In the Court of Appeal of the Republic of Singapore
[1998] SGCA 59
CA 57/1998
Between
San International Pte Ltd (fomerly known as San Ho Huat Construction Pte Ltd)
… Appellant
And
Keppel Engineering Pte Ltd
… Respondent
grounds of decision
Contract — Breach

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
San International Pte Ltd (fomerly known as San Ho Huat Construction Pte Ltd) v Keppel Engineering Pte Ltd
[1998] SGCA 59
CA 57/1998
Karthigesu JA; L P Thean JA; Yong Pung How CJ
16 September 1998
Judgment:
KARTHIGESU JA
Cur Adv Vult
(delivering the judgment of the court): This is an appeal from the decision of Kan Ting Chiu J on a preliminary issue of law, agreed between the parties, which arose in an action brought by the respondents (Keppel Engineering) as main contractors against their sub-contractors, the appellants (San International) for the construction of a two-storey warehouse with facilities known as W&T Distripark Phase II.
2.The sub-contract covered, inter alia, the PUB substation, transformer room and switch room, ancillary areas, repair shed and wash area, guard house and administrative office (phase A of the project), for which works the projected completion date was 29 May 1995 and other works (phase B) which included the architectural works of the office located in the main warehouse building (the main office works) the completion date for which was projected to 29 December 1995.
3.The letter of award issued after San International had commenced the sub-contract works was dated 17 April 1995. It provided that the form of contract shall be the `Conditions of Sub-Contract for use in conjunction with the Main Contract, First Edition 1980` (`the sub-contract`) and specified the following as the sub- contract documents: (a). tender submission dated 27 January 1995;
(b). revised tender submission dated 29 January 1995;
(c). revised tender submissions dated 4 February 1995;
(d). the main contract documents including the bills of quantities, specifications and construction drawings;
(e). the addendum issued by Keppel Engineering dated 19 January 1995;
(f). the letter of intent issued by Keppel Engineering dated 7 February 1995.
The letter of award also specified certain milestone dates to be achieved by San International in the execution of the sub-contract works and further provided that all sub-contract works related to applications for clearances by FSB/PUB/Sewerage Departments must be completed by 29 October 1995 so that applications to these departments may be made in time to enable the employer to obtain the temporary occupation permit (TOP) by 29 December 1995 failing which the liquidated damages provision provided for in the sub-contract would apply.
4.The preliminary issue for the court, it appears to us, was not framed and if it was, it was not framed with due particularity. It seems to have just arisen during the trial of the action. The learned judge referred to it in his judgment in these terms:
2 The action arose out of the defendants` (San International`s) refusal to complete the architectural works for the office located in the main warehouse building. The plaintiffs (Keppel Engineering) treated that as repudiation by the defendants, and terminated the sub-contract. The defendants denied that they had repudiated the sub-contract and counter-claimed on the basis that the plaintiffs were in breach.
3 The parties agreed that the question whether the plaintiffs were entitled to terminate the sub-contract be determined as a preliminary issue.
San International`s counsel in his submissions before us said:
This appeal arose (sic) from the judgment of Justice Kan Ting Chiu in respect of a preliminary issue, namely, whether the appellants had by their conduct repudiated the sub-contract with the respondents such that the respondents could lawfully rescind the sub-contract. The learned judge found in favour of the respondents. For the purposes of the trial of the preliminary issue, the parties had agreed on a statement of facts.
And Keppel Engineering`s case says this:
1 On 26 February 1998, the Honourable Justice Kan Ting Chiu delivered judgment on a preliminary issue. The preliminary issue raised was whether the appellants by their conduct, in particular the period between 17 and 29 November 1995, had repudiated their obligations under their sub-contract with the respondents, such that the respondents were entitled lawfully to rescind the sub-contract. The learned judge found in favour of the respondents and this appeal has been brought against that judgment.
5.The so called agreed statement of facts stated that four facts were agreed and that five further facts were not agreed but San International considered them relevant. The four agreed facts were: (i) that the bill value of the main office works was approximately $563,000; (ii) that the adjusted sub-contract sum was approximately $11.1m and that as at the date of termination the value of all outstanding work was approximately $2.3m in Keppel Engineering`s estimation and approximately $1.8m in San International`s estimation. Further that in Keppel Engineering`s estimation San International had completed about 79% in value of the adjusted sub-contract sum; (iii) that following the 28 October 1995 meeting between the parties Poh Jet had taken over the main office works and had worked on it from 1 November to 17 November; (iv) that at the date of termination of the sub-contract, the works were in delay but there was no admission of either party as to the cause of the delay - it could be caused by the other sub-contractors. Later the parties also agreed that Keppel Engineering could give directions or instructions to San International under the terms of the sub-contract and that an analysis on the claims submitted by San International was reflective of the proportion of the main office works left undone. Some photographs showing the state of construction of the main office works as at 10 November 1995 were also agreed. We will reserve our comments on the agreed statement of facts for later.
6.The circumstances leading to the termination of the sub-contract by Keppel Engineering began on 28 October 1995 when the parties were in discussions for Keppel Engineering to take over from San International the main office works. What actually transpired at that meeting has not been agreed upon and does not form part of the factual basis of the preliminary issue. It is however agreed that following that meeting Keppel Engineering instructed another of their sub-contractors, Poh Jet Construction Co (Poh Jet) to take over the main office works and to complete the same. Poh Jet commenced work on 1 November 1995 and continued until 17 November 1995.
7.Following the meeting of 28 October 1995 a dispute arose between the parties as to the basis on which the main office works were taken out of the sub-contract works. The dispute first manifested itself when Keppel Engineering wrote to San International on 6 November 1995, in connection with taking the final measurements of the sub-contract works done up to 28 October 1995. Keppel Engineering observed that:
it is agreed that Keppel Engineering will take back all the remaining architectural works for the main office from 30 October 1995. As confirmed by you during the meeting, (this refers to 28 October meeting) the reason for taking over the said works is due to the lack of manpower available from your company to complete the said works.
8.San International replied on 9 November 1995. They said that Keppel Engineering`s letter of 6 November was not a true reflection of the meeting of 28 October. They continued:
The reason for you to assume the remaining architectural works for the main office is the convenience you may have in liaison and co-ordination of your M&E works for which you are totally responsible for.
For the interest of the project and your desire to assume the remaining works for the sake of ease of liaison and co-ordination, we are in total agreement that you proceed as you desired. We have no qualms about it.
However, the omission of such works shall follow the working mechanism of variation clause as stipulated in the agreement.
9.The relationship between the parties deteriorated after this as the ensuing exchange of correspondence shows: (i). Keppel Engineering retaliated on 17 November 1995. They said that they were shocked that San International were disputing the agreement made on 28 October 1995; they had agreed to take over the main office works at the request of San International because San International did not have the resources to carry out and complete the works. Keppel Engineering`s intention was to mitigate the impact of San International`s breach on the progress of the works. Keppel Engineering said that since San International were now disputing the basis of the take over and asserted that they could carry out the works themselves, Keppel Engineering were not willing to continue to provide their assistance and would remove their workers (brought in to complete the works) from the site immediately. Finally Keppel Engineering said and we quote from their letter:
Accordingly, we hereby direct you to commence performance of the said works immediately. We also direct you to provide us with your revised work schedule within seven days hereof to show us how you intend to carry out the said works in order to comply with the contract completion date.
(ii). San International responded on 20 November 1995 stating
(a). that it was clear that Keppel Engineering had `reneged` on their decision to exclude the main office works from the sub-contract, an exercise Keppel Engineering clearly had the option to do by reason of cl 3 of Keppel Engineering`s letter of intent dated 7 February 1995, which formed part of the sub-contract documents;
(b). that Keppel Engineering had no express authority under the sub-contract to order San International to repossess the main office works;
(c). that San International had acted on Keppel Engineering`s decision on 28 October 1995 to exclude the main office works from the sub-contract by terminating their own sub-contractor for the execution of the works. Since engaging a new sub-contractor would take time `in view of the tight labour situation` and San International `would have to pay more than the market rate in order to get one urgently for the work you (Keppel Engineering) must undertake to reimburse us (San International) for any additional costs incurred and also to grant us (San International) the necessary extension of time`.
(d). San International said that they would inform Keppel Engineering when a suitable sub-contractor had been found and they would also forward the work schedule if Keppel Engineering`s order to repossess the main office works has not been withdrawn.
In the event San International did not follow up with information on the sub-contractor and the work schedule. (iii). By a letter dated 23 November 1995, Keppel Engineering strongly protested that they had `reneged` on their decision to exclude the main office works from the sub-contract. They also took strong exception at San International`s demand for additional costs and an extension of time before commencing to execute the main office works as entitlement to these could only be in accordance with the contractual provisions. Finally Keppel Engineering put San International on notice that if they did not recommence the main office works within 24 hours they would reserve their right to terminate the sub-contract forthwith without further reference to San International.
(iv). On 29 November 1995, not having heard from San International, Keppel Engineering terminated the sub-contract with San International in these terms:
By your failure to respond to our letter (23 November 1995) and to resume the works in question in accordance with the terms of the sub-contract, you have manifested an intention no longer to be bound by the sub-contract. This is a repudiatory breach of the sub-contract which we hereby accept.
The sub-contract is hereby terminated. We will liaise with you on the handover procedures.
(v). Also on 29 November 1995 but presumably after receipt of Keppel Engineering`s letter of the same date, San International sent a letter to Keppel Engineering in which they referred to Keppel Engineering`s letter of 23 November. San International expressed their confidence that Keppel Engineering`s termination of the sub-contract would be wrongful as San International had not suspended the sub-contract works; they had close to 100 workers working on the site.
(vi). Finally on 1 December 1995 San International responded to Keppel Engineering`s letter of 29 November 1995. This is what the letter said:
We refer to your letter dated 29 November 1995. The purported termination notice dated 29 November 1995 is given by your goodselves is a bad notice for the following reasons:
(a) We did not suspend the sub-contract works.
(b) By your letter dated 6 November 1995, it was agreed that you would take back all the remaining architectural works for the main office from 30 October 1995.
(c) The subsequent correspondence shows that there is a dispute as to the basis for the taking back of the architectural works. Be that as it may, the point remains that you have agreed to take back all the remaining architectural works.
(d) You did by letter dated 17 November 1995, required us to continue to perform our obligation under the sub contract. But this was never accepted by us. In fact, we continue to maintain by our letter dated 20 November 1995 that you have reneged on your decision to exclude the architectural works.
In the circumstances, there are no grounds for you to allege that we have failed to resume works in question in accordance with the terms of the subcontract. Nor were there any valid grounds for stating that we failed to respond to your letter dated 23 November 1995 as we have responded by our letter dated 29 November 1995.
As you have served the notice of termination wrongfully, you yourselves are now in breach of the subcontract which breach we hereby accept. We reserve to claim damages from you.
10.Both sides held fast to their respective contentions resulting in each suing the other. The two actions were consolidated and came on for trial on 9 February 1998 before Kan Ting Chiu J when it was decided to seek a ruling from the court whether San International had by their conduct repudiated their contractual obligations under the sub-contract with Keppel Engineering and whether Keppel Engineering were thereby justified in terminating the sub-contract (the preliminary issue).
11.The learned judge decided the issue in favour of Keppel Engineering holding that San International had by their conduct repudiated the sub-contract for the following reasons: (i). the parties` conduct after the disagreement over the basis for the exclusion of the main office works from the sub-contract up to 29 November 1995 showed that neither of them regarded that there was a binding agreement between them, excluding the main office works from the sub-contract. They both acted on the basis that the sub-contract still applied to the main office works and presumably that Keppel Engineering were entitled to require San International to recommence the main office works;
(ii). San International`s conduct up to 29 November 1995 showed that they had no intention to complete the main office works unless they received Keppel Engineering`s undertakings as to additional costs and extension of time and accordingly they exceeded their rights under the sub-contract and evinced an intention to repudiate the sub-contract;
(iii). that since the main office works were not completed in any sense of the word and the architect could not therefore apply for a TOP if the works were left in that state, San International`s refusal to resume work so late into the construction period could have many serious consequences for Keppel Engineering and accordingly they were entitled to terminate the sub-contract on the basis of this repudiatory breach.
12.The issues arising in this appeal may be stated as follows: (i). whether Keppel Engineering had the authority or power to order San International to re-commence the main office works;
(ii). whether San International had by their conduct subsequent to the 28 October 1995 meeting repudiated their obligations under the sub-contract; and
(iii). whether this repudiatory conduct (if any) entitled Keppel Engineering to treat the contract as discharged.
13. Whether Keppel Engineering had the authority or power to order San International to re-commence the main office works
Central to this issue is whether there was a separate binding agreement between the parties outside the terms of the sub-contract, as San International contend, to exclude from the sub-contract works the main office works or whether there was a variation within the terms of the sub-contract to omit the main office works from the sub-contract works as Keppel Engineering contend.
14.A determination of this question is made difficult as the agreed facts contained in the statement of facts do not bespeak the facts and circumstances leading to the meeting of 28 October 1995 or the negotiations during the meeting of 28 October 1995. The agreed facts and indeed the whole of the statement of facts is wholly unhelpful to determine the question raised by the preliminary issue. All that the court is given are two facts. One, that following the meeting on 28 October 1995 Keppel Engineering instructed another of their sub-contractors, namely, Poh Jet, to take over and complete the main office works and that Poh Jet worked on the main office works from 1 November to 17 November 1995. The other is that as at the date of termination of San International`s sub-contract the works (it is not clear whether this refers to the sub-contract works or the main office works or to both) were in delay but no admissions are made by either party as to the causes of the delay as there were other sub-contractors whose works were in delay and could have caused a delay in the completion of phases A and B. Hence the court is deprived from taking an objective view from all the facts, agreed or proven, to come to a determination.
15.Be that as it may there is an agreed bundle of documents containing the exchange of correspondence between the parties immediately following the meeting of 28 October 1995 to 29 November 1995 which we have digested in [para ][para ] 7, 8 and 9 above. Now, looking at this correspondence, Keppel Engineering`s position as indicated by their letters of 6 November 1995 and 17 November 1995 is that there was a consensual agreement made at the request of San International for Keppel Engineering to take over the main office works in an attempt to mitigate San International`s existing breach in delaying the progress of the sub-contract works by their lack of diligence. The basis of the take over is clearly an agreement to vary the sub-contract works by omitting therefrom the main office works. Since Keppel Engineering`s letter of 17 November 1995 refers to mitigating the impact of San International`s breach on the progress of the works it can also be inferred that the take over or omission of the main office works from the sub-contract works was not to prejudice Keppel Engineering`s remedies in respect of existing delay of the main office works. Thus San International were in anticipatory breach when they informed Keppel Engineering that they did not have the resources to carry out and complete the sub-contract works.
16.The first response San International made to Keppel Engineering`s letter of 6 November 1995 is dated 9 November 1995. We have set it out quite fully in [para ] 8 above. Apart from disputing the cause for the take over or omission of the main office works from the sub-contract works, San International make the significant assertion that `the omission of such works shall follow the working mechanism of variation clauses as stipulated in the agreement.` An objective construction of this letter clearly indicates that San International understood the omission to be pursuant to Keppel Engineering`s exercise of their power to exclude the main office works from the sub-contract works albeit following the amicable discussion on 28 May 1995.
17.We are fortified in this view from San International`s reply to Keppel Engineering`s letter of 17 November 1995 dated 20 November 1995 where they said, and we quote:
It is clear that you have reneged on your decision to exclude the architectural works to main office building; an option you had exercised by virtue of a provision contained in the sub-contract - cl 3 of Keppel Engineering`s letter ref: PI/W&T/95/0001 of 7 February 1995. The latter forms part of the sub-contract documents.
The clause referred to reads:
Keppel Engineering Pte Ltd shall reserve the right to exclude parts of the works from Scope of Works which exclusion shall include (1) the prime cost and provisional sum and (2) all steel structures, roof claddings and wall claddings under Bill No: 2, 4 and 5.
Any reduction in the contract sum due to the above exclusion shall be calculated based on the bill of quantities submitted by you on 27 January 1995 and revised on 29 January 1995 with a further discount of S$50,000.00 (Singapore Dollars fifty thousand).
18.In reality San International`s understanding as amply demonstrated by their own letters was that following the discussions between them and Keppel Engineering on 28 October 1995 Keppel Engineering acted to vary the sub-contract works by omitting therefrom the main office works. This was within the terms of the sub-contract. They did this by directing or instructing Poh Jet to execute the main office works from 1 November 1995. We are unable to discern from the correspondence exchanged between the parties a mutually agreed separate agreement to omit the main office works from the sub-contract least of all because if there was disagreement as to the cause or causes which led to the separate agreement, as indeed there was, then there was no consensus ad idem between the parties to conclude an agreement (see Chitty on Contracts Vol 1 para 2-017).
19.It follows from the foregoing that the sub-contract between Keppel Engineering and San International subsists and the omission of the main office works from the sub-contract works was a variation within the sub-contract terms. By the same token Keppel Engineering`s direction to San International to reinstate or reassimilate the main office works into the sub-contract works by Keppel Engineering`s letter of 17 November 1995 is also a variation within the sub-contract terms. It is not disputed that the sub-contract contains the power to alter or vary previous instructions or directions and also the power to order additional work to be undertaken. (See the main contract terms cll 1 and 14. The main contract is a designated sub-contract document.) It is also not disputed, which Mr Menon says was conceded by San International in the court below, that Keppel Engineering had the authority under the sub-contract to give directions or instructions to San International. Mr Chuah did not demur. Accordingly the learned judge was right in deciding this issue in favour of Keppel Engineering.
20. Whether San International had by their conduct subsequent to the 28 October 1995 meeting repudiated their obligations under the sub-contract
The law on repudiatory breach or renunciation can be summarised as follows: A renunciation of contract occurs when one party by words or conduct evinces an intention not to perform or expressly declares that he is or will be unable to perform his obligations in some material respect. Short of an express refusal or declaration the test is to ascertain whether the action or actions of the party in default are such as to lead a reasonable person to conclude that he no longer intends to be bound by its provisions. The party in default may intend in fact to fulfil the contract but may be determined to do so only in a manner substantially inconsistent with his obligations, or may refuse to perform the contract unless the other party complies with certain conditions not required by its terms: Chitty on Contracts Vol 1 para 24-016.
21.Keppel Engineering by their letter of 17 November 1995 required San International `to continue to perform [their] obligations under the contract`, and directed them `to commence performance of the said works immediately` and to provide Keppel Engineering `a revised work schedule within seven days`. It will be remembered that the main office works initially were included in the sub-contract works. Their omission from the sub-contract works is what gave rise to the contentions between the parties.
22.The position taken by San International is that relying on Keppel Engineering`s variation of the sub-contract to omit the main office works from the sub-contract works San International discharged their sub-contractors, whom they had engaged for the execution of the main office works and now that Keppel Engineering by a further variation of the sub-contract had reinstated the main office works into the sub-contract works San International needed time to find a suitable sub-contractor and engage them for the work. Having regard to the urgency of the work and the tight labour situation San International would have to pay more than the market rate. When San International had found a suitable and competent sub-contractor they will inform Keppel Engineering and send Keppel Engineering the work schedule for the main office works. Accordingly San International required Keppel Engineering to agree to pay the additional costs and grant an extension of time. On the other hand the position taken by Keppel Engineering was that San International was only entitled to additional payment or an extension of time in accordance with the sub-contract terms. Keppel Engineering by implication refused to give the assurances sought by San International.
23.The agreed facts are hopelessly inadequate for us to determine the answer to the loosely framed preliminary issue of law (see [para ] 4 above). The four facts agreed to do not help us to determine whether Keppel Engineering was right in the position they took or whether San International were justified in requesting for additional payment and an extension of time to execute the main office works. We would have to know a lot more as for example the circumstances and the terms under which Keppel Engineering took over the main office works on 28 October 1995. Was it due to lack of manpower available to San International to complete the main office works as Keppel Engineering contend or was it for Keppel Engineering`s convenience in co-ordinating the M&E works for which Keppel Engineering were responsible with the remainder of the project works as San International contend. Another example is whether in fact San International had engaged a sub-contractor for the main office works whom they discharged when the main office works were omitted from the sub-contract works following the 28 October 1995 meeting. Yet another example is whether Keppel Engineering`s letter of 17 November 1995 was or constituted a `direction` or `instruction` under the terms of the sub-contract or neither, and whether San International understood it as such, as different consequences flow from such distinction. These are all questions of fact material to the issue under discussion. We simply do not have enough facts to determine these questions and hence this issue.
24.In the circumstances we are unable to say whether San International`s conduct subsequent to 28 October 1995 was a refusal to execute the main office works. But even if we answered this question in the affirmative, to do which several assumptions in favour of Keppel Engineering would have to be made, we would still be unable to address the all important third issue which we have framed as we will now demonstrate, again because the necessary factual substratum has not been addressed.
25. Whether San International`s repudiatory conduct (if so found) entitled Keppel Engineering to treat the sub-contract as discharged
Not every intimation of an intention not to perform or of an inability to perform some part of a contract will amount to a renunciation. In the case of an entire and indivisible contract, a refusal to perform any part of the agreement will normally entitle the innocent party to treat the contract as discharged. Otherwise, a renunciation of some but not all the obligations under a contract will not entitle the innocent party to rescind the contract unless the renunciation amounts to a breach of a condition of the contract or deprive him of substantially the whole benefit which it was the intention of the parties that he should obtain from the obligations of the parties under the contract then remaining unperformed: The Nanfri; Federal Commerce and Navigation Ltd v Molena Alpha Inc & Ors [1979] 1 All ER 307; The Afovos; Afovos Shipping Co SA v Pagnan (R) & (F) Lli [1983] 1 All ER 449.
26.The crux of the matter under this issue is whether San International`s refusal to undertake the main office works unless they received additional payment and an extension of time (if so found) was sufficiently serious enough to justify Keppel Engineering terminating the sub-contract on 29 November 1995. San International`s principal argument was that at the date of termination the outstanding work on the main office works amounted to less than 4% of the overall sub-contract works. This they argued was substantial completion of the entire sub-contract works and could not justify termination of the sub-contract. Hoenig v Isaacs [1952] 2 All ER 176 was relied upon. However a reference to San International`s own analysis of claims submitted for the entire sub-contract based on the value of the sub-contract showed that only 79% of the sub-contract works was completed. San International`s approach ignores the principle that the materiality of the refusal must be weighed in the context of the obligation then remaining unperformed. See The Afovos . This is correct, in our view, particularly in the context of construction contracts where progress payments are provided for works already completed so that at the time of termination the parties are primarily concerned with the remaining unperformed obligations and the impact on them of the particular breach. The fact that the proportion of the uncompleted main office works was approximately 25% of the total sub-contract works still outstanding, as contended by Keppel Engineering, even if accurate, indicating that the sub-contract works were not substantially completed would not resolve this issue in favour of Keppel Engineering.
27.In our view the crucial question is what consequences San International`s failure to resume work on the main office works had on the project as a whole and not just on the sub-contract works. For example, we can gather from the statement of facts that the summary of claims on the main office works indicate what the state of progress of the main office works were; it gives no indication as to their relation to the rest of the project and phase B in particular. The drawing plans show that the main office is part of the main warehouse but one cannot automatically draw an inference that the main office works would necessarily affect the progress of work on the main warehouse. The photographs give an overall impression of the state of work in the main office itself, not of what relation this work and the main office works have on the project as a whole.
28.What is left of the statement of facts is that the main office works is one of a number of activities that were in critical delay, although it is not possible to state which activity was the critical activity to the completion of the project as a whole. We have already commented on the statement of facts, the agreed facts and the facts not agreed but which San International consider relevant. This form of statement of facts is wholly unhelpful and highly unsatisfactory. The agreed facts do not provide a direct factual substratum from which the court can properly decide this mixed question of fact and law.
29.Accordingly, this issue must also remain unresolved for the time being. What is needed is direct evidence showing what repercussions the main office works had on the rest of the project, and in particular the main warehouse. It was unfortunate that the learned judge did not take advantage of the last sentence in the statement of facts instead of doing the best he could on what was before him. The last sentence of the statement of facts reads:
If, however, it should be held that it would not be possible to reach a conclusion on this point of law, without first making a finding on any or all of these facts then it is agreed that evidence will have to be adduced.
30.All too often counsel are eager to take short cuts by taking preliminary points of law on inadequate agreed facts. This trend which is prevalent in building contract disputes is not to be encouraged. As it has been seen in this case it is counter productive and wasteful of time, expense and effort. We are reminded of what Lord Wilberforce said in his speech in the House of Lords in Tilling v Whiteman [1980] AC 1 at p 17:
I, with others of your Lordships, have often protested against the practice of allowing preliminary points to be taken, since this course frequently adds to the difficulties of courts of appeal and tends to increase the cost and time of legal proceedings. If this practice cannot be confined to cases where the facts are complicated and the legal issue short and easily decided, cases outside this guiding principle should at least be exceptional.
And Lord Scarman in the same case said at p 25:
Preliminary points of law are too often treacherous short cuts. Their price can be, as here, delay, anxiety, and expense.
31. Conclusion
In the result we must remit the second and third issues to the judge to hear the evidence and decide these two issues afresh.
32.However, we have determined the first issue as the learned judge did, upholding Keppel Engineering`s contentions and rejecting San International`s. Since San International has failed in this issue they should pay one-third of the taxed costs of the appeal to Keppel Engineering and we vary the judge`s order for costs made below to the effect that Keppel Engineering should recover only one-third of the costs below. As for the remaining two-thirds costs both here and below, we order that they abide by the order the learned judge makes on the remitted issues. The appeal deposit shall be paid out to Keppel Engineering or their solicitors to account of Keppel Engineering`s costs here.
Karthigesu JA
L P Thean JA
Yong Pung How CJ
Christopher Chuah and Tan Liam Beng (Drew & Napier) for the appellants
Menon Sundaresh And Desmond Ong (Rajah & Tann) for the respondents