Econ Piling Pte Ltd v Eltraco International Pte Ltd
[1998] SGHC 195
Suit 1240/1994
Judith Prakash J
03 June 1998
Judgment:
GROUNDS OF DECISION
1. I delivered written judgment in this action on 4 February 1998. At the end of the judgment, I asked parties to address me on costs. The costs hearing was held on 1 April 1998. After listening to the arguments, I made the following order:
‘The plaintiffs are awarded their costs as follows: full costs up to the date the trial started (to include the costs awarded in respect of the sum of $179,443.63 for which judgment was given on 28 April 1997) and 70% of their costs incurred thereafter as taxed.’
The defendants have appealed against the above order.
2. This claim arose out of piling works which the plaintiffs conducted at the request of the defendants. The plaintiffs’ claim was originally for $537,785.29 being the cost of the work done by them. The defendants did not dispute this sum. Their defence was that of set off. At the beginning of the trial it became clear that the total amount that the defendants were claiming to set off was $358,341.66. On the first day of the trial therefore, I gave the plaintiffs judgment for the difference between their claim and the amount which the defendants were claiming to set off ie the sum of $179,443.63.
3. The trial proceeded in respect of the remaining $358,341.66. During its course the plaintiffs conceded that they were liable to pay the defendants $23,420, for defective works. This meant that the main bulk of the trial was concerned with the sum of $334,921.66 which represented the defendants’ claims for damages caused by the delay of the plaintiffs in the execution of the piling works. I concluded that the defendants were only able to prove damages amounting to $68,900 for such delay and, at the end of my judgment, this sum was also set off against the amount claimed by the plaintiffs. Thus out of the balance of $358,341.66, the plaintiffs were able to recover $266,021.66.
4. When the parties appeared before me on costs, counsel for the defendants cited Re Elgindata Ltd (No. 2) [1993] 1 All ER 232 and argued that the third principle set out in that case should be applied in the present circumstances and that the plaintiffs were only entitled to 25% of their costs. In that case, Nourse LJ succinctly recited the principles which have to be applied when a court exercises its discretion in relation to the award of costs as follows:
‘The principles are these. (1) Costs are in the discretion of the court. (2) They should follow the event except when it appears to the court that in the circumstances of the case some other order should be made. (3) The general rule does not cease to apply simply because the successful party raises issues or makes allegations on which he fails, but where that has caused a significant increase in the length or costs of the proceedings he may be deprived of the whole or part of his costs. (4) Where the successful party raises issues or makes allegations improperly or unreasonably, the court may not only deprive him of his costs but order him to pay the whole or a part of the unsuccessful party’s costs.’
5. The defendants submitted that the basic question which had to be decided at the trial was whether there had been a delay in the execution of the works. They had succeeded in proving this delay and their efforts to establish their case in the face of the plaintiffs’ wholesale denial of the issue had caused a significant increase in the length of the proceedings. They pointed out that a substantial portion of the judgment had been taken up with issues relating to delay and the damages emanating therefrom.
6. The plaintiffs’ response was that the stand they had taken had not been unreasonable or unnecessary. The contract had been ambiguous and the factual matrix somewhat confused. Additionally, no reduction of costs should be ordered up to the time of trial because up to the first day of the trial the plaintiffs had not delayed anything.
7. I considered that the defendants’ arguments in support of the submission that the plaintiffs were only entitled to 25% of their costs went too far. The plaintiffs’ main difference with the defendants arose in relation to the extent of the delay and to the applicable work programme and on this they were entitled to subject the defendants’ witnesses to searching cross-examination. The plaintiffs did, however, contribute to the unnecessary prolongation of the trial by taking the stand at the beginning that there was no contractual time limit for their works at all and by denying their knowledge of the liability the defendants would incur by reason of delays in the piling works. Their failure to recognise at an earlier stage that part at least of the defendants’ claims were valid meant that time had to be spent in establishing liability which would not have been required had quantum alone been the issue.
8. I did not consider, however, that it would be fair to deprive the plaintiffs of 75% of their costs. I thought that they were entitled to their costs up to the time the trial started since it was not possible then to draw any distinction between the amount for which they recovered judgment on the first day of the trial and the balance found due at the end of the trial. The only reason they had not obtained judgment for that amount earlier is that the defendants had not been able to quantify their claims before then. There was no delay on the plaintiffs’ part in this regard. Accordingly, I awarded them their full costs up to the first day of the trial. As for the trial itself, I considered that a 30% reduction in the plaintiffs’ costs was a fair estimate of the time by which the trial had been prolonged by issues and allegations on which the plaintiffs had failed. In this connection, it was significant that the defendants succeeded in proving less than 30% of the claim which they had originally raised. Further, whilst the defendants complained that the court had to stand down for half a day because the plaintiffs had decided to call a witness from the Jurong Town Corporation (‘JTC’) at the last moment, it was the evidence of this witness which helped to clarify the issues and the facts and if the JTC documents and evidence had not been adduced, all parties would have been floundering around for a much longer time.
JUDITH PRAKASH
JUDGE
SINGAPORE
Chia Chor Leong (Chia Chor Leong & Co) for the plaintiffs
Pavan Kumar Ratty (P K Ratty & Partners) for the defendants