In the High Court of the Republic of Singapore
[1997] SGHC 65
Suit 1925/1993
Between
K G M Brothers Contractors Pte Ltd
… Plaintiff
And
Tang Dynasty City Pte Ltd (formerly known as Tang Dynasty Village Pte Ltd)
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
K G M Brothers Contractors Pte Ltd v Tang Dynasty City Pte Ltd (formerly known as Tang Dynasty Village Pte Ltd)
[1997] SGHC 65
Suit 1925/1993
Judith Prakash J
17 March 1997
Judgment:
Cur Adv Vult
JUDGMENT
Background 1. The plaintiffs are contractors in the business of laying underground sewer and other pipes. The defendants are the owners of the theme park known as Tang Dynasty Village in Jurong and were the main contractors for the construction of the park. In this action, the plaintiffs claim in tort for damages caused by the defendants to a stretch of industrial water pipes laid by the plaintiffs in August 1990 along the site of the park pursuant to a contract between themselves and the Ministry of the Environment ('MOE').
2. The park is set on a rectangular piece of land, lying alongside Jalan Ahmad Ibrahim and bounded by Yuan Ching Road to the west and the Jurong river to the east. Part of the route of the proposed pipeline ran in a straight line along the 700 metre long border fronting Jalan Ahmad Ibrahim. In the plans shown to me, this area was identified as running between chainage 533 and chainage 1233.
3. The defendants occupied the site of the park as licensees of a subsidiary of the Jurong Town Corporation ('JTC'). They submitted their plans for the park to the JTC in 1988 and to the Building Control Department ('BCD') in early 1989. The plans were approved by the JTC in February 1989 and by the BCD in July 1991, but, according to the defendants' evidence, actual work on the park had started earlier.
4. The park was divided into four zones. Part of the plan for the park, as designed, was to create an artificial hill in zone 4 which was to simulate the cemetery in which the Empress Yang Gui Fei had been buried. According to the defendants, from June 1989 construction and piling works were carried out on their site and from about July 1989 onwards their sub-contractors started excavation works to construct various pools and ponds on the site. The earth excavated was then stockpiled and, the defendants said, used as the foundation of the artificial hill.
5. The plaintiffs first went on to the site in about July 1990 prior to commencing their pipe laying works in August 1990. The strip where the pipes were to be laid bordered Jalan Ahmad Ibrahim. If one was standing on Jalan Ahmad Ibrahim looking in the direction of Yuan Ching Road and away from the city, then one would have noticed that about 20 metres right of the road ran a 2 metre wide concrete U-drain. The pipeline was to be laid further inland, parallel to the drain and about 24 metres from the road. The plaintiffs noticed that about 2 metres right of the proposed pipeline the defendants had built a high fence wall stretching from chainage 556 to chainage 864. From that point up to chainage 1222, the defendants had built a plywood boarding.
6. The plaintiffs commenced their pipe laying on 8 August 1990 at chainage 1222 and completed the stretch of pipeline up to chainage 1222 by 24 August 1990. They continued upstream, and by 21 December 1990 had laid pipes up till chainage 548. When they commenced work, the plaintiffs noticed that the defendants were conducting piling works on their land between chainage 864 and chainage 1064. They also noticed the presence of a cement batching plant and several cement mixers. The plaintiffs admitted that they had seen some earth stockpiled behind the batching plant but asserted that that pile was very far away from the site of their works.
7. The plaintiffs stopped work after 21 December 1990 as they had to wait for the arrival of some special pipes before continuing onwards from chainage 1222. They therefore left the site for some time. In August 1991 the plaintiffs' site supervisor, Mr Tan Peng Song, went to the site prior to commencing the remaining works. He noticed that the defendants' building works had progressed half way and that they had replaced the hoarding with a low fence wall from chainage 864 to chainage 1213. He also noticed certain developments in the stretch between chainage 1222 to chainage 1112. The defendants' low fence wall in that stretch had developed gaps at the joints and the wall of the U-drain was collapsing. He also saw a huge pile of earth on the defendants' land and estimated that it was about 9 metres away from the pipeline.
8. When the plaintiffs next returned to the site in November 1991 to commence the remaining work, Mr Tan noticed more extensive signs of damage to the defendants' low fence wall and to the U-drain. He therefore feared possible damage to the pipeline laid in the stretch from chainage 1222 to chainage 1155. Subsequently, the plaintiffs established that in fact 55 metres of pipes in this area had been damaged and had to be re-laid.
The brief particulars of the damage ascertained by the plaintiffs were that at joints numbers 1, 2, 3 and 4 (between chainages 1172.2 and 1188.7) there had been a dislocation of the joints with gaps ranging between 250 mm to 400 mm; the 5th to the 8th joints (between chainages 1194.2 and 1210.7) were dislocated with gaps of approximately 150 mm each; and at the 9th and 10 joints (between chainages 1216.2 and 1221.7) no dislocation of the joints had taken place but the pipe spigot had been forced into the socket and thereby deformed.
The pleadings 9. In their statement of claim, the plaintiffs alleged that the damages that they had sustained by reason of having to relay part of the pipeline had been caused by the defendants' negligent bringing onto and/or stockpiling of earth on their land in the vicinity of the plaintiffs' completed work and/or the escape thereof. The plaintiffs gave inter alia the following particulars of negligence:
(1) failing and/or neglecting to take account of or ascertain the presence of underground pipes in the vicinity before bringing on and/or stockpiling earth;
(2) failing and/or neglecting to take into account the ground conditions and/or ground stability before the bringing on and/or stockpiling of the earth;
(3) bringing on and/or stockpiling large quantities of earth on the defendants' land;
(4) heaping up the earth in close proximity to the plaintiffs' completed pipeline;
(5) not paying any or any adequate attention to the effects on the plaintiffs' work of the defendants' bringing on and/or stockpiling large quantities of earth on their land; and
(6) failing to take account of the possible earth movements the bringing on and/or stockpiling of earth may cause.
10. In their defence as originally filed, the defendants took various tacks. First, they denied that they were guilty of the alleged or any negligence and asserted that any damage which the pipeline may have sustained was not the result of the alleged or any negligence on the part of the defendants. This was a defence they maintained throughout. The defendants' second defence, which was dropped at the beginning of the trial was that if the plaintiffs' pipeline had been damaged then such damage was solely caused by the negligence of various named independent contractors appointed by the defendants.
11. Thirdly, as an alternative, the defendants maintained that the damage was caused wholly or in part by the plaintiffs' own negligence. This defence was relied on in the submissions. The particulars of the plaintiffs' negligence as asserted by the defendants were as follows:
(1) failure to pile the earth below the pipeline to ensure that the earth would be secure enough to support the weight of the pipeline;
(2) failure to line the earth below the pipeline with a protective layer to ensure that the earth was able to support the weight of the pipeline;
(3) backfilling the trench in which the pipeline was laid with earth without taking the necessary precautions to ensure that such backfilling would not affect and/or damage the pipeline;
(4) failure to take steps to protect the pipeline from possible soil movement ie driving sheet piles alongside the pipeline although the plaintiffs were well aware at all material times that there had been construction works on and around the site even before the plaintiffs had commenced work at the site; and
(5) failure to carry out a study on the nature of the soil or earth at the site and to sufficiently protect the pipeline from soil movements.
The evidence : (1) on the facts 12. Before I go into the evidence, I should explain how I will be identifying the various photographs adduced in court and referred to both by the witnesses and by counsel in their submissions. The photographs will generally be identified by reference to bundle of documents in which they appeared.
Photographs in the plaintiffs' bundle are therefore 'PB' followed by the page number and photographs in the defendants' bundle are 'DB' followed by the page number. On page 23 of the plaintiffs' bundle, there are two photographs arranged vertically. The top one is identified as PB23(1) and the bottom photograph as PB23(2). On page 162 of the defendants' bundle, there are also two photographs, this time arranged horizontally. As the left hand photograph was not used at all in the evidence, when I refer to DB162 I should be taken as referring to the right hand photograph on that page. Further, there were a number of photographs which were annexed to the report of the plaintiffs' expert witness. These photographs are numbered in the report and will be identified by the prefix ER followed by the relevant number appearing in the report.
13. The plaintiffs had two witnesses of fact. The first was their managing director, Mr G P M Pillai. In his evidence-in- chief, he recounted the plaintiffs' case as summarised in the introduction. Under cross-examination, he asserted that he had visited the site about a week prior to the commencement of the plaintiffs' works. During his visit he could see the defendants' land. It was an open space and, according to Mr Pillai, nothing much was going on. He did not see either piling works nor excavation works nor any area where earth was being stockpiled.
14. Subsequently, Mr Pillai stated that the defendants were carrying out some construction works but this was in an area further away from the plaintiffs' worksite. When shown photographs taken in July 1990, he identified a pile of earth on the defendants' land but disagreed that the defendants had already started stockpiling at that time. He said that in fact what he saw was some amount of sand and some plants. He was not aware of what the defendants were constructing on the land.
15. Mr Pillai was asked whether the plaintiffs had carried out a soil study in the area where the pipeline was to be laid. His response was that the MOE had done such a study and provided the plaintiffs with a copy. He did not agree that the soil was 'fill' ie that it had been laid. He also disagreed that the soil was very soft.
16. Mr Pillai explained the process that was followed in laying the pipes. First, a trench was excavated and then levelled with granite dust. Then the pipe was laid and the trench was filled with more granite dust up to half the height of the pipe. Then the trench was back-filled - ie covered with earth. A mechanical ram was used to push in the earth and compact it. In back- filling, the plaintiffs laid three or four layers of earth and compacted the soil after each layer was laid. The laying and compacting process was carried out in accordance with specifications given by the MOE.
17. Mr Pillai agreed with counsel for the defendants that it was common during the construction of a building to have a stockpile of earth on the site. He said, however, that this would not be a huge amount of earth. When asked whether it was common for earth to be stockpiled to about three to four metres, his response was that it depended on the worksite.
18. The next witness was Mr Tan Peng Song who had been the plaintiffs' site foreman for the pipelaying works. He stated in chief that the mains laying involved excavating a trench of about 3.5 metres deep and 1.6 metres wide with timber shoring. After the plaintiffs had made their first trench, it was test-piled under the supervision of a technician from the MOE to see whether piling had to be done to support the pipe. In this particular instance, the result of the test-piling showed that the pipes could be laid without previous piling.
19. Under cross-examination, Mr Tan elaborated that the test- pile depended on the supervising officer from the MOE. The depth of the test-pile was decided by that officer and when it was carried out, the finding was 'penetration was 1.3 metres'. This meant that the pile went into the ground to a depth of 1.3 metres and it then reached ground that was too hard for further penetration. He also described the soil at the area of the pipe route as being neither very soft nor very hard. It was easy to excavate and work and the plaintiffs did not expect the kind of problems that come with soft soil.
20. When the plaintiffs were carrying out the first stage of the works, the defendants had a boundary wall of about 5 metres in height built from chainage 556.5 to chainage 864 about 2 metres away from the plaintiffs' line of work. There was also a plywood hoarding about one to two metres from the pipeline, between the pipeline and the concrete U-drain, beyond chainage 864 towards chainage 1222. The plaintiffs removed that hoarding in order to lay their pipes and replaced it after completing the first stage of the work in December 1990.
21. At that time the defendants were not doing any work beside the plaintiffs' worksite. They were carrying on piling works about 10 metres away from the plaintiffs' works opposite the stretch from chainage 864 to chainage 1064, but there was no digging or earth stockpiling or earth moving activities of the defendants in the vicinity of the plaintiffs' works.
22. Under cross-examination, Mr Tan also described the precautionary measures which he had taken during the pipelaying process. What he did was to put in timber shoring at the side of the trenches. The dimensions of the timber sheets were 200 mm by 50 mm. The shoring was removed after the trench had been backfilled. Mr Tan stated that the shoring would only have been left in the earth after completion of work if he had been instructed to do so by the MOE's engineer. These instructions were needed because the MOE would have had to pay for any timber shoring left in the trench. He also said that if he had seen a stockpile near the site, he would have asked the engineer for instructions on what was to be done.
23. Under questioning by the defendants' counsel, Mr Tan reiterated that when the plaintiffs started work the defendants were doing piling works about 10 metres away from the plaintiffs' site. He did not see them doing excavation work along the stretch where the pipeline was to be laid. Neither did he see any stockpile of earth near that route nor any trucks depositing earth near it. When referred to the photograph PB23(2) taken in July 1990 he admitted it showed a small pile of earth but asserted that that was in an area which was very far away from his pipeline route. He denied that in July 1990 the defendants had started stockpiling earth to a height of about 3 to 4 metres and about 10 metres away from the route of the pipeline.
24. When Mr Tan returned to the plaintiffs' site in August 1991, he noticed that the defendants' building work had progressed half-way. The plywood hoarding had been removed and the defendants had built a low boundary wall from chainage 864 to 1213. At the stretch between chainage 1222 and 1112 Mr Tan noticed gaps in the joints of that wall. On the other side of the wall, he saw a huge pile of earth which was about 9 metres away from the plaintiffs' laid pipeline. Mr Tan also saw excavators and back-hoes and lorries dumping earth near his site.
He also noticed that the concrete U-drain wall in the area was collapsing. Mr Tan took photographs. He did not, however, immediately inform the defendants about his observations. He said that it was not his duty or right to tell them what to do though he would have done something if he had seen them excavating the site of the pipeline. He also agreed that in August 1991 he did not think that the stockpile would damage the pipe.
25. On 30 November 1991, the plaintiffs returned to the site to complete their work from chainage 1222 onwards. Mr Tan then saw that the concrete U-drain was damaged. One side of it had collapsed in several places. He found the low boundary wall to be cracked. There were gaps of about 50 mm wide behind the joints. At the base of the stockpile of earth on the site there were large cracks on the ground. Fearing that damage might have been sustained by the pipes laid in August 1990 between chainage 1222 to 1155 which was parallel to the damaged wall and drain, Mr Tan reported his observations. He also took photographs in December 1991 and in the following months.
26. Mr Tan testified that, in his experience, it was common that while carrying on construction works, earth would be stockpiled at the site of the construction. The height of the stockpile would depend on the project and the earth would only be stockpiled if it was needed for the project.
27. The defendants' only witness of fact was Mr Yu Hon Nam, their construction manager. In his evidence in chief, he stated that in June 1989 the defendants contracted with independent contractors to carry out the construction of the theme park. The work was carried out between June 1989 and the end of 1991. It included the construction of pools and ponds of various sizes and also the construction of an artificial hill of a height of 4 metres and a width of 100 metres.
28. According to Mr Yu's affidavit and an answer given in response to interrogatories served by the plaintiffs, excavation and stockpiling works were commenced in December 1989. In court, Mr Yu clarified that that was a mistake and that the work had actually started in July 1989 and that from then on all the earth excavated was stockpiled in the same location in zone 4 of the defendants' premises ie near the boundary wall in the vicinity of the area where the damaged pipes were later found. He asserted that the stockpiling of the earth was in accordance with the approved plan as the earth stockpiled was intended to be used as the foundation to create the artificial hill. He added that at all material times the earth did not exceed the height of 4 metres spread over a base of 100 metres.
29. According to Mr Yu's affidavit, at the time when the plaintiffs commenced their work, the stockpiled earth was clearly and ordinarily visible as the defendants' hoarding was about 1.7 metres high whilst the stockpile was around 4 metres high. In court, he identified photograph DB162 as being of the zone 4 area and confirmed that it showed the batching plant, some cement mixers and a stockpile. That photograph was taken in May 1990 and Mr Yu stated that the stockpile shown in the photograph was the same stockpile which was near the damaged pipe. By reference to the height of the cement mixers in the photograph, Mr Yu deduced that in May 1990 the stockpile was around 3 metres high.
30. In December 1991, the plaintiffs wrote to the defendants complaining of damage to the pipeline ie that it had been misaligned. In January 1994, the defendants engaged one Dr KK Soh to investigate the cause of the misalignment. Mr Yu went on to state that Dr Soh had advised that the misalignment of the pipeline was not due to the stockpiling of the earth. The rest of Mr Yu's affidavit of evidence in chief was a recounting of Dr Soh's advice and a statement of the defendants' grounds for their allegation of contributory negligence on the part of the plaintiffs.
31. In cross-examination, Mr Yu stated that he had been the defendants' construction manager from February 1989 onwards. In 1990, he had been on the site at the time that the plaintiffs were laying pipes. He saw some of their workers and machines at work but did not observe exactly what they were doing. Neither did he pay any attention to their work. He confirmed that permission had been sought from the defendants' architect for the plaintiffs to start work.
32. The witness was referred to a plan marked plan 22. He stated that it was the same plan as that approved by the BCD although it did not bear the stamp of the authority. According to Mr Yu, the area marked in pink on plan 22 showed that a hill had been approved. This hill had been designed in 1987 and the plan had been submitted to the BCD for approval at the end of that year. That approval had been given in 1988. Whilst he asserted that persons in the construction line looking at the plan would know that there were contour lines in the area marked pink, he agreed that a third party could not tell from the drawing how high the hill was going to be.
33. At the beginning of his cross-examination, Mr Yu reiterated that the earth once dug up had been placed in zone 4 and had been there in 1990. He disagreed that the pile was at least 30 to 40 metres away from the boundary facing Jalan Ahmad Ibrahim ie the area where the plaintiffs were working. When referred to the photograph DB162, he agreed that it showed a fence wall which faced Jalan Ahmad Ibrahim and that the line of the wall ran parallel to the boundary. When he was asked whether the heap of earth in DB162 was very far away from that line, his reply was 'this pile is very far away'. But he asserted that when they started doing the landscape of the hill, that pile was 20 metres away from the wall.
34. Mr Yu was then shown PB23(2), the photograph taken in July 1990, and asked to confirm that the earth pile shown there was 40 metres away from the boundary. He disagreed and said that the distance was less than 20 metres. He then said that that photograph showed the beginning of the stockpile. It was the same pile as could still be seen on the site. The plywood hoarding shown on the photograph had been removed but a wall had been put up in the same position and the path in the photograph had been designed as a road and had since been constructed as one. The pile of earth was near the road. It was suggested to Mr Yu that in 1991 the pile of earth shown in PB23(2) was either moved to within 9 metres of the boundary or fresh earth had been dumped up to a distance of 9 metres of the boundary. His response was 'From July 1989 we put soil in the same position as shown in < PB23(2) > . We were doing landscape works called Ma Kwei Por. Por means a slope. So we needed to spread the soil evenly to create an environment. From that time we started to accumulate the soil and moved backwards away from the boundary.'
He also stated that in December 1991, the distance between the bottom of the slope and the boundary was 10 metres as shown in PB23(2), but the highest part of the hill was 20 metres away from the boundary.
35. Mr Yu's testimony was interrupted by an adjournment. When hearing resumed, he was asked again about the stockpile shown in DB162. He replied that in July 1989 that pile had been about 2 metres high and in May 1990 when the photograph had been taken, the height had increased to 3 metres. He then said that the stockpile in DB162 was not sited at the place where the defendants' designers had intended the artificial hill to be. He was shown ER8, a photograph taken of the stockpile in December 1991, and asked where the stockpile in DB162 was in relation to that. His reply was that both were on the same site. He then said that ER8 showed the hill as it is presently located. He reiterated that in May 1990, in August 1990 and in December 1991, the stockpile had been at the same site as shown in DB162 and that at all these times its base had been about 10 metres away from the boundary wall and 20 metres from the concrete U-drain.
36. In relation to the defendants' building plans, Mr Yu, after some cross-examination, agreed that the plan for zones 3 and 4 had been submitted to the BCD around February 1989 and that it had received approval in July 1991 long after the plaintiffs had completed their work in that area. It was pointed out to him that the defendants' documents showed that over 1989 and 1990 the defendants were having discussions with the Public Utilities Board ('PUB') on the latter's requirement that the general level of the site be raised by 2 metres to 103 metres above sea level.
The suggestion was made that if in 1988 the defendants had already submitted a plan calling for an artificial hill in that area with a base area of 100 metres by 50 metres, they would not have needed to spend so much time considering the costs of complying with the PUB's requirement. Mr Yu's reply to that was that whilst the hill was a feature the general level was a requirement. Mr Yu stated that zone 4 had an area of around 300,000 sq feet and that the ground level throughout was eventually raised by 2 metres. The work had started in 1989 and had taken almost a year.
37. Mr Yu confirmed that between August and December 1991 neither he nor the resident engineer of the project nor any of the defendants' staff had discovered or observed any cause for complaint over the work the plaintiffs did in 1990.
38. The first complaint that the defendants received was from the Drainage Department on 25 October 1991. The complaint was about damage to the concrete U-drain. Mr Yu was told that there was a lot of slurry (waste concrete) in the drain which had come from the batching plant. At that time the defendants thought that the slurry had damaged the drain and did not fear that there might be damage to other works in the area.
39. Mr Yu agreed that zone 4 had a frontage of about 172 metres along Jalan Ahmad Ibrahim. He said that about 80 metres of the drain in the area of zone 4 was damaged. He disagreed that the length of the damaged drain was precisely opposite the 55 metres of the damaged pipeline between chainage 1221 and 1165 but did concede that the defendants' wall was damaged along the same stretch. He also admitted that the hill was in the same area as the damaged pipe and drain and that the hill had been often levelled and trimmed by excavators in 1991 and 1992. According to plan 23, the topographical plan which the defendants adduced in evidence, in 1993 the hill was 107 metres above sea level at its highest point, ie slightly over 4 metres in height. By then the general level of the ground was just below 103 metres above sea level.
(ii) The expert evidence 40. In December 1992, the plaintiff engaged Executive Decisions Inc, a firm of civil and structural consulting engineers, to advise them in connection with the rectification of the damaged pipeline. The plaintiffs also wanted a report on the possible causes of the damage. Mr Bobby Ho Eng Hean, a structural engineer, attended to the project. He designed the temporary works required for the damaged pipes to be reconstructed and also supervised the reconstruction itself. Mr Ho made a site visit in late 1992 before the rectification works started. He also visited again while the rectification works were in progress.
41. In the report which Executive Decisions Inc produced for the purpose of this litigation, Mr Ho made it clear that his conclusions were based both on information given to him by the plaintiffs as to the sequence of events and also on the actual damage seen by him on his visits to the site. In particular, he understood that during the time of the laying of the pipeline from August to December 1990, the defendants had not carried out any stockpiling works nor was there any stockpiling of earth in the vicinity. The stockpile of earth had been seen much later.
42. A soil report of the area was made available to Mr Ho by the MOE. This showed that the ground condition of the site consisted of:
1.4 metres of soft silty clay followed by 2..8 metres of loose clay silt followed by 5.1 metres of soft silty clay followed by 5.2 metres of loose clay silt.
According to Mr Ho all of the above are extremely soft material.
43. The report explained that upheaval or failure in the ground may take place in different forms. These can be categorised generally as bearing capacity failures, soil slip failures and wedge failures. Soil slip failures are occasioned by instability of natural slopes or the slopes of excavations and embankments and are caused by gravitational and seepage forces. There are basically two types of soil slip failures viz rotational slips and translation and compound slips.
44. In his calculations to ascertain the stability of the ground concerned, Mr Ho took into account the data from the soil report, the height of the stockpile as being 4 metres (as the greater height of 9 metres complained of by the plaintiffs was not shown in the documentation) and the fact that the stockpile was located 10 metres away from the pipeline. His calculations revealed that if there had been no stockpile present, the ground would have had a safety factor of 1.875 and would have been classified as safe and stable. Once the stockpile of 4 metres height was factored in, the safety factor was reduced to 0.88 and the ground therefore failed.
45. Mr Ho's conclusion was that the failure of the ground had been occasioned by a rotational slip causing upheaval at the base of the slope as a direct result of the stockpiled earth. He pointed out that the soil condition of the stockpiled earth had been taken as saturated soil. If he had considered that heavy rain might have fully saturated the stockpiled material, the safety factor of the slope would have been even lower. It was therefore his opinion that the damage to the pipes, the wall and the drain was a direct result of the presence of the stockpile on the type of ground conditions existing on site.
46. The defendants' expert, Dr KK Soh, of Associated Geotechnical Consultants, is a civil and geotechnical engineer by profession. He was asked by the defendants to ascertain the cause of damage to the pipeline. He presented two reports, the first in January 1994 and the second in September 1995. He confirmed in court that his reports were made on the basis of information, photographs and documents given to him by the defendants. As he was appointed sometime after the events had occurred, he had no first hand knowledge of the site conditions.
47. According to Dr Soh's first report, in order to realistically evaluate the cause of the movement of the pipes, the construction sequence must be taken into consideration. In this case he said that the construction sequence was as follows:
(1) surcharging of the earth fill (ie the building of the stockpile); (2) excavation and trenching for laying the pipes; (3) backfilling of the trench.
In Dr Soh's words 'an assessment of the soil movement at the location of the ductile pipe must be strictly correlated with the sequence of construction'.
48. Dr Soh characterised the soil profile of the site as being fill ground, very soft peaty clay/marine clay and very soft clay silt. He commented that based on experience of similar job sites, the surcharge load of 3 to 4 metres over good fill ground of 4 metres thick would not give the magnitude of lateral movement of the pipes that was noticed in the present case.
Taking into account the sequence of construction, as told to him, he assessed the movement of the pipe at various stages. He concluded that the total lateral movement of the ground would have been of the magnitude of 51 mm and this could not account for the movement of 200 mm which, he deduced from one photograph, had been experienced by the plaintiffs' pipes.
49. In his first report, Dr Soh's conclusion was that based on the photographs available to him, the timber shoring which the plaintiffs had used at the site of the trenches when laying the pipes, would have created a gap of 100 to 150 mm upon being removed. In his view, it was probable that the backfill in the trench was not adequately compacted. In normal circumstances where the ground is level, the lateral forces are balanced. In this particular situation, the gaps in the ground in combination with the loose earth did not provide any lateral restraint to the surcharged earth. The unrestrained lateral force subsequently moved the earth mass and then caused the pipeline to move laterally in excess of 200 metres. His conclusion was, therefore, that the plaintiffs had caused the problem by removing the timber shoring and not adequately compacting the earth when backfilling the trench. In court, he confirmed that he had based his findings on the survey drawing marked plan 23 and the photograph marked DB56 (which showed the dislocation of the pipe at one of the joints).
50. In his second report, Dr Soh stated that for the pipeline to move laterally by 200 mm at a depth of 3.8 mm there would have to be the following occurrences on site:
(1) a general upheaval of the site and a general subsidence of the fill; (2) a general or complete failure at several locations of the pipeline and most buried service lines around the vicinity. He pointed out that these two conditions had not been reported on site.
51. He reiterated his view that the cause of the isolated movement of the pipeline was due to the temporary work that was not adequately designed. He also stated that it was a proven fact that four years from the damage report of the pipeline and although the stockpile remained at a height of 4 metres all that time, there was no further reported damage to the repaired pipeline or other service lines. It could thus be interpreted that the height of the stockpile was not the cause of the isolated detrimental movement to the pipeline.
Findings: (i) what was the sequence of events? 52. It would be noted from the brief accounts of the expert evidence set out above that the two experts proceeded on different premises. Mr Ho's approach and the conclusion he reached were both predicated on the plaintiffs' story that there had been no stockpile of earth near the site of the pipeline at the time they commenced work in August 1990. Dr Soh confirmed that the sequence of work was of the utmost importance to his conclusions as well and he proceeded on the basis that there was an existing stockpile about 10 metres away from the plaintiffs' site in August 1990. The first question that I have to determine, therefore, is what came first, the stockpile or the pipes.
53. On this aspect, the plaintiffs' witnesses of fact were firm. They maintained throughout that no stockpiling work was being carried on near their site between August and December 1990. Whilst the defendants were carrying out construction work and accumulating some amount of earth at that time, the works were some distance away from the route of the pipeline. The defendants' evidence, of course, was the exact opposite, at least at the beginning. Mr Yu maintained that the defendants had been stockpiling earth in the vicinity of what was later termed 'peak B' (ie the hill 9 metres away from the pipeline) from July 1989 onwards and that by the time the plaintiffs started their works, this stockpile had reached 3 metres and would have been clearly visible above the 1.7 metre high hoarding which the defendants had erected between their site and the concrete U-drain.
54. The defendants' photograph DB162 taken in May 1990, showed the high wall along the boundary of the park. To the left of this wall, at the top of the photograph, there was a pile of earth and next to it some concrete mixers. The plaintiffs' pipeline was to run to the right of the wall and parallel to it.
In the photograph the batching plant was seen further away, behind the pile. Two photographs that the plaintiffs took in July 1990 are relevant here. PB23(1) was taken in the same direction as DB162 but very much closer to the batching plant. No pile of earth is visible in this photograph. PB23(2) appears to have been taken from a point beyond the batching plant as shown in PB23(1) and on the left hand side of this photograph can be seen the start of a stockpile. If the three photographs are taken together it would seem that in July 1990, the stockpile was quite a distance beyond the batching plant.
55. If one looks at the length of the wall in DB162, then at the distance of the batching plant in PB23(1) from the place where the wall seen in DB162 had ended and then considers the distance to the stockpile in PB23(2) from the point of the batching plant, it appears that the stockpile must have been a considerable distance from the point where DB162 was taken. On that basis, the stockpile in DB162 must be well over 40 metres from the fence (which was later built beyond the wall and along the trees). In fact this coincides with the lower part of what the defendants called the Hua Ching Pool located in zone 4 which area is about 40 metres from the fence as shown in the approved plan DB215. This inference, of course, runs counter to Mr Yu's evidence in chief but I do not find Mr Yu to be convincing witness on this point.
56. In court, Mr Yu insisted that the stockpile seen in DB162 and PB23(2) was a distance of 20 metres or less from the wall and was the same pile as could presently be seen on the site. He said that that pile had never changed. He disagreed that the pile in DB162 was 40 metres away from the fence. When I asked him what the distance between the bottom of the slope and the boundary was, he replied firmly that it was the same as shown in PB23(2) ie about 10 metres but that the highest part of the hill was 20 metres away from the boundary.
57. At the next hearing, Mr Yu claimed that the DB162 stockpile was at the same location as the stockpile found in November/December 1991 and shown in ER8. But he then denied that that stockpile was in fact located where the designer had intended the artificial hill to be. When I asked him whether the ER8 stockpile was located where the hill is presently located, however, his answer was yes. So the purport of all this evidence was that the present hill was the ER8 stockpile was the DB162 stockpile and was at its present position from May 1990 onwards. He agreed that at all times the base of this pile was 10 metres away from the boundary wall but he also asserted that this pile was not the designed artificial hill.
58. Mr Yu then went on in re-examination to agree with the defendants' counsel that apart from the DB162 stockpile there was another stockpile at the proposed site of the artificial hill in 1990. He said that the topographical map, plan 23, showed one stockpile with two peaks which he marked A and B. He pointed out that there was a concrete road running between and separating the two peaks. He then testified that the DB162 stockpile was peak A and that it was built after peak B which was the originally designed hill. He then said that he had no photograph for peak B in May 1990 and that peak B was the one closer to the damaged area. He next testified that the ER8 stockpile was peak A near the batching plant and peak B was shown in another photograph (ER23) taken in April 1992. This photograph showed the trimming of a stockpile adjacent to the Jurong river.
59. It can be seen that Mr Yu's evidence causes the defendants some problems. If the DB162 stockpile (on which the defendants rely to establish the existence of a stockpile 10 metres from the fence prior to the plaintiffs commencing work) was at the same site as the peak A marked by Mr Yu in plan 23, then the plaintiffs are right in saying that the DB162 stockpile was at least 40 metres away from the fence wall facing Jalan Ahmad Ibrahim because the original of plan 23 (DB170) drawn to the scale of 1 cm = 2 metres, shows that the distance from the fence to peak A was above 40 metres and the distance to peak A from the concrete U-drain was about 50 metres.
60. Secondly, Mr Yu's evidence that the stockpile in ER8 was not the same as that shown in ER23 but rather was the same as the DB162 pile is difficult to accept. If the photograph ER25 (taken in April 1992 at the same time as ER23) is examined and compared with ER8 and ER23 it would appear:
(1) that photographs ER8 and 25 were taken of the same pile from roughly the same direction (the photographs both show the same structures appearing behind the stockpile) but at different dates ie December 1991 and April 1992 respectively. It would be noted that ER8 shows a patch of grass in the lower right hand corner which also appears in the foreground of ER25 and, on close scrutiny, the lower hanging bough of a tree which appears in both photographs is the same bough.
(2) ER23 was taken in the opposite direction from that of ER25 - it shows Jurong river in the background whereas ER25 shows the river in the foreground.
It is therefore obvious that ER8, ER23 and ER25 all show the same stockpile and this is not the DB162 stockpile.
61. Finally, Mr Yu, having acknowledged that the defendants had no photograph of peak B which was the one he himself identified as being closer to the site of the damaged pipeline, obviously conceded that peak B was not the DB162 stockpile. Peak B must have been the ER8 stockpile and, as all the defendants' evidence was that the stockpile that was present when the plaintiffs commenced work was the DB162 stockpile, the defendants had no evidence that there was any pile of earth near the plaintiffs' site of which the plaintiffs should have been aware when they started work.
62. Bearing all the foregoing in mind, I have concluded that the plaintiffs' version of the state of the site in August 1990 is the more credible one on the balance of probabilities. I also think that this conclusion is supported by the evidence of the defendants having to move a great deal of soil onto the area of zone 4 in order to raise its general level by 2 metres quite apart from their actual construction of the artificial hill.
This work would have taken a considerable period of time (zone 4 covered about 300,000 square feet) and a lot of earth must have continued to have been moved about after August 1990. I cannot accept that both peaks and the raising of the general level of the ground could have been completed before August 1990 especially since the defendants were, as late as January 1990, still discussing the PUB's requirements which there would have been no need to do had they been whole-heartedly raising the earth level with the objective of completing the work by mid- year. Further it was clear both from the plaintiffs' oral testimony and the defendants' photographs that the defendants' earth shaping works continued long after August 1990 (and at least up to April 1992) which would not have happened if the main earth works had actually been completed by mid 1990. Having come to the foregoing conclusion, I also agree with the plaintiffs' submission that the defendants' assertion that the May 1990 stockpile was only 10 metres from the fence before the plaintiffs laid the pipes in August 1990 is untrue.
(ii) did the stockpile cause damage? 63. The next issue is whether the damage to the plaintiffs' pipeline was caused by the second stockpile (ie peak B) which the defendants built up after December 1990 when the plaintiffs left the site temporarily. This stockpile was located about 10 metres away from the wall and its height varied from time to time. In July 1992, it was 4 metres high but previously it had been higher than that as the defendants' admission of frequent levelling and trimming indicates. There is no corroboration, however of the plaintiffs' assertion that it had reached as high as 9 metres.
64. The two expert witnesses gave diametrically opposed evidence on the cause of the damage to the pipes, the wall and the U-drain. Dr Soh suffered under the substantial disadvantage of being called in long after the damage was discovered and the rectification works completed. He had to work on the basis of information, reports and photographs given to him by the defendants and had no first-hand knowledge of the site conditions.
65. I have various difficulties with Dr Soh's evidence emanating from his lack of first-hand knowledge. First, and most important, Dr Soh agreed that his assessment of soil movement had to be correlated with the construction sequence and that his assessment only took account of what he had been told by the defendants ie that the stockpile existed before the pipes were laid. Although in re-examination he stated that even if the latter situation had been the case, the stockpile would have had a very small effect on the lateral movement of the pipe, I find that difficult to accept since at the same time he was trying to lay the blame for the pipes' movement on the presence of a surcharge of earth above the U-drain at the time it was being repaired. The importance of the construction sequence to his analysis was shown by his statement at the very beginning of his report that in order to realistically evaluate the earth movement the construction sequence had to be taken into consideration.
66. Dr Soh was extensively cross-examined in relation to the sequence of construction. It appeared that he did not know when the embankment above the U-drain had in fact been constructed although he dated it in his report as having been before 8 August 1990. He also conceded that he did not know what the actual date of commencement of construction of the pipeline was although in his report he had stated it as being 26 October 1990. Various facts he had relied on thus appeared to be errors.
67. There are other problems with Dr Soh's evidence. He referred to a photograph at DB55 which was taken during the rectification of the pipeline and assumed that timber shoring similar to that shown in the photograph had been placed at the time of original pipelaying in 1990. On that basis he deduced that when the timber shoring had been pulled out of the earth after backfilling, the resulting gaps 'in combination with the loose earth < did > not provide the lateral restraint to the surcharge earth'. Because the lateral force was not restrained, it moved the earth mass and caused the pipeline to move laterally in excess of 200 metres. This seems quite a lot to deduce from one photograph especially since he did not know the dimensions of the timber shoring actually used when the pipes were laid or what gaps, if any, were left when the shoring was removed. Further, if the damage was caused by either the removal of the timber shoring or the long term lack of permanent support for the pipeline, then one would have expected the whole length of 700 metres of pipeline to be damaged and not only 55 metres of it.
68. Secondly, the lateral dislocation of more than 200 mm was not something which Dr Soh had observed personally. It was another deduction which he had made on the basis of photographic evidence. He had relied on one photograph only, DB56, which showed the dislocation of two ends of the pipeline at a joint.
Knowing the diameter of the pipe, he had attempted, by scaling, to measure the gap between these ends and had deduced it to be 160 mm. For such a dislocation to occur, he said the lateral ground movement must have been more than 200 mm. He agreed that he had made assumptions on facts supplied by others but asserted that his report as to surcharge heights and the effect of the horizontal movement were correct based on the information given. This turned out to be no more than plan 23 and the photograph DB56. In regard to plan 23, he agreed that it was made in 1993 and that there could have been many changes to the topography of the land between 1990 and 1993.
69. Although in his first report Dr Soh had theorised, as pointed out above, that there had been a lateral ground movement of 200 mm caused by the removal of restraints on such movement, in his re-examination he apparently changed this position while referring to photograph ER29 which was taken in June 1992 while the defendants were rectifying the damage to the U-drain. This photograph shows a seemingly high embankment above the drain which is filled with timber shoring and is under reconstruction.
Dr Soh estimated the height of the embankment as being 4 metres and then went on to opine that this embankment together with the original fill ground was the major cause of 'the high observed damage to the pipe'. I then asked him whether there was no lateral movement and he replied that most of the settlement of the pipe was in a vertical direction and acknowledged only a very small lateral movement. This evidence was obviously inconsistent with his report.
70. Further, when I asked him what was indicated by the fact that the drain was all right in August 1990 but damaged in August 1991, he replied that several factors could have caused this. First, the construction load. Secondly, the temporary work or the poorly recompacted soil. Thirdly, the edge of the drain itself. Fourthly, there could have been an additional surcharge on the embankment. In relation to his fourth reason, he was asked whether the surcharge could have been the stockpile. Dr Soh admitted that as a possibility. He added, however, that the stockpile as a source of pressure was unlikely as the embankment immediately above the drain was quite high and the stockpile was 8 to 9 metres away. While having to admit the effect that the weight of extra earth could have had on the ground, Dr Soh seemed rather reluctant to acknowledge the probability of the stockpile being the source of such weight.
71. It is interesting that no one else seems to have noted the oversized embankment above the drain along this particular stretch. Certainly, no one who was actually at the site at the material times mentioned this structure in court. In my view, even if the height of the embankment above the drain had ever reached 3 to 4 metres, the embankment cannot have remained at that height for very long. First of all, there is no indication in the photographs taken before March 1992 (which was about the time the rectification works in respect of the drain started) of an embankment of such a height and, secondly, plan 23 drawn in mid 1993 shows that by then the embankment was only about 0.75 metres high. In contrast to that, peak B having a height of at least 4 metres was continuously present from some time in early 1991 onwards. If any earth movement was going to be caused by the presence of a surcharge of earth it is much more likely that such movement was caused by peak B than by a temporarily high embankment.
72. In his second report, Dr Soh referred to the general subsidence of the fill which he expected to find if ground movement of a large magnitude had taken place. He said that the absence of such subsidence showed that the stockpile was not the cause of the movement of the pipe. Dr Soh appears to have been wrongly informed on this too. The fact that the wall, the U- drain and the pipe were all damaged at one locality directly opposite the stockpile shows that there was a certain amount of subsidence and/or movement of the earth. More than 700 metres of pipeline were laid along the boundary of the defendants' site. Yet the damaged stretch of 55 metres was directly opposite the stockpile. So too were the damaged sections of the wall and the U-drain. Although Mr Yu asserted that the damage to the U-drain was seen over a length of about 80 metres, this does not detract from the fact that a substantial section of the damaged drain was in the vicinity of the stockpile. Further, the fact that the stockpile was constantly added to, or levelled, or sloped, by tractors, as Mr Yu himself conceded, would have led to the wiping out of all signs of differential levels or subsidence.
73. Dr Soh also stated that the fact that there had been no further damage to the pipeline after 1992 showed that the stockpile could not have caused the original problem. I find it difficult to accept this reasoning. First, in mid 1992 after they had been advised by the plaintiffs that their stockpiling work had caused damage to the pipeline, the defendants drove a sheet pile into the ground between the stockpile. As the defendants themselves said, the purpose of this sheet pile was to give some protection to the plaintiffs' works. Secondly, when the plaintiffs carried out rectification works they did so in accordance with Mr Ho's specifications. This meant that after the new pipes had been laid and the trenches backfilled, the timber shoring was left in the ground. The purpose of this was to provide protection to the pipeline on the basis that the stockpile would remain as it was in mid 1992 and that no further earth would be added to it.
74. Dr Soh gave various explanations for the damage to the pipeline. I have stated above why I find some of his explanations improbable. I think that the major problem with them is that the conditions which he specified as having led to the damage were all conditions that could have existed over the entire length of the pipeline and/or over several portions of the pipeline and were not confined to the stretch that was actually damaged. The only major difference in conditions between the damaged stretch and the rest of the pipeline was the presence near the damaged stretch of a large and heavy stockpile of earth.
If the close proximity of this stockpile had nothing to do with the damage to the pipeline then the plaintiffs should have discovered many more stretches of damaged pipeline along the route.
75. Having considered the evidence, I find Mr Ho's explanation of the cause of the damage to the pipeline, the wall and the U- drain to be the more probable one. The defendants did criticise his analysis on several counts but I think that Mr Ho was able to rebut these criticisms convincingly. For example, Mr Ho had said that the rotational slip which he hypothesised as having occurred would have caused there to be a differential step or a differential in the level of the stockpile. The defendants pointed out that this was not in fact seen in the photographs.
But they were constantly trimming and working on the stockpile. Since all their earth moving work would have obliterated such a differential, its absence cannot adversely affect Mr Ho's theory.
76. It was suggested to Mr Ho in cross-examination by the defence that he had averaged the soil parameters of the different layers of earth found on the site and that this would not represent the actual soil conditions. His answer was that the average of the parameters of the different layers would be the fair representation. He did not take the weakest of the different figures because that would have the effect of lowering the safety factor which in turn would enhance the likelihood of a slip to the detriment of the defendants. Mr Ho's methodology was to some extent supported by Dr Soh. He agreed that he himself had approximated the thickness of layers in the analysis of a soil profile which he had done and agreed that Mr Ho had been equally correct in approximating soil depths.
77. According to Mr Ho's report, the ground conditions comprised 1.4 metres of soft silty clay followed by 2.8 metres of loose clay silt followed by 5.1 metres of soft silty clay followed by another 5.2 metres of loose clay sit. This was all extremely soft material. However, in court, he stated that below the loose clay silt at a depth of 14.5 metres there was very stiff silty clay. It had been suggested to Mr Ho that he had wrongly used a chart for the calculation of the stability of the soil because the chart was meant for soft ground overlying a firm base and this was not true of the actual sub-soil condition which was alternating layers of soil and loose sub-soil. This suggestion was misplaced as Mr Ho himself pointed out by reference to the hard silty layer 14.5 metres below the surface.
(iii) was the damage foreseeable? 78. The defendants submit that even if the pipeline had been damaged by reason of the proximity of the stockpile, that does not in itself make them responsible to the plaintiffs in negligence. They point out that liability in negligence only arises when there is a legal duty to take care and the test of the existence of such duty is whether injury to the plaintiffs would have been in the contemplation of a reasonable man. They say that the plaintiffs have failed to establish that in this case it was foreseeable that the act of stockpiling earth would cause damage to their pipeline.
79. The defendants rely on the fact that neither of the plaintiffs' witnesses of fact stated in their evidence in chief that it was their view that stockpiling of earth could cause damage to a pipeline laid 9 metres away and 3.5 metres underground or that it could be reasonably anticipated that a stockpile of earth of 4 metres could cause damage to its surrounding area. Further, although in August 1991, Mr Pillai had visited the site and seen the stockpile nearby he did not notify the defendants until December 1991 that the plaintiffs feared damage to their pipeline. The defendants infer that Mr Pillai did not foresee in August 1991 that the stockpile would cause such damage especially since he had also said that it was common for earth to be stockpiled to about 3 to 4 metres depending on the worksite. The defendants say this inference is further supported by Mr Tan's evidence that in August 1991 he had not discussed the stockpile with the defendants because he had not thought that it could damage the pipe.
80. I have found this issue of foreseeability a difficult one. There is some force in the defendants' contention that if both Mr Pillai and Mr Tan, contractors of reasonable experience, did not in August 1991 fear damage from the stockpile, such damage would not have been in the contemplation of the reasonable man. However, the reactions of those two witnesses cannot be conclusive of the issue. This is especially because they may have been unduly complacent about the effect of the stockpile since the test piles driven had indicated that the soil conditions of the site were good enough that no reinforcement was required for the works.
81. Other witnesses, however, had different expectations. Mr Bobby Ho, an extremely experienced civil engineer, having been in active engineering practice since 1960, had no doubt that the presence of such a stockpile on the existing soil conditions would create a horizontal pressure on the ground leading to the movement of an entire wedge of earth and thus a rotational landslip. Obviously, in his view, foreseeability was not an issue.
82. Although Dr Soh did not expressly state that it was foreseeable that the stockpile could possibly cause damage to works in its vicinity, I think that conclusion can be drawn from his report. First, he recognised that a surcharge of earth does create a force which can damage pipes and drains. This is clear from the fact that he attributed the damage to the pipe to the high embankment which he considered existed above the drain. Secondly, he was at pains to state in his report that a surcharge load of 3 to 4 metres over 'good filled ground of 4 metres thick' would not give rise to lateral movement of the magnitude of 200 mm. In fact, he stated that the total lateral movement was of the magnitude of 51 mm, at the utmost. Obviously he had accepted the principle of the surcharge having an impact, he was just bickering about its possible extent bearing in mind his opinion of the soil conditions. It is worth noting that in calculating a movement of 51 mm he was working on the basis that the stockpile was only 3 metres high when the evidence shows it was at least 4 metres high most of the time and, probably, at times even higher.
83. It was also significant that Mr Yu who was the defendants' construction manager and therefore experienced in construction matters did not come straight out in his affidavit of evidence- in-chief and assert that he could not have foreseen that the stockpile in question could damage the pipeline and the drain. Bearing in mind that foreseeability must have been a live issue for the defendants, the omission of such an assertion on Mr Yu's part is unlikely to have been an oversight. What Mr Yu actually said was that he had been advised by Dr Soh that the misalignment of the pipeline was not due to stockpiling of the earth. He thus avoided the issue very nicely by reference to another's opinion. He also said that since Dr Soh had confirmed that stockpiling of earth is a common practice in the construction industry, he himself believed that the defendants' sub-contractors had not been negligent in building the stockpile in the course of their work. It was interesting that the defendants did not call their sub-contractors to give direct evidence to this effect or to allege that it had never been known for stockpiles of 4 metres or more to cause damage to works in the vicinity. I think that I am entitled to draw an adverse inference from the failure of the defendants to call these witnesses.
84. On balance, therefore, I have come to the conclusion that it was foreseeable that the construction of the stockpile only 9 metres away from the pipeline in view of the existing soil conditions of which the defendants must have been fully aware could have damaged the pipeline. Accordingly, I find that in building up the stockpile in the vicinity of the plaintiffs' pipeline without taking any precautions to protect the pipeline from the effects on the ground of the surcharge of earth, the defendants were negligent and in breach of duty to the plaintiffs as they ought to have had the plaintiffs in their contemplation as persons who would be affected by their stockpiling activities. (iv) were the plaintiffs themselves negligent?
85. The findings of fact which I have made above are also pertinent to the issue of whether there was any negligence on the part of the plaintiffs in their works which contributed to the damage sustained by the pipeline. The rationale underlying the accusation of contributory negligence was that the plaintiffs did not have due regard for the presence of the defendants' stockpile peak B and the effect it would have on the ground conditions existing at the site. Since I have found that peak B was not in existence when the relevant section of the plaintiffs' pipe was laid, that rationale has no basis.
86. The unchallenged evidence of the plaintiffs was that they had laid the pipeline in accordance with the specifications given to them by the MOE. The plaintiffs had taken the advice of the MOE engineer on the lack of a need for supportive piles and also, had not been advised by the MOE engineer to leave the timber shoring in the ground after backfilling of the trench. Mr Ho stated that if there had been no stockpile then no fault could have been found with the manner in which the pipes were laid. In fact, his opinion was that even if in August 1990 timber shorings had been left in the ground, the damage to the pipeline caused by the force exerted by the stockpile would still have occurred. The fact that the plaintiffs' pipelaying works were properly effected for the soil conditions found is also established by the lack of damage to any section of the pipeline which, though running through the theme park, was not in the vicinity of peak B.
87. In my judgment, the defendants have failed to establish that the plaintiffs were negligent in the way that they laid the pipes. Further, their allegation that it was negligent for the plaintiffs not to drive sheet piles alongside the pipeline cannot be supported since the plaintiffs had no way of knowing that there was going to be a stockpile close to the pipeline. First, they were not informed by the defendants of this. Secondly, there was no sign of a stockpile when the plaintiffs started work. Thirdly, even if the plaintiffs had taken the trouble to ask for and look at the defendants' plans (though in my view they were not in the circumstances then existing obliged to do so), they would not have been able to detect that there would be a 4 metre high stockpile 9 metres away from their pipeline. All in all, the defendants have failed to establish the particulars of negligence on the part of the plaintiffs which they had pleaded in their defence.
(v) what can the plaintiffs recover? 88. The plaintiffs' monetary claim has two components. The first is a sum of $114,963.98 which comprises the actual cost of rectifying the damaged pipeline, including the cost of digging up the pipeline and ascertaining the damage caused, and also the expenses of employing Executive Decisions Inc and an inspection firm called Insight Vision Systems Pte Ltd. This sum is obviously recoverable.
89. The second component is a claim for a reasonable profit margin for the plaintiffs in respect of the cost of rectification. In the statement of claim, the plaintiffs did not give particulars of the profit margin which they were claiming. Mr Pillai, however, testified that on the original contract with the MOE, the plaintiffs' profit margin had been between 10% to 15% for various components of the job. The defendants submitted that since the plaintiffs had failed to plead the particulars of the profit margin, they should not recover any profit.
90. Whilst I agree that the plaintiffs should have specified the actual profit margin that they were claiming on the basis of what they could have got for similar jobs, in this instance, I do not think that the defendants were embarrassed by the lack of particularisation. They knew that the plaintiffs wanted a reasonable profit and they could have adduced evidence as to what is considered a reasonable profit margin in the construction industry. If the plaintiffs had asked for an astronomical profit figure they would have had to prove it, of course. They asked only for reasonable profits and the defendants did not challenge the basic premise that pipelaying contractors do earn profits on their pipelaying contracts. I think that Mr Pillai's estimate of 10% is a reasonable one and I am therefore prepared to award the plaintiffs 10% of their cost of repairs (less $10,950 paid as fees to Executive Decisions Inc and Insight Vision Systems Pte Ltd).
Conclusion 91. There will be judgment for the plaintiffs in the sums of (i) $114,963.98 and (ii)$10,401.40 as profit together with interest on both sums at the rate of 6% p.a. from the date of the writ herein till judgment. The plaintiffs are also awarded their costs of this action.
JUDITH PRAKASH
JUDGE
SINGAPORE Date: 17 March 1997
Judith Prakash J
Gopal Krishnan Nair (G Raman & Partners) for the plaintiffs
Lisa Theng with Chua Boon Tien (Colin Ng & Partners) for the defendants