This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

In the High Court of the Republic of Singapore
[1997] SGHC 43
Suit 1043/1996, SIC 3798/1996
Between
Chip Hua Poly-Construction Pte Ltd
… Plaintiff
And
Housing and Development Board
… Defendant
grounds of decision
Credit and Security — Performance bond; Credit and Security — Performance bond; Civil Procedure — Injunctions; Words and Phrases

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Chip Hua Poly-Construction Pte Ltd v Housing and Development Board
[1997] SGHC 43
Suit 1043/1996, SIC 3798/1996
MPH Rubin J
28 February 1997
1 Chip Hua Poly-Construction Pte Ltd, the plaintiffs herein, applied to the court for the continuation of an ex parte injunction obtained by them on 10 June 1996 restraining the Housing and Development Board (HDB), the defendants herein, from calling on a security bond provided by the plaintiffs to the defendants in connection with the defendants` construction project at Jurong West (the Jurong West contract). After hearing arguments from both sides, I disallowed the plaintiffs` application and my grounds now follow.
2 The averments contained in the affidavits of the plaintiffs and the defendants establish that the plaintiffs who were the sole contractors in relation to the Jurong West contract were also joint contractors with one Hock Heng Trading and Construction Pte Ltd (Hock Heng) in respect of the defendants` five other projects at Choa Chu Kang, Bukit Panjang, Hougang and Serangoon (the five contracts).
3 The Jurong West contract was entered into between the defendants and the plaintiffs on or about 30 July 1992, pursuant to which the plaintiffs furnished the defendants with a security bond dated 4 August 1992 (Jurong West security bond) issued by UMBC Insurance Sdn Bhd for a sum of $818,500 - the subject matter of dispute in the proceedings before me.
4 Inasmuch as the dispute between the parties centre round the construction of the said Jurong West security bond, the relevant provisions thereof read as follows:
[Preamble:]
By this bond we Chip Hua Poly-Construction (Pte) Ltd of No 45 Lorong 27 Geylang Singapore 1438 (hereinafter called the contractor) and UMBC Insurance Sdn Bhd of 1 North Bridge Road [num ]08-01 High Street Centre Singapore 0617 (hereinafter called the surety) are held and firmly bound unto the Housing and Development Board, Singapore [HDB] in the sum of dollars eight hundred eighteen thousand and five hundred only ($818,500) for the payment of which sum the contractor and the surety bind themselves, their successors and assigns jointly and severally by these presents.
[Recital (1):]
The [HDB] has accepted the tender of the contractor for building including sanitary, water and gas installation at Jurong West Neighbourhood 3 Contract 21 (neighbourhood centre), Singapore (Contract No A/296/92) (hereinafter called the said works) resulting in a contract for the said works (hereinafter called the said contract).
[Clause 1:]
The contractor and the surety shall immediately without question and unconditionally pay on demand any sum or sums which may, from time to time, be demanded by the [HDB] up to a maximum aggregate sum of $818,500.00. [Emphasis added.]
[Clause 3:]
The [HDB] may demand payment of a sum or sums under this bond in satisfaction of moneys due from the contractor to the [HDB] under the provisions of any other contractmade between the contractor and the [HDB]. The [HDB] shall not in connection with a demand whether made under the said contract or under any other contract be required to prove either a breach of contract or duty or damages arising from such breach. [Emphasis added.]
[Clause 8:]
... any demand under this bond shall be conclusive that the sum or sums demanded is or are due and payable provided that, ... the sum or sums demanded shall be paid irrespective of:
...
(c) the use or intended use by the [HDB] of the sum or sums demanded;
(d) any dispute or matter between the surety and/or the contractor on the one hand the [HDB] on the other hand regarding directly or indirectly the said contract or any other contract or otherwise . [Emphasis added.]
[Clause 9(a):]
... the [HDB] is not liable to account or explain to the contractor or the surety for the application of any sum or sums paid hereunder and the [HDB] may apply the sum or sums in any way that it thinks fit. [Emphasis added.]
[Clause 9(b):]
Without prejudice to or limiting Clause 9(a) above, the [HDB] may apply the sum or sums paid hereunder:
i towards reducing or settling any liability of the contractor ... whether contractual or otherwise , and if contractual, whether under the said contract or any other contract and/or;
ii by paying some or the entire part thereof to the surety or the contractor or to any other person as the [HDB] thinks fit. [Emphasis added.]
5 Insofar as material, the Jurong West contract entered into between the plaintiffs and the defendants as regards the construction project at Jurong West incorporated the following clauses from the HDB`s general conditions of contract (GCOC):
Clause 14(1):
... the contractor shall deposit free of interest with the [HDB] the sum provided in the contract to be held by the [HDB] as security for due performance by the Contractor of each and every liability and obligation owing by the Contractor to the [HDB], whether of a contractual or tortious nature and whether arising under the Contract or otherwise, such sum to be retained or otherwise properly dealt with by the [HDB] ...
Clause 14(2):
the contractor may in lieu of the deposit as ... required under sub-cl (1) of this clause provide the [HDB] with a security bond for an equivalent sum ...
Clause 62(1):
All damages (including liquidated damages), costs, charges, expenses, debts or sums for which the contractor is liable to the employer under any provision of the contract may be deducted by the employer from monies due or becoming due to the contractor under the contract or under any other contract between the employer and the contractor including any retention moneys, financial bonds or security deposits or bonds. [Emphasis added.]
Clause 62(2):
All damages (including liquidated damages), costs charges, expenses, debts or sums for which the contractor is liable to the employer under any provision of any other contracts between the contractor and the employer may be deducted by the employer from moneys due or becoming due to the contractor under the contract, including any retention moneys, financial bonds or security deposits or bonds.
6 In relation to the five contracts awarded to the plaintiffs jointly with Hock Heng by the defendants between 6 December 1993 and 17 January 1995, the plaintiffs and Hock Heng provided the defendants with five additional security bonds at various intervals - the value of which totalled $4,798,340.
7 It was common ground between the parties that the work under the five contracts did not proceed according to expectation. The defendants` claim that they had suffered losses under the five contracts (excluding losses that had arisen as a result of re-tendering) as at 14 June 1996 as follows:
(a)
Total amount outstanding on HDB bills
$
1,545,484.26
(excluding a sum of $358,217.41 which
was deducted under the Jurong West contract)
(b)
Shortfall in certified workers
$
394,500.00
(c)
Accrued liquidated damages
$
4,610,269.00
Sub-total:
$
6,550,253.26
Less:
(1)
Amount retained by HDB on the five contracts
$
483,350.00
(2)
Amount recovered under the five security bonds
$
4,798,340.00
Total amount due to the HDB:
$
1,268,563.26
8 It was not in dispute that the plaintiffs had already made a call and received a sum of $4,798,340 on the security bonds under the five contracts and the dispute between the parties herein is solely in relation to the Jurong West security bond. It should be mentioned at this juncture that the issue for resolution before me was not whether the amount claimed as damages was indeed payable but whether the call made by the defendants on the Jurong West bond was invalid or unlawful in the context of the affidavit evidence placed before me and on the construction to be placed on the Jurong West security bond and the Jurong West contract.
9 The plaintiffs` main contention before me was that the defendants were not entitled in law or in equity to call on the Jurong West security bond in respect of losses suffered by the latter in relation to the five contracts. In this regard, the plaintiffs` allegations and contentions as summarised by their counsel in paras 8 to 14 of his written submission are as follows:
... During the progress of the works for the five other projects, there were delays in the works for the five projects resulting in disputes between the plaintiffs and Hock Heng.
... There were various meetings between the plaintiffs, defendants and sureties of the bonds for the five other projects wherein the plaintiffs say that an agreement was reached the effect of which is that the plaintiffs/Hock Heng were to cease work on the five other projects after which the defendants would formally terminate the five contracts and award the work to the insurance companies or contractors nominated by them to complete the balance of the works. However, contrary to the agreement, the defendants awarded the contract to other contractors with higher prices pursuant to public tenders. (Paras 11 to 21 of plaintiff`s joint affidavit 10 June 1996).
... Further, the defendants` representative agreed with the plaintiffs that the Jurong West C21 contract and the Jurong West security bond would not be affected by the five other projects and that the defendants would treat this separately from the other five projects and they would not call for payment under the Jurong West security bond if the plaintiffs put in extra effort and accelerated the works for the Jurong West C21 contract.
... Pursuant to the agreement and in reliance on the defendants` representation, the plaintiffs put in extra effort and incurred extra costs and laboured throughout the night to accelerate the works and complete the same on 15 November 1995, before the contractual date of 20 November 1995 and the certificate of completion of the Jurong West C21 contract was issued by the defendants on 9 March 1996. (Paras 22 to 24 of plaintiff`s joint affidavit 10 June 1996).
... Subsequently, the defendants informed the plaintiffs that they intended to call on the security bonds for the five other projects as well as the Jurong West security bond in satisfaction of the alleged losses for the five projects. The defendants then proceeded to make a `call` on the five bonds and also the Jurong West security bond. (Paras 25 to 27 of plaintiff`s joint affidavit 10 June 1996)
... The wordings of the `call` dated 29 May 1996 on the Jurong West security bond [CHP-8 p 191] are as follows:
1 Pursuant to the abovesaid bond, this is our formal call of payment of the sum of Singapore dollars eight hundred and eighteen thousand and five hundred only (S$818,500).
3 We would appreciate your remittance of S$818,500,00 in favour of the Housing and Development Board by 12 June 1996.
... The plaintiffs submit that the Jurong West security bond may not be applied in satisfaction of moneys allegedly due for the five other projects on the following main grounds:
Ground (a) Based on a true construction of the Jurong West security bond, the bond cannot be so applied.
Ground (b) Based on a true construction of the Jurong West security bond, the call for payment dated 29 May 1996 was invalid.
Ground (c) Based on the agreement and/or representation by the defendants that they would not call on the Jurong West security bond if plaintiffs accelerated the works and it is unconscionable for the defendants to do as the defendants would be estopped from asserting otherwise and,
Ground (d) It is unconscionable for the defendants to call on the Jurong West security bond in satisfaction of the losses for the five other projects as the defendants did not take reasonable steps to mitigate their losses but proceeded to call for public tender contrary to what was agreed.
10 Dealing first with the allegation that the defendants had agreed to formally terminate the Five Contracts and award fresh contracts to insurance companies to complete the remainder of the work, I found that these assertions were not borne out by the documents referred to me by plaintiffs` counsel; neither was I referred to any material to substantiate yet another contention by the plaintiffs that the defendants` representatives had agreed with the plaintiffs that the former were amenable to treating the Jurong West Security Bond as separate and apart from the Five Contracts. I must hasten to add presently that in arriving at the foregoing conclusions, I was mindful of the limitation that what I had before me was only affidavit evidence and that too had yet to be tested by cross-examination. I was equally conscious of the aspect that the issue as to liability between the parties was still extant and whatever evidence adduced through affidavits would have to be revisited and fully evaluated by the court hearing the main action later. The scope of my adjudication in regard to the application before me was plainly confined to the question whether the documents and affidavit evidence placed before me would justify my granting an order for the continuation of the interlocutory injunction restraining the defendants from exercising whatever rights they may have under the Jurong West Security Bond.
11 The defendants` denials in this regard had been set out in the affidavit of their chief contract manager, Mr Tan Thai Hong filed on 2 July 1996. It is unnecessary for me to recapitulate them except to say that the denials contained therein appeared to possess a ring of cogency around them as opposed to the several unverified claims of the plaintiffs.
12 Following the principles enunciated by the Singapore Court of Appeal in Bocotra Construction Pte Ltd v A-G (No 2) [1995] 2 SLR 733 , an injunction will only be granted to restrain a beneficiary from calling on a performance bond in exceptional cases where the party seeking the injunction presents to the court compelling evidence of fraud or unconscionability.
13 In Bocotra , Karthigesu JA in delivering the judgment of the Court of Appeal, observed at p 746I:
In our opinion, whether there is fraud or unconscionability is the sole consideration in applications for injunctions restraining payment or calls on bonds to be granted. Once this can be established, there is no necessity to expend energies in addressing the superfluous question of `balance of convenience`. It does not lie in the mouth of the defendant to claim that damages would still somehow be an adequate remedy.
14 Later, addressing the issue relating to the standard of proof required on allegations founded on fraud or unconscionability, Karthigesu JA commented (at 747C) that `[indeed], a higher degree of strictness applies, as the applicant will be required to establish a clear case of fraud or unconscionability in interlocutory proceedings. It is clear that mere allegations are insufficient.`
15 In my view, the exchange of letters referred to and the negotiations which were under way consequent upon the breach of the five contracts, do not establish even a faint case of unconscionability or fraud - let alone the `higher degree of strictness standard` propounded in Bocotra . Given the factual matrix, the plaintiffs` contention that the defendants acted unconscionably when they made the call on the bond, is an allegation without any foundation.
16 Another major contention advanced by the plaintiffs is that on the true construction of the Jurong West security bond, the same could not be applied in satisfaction of moneys due for the five contracts. In my opinion, this contention does not take into account the express phraseology employed in the Jurong West security bond which permits little room for debate. First, cl 1 of the Jurong West security bond could not be more precise. It expressly states that once the demand had been made, payment must be made `immediately without question` and `unconditionally`. Secondly, cl 3 of the same bond states that `the defendants may demand payment ... under [the] bond in satisfaction of moneys due from the [contractor] to the [HDB] under the provisions of any other contract made between the [contractor] and [HDB]`. Thirdly, leaving for the time being the import of cl 8 of the bond under reference which I shall refer to shortly, cl 9(b) therein enables the plaintiffs to apply the sums to be received thereunder: `(i) towards reducing or settling any liability of the [contractor] ... whether contractual or otherwise , and if contractual, whether under the said contract or any other contract ...` `Any` is a word which excludes limitation or qualification (per Fry LJ, Duck v Bates 53 LJQB 344). The phrase `any other` makes the context even wider and does not permit limitation ( Bastow v Bennett [1812] 3 Camp 220 ; 170 ER 1360).
17 In the premises, the argument by plaintiffs` counsel that the Jurong West security bond can be called on only in satisfaction of a breach under the Jurong West contract and not in relation to the five contracts where the plaintiffs and Hock Heng had a joint venture, causes much violence to the explicit and pointed phraseology of the said bond. I could not discern any ambiguity in the phraseology used and therefore the submission that the court should apply the contra proferentum rule against the defendants is wholly misconceived.
18 The next aspect relates to the conclusive evidence provision contained in the Jurong West bond. Clause 8 of the bond provides that any demand made thereunder shall be conclusive; that the sums so demanded shall be due and payable and they shall be paid irrespective of any dispute between the parties whether directly or indirectly, under the said contract, any other contract or otherwise. The conclusive evidence clause has been a subject of discussion in many leading cases. In Singapore, decided cases support the principle that in the absence of fraud or a patent error on the face of the certificate, a certificate so issued under such a clause is conclusive evidence as to the amount stated therein as well as to liability (see Bangkok Bank Ltd v Cheng Lip Kwong [1990] 2 MLJ 5 approving Dobbs v National Bank of Australasia Limited (1935) 53 CLR 643).
19 Having regard to all the facts placed before me, including the feature that the bond under reference was furnished by the plaintiffs in lieu of cash, as provided under sub-cll 14(1) and (2) of the GCOC (see para 5, supra), I found the plaintiffs` application that the defendants be restrained from calling on the Jurong West bond and that the exparte injunction issued on 10 June 1996 be allowed to continue, ill-founded. The plaintiffs had, in my view, fallen well short of the higher standard of proof required for the issue of an interlocutory injunction based on grounds of unconscionability, fraud or some obvious error on the part of the defendants. In the result, the plaintiffs` application was dismissed with costs. Against my order the plaintiffs now appeal.
20 Application dismissed.
MPH Rubin J
Peter Chow and Lim Yong Khern (Wee Swee Teow & Co) for the plaintiffs
Andre Francis Maniam and Lawrence Tan (Wong Partnership) for the defendants