In the High Court of the Republic of Singapore
[1998] SGHC 365
Suit 258/1994
Between
Management Corporation Strata Title No 964
… Plaintiff
And
Gordon Industrial Land Pte Ltd
Embelton Singapore Pte Ltd
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Management Corporation Strata Title No 964 v Gordon Industrial Land Pte Ltd and Another
[1998] SGHC 365
Suit 258/1994
Lee Seiu Kin JC
05 November 1998
Judgment :
GROUNDS OF DECISION
1. This is an appeal by the Plaintiffs against my decision on 28 August 1998 dismissing their claim against the Second Defendants with costs. The Plaintiffs have appealed I now give my grounds of decision.
2. The Plaintiffs are the Management Corporation, constituted under the Land Titles (Strata) Act, of a 7-storey flatted warehouse cum industrial building known as Gordon Industrial Building ("the Building") situated at 113 Eunos Avenue 3. The first Defendants are the developer of the Building. The Plaintiffs’ claim against the first Defendants has been settled.
3. The Second Defendants, ("Embelton") are a company involved in the installation of building waterproofing systems. The main contractor for the construction of the Building was Seah Construction Pte Ltd ("SCPL"). Embelton were the nominated sub-contractor for the waterproofing system to the roof. Embelton were also to carry out waterproofing treatment to certain parts of the building such as the underground water tank, lift shaft pits, drains, etc. However this aspect of the work is not the subject matter of this claim. The Plaintiffs’ claim against Embelton is only in respect of the roofs.
4. Embelton gave a number of quotations to SCPL. The relevant one is that contained in their letter dated 4 August 1983 which was accepted by SCPL on 6 October. The letter states as follows:
"Attn: Mr A.H. Ong 4 August 1983
M/s. Seah Construction Pte Ltd
246-P, Upper Thomson Road
Singapore 2057
Dear Sirs,
Re: Gordon Eunos Warehouse Complex
We wish to confirm our discussion regarding the use of our products for the above project, and submit herewith our revised quotation for your kind consideration as follows:
Quotation:
a) To submit labour and materials (admixture only) for injection of Embelton integral concrete waterproofer to concrete inclusive of transportation and delivery to premix plant as per your Architects specification at the rate of $60.00 per cubic metre for an approximate quantity of 465 cubic metre = $27,900.00 less 30% discount = $19,530.00.
b) To supply labour, equipment and waterproofing admixture only (excluding cement and sand and hoisting of these materials to the roof) for installation of 50mm thick Embelton waterproofing screed to roof with gradient to gutter and R.W. outlet as per your Architects specification @ $10.50 per metre square for an approximate area of 3,572 = $37,506.00 less 5% discount.
c) To supply labour, equipment and hardener (excluding cement, sand & 6mm granite chipping and hoisting of these materials to the designated area) for installation of 25mm thick Embelton non-metallic hardener as per our Architect’s specification at $9.00 per square for an approximate area of 2779m2 = $25,011.00 less 5% discount.
d) To supply labour, equipment and hardener (excluding cement, sand, 6mm granite chipping and hoisting of these materials to designated areas) to staircase treads and riser @ $8.00 per lineal metre less 5% discount.
Condition of contract
:
a) The above floor hardener topping is advised to be paved after placing of the base slab and roofing. However, we will have to liaise with you to work out a progress chat in conjunction with your construction programme at a later date.
b) The above quotation is based on a screed thickness of 25mm. Should the thickness of the hardener screed exceed, we reserve the right to charge the additional thickness at a pro-rata rate (additional thickness) will be checked between both parties before we proceed with our screeding work.
c) Free storage space, water and electricity and tower crane must be provided by you for transportation of our materials during our installation work.
d) All designated areas to be screeded with our hardener/sealer must be free from debris and clear from obstruction during the installation of our floor hardener topping.
e) We require your early confirmation in order that we can organise and arrange for all materials involved for the above so as to control escalation of prices of these commodities at a later date.
f) Work will commence within 2 weeks of receipt of your instruction to start. But we will require to work out a progress chart to meet with your programme.
g) A 90% interim (progress) payment must be made fortnightly after receiving of our invoices according to the work completed on site.
h) Final and full payment shall be made according to the measurement of work for the above within 2 weeks after receiving of our invoice.
We thank you for your interest in our products and look forward to receiving a favourable reply from you.
Yours faithfully,
for Embelton Singapore Pte Ltd
GEORGE TOH KUM YEOK
CONSTRUCTION PRODUCTS MANAGER"
5. Embelton eventually carried out the works set out in their quotation. The Building was completed in 1984 and various units were subsequently sold to various purchasers. The Plaintiffs took over the management of the Building from the first Defendants on 1 June 1986.
6. By an agreement dated 22 April 1984 ("the Warranty"), Embelton gave a 10-year warranty to the first Defendants in respect of the "Embelton Integral Waterproofing System" supplied in respect of the Building pursuant to a contract dated 2 April 1984 between Embelton and the first Defendants. For some reason the parties did not exhibit the 2 April contract but nothing turns on that. Subsequently on 20 November 1987 the first Defendants assigned the benefits of the Warranty for the remainder of the period to the Plaintiffs. Embelton agree that this assignment effectively passed to the Plaintiffs the benefits of the Warranty.
7. According to the Plaintiffs, sometime around 1990 they received several complaints of water leakage from the occupiers of several units on the first and seventh stories. These units were beneath the roofs at those levels. The Plaintiffs engaged Dr C K Murthy, a Professional Engineer from CKM Consultants Pte Ltd ("CKM") to inspect the Building and prepare a report. In the event Dr Murthy prepared 2 reports, the first dated 6 April 1990 and a supplementary report dated 6 December 1990. Among other things, these reports found that:
(i) there were no defects affecting the structural integrity of the Building, and only non-structural defects were present;
(ii) the waterproofing system on the main roof and the roof over the first storey had failed leading to water penetration problem.
The report proceeded to make recommendations for the rectification of the said defects which was eventually carried out by the Plaintiffs.
8. By a letter dated 1 February 1991 the solicitors for the Plaintiffs notified Embelton of numerous complaints about leakage to the waterproofing system of the Building and that a survey had ascertained that the said system had failed. They gave notice under the Warranty for Embelton to confirm their willingness to rectify the defects, failing which the Plaintiffs would proceed to appoint a contractor to carry out the repairs and recover all costs incurred from Embelton. Embelton replied on 6 March 1991 to deny that they were liable for the defects causing the leaks. They averred that complaints of roof leakage had been made some years earlier and that in November 1987 a joint inspection was made by them with the Plaintiffs’ representatives, the main contractor SCPL. Embelton claimed that the problem was not due to the failure of the waterproofing system and that remedial work was carried out on the roof structure by SCPL.
9. At the same time the Plaintiffs’ solicitors also wrote to the first Defendants alleging the presence of structural defects to the building and giving them 7 days to repair those defects failing which they would engage a contractor to do it and recover all costs and expenses from the first Defendants. The first Defendants denied all liability to the Plaintiffs, claiming that the 12-month defects liability period had expired. In relation to the roof leaks, they referred the Plaintiffs to the Warranty which they had assigned to the Plaintiffs. There were further exchanges of correspondence between the Plaintiffs, the first Defendants and Embelton. The Plaintiffs notified both of them of their intention to engage a contractor to carry out the necessary repair works. The first Defendants and Embelton continued to deny liability. In the event the Plaintiffs, through their consultant CKM invited tenders for the repair works. A contractor, K L Coats (S) Pte Ltd was appointed and they carried out repair works to the Building comprising repairs to the structural defects and the roof leaks. The contractor completed the repair works in February 1993.
10. On 22 February 1994, the Plaintiffs commenced this action against the first Defendants and Embelton by filing a Writ of Summons. Against Embelton, the Plaintiffs’ claim is in negligence and in contract, viz. under the provisions of the Warranty. In their Defence, Embelton deny liability under both heads, i.e. they were not negligent at all and that the Warranty did not cover the defects that caused the leaks. Embelton also raised the defence that the Plaintiffs’ claim is barred by the Limitation Act.
Limitation Act
11. I deal first with the issue of limitation as it is easily disposed of. Embelton say that the claim in negligence is barred by the Limitation Act as the waterproofing system was installed by 1984 which was when the Building was completed. Therefore at the latest, the cause of action arose in 1984 and the 6-year limitation period for an action in negligence would have expired by 1990.
12. Furthermore, Embelton say that the Plaintiffs had knowledge of the defects as far back as 1986. On various dates between 1986 and November 1987 representatives of the Plaintiffs, together with those of the first Defendants and Embelton, jointly inspected the roof concrete slab and found various cracks in the said slab. Inspections were also carried out in respect of leaks to various units on the 7th floor and to the canteen after complaints were received by the Plaintiffs of leakage to the roof. The Plaintiffs’ witness, Mr Low Ser Seah (PW4) said in paragraph 13 of his affidavit evidence-in-chief that sometime in late 1989 and 1990 the Plaintiffs received several complaints of water leakage from subsidiary proprietors and occupiers of various units under the roofs. However under cross-examination he was shown a letter from the first Defendants to SCPL dated 26 September 1986 (1DB52) which was after the Plaintiffs took over the maintenance of the Building on 1 June 1986. In this letter the first Defendants made reference to their previous letters informing SCPL of roof leaks to units 07-07 and 07-09 and complained that the defects had not been rectified yet. Based on this PW4 agreed that the Plaintiffs were aware of leaks at that time. PW4 was next shown another letter from the first Defendants to SCPL dated 19 November 1986 (1DB56) which complained about Embelton not repairing the roof leaks to units 07-07 and 07-08. PW4 gave the same response. It was then put to PW4 that the Plaintiffs knew of leaks to the 7th storey roof in November 1987 or earlier and he said that "based on the correspondence, the Managing Agent or developer were aware of the problem at that time." PW4 said that it never occurred to the Plaintiffs that the leaks were serious until Dr Murthy put up his report in 1990.
13. Embelton was represented by Mr George Toh (DW2). In his affidavit evidence-in-chief he said that the first complaints of roof leakage were received in July 1984. Further complaints were received between January 1985 and September 1986. He exhibited in "GTKY-2" of his affidavit copies of letters and telexes from SCPL, the architect and the first Defendants over this period complaining about the roof leaks. DW2 said that he inspected the leaks and found that the leaks were not caused by failure of the waterproofing system but were due to cracks in the roof slab. He thus denied responsibility for the leaks. DW2 exhibited three telexes in "GTKY-4" of his affidavit. Two were from the Plaintiffs to Embelton dated 2 and 5 November 1987 which complained about roof leaks and requested Embelton to expedite repairs. The third telex, from Embelton to the Plaintiffs and the architect and dated 9 November 1987, recorded a joint inspection carried out on 5 November by DW2 and the Plaintiffs’ representative, one Mr Ong. As DW2 was not cross-examined on this part of his evidence, the Plaintiffs must be taken to have accepted its veracity. Indeed given the telexes and letters exhibited by DW2, the authenticity of which was not challenged, it is clear that the Plaintiffs had known of the roof leaks by November 1987.
14. Under section 24A(3)(b) of the Limitation Act, in the case of latent damage, the time for bringing an action is limited to 3 years from the earliest date on which the Plaintiffs first had the knowledge and right to bring an action. The Writ was filed on 22 February 1994. For the Plaintiffs to be entitled to bring the action in negligence they must have acquired the knowledge no earlier than 23 February 1991. Accepting as I do Embelton’s evidence on this, the Plaintiffs had such knowledge by November 1987. Even on the Plaintiffs’ position, Dr Murthy’s report was completed in 1990 and they well knew by then of the leaks.
15. Therefore any cause of action that the Plaintiffs had in negligence against Embelton in respect of the leaks is barred under the Limitation Act.
Warranty
16. In respect of the Warranty, Embelton submit as follows:
(i) the Warranty does not cover the leaks that occurred in the roofs of the Building; and
(ii) even if it does, the Warranty had expired.
17. I deal with the second point first, i.e. that the Warranty had expired. Embelton’s case is that the first demand to repair the leaks to the roof was made by the Plaintiffs in November 1987. They say that the cause of action arose on that date and expired 6 years thereafter, i.e. in November 1993. Therefore an action in contract is barred after that date.
18. I disagree with Embelton’s position. The Warranty is an undertaking to repair any leaks caused by defective materials or workmanship within a 10-year period after the installation of the waterproofing system. As the Building was completed in 1984, the warranty period expired in 1994. The effect of the Warranty is to oblige Embelton to repair any such defects that arise within this period. A cause of action in contract arises when Embelton fails to do so within a reasonable time from the date the Plaintiffs report any defect. As there is evidence of demands made to Embelton throughout the period 1990 to 1994, time runs from the date of the last demand and not from November 1987.
19. However I agree with Embelton on the second point, viz. that the leaks encountered in the Building fall outside the scope of the Warranty. To understand their position it is necessary to venture a little into the technical details of the roof construction and waterproofing system. The Plaintiffs and Embelton both called expert witnesses on this. Dr C K Murthy (PW1) was the expert called by the Plaintiffs and Mr Bruce Jamieson Loggie (DW1) by Embelton. I note that Mr Loggie is a Chartered Building Surveyor rather than a structural engineer, which Dr Murthy is. Although Mr Loggie said that structural engineering was part of his academic training I find that the question of roof leaks involves structural engineering issues and that Dr Murthy is better qualified to give expert evidence on this matter. However, as it turned out the evidence of both witnesses are in accord in respect of the relevant factors that led me to the conclusion I arrived at.
20. At the outset the experts were asked to produce an agreed statement of facts. This they did and it is as follows:
1. The Embelton-Integral concrete waterproofer ("the System") is used as a liquid additive mixed with concrete to provide an increased resistance to water permeability and to minimise absorption and permeation of water by resisting capillary action.
2. When used in a roof screed it is added to the screed mix which when laid will bond directly to the structural slab, in effect forming an integral skin with the underlying slab to enhance waterproofing qualities.
3. The screed however is a rigid inelastic structure which is totally dependant on the stability and structural integrity of the base slab.
4. Water seepage has occurred before 1990 through the screed and reinforced concrete roof slab due to cracks within the screed and the reinforced concrete roof slab.
5. The cracks in the roof slab are caused by shrinkage and general movement within the structural concrete roof slab. As the slab and screed form an integral structure, movement in the roof slab will inevitably cause cracking to the slab and the screed.
6. Due to cracking, water seepage through the said cracks are inevitable.
7. There is no evidence of water leakage other than through the cracks in the roof screed and slab.
8. A membrane waterproofing system would have been more appropriate given the structure of the roof slab and the environment in which the waterproofing was to operate.
21. In his evidence-in-chief, Dr Murthy had said that he concluded that there was a "failure of the waterproofing systems" at the roofs and that the leaks were due to failure to use good materials and experienced workman, and to insufficient and wrong application of sealers. However these were general statements and in cross-examination he gave a detailed account of the mechanisms involved. The roof is a reinforced concrete structure. The main characteristic about concrete is that while it is very strong in compression it is much weaker under tension and when its tensile strength is exceeded, it cracks. In concrete roof slabs common causes of cracks are construction error, i.e. poor quality of concrete, improper curing, or design error, or environmental factors such as high temperature or a marine environment. The roof structure comprised reinforced concrete slabs supported by beams. Dr Murthy said that all reinforced concrete roof slabs move to some degree, depending on shrinkage, temperature change, creep and wind load, and how much reinforcement there is in it. The waterproofing system comprises adding an admixture called the "Embelton integral concrete waterproofer" to the concrete mix. This is supposed to reduce the permeability of the concrete by sealing the pores and voids in it. Hence a concrete slab treated with the admixture would be less permeable to water than an untreated one. Additionally, a 50 mm screed, i.e. a cement sand mortar, to which is also added the admixture, is laid on top of the slab to give additional protection against water seepage. That is the extent of the waterproofing system supplied by Embelton. I should add that this is borne by reference to the Embelton quotation of 4 August 1983 supplied to and accepted by SCPL. The problem is that if the concrete slab cracks for the various reasons postulated by Dr Murthy, which may well be through no fault of Embelton, the screed above it will also crack. Water will flow through such cracks, even if the concrete between cracks are perfectly sealed by the admixture. The Embelton system is called a "rigid waterproofing system", i.e. it cannot take cracks. This is in contrast to a flexible membrane which can stretch across cracks that may occur on concrete and still form a barrier to water penetration. As Dr Murthy said in cross-examination, the Embelton system is not suitable in the particular roof design in the Building where there was no movement joints to control cracks.
22. As it turned out, Dr Murthy had recommended to the Plaintiffs to use a flexible membrane system for their roof and this was just what the Plaintiffs had done in carrying out the repairs in 1993. On the question whether the Warranty covered the defects found in the Building, it is necessary to examine its terms. The Warranty states as follows:
EMBELTON INTEGRAL WATERPROOFING WARRANTY
THIS AGREEMENT is made on the 22nd day of April 1984, BETWEEN EMBELTON SINGAPORE PTE LTD… (hereinafter called the "Guarantor") ... AND Gordon Industrial Land Pte Ltd … (hereinafter called "the Company") … IN RESPECT OF the proposed "PROJECT"; Gordon Industrial Building … WITH REGARD to the use of "Embelton Integral Waterproofing" to the Execution and Completion of Waterproofing to "PROJECT".
Whereas
1. The Guarantor by a contract entered into by Embelton Singapore Pte Ltd and M/s. Gordon Industrial Land Pte Ltd for the sale and application of "Embelton Integral Waterproofing System" on 2nd day of April 1984 hereby guarantee for the Product for the above project for a period of ten (10) years commencing from the date of completion of the application of the material to the designated area; against water leakage due to our defective workmanship and/or material.
IT IS HEREBY AGREED AND DECLARED AS FOLLOWS THAT:
1) Any roof or any part of the roof allowing absorption or permeation of water or dampness as a result of defective material and/or workmanship of the product within the Guarantee Period shall be replaced and made good entirely at the Guarantor’s own cost.
2) Any such absorption or permeation of water or dampness shall not include absorption or permeation caused by structural defect of the building, wilful damage or damage caused by fire or natural disaster. Absorption or permeation of water or dampness caused by floor or wall movement and/or shrinkage or expansion cracks shall be made good under the terms of this guarantee where such absorption or permeation is attributable to defective material and/or workmanship of the Product.
3) The liability under this Agreement shall not extend to or include any liability on the part of the Guarantor to indemnify in any way the Client of the occupants or any person or persons against any damages or losses of any kind irrespective of the damage or losses that are directly or indirectly due to any defects in the product.
4) This guarantee is limited only as so far as the conditions and warranties of this guarantee are heeded to.
23. It can be seen that the Warranty covers only the effectiveness of the sealing qualities of the admixture. It expressly excludes the situation where the leaks are due to structural defects, floor or wall movements and shrinkage or expansion cracks. Dr Murthy did not carry out any tests on the permeability of the concrete. Therefore he could not say for certain that the admixture had failed in terms of its sealing qualities. It is abundantly clear that the Embelton system was the wrong choice for this kind of roof and the fact that Dr Murthy recommended the flexible membrane method bears testimony to this. In any case the Plaintiffs have not proved that the leaks were due to the failure of the Embelton system; all they have proved is the existence of leaks, which I find on the evidence before me were caused by cracks in the slab. Such cracks could be due to a whole host of possible causes. If any conclusion can come out of this, it is that the selection of the Embelton system for the roof in question was clearly a mistake. Embelton is not liable to the Plaintiffs under the Warranty.
Negligence
24. Although I have held that the action in negligence is barred by the Limitation Act, nevertheless for completeness I give my finding on the question of whether the Plaintiffs had a cause of action in negligence. For the same reasons given in relation to the Warranty, I find that there is no evidence of negligence on the part of Embelton in the installation of the waterproofing system. The only possibility of negligence in this situation is where Embelton had advised the use of their system in this situation where they knew or ought to have known that the roof in question was not suitable for a rigid waterproofing system. However this is not pleaded by the Plaintiffs.
Conclusion
25. Accordingly I dismissed the Plaintiffs’ claim against Embelton, with costs.
LEE SEIU KIN
JUDICIAL COMMISSIONER
SINGAPORE
Lee Seiu Kin JC
Lawrence Hussein (Ng Thin Wah & Partners) for the plaintiffs
M Sivakumar (Azman Soh & Murugaiyan) for the second defendants