In the High Court of the Republic of Singapore
[1998] SGHC 55
Suit No 2152 of 1995
Between
Keppel Engineering Pte Ltd
… Plaintiff
And
San International Pte Ltd (formerly known as San Ho Huat Construction Pte Ltd) (in liquidation)
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Keppel Engineering Pte Ltd v San International Pte Ltd (formerly known as San Ho Huat Construction Pte Ltd) (in liquidation)
[1998] SGHC 55
Suit No 2152 of 1995
Kan Ting Chiu J
26 February 1998
Judgment:
The parties
1. This is an action between the Plaintiffs, Keppel Engineering Pte Ltd, the main contractors for the construction of a two-storey warehouse with ancillary facilities known as WT Distripak Phase II, and the Defendants, San International Pte Ltd, who were their sub-contractors. The sub-contract covered the sub-station, transformer room and switch room, container repair shed/wash area, guard house and administrative office of the development.
2. The action arose out of the Defendants' refusal to complete the architectural works for the office located in the main warehouse building. The Plaintiffs treated that as repudiation by the Defendants, and terminated the sub-contract. The Defendants denied that they had repudiated the sub-contract and counter-claimed on the basis that the Plaintiffs were in breach.
3. The parties agreed that the question whether the Plaintiffs were entitled to terminate the sub-contract be determined as a preliminary issue.
The disputes
4. The Defendants started work under the sub-contract in February 1995. In October 1995 the parties were in discussions for the Plaintiffs to take over from the Defendants parts of the architectural works for the main office. Those works were taken over by the Plaintiffs who deployed another set of sub-contractors to work on them, but disagreements arose when they sought to put on record the reason for the take-over.
5. The Plaintiffs said they took over the works because the Defendants were unable to complete them. On 6 November 1995, they wrote to the Defendants that
Following the meeting on 28 Oct 95 between yourself and Mr.Vernon Tan from your company with our Mr Cheng II. K and the undersigned, it is agreed that Keppel Engineering will take back all the remaining architectural works for the Main Office from 30 Oct 95. As confirmed by you during the meeting, the reason for taking over the said works is due to the lack of manpower available from your company to complete the said works.
6. The Defendants contended that the works should be taken back as a variation omission of the sub-contracted works. In their reply of 8 November they said
We do not agree to your intended action. We do not accept your contention in regard to our Company's inability. ...
As your wish, you can take over the said works as a variation omission from our contract. Our agreement for you to take over base on the understanding that we have not in any way breached our subcontract conditions with you and further on a condition to our agreement to allow the said works to be undertaken by you that you shall not bring or institute any action against us based upon or in respect of our agreement or any subsequent liabilities which you may incur in relation to your undertaking of the said works.
7. The relationship between the parties became strained after that. On 17 November the Plaintiffs wrote to inform the Defendants that
We are shocked that you are now disputing the agreement made between us on 28 October 1995.
We had then agreed at your request to take over the architectural works for the Main Office from you because you told us that you did not have the resources to carry out and complete the said works. You are well aware that our intention was to mitigate the impact of your breach on the progress of the works which was already and continue to be in delay due to your overall lack of diligence in performing your works.
Since you are now disputing the basis on which we had taken over the works from you and taking the position that you are able to carry out the said works yourself, we are not willing to continue to provide such assistance to you in completing the said works. Therefore, we are withdrawing all our workers brought in for the performance of the said works from the site immediately.
8. The Defendants were equally unyielding. They replied on 20 November that
Your letter dated 17 November 1995 refers.
It is clear that you have reneged on you decision to exclude the architectural works to Main Office Building ...
We noted your order requiring us to repossess the aforesaid architectural works though you have no express authority to do so under the Sub-Contract. We had acted upon your decision and representation made on 28 October 1995 and terminated the arrangement with our sub-sub-contractor for the execution of that part of the works. We shall need time to look for a new gang of sub-sub-contractor and in view of the tight labour situation, we would have to pay more than the market rate in order to get one urgently for the work. Hence you must undertake to reimburse us for any additional cost incurred and also to grant us the necessary extension of time.
We shall inform you when a suitable and competent sub-sub-contractor has been found for the work and let you have the work schedule if your order has not been withdrawn then.
9. They did not follow up with information on the sub-sub-contractor and the work schedule.
10. By 23 November the Plaintiffs' impatience was showing when they wrote to the Defendants to say
We strongly deny the allegation made by you in paragraph 2 of the said letter.
Such allegation is shocking since you knew all along the true basis on which we had agreed to take over the architectural works. You are also well aware that we did not at any time purport to exclude the architectural works from your scope of works. In fact, it was you who first came up with the suggestion in your letter dated 8 November 1995 to omit the said works which we had refuted categorically in our letter of 17 November 1995 because it did not accord with the true agreement between the parties and responded with an immediate withdrawal of all our men from site.
... ...
We also take strong exceptions to your preposterous demand that we must undertake to pay you additional labour cost and grant you the necessary extension of time before you would commence performance of the said works. We take the position that you are only entitled to any price payable or extension of time granted in accordance with the Sub-Contract. You are not entitled to hold the progress of the works to ransom by requiring us to agree to terms outside the Sub-Contract.
Your position that we are not entitled to order you to commence performance of the said works is wholly misconceived. In truth, that is a refusal on your part to obey our instructions in connection with the execution of the Sub-Contract works.
... ...
Take notice that unless you recommence performance of the said works in accordance with the terms of the Sub-Contract within twenty four (24) hours hereof, we reserve our rights to terminate your Sub-Contract forthwith without further reference to you.
11. When they did not hear from the Defendants, they wrote on 29 November and made good their warning by informing them that
By your failure to respond to our letter and to resume the works in question in accordance with the terms of the sub-contract, you have manifested an intention no longer to be bound by the sub-contract. This is repudiatory breach of the sub-contract which we hereby accept.
The sub-contract is hereby terminated. We will liaise with you on handover procedures.
Please note that all our rights are hereby reserved.
12. On the same day, but after having sent their letter, the Plaintiffs received two letters from the Defendants. In one of them they said
... we have received a copy of your letter dated 23 November 1995, among other things, threatened to terminate our Sub-Contract. As we have not suspended the Sub-Contract Works, and have close to 100 workers still working on the site, we are confident that your termination, if exercised, will be wrongful and shall liable you to be sued for damages. Also, we have concluded that a dispute has arisen in the Sub-Contract and all the issues or contentions that you had raised in the letter are therefore not worth commenting.
13. These letters showed how the matters deteriorated during October-November 1995, leading to this action.
The statement of facts
14. When counsel agreed on the trial of the preliminary question, they prepared a statement of facts on which arguments was to proceed. The nine-point statement read
Agreed Facts
1. The architectural works for the main office ("Main office Works") had a bill value of approximately $563,000.00
2. The adjusted Sub-Contract sum was approximately $11.1 million. As at the date of termination, the value of all outstanding works amounted to approximately $2.3 million on Keppel's case or approximately $1.8 million on San's case. On Keppel's case, as at date of termination, San had completed about 79% in value of the adjusted Sub-Contract sum.
3. Following the meeting on 28 October 1995, Keppel instructed another of its Sub-Contractors, Poh Jet Construction Co ("Poh Jet"), to take over the Main Office Works and to complete the same. Poh Jet commenced work on the Main Office Works on 1 November 1995 and continued until 17 November 1995.
4. As at date of termination of San's Sub-Contract, the works were in delay (no admissions being made by either party as to the causes of the delay). There were several independent and interdependent activities outstanding, all of which were in delay and could have caused a delay to completion of Phase A and B. Aside from the Main Office Works, these activities included works within Keppel's scope of Works and/or taken over by Keppel and sub-contracted to other namely:
Nature of Works
Documents
Phase A
Poh Jet
Canteen/ Administration Office
Annex A
Phase B
Thye Siong Hoe Kee
External Works
Annex B
M & E Works
Facts which are not agreed but which San contends are relevant
5. Poh Jet ceased work on or about 17 November 1995 but the parties are not agreed as to the reasons for this. However, Poh Jet did resume work on the Main Office Works on or about 24 November 1995.
6. San contends that the notices to recommence performance of the Main Office Works given by Keppel were unreasonable.
7. Between 17 and 29 November 1995, San was sourcing for a new sub-sub-contractor for the Main Office Works on the basis of San's letter dated 20 November 1995 to Keppel. Even if true, it is agreed that Keppel had no knowledge whether San was or was not in fact sourcing for a new sub-sub-contractor for the Main Office Works.
8. San contends that the Main Office Works as at date of termination were not the critical activity to completion of the Phase B works. There were delays in other works for which San was not responsible which were also critical to completion of the works in Phase A and B including the activities mentioned in paragraph 4 above.
9. Keppel maintains that the factual disputes referred to in paragraphs 5, 7 and 8 above are irrelevant; so that even if it were to be assumed for the purposes of the trial of the preliminary issue that:
(i) Poh Jet were instructed to and did resume work on the Main Office Works on or after 24 November 1995;
(ii) San was on its own accord, sourcing sub-contractors on the basis of its letter of 20/11/95; and
(iii) the Main Office Works were one of a number of activities that were in critical delay (the others, including the works identified above as having been sub-contracted by Keppel to others) and that it was therefore not possible to state which activity was the critical activity to completion of the works.
Notwithstanding this, given the events that transpired between 17 and 29 November 1995, Keppel was entitled to rescind the sub-contract on the basis that San had repudiated the contract. Save for an agreed bundle of documents and the contract documents, no other evidence will be adduced for this purpose. If however, it should be held that it would not be possible to reach a conclusion on this point of law, without first making a finding on any or all of these facts then it is agreed that evidence will have to be adduced.
15. In the course of arguments the parties also agreed to an analysis on the claims submitted by the Defendants and to a photograph showing the state of construction of the main office as at 10 November 1995.
Whether the sub-contract applied to the remaining architectural works after the aborted take-over
16. If there was a binding agreement made in October for the take-over, that would exclude the remaining works from the sub-contract. In that event, the remaining works would cease to be governed by the sub-contract and would be governed by the terms of the take-over even if the take-over was aborted, unless the parties agreed that the works should revert to the sub-contract.
17. According to the Plaintiffs the remaining architectural works for the main office were taken over from 30 October because of the Defendants' lack of manpower to complete the works. The Defendants, however, regarded the take-over as a variation omission which released them from all liabilities in respect of the affected works. In the face of the disagreement, the Plaintiffs withdrew their workers and ordered the Defendants to resume work and to submit their revised work schedule. The Plaintiffs' letters showed that they were putting the take-over aside and were looking to the Defendants to fulfill their obligations under the sub-contract. They were not proposing that they and the Defendants enter into another agreement for the latter to complete the architectural works.
18. The Defendants were willing to continue with the works, appoint another sub-sub-contractor to carry out the works and submit a work schedule if the Plaintiffs undertook to reimburse them all additional costs incurred and to grant them extensions of time. They did not maintain the position that the works had been taken out of the sub-contract by a variation omission. In their submissions they stressed that nothing in the letter of 20 November suggested even remotely any intention not to be bound by the sub-contract.
19. After the Defendants received the Plaintiffs' notice of termination they informed them on 1 December that
... The purported termination notice dated 29th November 1995 is given by your goodselves is a bad notice for the following reasons:-
a) We did not suspend the Sub Contract Works.
b) By your letter dated 6th November 1995, it was agreed that you would take back all the remaining architectural works for the main office from 30th October 1995.
c) The subsequent correspondence shows that there is a dispute as to the basis for the taking back of the architectural works. Be that as it may, the point remains that you have agreed to take back all the remaining architectural works.
d) You did by letter dated 17th November 1995, required us to continue to perform our obligations under the sub contract. But this was never accepted by us. In fact, we continue to maintain by our letter dated 20th November 1995 that you have reneged on your decision to exclude the architectural works.
In this circumstances, there are no grounds for you to allege that we have failed to resume works in question in accordance with the terms of the subcontract. Nor were there any valid grounds for stating that we failed to respond to your letter dated 23rd November 1995 as we have responded by our letter dated 29th November 1995.
As you have served the notice of termination wrongfully, you yourselves are now in breach of the subcontract which breach we hereby accept. We reserve to claim damages from you.
20. That was the first time they said that the Plaintiffs' request for them to continue with the remaining architectural works was unacceptable to them, and that contrasted with the position taken in their letter of 20 November that they would complete those works on terms.
21. The parties' conduct after the disagreement over the take-over up to 29 November showed that neither of them regarded there to be a binding take-over agreement. They both acted on the basis that the sub-contract applied to those works after the take-over failed.
Whether the Defendants evinced an intention to repudiate
22. The Defendants made it clear that the Plaintiffs must undertake to reimburse them additional costs and grant them extension of time as a condition for them to resume work on the remaining architectural works. The sub-contract had provisions for claims for additional payments and extension of time and the procedures by which they were to be dealt with. In insisting on the Plaintiffs' undertaking to pay and to extend time even before they resumed work, the Defendants had exceeded their rights under the sub-contract.
23. This was brought to their attention by the Plaintiffs in their letter of 23 November, but they did not respond to it. They also did not follow up on their promise to inform the Plaintiffs the sub-sub-contractor who was to complete the works and to submit a work schedule.
24. Their conduct up to 29 November showed that they had no intention to complete the architectural works unless they received the Plaintiffs' undertakings. This was corroborated by their letter of 1 December where they stated that they had never accepted that they were obliged to perform their obligations under the sub-contract.
25. In their submissions, counsel for the Defendants contended that the Plaintiffs were wrong to direct the Defendants to resume work in their letter of 17 November. Counsel referred to Clause 1(2) of the SIA Articles and Conditions of Building Contract (Measurement Contract) which applied to the sub-contract. Clause 1(2) defined a direction as an order which will not entitle the contractor to additional payment or compensation or in an increase in the contract sum, as contrasted to an instruction, which will entitle the contractor to additional payment or compensation or an increase in the contract sum. Counsel contended that the Plaintiffs should have issued an instruction rather than a direction. (In fact the Plaintiffs had also referred to their order as an instruction when they wrote to the Defendants on 23 November.)
26. Even if they were correct on this, that did not justify the Defendants' failure to resume work. They did not seek clarification from the Plaintiffs whether the order was a direction or an instruction. They were not bound by the Plaintiffs' classification of orders as directions or instructions. Under clause 1(5) of the conditions a contractor can dispute the classification. If a contractor believed that an order issued to it should be an instruction rather than a direction, it is not entitled to disregard the order. It should give notice that it disagreed with the classification, and comply with the order. When the Defendants replied to the Plaintiffs' letter of 17 November on 20 November they did not refer to the classification of the order, nor did they refer to it in their letter of 1 December when they notified the Plaintiffs that they were terminating the sub-contract.
27. Counsel also complained that the order to resume work immediately was unreasonable and oppressive. It may be that the Defendants were not able to mobilise their work force and resume work immediately. If the Plaintiffs had terminated the sub-contract because they had failed to do that, the termination may be wrongful. However the short time given did not entitle the Defendants to ignore the order. They could ask for more time, or they could resume work when they were ready, but they did neither up to 29 November when the Plaintiffs terminated the sub-contract.
Whether the Plaintiffs were entitled to terminate the sub-contract
28. Counsel for the Defendants referred to JW Carters' Breach of Contract at para 808 that
There is no rule of law that a refusal to perform is necessarily a repudiation of obligation if it is a wilful refusal. In Adami v. Maison de Luxe Ltd (1924) 35 C.L.R. 143 at 151 Isaacs A.C.J. explained that wilful conduct must not merely be a breach, it must be a "radical breach'. ...
Therefore, proof that a promisor's words or conduct involve a wilful contravention of the contract does not per se establish a repudiation of obligation. If the wilful refusal relates to a minor obligation it will give rise to a right of termination only if the refusal has serious consequences for the promisee or is indicative of conduct which will be repeated to such a degree as to satisfy the requirement of seriousness. (Emphasis added)
and to Halsbury's Laws of England (4th Edn) Vol. 9 para 547 that
Not every refusal to perform a part of the contract amounts to a repudiation which entitles the other party to treat the contract as at an end; there must be a refusal to perform something which goes to the root or essence of the contract. The question whether the refusal to perform part of the contract amounts to a repudiation of the whole contract depends on the construction of the contract and the circumstances of the case. ... The main tests in deciding this issue are the ratio quantitatively which the breach bears to the contract as a whole and the degree of probability or improbability that such a breach will be repeated. (Emphasis added)
29. It was contended that under the sub-contract, the Defendants had until 29 December to complete their work on the main office and that deadline was not exceeded on 29 November. The deadline must be read with the Plaintiffs' Letter of Intent of 7 February 1995 to the Defendants which formed part of the sub-contract. This letter stated that
The contractual validity period shall be from the date of this letter to 29 December 1995. All Works must be completed by 29 October 1995 to allow the Architect to apply for a Temporary Occupation Permit.
30. It was also contended for the Defendants that
As at 29 Nov 95, San was not in breach of its obligation to complete. The fact that San had not physically completed the Main Office Works by 29 Oct 95 is irrelevant. San has until midnight of 29 Dec 95 to obtain TOP. If San had physically completed the works after 29 Oct 95 but manage to obtain TOP within the remaining compressed timetable before the 29 Dec 95, there is no breach.
As a rule, time for completion in building contracts is not of the essence of the contract.
31. Counsel appeared to have overlooked clause 24 of the "Preliminaries and General" provisions of the contract documents which stipulated that time was of the essence to the contract. Furthermore, the Architect was responsible for applying for the TOP, not the Defendants.
32. The Defendants assessed the remaining architectural works to the office to be between 4% and 5% by value of the sub-contract amount. The Plaintiffs valued them at 5%, or 25% of the works remaining under the sub-contract.
33. From the breakdown of the progress claims submitted by the Defendants the following data was obtained about the progress of the works on the office -
Architectural Works for the Office
Contract Value
Claims Made to 3-Nov 1995
% of Claims By Value
Built-up membrane roofing
71,358.00
3,099.00
4.34
Staircase finish
64,183.00
-
-
External door & windows
9, 718.00
90.00
0.93
Internal walls & partition
100,320.00
56,610.00
56.43
Internal doors
48,097.00
7,676.00
15.96
Wall finishes
76,394.60
35,755.80
46.80
Floor finishes
82,712.50
-
-
Ceiling finishes
74,027.00
-
-
Builders' work & finishes
17,022.00
3,050.00
17.92
34. As can be seen, work on the external walls and partition have just passed the half-way stage and, work on the wall finishes were reaching the half-way stage. Progress on the other aspects of the works was much slower, and only 20% of the works were done.
35. For the determination of the preliminary question the parties were prepared to proceed on the basis that the completion of remaining architectural works was not the critical activity to the completion of the main office work and that there were other works for which the Defendants were not responsible that were also critical to the completion of the works (see paragraph 8 of the Statement of Facts set out in paragraph 14 hereof). In other words, the parties were prepared to argue on the basis that the remaining architectural works were part of the works critical to the completion of the office without being the only critical works for the completion.
36. From the breakdown of the completed works set out in paragraph 33 hereof it can be seen that main office construction was quite unfinished. The internal walls and partitions were 56% completed and the wall finishes 47% completed. The other items were between 1% and 18% done, and work on the staircase finish, the floor finishes and he ceiling finishes had not started.
37. It was evident that the construction of the main office was not completed in any sense of the word. The Architect cannot apply for a TOP when the office was in that state. The Defendants' refusal to resume work so late into the construction period could have very serious consequences for the Plaintiffs. With the works unfinished, the office cannot be handed over to the employers and that could set back the completion and operation of the warehouse, as the office was an integral part of the warehouse.
38. The Defendants had by their conduct repudiated their contractual obligations, and the Plaintiffs were justified in terminating the sub-contract. The Defendants shall pay the Plaintiffs' costs on this preliminary issue.
Kan Ting Chiu
Judge
Kan Ting Chiu J
Sundaresh Menon with Desmond Ong and S Bhaskaran (Rajah & Tann) for the plaintiffs
Christopher Chuah and Tan Liam Beng with Lee Chau Ee (Drew & Napier) for the defendants