Sit Ley Timber Pte Ltd v Ho Lee Construction Pte Ltd
[1997] SGHC 246
Suit 433/1995
Chao Hick Tin J
30 September 1997
Judgment:
1 In this action the plaintiff, which is a company dealing in timber, sued the defendant for the return of certain machineries - a concrete batching plant and four passenger hoists. At the conclusion of the trial I ruled in favour of the plaintiff. I now give my reasons.
Background
2 Towards the end of 1993 the defendant, Ho Lee Construction Pte Ltd (Ho Lee), was appointed by the Housing and Development Board (HDB) as the main contractor for the construction of HDB flats at a site known as Tampines N3 C15 ("the site"). In turn, pursuant to a sub-contract dated 20 December 1993, Ho Lee engaged Wee Star Construction Ltd (Wee Star) as sub-contractor to carry out the construction works. The person in charge of Ho Lee was one Peter Tan, the Managing Director. The person managing Wee Star was one Leow Cheng Hoe (Leow).
3 On or about 31 December 1993 Ho Lee sold the following items of machineries and vehicles (the machineries) to Wee Star for a consideration of $313,600:-
(i) 1 unit - CFA Batching with two silos and two water tanks;
(ii) 4 units - Passenger Hoist.
(iii) 1 unit - Catepillar Wheel Loader.
(iv) 1 unit - Nissan Mixer Truck (RD8-101560).
(v) 1 unit - Nissan Mixer Truck (RD8-101226)
(vi) 1 unit - Isuzu Mixer Truck.
(vii) 1 unit - Manitou Maniscopic Forklift; and
(viii) 2 units - Winget Model Dumper.
4 To obtain the funds to pay for some of the above, Wee Star entered into hire-purchase arrangements with Singapore Finance with regard to items (iii), (iv), (vi) and (viii). The machineries were brought onto the site and used for the project.
5 To carry out the construction works, Wee Star ordered timber materials from the plaintiffs, Sit Ley Timber Pte Ltd (Sit Ley), whose executive director was one Tan Ah Piaw (Piaw). Sometime in September 1994, Leow approached Piaw for a loan from Sit Ley because Wee Star was in financial difficulties and it could not pay its workers and sub-sub-contractors. If the work did not proceed, there would be delay and Wee Star would be liable to Ho Lee for liquidated damages. Piaw, however, refused to give any loan.
6 Some days later, Leow approached Piaw suggesting that Wee Star would use the machineries as security for the loan. This was again rejected. The next day, Leow told Piaw that the machineries which Wee Star had could be disposed of in the market for $300,000 but as he needed to use the machineries to continue the works he was prepared to sell the machineries to Sit Ley for $200,000, provided that Sit Ley enter into a lease-back agreement with Wee Star to enable Wee Star to continue to use them until 28 November 1994 for a monthly rent of $8,000. Wee Star also promised to buy back the machineries from Sit Ley at $200,000 when Wee Star’s financial position improved in three months’ time. But if Wee Star were unable to buy them back in the said three-month period, Sit Ley would be entitled to dispose of them to third parties and keep the proceeds. Piaw was agreeable to the purchase and lease-back. Accordingly, on 24 October 1994 the machineries listed above were bought over by Sit Ley for a sum of $200,000. The payment was made.
7 I should add here that, though Sit Ley was not in the machinery trade, I found it agreed to buy over the machineries from Wee Star to advance its timber business vis-a-vis Wee Star. A second point is that though Piaw never inspected the machineries, he felt that as the machineries were worth $313,600 on 31 December 1993, a discount of more than a third in just ten months should be a good buy. A third point is that Leow never told Piaw that some of those machineries were on HP from Singapore Finance and that he had no right to sell them. To that extent Leow had deceived Piaw. Piaw only knew of that fact after the commencement of the present action.
8 On or about 31 October 1994, a formal lease-back agreement was entered into between Sit Ley and Wee Star. There was some controversy as to the date on which the lease-back agreement was entered into. On the evidence I found that it was either on 31 October 1990 or 1 November 1994. Nothing turned on that. The lease was for up to 28 November 1994. The agreement was drawn up by Sit Ley’s solicitors and I was satisfied that it was a bone fide arrangement.
9 Upon the expiry of the lease period, Leow informed Sit Ley that Wee Star had not received payment from Ho Lee for work done and asked for an extension of the lease of the machineries . Piaw, for Sit Ley, agreed to an extension.
10 Sometime in mid-December 1994 Wee Star could no longer carry on with the sub-contract. Leow approached one Yong Kok Sian (Yong) of Atisa Service Pte Ltd (Atisa) to take over and complete the works. Atisa agreed. A deed of assignment dated 29 December 1994 was accordingly entered into among Wee Star, Atisa and Ho Lee, under which Atisa assumed all rights and liabilities of Wee Star (other than a sum of $39,000 due to Wee Star from Ho Lee) under the sub-contract. I should add that Atisa started work even before the deed of assignment was formally executed. A pre-condition of the assignment was that Atisa would furnish a security bond for $500,000 for the due fulfillment of the terms of the sub-contract. In addition, Atisa, was also required to furnish a separate security bond for $150,000.
11 Piaw was aware of the assignment of the sub-contract to Atisa and he agreed with Yong to allow Atisa to use the machineries on the site on condition that Yong agreed to (i) buy the machineries for a sum of $200,000 in a few months time when Atisa would have received payment from Ho Lee and (ii) purchase all timber and timber products required for the works from Sit Ley.
12 At the time when negotiations on the assignment were in progress, Yong told Piaw of the requirement of Ho Lee that he must furnish a performance bond of $500,000. Yong asked Piaw for his personal help to obtain the performance bond as Atisa had then just started and did not have the capital or standing to obtain such a bond. I will now quote from Piaw’s affidavit of evidence-in-chief where he stated why he helped Atisa:-
"I agreed to help Atisa as my discussions with Mr Yong convinced me that he was capable of completing the contract with Defendants and thinking that the performance bond was something like an insurance policy whereby I would not be liable for the full sum of $500,000-00 if I were to pay the premiums regularly, I agreed to stand as one of the guarantors indemnifying The Tai Ping Insurance Company for losses it might incur in providing the Defendants with a performance bond to guarantee the due performance of the contract of assignment by Atisa. I only realized that my actual liability under the performance bond could be as high as of $500,000-00 when I sought the advice of solicitors after Atisa defaulted on its contract with the Defendants."
13 Having heard him I was prepared to accept Piaw’s evidence that he stood as a guarantor on account of that misunderstanding. Though he had been in business for sometime he really thought that his liability was only for the premium due, the performance bond being provided by an insurer. I could not find any other reason for Piaw assuming that liability. There was no suggestion that Piaw was in any way related to Wee Star/Leow or Atisa/Yong. Piaw’s relationship with them was purely business and that was in timber. He agreed to assume the liability for the premium in the hope of advancing his timber business.
14 Before a formal contract for the lease and sale of the machineries to Atisa could be drawn up, Atisa encountered difficulties in proceeding with the works because payment received from Ho Lee was less than expected. Thus by 20 January 1995 Atisa had abandoned work. Indeed about a week before 20 January 1995 Atisa intimated to Ho Lee that it could not carry on with the works.
15 In order to pre-empt a call on the performance bond, discussions took place between Ho Lee, Atisa, Piaw and Tai Ping Insurance Co (who issued the performance bond). On 19 January 1995, following the discussions, Lie Kee Pong & Co, solicitors for Ho Lee wrote to M/s Choy & Partners, solicitors for Atisa, inter alia, as follows:-
"We act for M/s Ho Lee Construction Pte Ltd, the main contractor, and understand that you act for M/s Atisa Services Pte Ltd, the sub-contractor for the abovementioned project (the "Project").
We are instructed that your clients have stopped all works on the Project and indicated to our clients that they are unable to proceed further.
Your clients have also requested our clients to take over and complete all the building works. Negotiations have been going on between our respective clients in the meantime with the view of reaching an amicable settlement.
Entirely without prejudice, we are instructed that our clients are willing not to make demand for payment under the Sub-contract Performance Bond if:
1. Your clients pay to our clients the sum of $225,000.00 forthwith by way of Cashier’s Order as partial compensation;
2. Your clients release and forgo and hereafter shall have no claim against our clients for the sum of $150,000.00 or any part thereof now held and retained by our clients as separate security which said sum shall hereafter be forfeited in favour of our clients;
3. Your clients forthwith release or cause to be released in favour of our clients the sum of $100,000.00 deposited by your clients with The Tai Ping Insurance Co Ltd as cash collateral for the issuance of the Sub-contract Performance Bond. For this purpose, your clients shall sign a proper Letter of Authority addressed to the said Insurance Co authorising them to release and pay the said sum of $100,000.00 to our clients.
4. Upon all the abovementioned payment duly received by our clients, the said Sub-contract between our respective clients shall be treated as terminated. Thereafter, your clients shall have no claim whatsoever against our clients for anything whether in respect of the Project, Sub-contract, or all the materials presently on the worksite."
16 It would be noted that what was proposed concerned Ho Lee and Atisa and under it neither of them would have any claim against the other "in respect of the project, sub-contract, or all the materials presently on the site." It did not and could not affect the rights over assets of third parties. On the same day, M/s Choy & Partners, acting for Atisa and all the guarantors (including Piaw), confirmed acceptance of the above and stated that upon payment, "the sub-contract between (Ho Lee) and Atisa shall be treated as terminated and each party shall not pursue any claims against the other." Again what was confirmed was that Ho Lee and Atisa would not have any claim against each other on account of the sub-contract.
17 Another significant point to note is that while the letter of M/s Lie Kee Pong referred to "all the materials presently on the site" nothing was mentioned of the machineries.
18 Sometime in early February 1995 Sit Ley secured a buyer for the machineries (including the vehicles listed in paragraph 3 above) for $309,000. At the time Piaw did not know yet that some of the machineries were on HP from Singapore Finance. The plaintiffs sought to remove the machineries from the site. Ho Lee’s staff refused Sit Ley’s representatives access to the site to identify the machineries. On 21 February 1995 Sit Ley’s solicitors offered to forward documents to prove that Sit Ley was the owner. Ho Lee did not respond to that.
19 In the meantime, soon after the settlement was reached, Leow wanted to take away the equipments of Wee Star which were in the site office. The evidence of the parties is at variance as to what Leow wanted to remove. According to Ho Lee’s witnesses, Leow wanted to remove the batching plant and the passenger hoists. It was alleged that Leow told Peter Tan that he was in dire financial strait. To stop Leow’s nuisance, on 28 January 1995 Ho Lee paid a sum of $15,000 to Leow "as purchase of their reversionary and other rights in the machineries." However, according to Leow, the $15,000 was in payment of the equipments and other assets in the site office; he did not sell the machineries as they did not belong to Wee Star. Furthermore, he said that it was absurd to suggest that he would sell the machineries for only $15,000, when they were worth $309,000 a year ago.
20 The present action was instituted by Sit Ley on 15 March 1995 to recover items (i), (ii), (iv), (vii) and (viii) of the machineries listed in paragraph 3 above. On the same day Sit Ley obtained an ex-parte order directing Ho Lee to deliver up the machineries to Sit Ley. On 22 March 1995 the ex-parte order was set aside on the application of Ho Lee.
21 On 19 April 1995, Sit Ley amended the Statement of Claim to exclude those items of machineries which were either on HP or could not be found and claimed only the batching plant and the four units of passenger hoists (hereinafter called "the batching plant and hoists"). In July and August 1995, pursuant to orders of court, the batching plant and hoists were sold and the net proceeds were held by the plaintiffs’ solicitors as stakeholders. At the time of the trial before me the proceeds of $61,000 were still held by the plaintiff’s solicitors.
Issues
22 Sit Ley claimed the batching plant and hoists as owner, having bought them, together with the other machineries, from Wee Star, who in turn bought them from Ho Lee. In their Defence filed, Ho Lee pleaded that "the sale from Wee Star to Sit Ley was a sham and not bona fide as a result of which Sit Ley did not acquire good title." An alternative defence was that Sit Ley were estopped by their conduct from asserting their title to the machineries.
23 I should at this juncture mention that on the day of the commencement of the trial, Ho Lee sought to amend its pleadings to plead a defence based on the Bill of Sales Act. As no acceptable reason was advanced why that defence was not raised earlier and as granting leave to amend would lead to vacating the trial dates, I refused the application to amend. They should have seen this point well before the trial.
Sale
24 There was clear documentary evidence before me (7AB64) to show that Wee Star sold the entire lot of machineries to Sit Ley. There was also evidence which proved that Sit Ley paid $200,000 for them. Ho Lee was not able to adduce anything concrete or credible to challenge the genuineness of those documents.
25 As mentioned above, it was true that at the time when Sit Ley bought those machineries for $200,000, Piaw did not inspect them. But he relied upon the fact that barely ten months before, Wee Star paid $313,000 for them. He saw the sale invoice of Ho Lee. Piaw accepted Leow’s assurance that $200,000 was a good price so much so that Leow even promised Piaw that in a few months’ time, when his cash flow situation improved, he would buy the machineries back from Sit Ley. This promise of Leow to re-purchase was of course, at best, conditional. However, if Wee Star did not buy them back within a few months, Sit Ley would be free to sell them to any person at any price.
I found that what was effected was a sale by Wee Star to Sit Ley. That was what was intended by Piaw, who was prepared to help Wee Star having regard to the then existing business relationship between Wee Star and Sit Ley, with the former buying timber from the latter. Furthermore, after the 3-month period, Sit Ley would not be bound to sell to Wee Star and could sell to any third party and if the sale price were more than $200,000, Sit Ley would not have to account for the excess to Wee Star. Indeed Sit Ley could also not recover any shortfall from Wee Star if the sale price were less than $200,000. If it were a loan, Sit Ley should be able to do that. In any case, upon assignment of the sub-contract from Wee Star to Atisa, Wee Star’s promise to buy back in 3 months’ time had effectively been withdrawn. Atisa was told that the machineries belonged to Sit Ley.
26 Much was made of the fact that Piaw did not inspect the machineries before he agreed to purchase from Wee Star. Basically, he trusted Leow and accepted the sale invoice of Ho Lee showing the price which Wee Star paid. Even Ho Lee agreed to Atisa taking over the sub-contract from Wee Star without checking the credentials or previous work experience of Atisa.
Estoppel
27 I now turn to the question of estoppel. Here Ho Lee argued, relying on the first assignment of the sub-contract from Wee Star to Atisa, that upon further assignment by Atisa to Ho Lee, that the right to use the machineries, as opposed to ownership, must also have been assigned along with it. This was the confusion in Ho Lee’s case; they seemed to be concerned more with the right to use rather than ownership.
28 Ho Lee, by its Managing Director, Peter Tan, also relied upon the fact that in the course of negotiations leading to the settlement on 19 January 1995, Piaw never mentioned that the machineries had been bought over by Sit Ley. This was the basis upon which Ho Lee alleged estoppel. Now I shall quote what Peter Tan said in his affidavit of evidence-in-chief:-
"In the absence of any protest or any mention of the ownership rights by the Plaintiffs, the defendants accepted the terms of settlement on the understanding that the defendants would be entitled to retain and use the Machineries to complete the construction work. If the Plaintiffs had fulfilled their duty to speak and made known their rights over the Machineries at the various meetings where they had ample opportunities so to do, the Defendants would not have settled the matter with Atisa on the terms they had. This is because, as stated earlier, the removal and installation of new concrete batching plant and hoists would involve great expense and tremendous losses from hindrance to the work in progress. The defendants would have insisted on all their rights, that is to say, call upon the performance bond in full and forfeit the security bond of $150,000.00 (i.e. $650,000.00 in total)"
29 I was surprised by what Peter Tan’s alleged. If the continued use of the machineries was very much in his mind why didn’t Peter Tan raise it expressly, either at the discussion or in writing. The letter from Ho Lee’s solicitors of 19 January 1995 referred to the "materials" on site, not the machineries. If it were true that the question of the "machineries" was in the mind of Peter Tan, why didn’t he say so. It would have been the most natural thing to do. In his evidence, Peter Tan agreed that there is a difference between "materials" and "machineries". Indeed, he being an experienced contractor, must know the difference.
30 The indisputable fact is that at the negotiations no one mentioned about the machineries. In appropriate circumstances, it is possible to infer representation by conduct. But here Peter Tan said that at the time of the negotiation for a settlement the machineries were very much in his mind. There was nothing to suggest that it was in Piaw’s mind. In fact Piaw’s evidence was he did not think of the machineries. It was perfectly understandable if Piaw’s mind was pre-occupied with his liability under the guarantee having then discovered the mistake and the grave consequence of his error. I accepted his evidence that the machineries were not in his mind
31 The truth of the matter is this: this aspect did not enter Peter Tan’s mind when he was negotiating on the settlement, as it did not enter the mind of Piaw. I found this to be an instance of ex-post facto rationalization. There was no question of any reliance; thus no estoppel.
32 What Ho Lee was really saying is that it was an implied term that the machineries would belong to Ho Lee following the assignment of the works back to Ho Lee. From the affidavits filed in the interlocutory proceedings reliance was placed on clause 55 of the main contract, which Ho Lee contended formed a part of the sub-contract. Assuming this contention is valid, there is a need to examine what clause 55 provided and here I quote:-
(1) All Plant Temporary Works materials and goods provided or owned by the Contractor or by any person firm or corporation in which the Contractor has a controlling interest shall when brought on the Site be deemed to be the property of the Employer, and the Contractor shall not remove the same or any part thereof without the prior written consent of the Superintending Officer’s Representative, which consent shall not be unreasonably withheld. The Employer will
permit the Contractor the use of all such Plant Temporary Works materials and goods for the carrying out and completion of the Works which permission shall cease upon the occurrence of any event entitling the Employer to exclude the Contractor from the site and proceed himself to complete the Works.
(2) Upon the removal from the Site of any plant Temporary Works materials or goods with consent as aforesaid, the property in the same shall be deemed revested in the Contractor." (Emphasis added).
33 Clause 55 could not apply to the instant situation because the machineries did not belong to Ho Lee but to Wee Star and later to Sit Ley. For plants and materials to fall within that clause, those things must be provided or owned by Ho Lee or by "any person, firm or corporation in which (Ho Lee) has a controlling interest."
34 In the circumstances of the present action I could not see how any term could be implied. It was expressly stated in the correspondence that materials on site would go to Ho Lee following the settlement. By not mentioning machineries or plants, if there was anything to be implied, I would have thought that it would be the other way, namely, plants/machineries would not go to Ho Lee.
35 The evidence of Peter Tan showed that he was quite confused as to whom he thought owned the machineries. At one point he said he thought the machineries belonged to Wee Star and the latter had only allowed Atisa to use them. Later, he said he thought the machineries belonged to Atisa. Furthermore, as mentioned before, even on Peter Tan’s evidence he was talking of right to use rather than ownership. He said that upon assignment of the sub-contract from Wee Star to Atisa, the right to use the machineries was assigned to Atisa. He also said "the defendants accepted the terms of settlement on the understanding that the defendants would be entitled to retain and use the machineries to complete the construction work." There was no assertion that ownership passed. Even on this basis, Ho Lee should have returned the batching plant and hoists to Sit Ley sometime in May 1995 when the works at the site had been completed.
36 Finally, there is the payment of $15,000 which Ho Lee made to Leow. According to Ho Lee’s payment voucher, it was for "purchase of batching plant and four units of passenger hoists". Peter Tan tried to explain away the significance of this payment by saying that this was a payment to get rid of a nuisance, so that Leow would not come to cause trouble anymore. This was in contradiction to what was stated on the voucher. There were other questions to be answered. He said he thought the machineries had already belonged to Ho Lee under the settlement. Then why the need to pay for them again. Peter Tan said he paid the $15,000 to emphasise Ho Lee’s ownership: what that means is far from clear. As mentioned above, Peter Tan also thought the machineries belonged to Atisa. Then why pay to Wee Star? Why was he paying only $15,000 when the machineries (or even just the batching plant and hoists) were worth much more than $15,000? The truth as I found, was that Peter Tan paid Leow $15,000 for two things: (ii) the office equipments which were left behind by, and which belonged to Wee Star, and (ii) to ensure that Leow did not cause any more nuisance.
37 In any case, even if it were true that Ho Lee was buying the machineries for $15,000, Leow (and Wee Star) had no title to pass to Ho Lee in the same way that Wee Star had no title to pass to Sit Ley in respect of those items on HP from Singapore Finance. A person can only sell what he owns. Ho Lee was deceived by Leow; in the same way that Sit Ley was deceived by Leow to the extent that the latter purported to sell machineries which did not belong to Wee Star.
Orders
38 In the light of the foregoing I made an order in terms of prayer 1 to declare that Sit Ley was the owner of the batching plant and the four passenger hoists.
39 Accordingly, Sit Ley was entitled to have the plant and hoists returned to them in February 1995. As mentioned before, pursuant to orders of court, the batching plant and hoists were sold in September 1995 and the proceeds of $61,000 were being held by the plaintiff’s solicitors as stakeholders. It became necessary to determine what was their value as at February 1995.
40 There was evidence before me to show that before the batching plant and hoists were sold by auction they were dismantled by Ho Lee separately, and over a period of time, incurring a total cost of about $16,000. It was argued for Ho Lee that had the batching plant and hoists not been dismantled, they would not have fetched $61,000. On the other hand the plaintiffs argued that had the plant and hoists been dismantled in one exercise, the costs would be significantly less. There was no evidence before me to show how much the buyer would have paid for them if the buyer had to dismantle them. However, for the purpose of determining that value, I was prepared to take a broad view of things and reckon that the actual price paid would be reduced by $11,000, (being the reasonable cost of dismantling) giving it a value of only $50,000.
41 It was not disputed that Wee Star bought the batching plant and hoists from Ho Lee on 31 December 1993 for $135,000. In September 1995 their value, as computed above, was only $50,000. In the absence of any other evidence to help me determine the true value of the plant and hoists as at February 1995, I felt it would not be unfair to use the straight line depreciation method. Therefore, for approximately 20 months (1 January 1994 to September 1995) the depreciation was $85,000 ($135,000 less $50,000). Up to February 1995, it would be only about 13 months. It follows that as at February 1995 their value would be ($50,000 + [$85,000 x 7/20]). Thus Sit Ley should be entitled to $79,750. Accordingly, I directed that the plaintiff’s solicitors, the stakeholders, pay the $61,000 over to the plaintiff and in addition the defendant should pay the plaintiff the difference of $18,000 (rounding it down from $18,750).
42 I awarded costs to the plaintiff on the District Court scale to be taxed, if not agreed.
Chao Hick Tin
Judge
Singapore
30th September 1997
Joseph Lopez with Aaron Nathan (Choy & Lopez) for the plaintiffs
Peh Chong Yeow with Lim Mei Ann (Lie Kee Pong & Co) for the defendants