Thong Huat Brothers (Pte) Ltd v Dicksonland Holdings Pte Ltd
[1998] SGHC 4
Suit No 943 of 1997, RA No 231 of 1997, RA No 282 of 1997, RA No 2065 of 1994
Choo Han Teck JC
05 January 1998
Judgment:
GROUNDS OF DECISION
1. The Respondents were the main contractors in a building project pursuant to a contract dated 8 September 1992. The Appellants were the Employers (owners) of the building under construction. The project was completed and the architect signed the final account certificate on 17 April 1997 stating that the defects had been satisfactorily rectified.
2. It was not disputed that the revised contract price was $2,191,985.39 of which $1,904,950 had been paid. The Respondents sued in this action for the balance of $287,035.39. The Appellants obtained summary judgment before the learned assistant registrar. The Appellants had also taken out an application to stay proceedings on the ground that the contract stipulated that disputes should be referred to arbitration. That application was heard before another assistant registrar who dismissed it. The appellants appealed before me against the two orders of the assistant registrars.
3. The Appellant’s defence was that the Respondents owe them a larger sum of $442,500 being liquidated damages for 177 days of delay. Counsel for the Respondents submitted that in a previous action in Suit 2065 of 1994 the Respondents claimed under the 12th interim certificate for interim payment of $527,000. The claim was allowed in summary judgment and on appeal the Honourable Justice Goh Joon Seng upheld the award to the Respondents. In that action the Appellants also raised the same issue of liquidated damages relying on the same certificate of the architect, claiming a set-off of the same $442,500. There was no appeal against the decision of Goh J. This was conceded by counsel for the Appellants. The issue of whether the Respondents were obliged to pay the Appellants the amount of $442,500 having been raised and adjudicated the Appellants cannot now resuscitate it in a fresh attempt to claim it (by way of set-off and counter-claim) against the Respondents. The learned assistant registrar was clearly right in granting summary judgment to the Respondents in this action and the Appellants’ appeal before me was dismissed.
4. I shall now deal with the Appellants’ appeal against the order of the assistant registrar refusing to stay the proceedings for the matter to go before an arbitrator.
5. Clause 37 of the contract (which was in the Singapore Institute of Architects’ standard form) provides that any dispute between the contractor and the employer shall be referred to arbitration. However, sub-clause (4) provides that:
"For the avoidance of doubt, in any case where for any reason the Courts and not an arbitrator are seized of a dispute between the parties, the Courts shall have the same powers as an arbitrator appointed under this clause."
This sub-clause has probably created more doubt than it hopes to avoid, but in my view, its presence in clause 37 renders sub-clause (1) as a permissive and not mandatory provision. For whatever reason, the High Court was indeed seized of the dispute between the Appellants and the Respondents in this action. The jurisdiction of this court was not ousted by Clause 37. The Appellants must, therefore, be bound to accept the determination of the issues so brought before it and the assistant registrar was correct in refusing a stay of the proceedings. Accordingly, I also dismissed this appeal of the Appellants.
- Sgd -
Choo Han Teck
Judicial Commissioner
Singapore, 5 January 1998.
Hilda Lee [Cooma Lau & Loh] for the plaintiff
Lawrence Hussien [Ng Thin Wah & Partners] for the defendant