United Rubber Estates Ltd. v. Craddock (No. 3) [1968] 1 W.L.R. 1555, 1590.) In Seagate Technology Pte. Ltd. v. Goh Han Kim [1995] 1 S.L.R. 17, the Court of Appeal accepted Millet J.'s view in Agip (Africa) Ltd. v. Jackson & Ors. [1990] 1 Ch. 265, that dishonesty connotes (i) actual knowledge; (ii) wilfully shutting one's eyes to the obvious; and (iii) wilfully and recklessly failing to make such inquiries as an honest and reasonable man would make. Admittedly, in a subsequent case, Royal Brunei Airlines Sdn. Bhd. v. Tan Kok Ming [1995] 3 M.L.J. 74, the Privy Council took the view that the term 'knowingly' is better avoided as a defining ingredient of the accessory liability principle and preferred to focus attention on the dishonesty of the third party who encourages a breach of a fiduciary obligation. Lord Nicholls of Birkenhead said that their Lordships' overall conclusion was that dishonesty is a necessary and sufficient ingredient of accessory liability. His Lordship, who added that in the context of the accessory liability principle, acting dishonestly means simply not acting as an honest person would in the circumstances, accepted that the standard of honesty is not subjective. It is not an optional scale, with higher or lower values according to the moral standards of each individual. If a person knowingly appropriates another person's property, he will not avoid liability merely because he does not see that his behaviour is wrong.
33. Whichever view one takes of the ingredients of the liability of an accessory who encourages a breach of a fiduciary obligation, the second defendant was not guilty of dishonesty when he accepted Derek Lew's services as a negotiator. It has not been established that the second defendant knew that Derek Lew was negotiating the purchase of the properties on behalf of the second plaintiffs. The second defendant said that Derek Lew told him that the second plaintiffs were not interested in the project. A question arises as to whether the second defendant was obliged to probe further and ask whether Derek Lew had kept his company fully informed of the situation. In the circumstances of the case, he was not. As a general rule, commercial transactions cannot be properly conducted on the basis that a person who is dealing with a company's agent is, without more, obliged to take steps to convince himself that the agent in question is not breaching his fiduciary duty. Indeed, in Cowan de Groot Properties v. Eagle Trust Plc. [1991] B.C.L.C. 1045, 1111, where the directors of Eagle Trust were in breach of their fiduciary duties by selling properties at a price below their true value, Knox J., who did not think it appropriate to impute knowledge of this breach to the purchasing company, said that the duty of directors of a purchasing company is to buy as cheaply as they can in the light of the mode and terms of the proposed sale and it would be a slippery slope upon which to embark to impose upon directors of a company a positive duty to make inquiries into the reasons for an offer made to their company at what appears to be a bargain price. Knox J.'s approach applies with equal force to the present case.
34. It must also be borne in mind that as no confidential information was used by Derek Lew in relation to the purchase by the fourth defendants of the Tessensohn Road properties, it was less likely that an honest and reasonable man would suspect that he was breaching his fiduciary duty to his company. The sale of these properties had been advertised in the local newspapers and it was public knowledge that the vendors were willing to sell their properties to anyone who offered them the right price. In this regard, an Australian case, Consul Development Pty. Ltd. v. D.P.C. Estates Pty. Ltd. [1975] 49 A.L.J.R., merits attention. The facts in this case, shorn of details for present purposes, are as follows. W., the managing director of a group of companies engaged in the acquisition of run down estates and in their re-sale at a profit after renovation, appointed G. as the working manager of one of his companies. G.'s main responsibility was to locate suitable properties for acquisition and subsequent disposal by companies in the group. The appellants, Consul Development Pty. Ltd., an investment company run by the family of one C., entered into W.'s line of business and collaborated with G. on the basis that profits and losses with respect to properties purchased were shared equally. At one stage, G. told C. that his group was not interested in a purchase, which was eventually made by the appellants. On the basis that the respondents would have been nominated by W. to purchase the properties in question had G. not denied it the opportunity to acquire the said properties, the respondents sought, inter alia, a declaration that the properties purchased by the appellants were held on trust for them. The High Court of Australia, which noted that the trial judge was not satisfied that C. was aware that G.'s conduct involved any breach of fiduciary duty, held that the appellants were not constructive trustees for the respondents of the properties concerned and that the appellants were not entitled to the relief sought. With respect to G.'s disclosure of information regarding the availability of properties, a measure of emphasis was placed on the non-confidential nature of the information. Stephen J., with whom Barwick C.J. agreed, said at p. 92:
It is inherent in what I have said that I do not regard [the appellants] as having received any property impressed with a trust. It did obtain the advantage of having had brought to its attention the fact that willing vendors existed who were prepared to sell on terms thought to be advantageous but this knowledge, the essence of which is in the public domain, was not properly capable of being owned by anyone; it was freely available to all who might seek it and to much of it the vendors had given such publicity as their means permitted.
35. As for Derek Lew's subsequent purchase of No. 35, Tessensohn Road at the auction, it has not been established that the purchase of this property was part of a scheme to give the fourth defendants profits at the expense of the second plaintiffs. The pricing of the properties offered for sale at the auction by the fourth defendants was recommended by their property agents, M/s Jones Lang Wootton. Apparently, at the time of the purchase, Michael Ng, the second plaintiffs' present managing director, was quite prepared to accept Derek Lew's view that the second plaintiffs should purchase No. 35 Tessensohn Road for $1.48 million. In contrast, in regard to the first contract sum for the construction work in the Swiss Club project, Michael Ng had thought it to be too high and had asked Derek Lew to have the contract sum reduced. When Michael Ng was asked whether a company which is not interested in buying all the five properties at Tessensohn Road might be interested in buying one of the properties, his reply was as follows:
Like Derek says, it's a conservation shop, it's a good one, like those in Little India it can go up to $2 million. So ... it's quite reasonable. So he bought one.
36. If all the facts relating to the purchase by the fourth defendants of the Tessensohn Road properties from Corplan Pte. Ltd. and the subsequent purchase by the second plaintiffs of No. 35 Tessensohn Road from the fourth defendants are taken into account, there is no basis for the second plaintiffs' application for a declaration that the Tessensohn Road properties are held on constructive trust for their benefit or for an order that the fourth defendants transfer the properties to the second plaintiffs. The question of taking an account of profits made by the fourth defendants also does not arise.
D. THE PLAINTIFFS' CLAIM IN CONTRACT
37. For the purpose of discussing the first and second plaintiffs' claims against the first defendants for breach of contract, the Swiss Club and Cornwall Gardens projects will be considered separately.
Termination of the Swiss Club contract
38. Whether the first plaintiffs are entitled to damages for breach of the construction contract for the Swiss Club project depends on who breached this contract. The first defendants contended that the first plaintiffs interfered with the work of the architect and that this serious breach entitled them to terminate the contract under section 33(1) of the contract, which provides as follows:
The Contractor shall be entitled by a written Notice of Termination given to the Employer to terminate his employment under the Contract on any of the following grounds:-
....
(c) If the Employer improperly or fraudulently interferes or influence or obstructs the issue of a certificate by the Architect or there is fraudulent collusion between the Employer and the Architect.
39. The alleged interference in this case concerns the architect's revision of the fourth interim certificate. In the first, second, third and fourth certificates, the contract sum was stated as $3.9 million and not $3.45 million, as provided for in the revised award. Furthermore, the first plaintiffs' advance payment of $1,035,000 was not reflected in these certificates. The architect, Kok Siew Weng, explained that the contract sum was stated as $3.9 million because he was of the view that this was a fairer figure after cost-cutting measures had been introduced. After the fourth interim certificate was issued, the first plaintiffs asked the architect on 24 August 1994 to furnish by noon on the following day a corrected certificate of payment, which was to reflect the following:
(a) the advance payment of $1,035,000.
(b) the amount still owing to the first defendants.
(c) a revaluation of the quantum of work done
according to the contract sum of $3.45 million.
40. On 25 August 1994, the architect issued a revised certificate in the following terms:
'Pursuant to Clause 31(4) of the contract conditions, I now revised my previous certificate, having decided as above and hereby certify that, allowing for previously paid amount of $1,035,000 there is now due and owing as a consequence of my said revision (from the contractor to the employer) the sum of Singapore $676.60 calculated as attached.'
The revised certificate also reduced the value of work already done on the site from $1,325,608 to $1,102,366.
41. On 31 August 1994, the first defendants, who were puzzled as to how a previously certified value of work done on the site can be reduced to a smaller sum in a subsequent certificate, asked the architect to explain why the revision certificate was issued. The architect replied that he acted on the first plaintiffs' instructions. On 6 September 1994, the first defendants notified the first plaintiffs that a dispute had arisen with regard to the total value of the work already done on the site as well as the contract sum and invited the first plaintiffs to settle their dispute through arbitration. On the same day, the first defendants terminated the construction contract. In their letter of termination, they stated as follows:
We hereby give notice of the termination of our employment for the above works pursuant to Clause 33(1) of the Conditions of Contract in that you and/or your agents, Messrs. Drew & Napier, have improperly interfered with or have influenced or have obstructed the Architect in the issuing of a certificate. This is evidenced by the fact that you have influenced the Architect to withdraw his Certificate No:4 dated 25 July 1994 which certified that the sum of $220,488.20 was payable to us and have influenced him to issue his Revision Certificate dated 25th August 1994 which certified that the sum of $676.60 is owed by us to the Employer.'
42. On 8 September 1994, the first plaintiffs replied that neither they nor their solicitors had improperly influenced the architect to issue the revision certificate. They added that as the first defendants had wrongfully terminated and/or repudiated the contract, they accepted the said repudiation.
43. To appreciate the seriousness of an allegation of interference with the work of an architect in the certification process, the following elucidation of the role of an architect in the issuance of interim certificates by Lord Radcliffe in R.B. Burden Ltd. v. Swansea Corporation [1957] 1 W.L.R. 1167 is helpful:
To take the architect first, it is obvious that his general function is to act on behalf of the owner, and he is the owner's agent to give the required instructions to the contractor. He is placed in office to protect the owner's interests. But in those parts of his duties which relate to the giving of certificates for payment I think that he stands apart from the owner and enjoys to some extent an independent authority of his own. The terms of the contract itself involve that he should have an irrevocable authority from the owner to issue certificates for payment to the contractor up to the amount and according to the terms which the contract prescribes. Hence under this contract, if the owner even attempts to prevent him from doing so by interfering with or obstructing their issue, the contractors are entitled to call off the whole transaction by summary notice.
44. It is also pertinent to note that in the above-mentioned case, Lord Tucker rightly pointed out at p. 1180 that, without attempting an exhaustive enumeration of the acts of the employer which can amount to an obstruction or interference, a clause in relation to interference is designed to meet such conduct of the employer as refusing to allow the architect to go onto the site for the purpose of giving his certificate, or directing the architect as to the amount for which he should give his certificate or as to the decision which he should arrive at on some matter within the sphere of his independent duty.
45. In this case, the architect admitted, when cross-examined, that apart from having been told to state the contract sum as $3.45 million, he had received no instructions as to the amount due to the first defendants. It is thus necessary to determine whether the contract sum was indeed $3.45 million, as stated in the revised award. If it was not so, the first plaintiffs had no right to instruct the architect to state this sum in the revised interim certificate. The revised award, which was in crystal clear terms, stated as follows:
FIXED PRICE TENDER
The revised and adjusted Contract Sum shall be fixed Lump Sum and firm, no provisions will be allowed for fluctuations whatsoever for the duration of the contract provided that this clause shall not be held to prohibit variations duly authorised under the Conditions of Contract.
The revised award also included the following important clause:
The Revised Lump Sum of $3,450,000.00 includes for Provisional Sum and Prime Costs - refer to Appendix A for details.
Appendix A of the revised award, which listed a number of changes to the proposed specifications for the bungalows, also stated that the revised contract sum of $3.45 million included the cost resulting from the changes referred to therein. In short, although some of the specifications referred to in Appendix A had not been finalised, the revised contract sum of $3.45 million was, without more, binding on the parties to the contract.
46. Notwithstanding the clarity of the terms of the revised award, the first defendants insisted that the contract sum was $6,480,191.61, as stated in the first award, although they conceded that this sum could be revised downwards if certain specifications were downgraded. They contended that Derek Lew understood that this was the position. However, there is no written record of the so-called understanding, whether in the form of minutes of meetings or an exchange of letters, The first defendants did not refer to the earlier contract sum of $6,480,191.61 in their reply to the architect on 12 January 1994. In this crucial letter, the first defendants thanked the architect for the revised letter of award dated 20 December 1993, and pointed out that it had also been agreed that a performance bond was not required, and that in addition to the changes referred to in Appendix A of the revised award, there was a further short list of items to be incorporated into the contract. The first defendants ended their letter with the following sentence, which stated their position in unequivocal terms:
Our acceptance of the contract price was based on the principle that suitable economical alternative methods proposed by us would be accepted by the Client.
There is no evidence that suitable economical alternative methods proposed by the first defendants were not accepted by the first plaintiffs. Note must also be taken of the fact that the first defendants subsequently formally accepted the revised award in the following terms:
We hereby agree and accept the terms and conditions as appended herein together with our letter ref FSC/9008/Arch/94.028 dated 12 January 1994 ....
Apart from accepting the revised award for $3.45 million in unequivocal terms, the first defendants asked the first plaintiffs for an advance of 30% of the contract sum, which, according to their own calculations, amounted to $1,035,000. This showed that the first defendants accepted that the contract sum was $3.45 million. Furthermore, in the first defendants' contractors' all risks policy issued by the Tai Ping Insurance Co. Ltd., the 'contract price' was recorded as $3.45 million. Mr. Danny Cheng, the second defendant's personal assistant, conceded that this showed that his company accepted that the contract sum was $3.45 million. His evidence was as follows:
Q. [Y]ou took out what is a necessary contractors' risk insurance policy.... [Y]ou look under 'Contract Price'. It is as clear as daylight.
A. Yes.
Q. $3.45 million.
A. Correct.
Q. Right? There was again, you see, an acceptance by your company, on your boss's instructions, no doubt, contract sum is $3.45 million, right?
A. Yes.
47. Both the architect and the quantity surveyor admitted, when cross-examined, that the effect of the revised letter of award was that the contract sum was $3.45 million. The evidence of the architect, Kok Siew Weng, was as follows:
Q. So how can you say to Court that 'at that time when we issued this letter of award, we did not mean for the figure $3.45 [million] to be the contract sum but that we were going to work from $6.48 million down'? This is a clear contract that you wrote. It is a fixed sum contract with no fluctuations.
A. Except for the item mentioned here.
Q. So what if there are changes to the items? But [they are] within the $3.45 [million], you have told the Court that.
A. Yes.
Q. So the sum of $3.45 [million] will remain fixed regardless of whatever architectural finishes that may be agreed in Appendix A. That is the plain reading of your letter.
A. Yes ....
48. As for the quantity surveyor, Lee Boon Cheang, he finally agreed that, in the absence of any subsequent agreement on another contract sum, the revised contract sum of S3.45 million was binding on the parties to the contract. His evidence was as follows:
Q. Are you telling us that there was a contract offered at 3.45 [million], accepted by the contractors at 3.45 million and subsequently the parties appear to be re-negotiating?
A. The re-negotiating has been from ever since. It was from 6.48 [million] --
Q. Please, just answer that. I'm talking about from 3.45 [million] .... So, there is an offer, 3.45 million, you drafted, they accepted it. There is a concluded contract, isn't there?
A. OK.
Q. Right, and subsequently, all these attempts to talk about the different materials and then to change the price, isn't that re-negotiations? Isn't that termed as re-negotiations in one sense?
A. In one sense, yes.
Q. Because if it is not successful, the last contract concluded is 3.45 [million], isn't it?
A. That's right.
Q. Isn't it so?
A. Yes, that's right, yes....
Q. Yes. If no agreement is subsequently reached, you fall back on 3.45 [million], isn't it?
A. That would be right, yes.
49. Taking all the circumstances into account, it is clear that, whatever may have been the position in the past, the revised contract sum of $3.45 million was binding on the parties to the contract. Whether or not the revised contract sum of $3.45 million was a fair amount for the first plaintiffs to pay for the construction work undertaken by the first defendants is not relevant and it does not follow from my finding that the first contract sum of $6,480,191.61 was not a fraudulently exaggerated sum that this higher figure was either a fair contract sum or one to be used as the basis for negotiations with respect to a revised award. It is for the parties themselves to agree on the contract sum. As it has not been established that the revised contract sum of $3.45 million was not intended to bind the contracting parties, the first plaintiffs were entitled to demand that this sum be stated in the interim certificates.
50. As for the reduction in the revised interim certificate of the value of work already done on the site, the first defendants pointed out that as there was no actual revaluation of the work done, the purported revaluation and subsequent issuance of the revision certificate was without any basis. Evidently, Lee Boon Cheang, the quantity surveyor, arbitrarily reduced the value of work already done on the site by the first defendants. He admitted that he had received no instructions from the first plaintiffs with respect to the manner in which the amount due to the first defendants for work already done should be calculated. He said that he reduced the value of work done by applying the 'proportionality' principle because of the reduction of the contract sum to $3.45 million in the revised interim certificate. In his letter to the architect dated 25 August 1994, he said that 'since there was no breakdown for $3,450,000, .... we are suggesting to proportion the sum to various trades to facilitate the progress valuation'. Whether or not his approach is correct may be questioned. Derrick Morris, the first defendants' expert witness, took the view that this was a mistake. If this was so, it was the quantity surveyor's own mistake and the question of the first plaintiffs' interference with the work of the architect in the certification process does not arise. After all, in R.B. Burden Ltd. v. Swansea Corporation [1957] 1 W.L.R. 1167, 1180, Lord Tucker stressed that negligence or errors or omissions by someone who at the request or with the consent of the architect is appointed to assist him in arriving at the correct figure to insert in his certificate cannot amount to interference, which connotes intermeddling with something which is not one's business.
51. What other evidence of interference with the architect's work is there? Reference was made to a letter dated 3 August 1994 from the first plaintiffs to the architect, which contained the following paragraphs:
You are hereby notified that you shall not make any commitment, financial or otherwise on behalf of the Companies (as the Companies' agent) vis--vis third parties, including but without limitation to Four Seas Construction Co. Pte. Ltd. without the prior written approval of any of the following persons first obtained:
1) Mr. Gary Ong
2) Mr. Nelson Ng
3) Messrs Drew & Napier
We shall hold you personally liable in the event that you fail to abide by the aforesaid notification. Kindly note that the same shall apply to the other members of your consulting team.
52. The architect, Kok Siew Weng, stated in his affidavit that the letter in question severely restricted and hampered his work and claimed that when he wrote to the first plaintiffs' solicitors, Messrs. Drew & Napier, he did not receive a satisfactory reply. The first plaintiffs' letter dated 3 August 1994 must be viewed in the proper context. When it was written, the first plaintiffs were rather annoyed that their architect had not stated the contract sum as $3.45 million in his interim certificates for progress payments. Furthermore, he had apparently agreed with the first defendants that the contract sum may finally be around $4.7 million. It was in the light of these developments that the architect was warned not to commit the first plaintiffs financially without their consent. The first plaintiffs had already committed themselves to a contract for $3.45 million and it was not their intention to fetter the architect's right to continue to issue certificates for progress payments under the revised award for $3.45 million. The architect must have known that this was the case.
53. As there was no evidence of any other interference or obstruction, the allegation of interference by the first plaintiffs with the work of the architect in the Swiss Club project has not been proven. In the circumstances, the first plaintiffs were entitled to regard the termination of the construction contract by the first defendants as a breach which entitled them to repudiate the contract.
54. A question arises as to the amount of damages to which the first plaintiffs are entitled for the first defendants' breach of contract. They decided not to complete the Swiss Club project and their solicitors, Messrs. Drew & Napier, assisted them in reaching a financial settlement with the two purchasers of their bungalows. The first plaintiffs claimed that they sustained a loss of $526,000 as a result of their settlement with one of the purchasers and a loss of $967,000 a result of their settlement with the other purchaser. For the purpose of ascertaining the loss suffered by the first plaintiffs as a result of their arrangements with the two purchasers, account must of course be taken of the construction cost which would have been incurred had the building project been completed.
55. The first defendants contended that even if they are liable for breach of contract, the first plaintiffs ought to have mitigated their loss by appointing new contractors to complete the project. It appears that the first plaintiffs would have required some 18-20 weeks to remobilise and that the cost of construction would have been at least 20% more if a new team of contractors had been brought in to complete the work. Counsel for the first plaintiffs submitted that if these facts are taken into account together with liquidated damages for delayed delivery to the purchasers, the damages to which the first plaintiffs would be entitled if the project had been completed by another contractor would have been $1,090,204. Of this, $729,200 would have been in respect of one bungalow and $361,004 would have been in respect of the other bungalow.
56. The question of mitigation of loss arises as an innocent party 'can recover no more than he would have suffered if he had acted reasonably, because any further damages do not reasonably follow from the defendant's breach'. (per Scrutton L.J. in Payzu Ltd. v. Saunders [1919] 2 K.B. 581, 589.) In British Westinghouse Electric and Manufacturing Co. Ltd. v. Underground Electric Railways Company of London Ltd., [1912] A.C. 673, 688, 689, Viscount Haldane L.C. explained:
The quantum of damage is a question of fact, and the only guidance the law can give is to lay down general principles which afford at times but scanty assistance in dealing with particular cases.... The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach; but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps.
57. It is the first plaintiffs' case that considering their own inexperience in the housing development business, their lack of faith in the project consultants, and the possibility of uncovering further side agreements between their former managing director and the respective purchasers, they would have moved onto quicksand if they continued with the construction of the bungalows. They had the impression that their architect, who refused to hand over the building plans unless his fees were paid, was only interested in his fees and not in the completion of the building project. They could not resolve the question of the architect's fees quickly as they did not know what had been agreed upon between Derek Lew and the architect with respect to such fees. Besides, even if the first plaintiffs appointed new contractors, they would still have to try and connect the minor sewer across the second defendant's mother's property. As relations with the second defendant had soured, the first plaintiffs doubted that they would be able to complete the connection. As such, the first plaintiffs preferred to reach a settlement with the purchasers rather than complete the construction of the bungalows.
58. Whether the damage suffered by an innocent party could have been mitigated is a question of fact and not one of law. (See Payzu Ltd. v. Saunders [1919] 2 K.B. 581, 588-589). It is for the first defendants to prove that the first plaintiffs should have taken another course of action to mitigate their loss. Admittedly, not all the reasons given by the first plaintiffs for not completing the building project are relevant to the issue of mitigation. Their inexperience and their lack of faith in their architect are of no concern to the first defendants. Furthermore, the first defendants cannot be held responsible for the difficulties which might have arisen if side agreements between Derek Lew and the purchasers of the bungalows are uncovered. All the same, after taking all the circumstances into account, the plaintiffs cannot be faulted for having reached a settlement with the purchasers. As it is always easier to view matters from hindsight, the law is not unduly harsh on an innocent party who has to deal with the consequences of the wrongdoer's breach. In Banco de Portugal v. Waterlow & Sons Ltd., [1932] A.C. 452, 506, Lord MacMillan explained:
Where the sufferer from a breach of contract finds himself in consequence of that breach placed in a position of embarrassment the measures which he may be driven to adopt in order to extricate himself ought not to be weighed in nice scales at the instance of the party whose breach of contract has occasioned the difficulty.... The law is satisfied if the party placed in a difficult position by reason of the breach of a duty owed to him has acted reasonably in the adoption of remedial measures, and he will not be held disentitled to recover the cost of such measures merely because the party in breach can suggest that other measures less burdensome to him might have been taken.
59. The above approach was adopted by the Court of Appeal in China Resources Purchasing Co. Ltd. v. Yue Xiu Enterprises (S) Pte. Ltd. [1996] 1 S.L.R. 734, 741, where Karthigesu J.A. said that if there is a duty to mitigate, then the standard of reasonableness to be applied to the decision of the innocent party is not a high one. (See also Mbf International Ltd. v. Royal Trust Merchant Bank Ltd. [1993] 3 S.L.R. 216 and Teo Sing Keng v. Sim Ban Kiat [1994] 1 S.L.R. 634.) As such, the first defendants are liable to the first plaintiffs for the loss suffered by them as a result of the settlements. The first plaintiffs are also entitled to interest on the damages from the day the writ was served until the date of judgment at the rate of 6% per annum.
Termination of the Cornwall Gardens contract
60. As for the Cornwall Gardens project, which was developed by the second plaintiffs, the first defendants withdrew from the building project because the second plaintiffs did not accede to their demand for an advance of 30% of the contract sum of $1.5 million or $450,000. On 1 September 1994, the second plaintiffs made it clear in a letter to the first defendants that the contract did not require them to make such an advance payment. After receiving this letter, the first defendants wrote to the second plaintiffs on 6 September 1994 to terminate the construction contract for the Cornwall Gardens project. The relevant part of this letter is as follows:
We refer to your letter dated 01 September 1994.
From that letter it is clear that you do not intend to honour your obligation under the contract to make an advance payment of $450,000 as promised to enable us to carry out the necessary preparation and purchase of overseas products.
Your refusal amounts to a repudiation of the contract and we hereby accept same. We will be submitting our claims for our losses incurred as a result of said repudiation in due course.
61. On 7 September 1994, the second plaintiffs denied that they had repudiated the contract. They pointed out that the first defendants had by their letter of 6 September 1994 clearly evinced an intention to repudiate the contract and that they accepted the repudiation.
62. The award of the construction contract with respect to the Cornwall Gardens project made no reference whatsoever to any advance payment. Admittedly, an advance payment was made by Derek Lew after a request by the first defendants for such a payment on 23 May 1994. The sum paid in advance was handed back to the second plaintiffs when they demanded its return after their investigations into the activities of Derek Lew. There was thus no basis for the first defendants to regard the second plaintiffs' refusal to pay this sum as a repudiatory breach which entitled them to treat the contract as having come to an end. It follows that the first defendants were themselves in breach when they withdrew from the Cornwall Gardens project and this breach was serious enough to entitle the second plaintiffs to regard themselves as having been discharged from the contract.
63. The fact that the first defendants breached the contract for the Cornwall Gardens project offers little comfort to the second plaintiffs as they ought to have taken steps to mitigate their loss. Unlike the Swiss Club project, where the bungalows were already under construction when the first defendants withdrew their services, construction work had not commenced in the Cornwall Gardens project when the first defendants breached the contract. In fact, for several months after the contractors' breach, the plans for the only bungalow to be built in the project could not be finalised because the purchaser contended that the second plaintiffs had represented to her that the bungalow would be built on much higher ground than that proposed under the building plans. Furthermore, the purchaser had required some changes in the building plans, which led to a slight increase in the built-up area of the bungalow and the second plaintiffs and the purchaser could not agree on the additional amount payable for the slightly increased built-up area. In short, considering that it would not have taken much time to have another team of contractors on the Cornwall Gardens project site, the second plaintiffs should have taken this step to mitigate their loss. A new contractor may not have charged more for the construction work as the question of taking over the construction of an uncompleted building did not arise. Having not taken this step, the second plaintiffs cannot expect the first defendants to be liable for the loss which they suffered as a result of their settlement with the purchaser. In the circumstances, the second plaintiffs are only entitled to nominal damages and are awarded $1 for the first defendants' breach of contract.
E. THE FIRST DEFENDANTS' COUNTERCLAIM
64. The first defendants breached the construction contracts for the Swiss Club and Cornwall Gardens projects. As such, although they are entitled to be paid in accordance with the terms of the revised award for $3.45 million for the work done in the Swiss Club project, their counterclaim against the first and second plaintiffs for damages for breach of the construction contracts for the Swiss Club and Cornwall Gardens projects is dismissed. In the circumstances, only the first defendants' counterclaim in relation to the construction of the minor sewer line for the first plaintiffs' Swiss Club project needs to be considered.
65. The first defendants agreed to construct the minor sewer line for the Swiss Club project and connect it to the second defendant's mother's property for $108,295. By the time the first defendants withdrew from the Swiss Club project, about 75% of the work had been completed. On 3 September 1994, the first defendants submitted a claim for $79,117.50 for the work already done to that date. This sum was not paid to them. The first defendants alleged that after their withdrawal from the Swiss Club project in September 1994, the first plaintiffs refused to allow them to enter the Swiss Club project site. They regarded the first plaintiffs' refusal to pay them the amount claimed and to allow them to work on the construction site as a repudiation of the minor sewer contract and they accepted the repudiation.
66. The first plaintiffs have not strenuously denied that they breached the minor sewer contract. What they have asserted is that even if they have breached the minor sewer contract, the first defendants are only entitled to nominal damages as they have suffered no loss as a consequence of the breach. This is because the first defendants subsequently made a contract with one S.K. Ng, who acted on behalf of a number of other persons interested in the minor sewer connection, to complete the minor sewer and connect it to the second defendant's mother's property. Under the contract with S.K. Ng, the first defendants were paid $110,000 for the work already completed under the latter's contract with the first plaintiffs as well as another $110,000 for the work which had to be done to complete the minor sewer line. As the first defendants have already been paid for the entire minor sewer line, they have suffered no loss. The first defendants pointed out that they offered to pay S.K. Ng an amount equal to that owed to them by the first plaintiffs for the work already done if they succeeded in their counterclaim against the first plaintiffs. S.K. Ng, who gave evidence, admitted that the first defendants' offer was not a condition of his contract with the first defendants for the completion of the minor sewer connection. In the circumstances, the first defendants are only entitled to nominal damages of $1 for the first plaintiffs' breach of contract.
F. COSTS
67. As for costs, it is noted that the plaintiffs have only succeeded on the ground of breach of contract. After taking all the circumstances into account, the plaintiffs are entitled to only 50% of their taxed costs.
TAN LEE MENG
JUDGE
Tan Lee Meng J
Jimmy Yim and Richard Choong (Drew & Napier) for the plaintiffs
Chee Wai Pong and Ng Keng Chye (Ng, Ong and Chee) for the defendants