In the High Court of the Republic of Singapore
[1999] SGHC 168
Suit 2033/1997
Between
The Ngee Ann Kongsi
… Plaintiff
And
The Tai Ping Insurance Company Limited
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
The Ngee Ann Kongsi v The Tai Ping Insurance Company Limited
[1999] SGHC 168
Suit 2033/1997
Goh Joon Seng J
28 June 1999
JUDGMENT:
GROUNDS OF JUDGMENT
1 This was a claim by the Plaintiff under a performance bond dated 28 August 1995 (‘the Bond’) issued by the Defendant. By the Bond, the Defendant guaranteed the due performance by the contractor Inte’con Pte Ltd (‘the Contractor’) of the terms and conditions of its contract with the Plaintiff for the additions and alterations to the building at No. 97, Tank Road, Singapore (‘the Building’). After hearing arguments, I held the Bond to be an unconditional one under which the full sum of $1,369,500.00 (‘the guaranteed sum’) was payable on demand. Accordingly, I entered judgment for the Plaintiff for the guaranteed sum with interest at 6% per annum from 16 October 1997 and costs. The Defendant has appealed to the Court of Appeal. I now give my reasons.
The parties
2 The Plaintiff is a body corporate incorporated under the Ngee Ann Kongsi (Incorporation) Ordinance (Cap 307). Its objects and general purposes are the promotion of charitable causes for the benefit of the Teochew community in Singapore. A large portion of its income now goes toward financing the running of the Ngee Ann Polytechnic.
3 The Defendant is a company incorporated in the People’s Republic of China and are carrying on business as an underwriter in Singapore.
The facts
4 The Plaintiff is the owner of the 6-storey Building. It used to house the Tuan Mong High School. The Plaintiff then decided to convert the Building to a cultural centre and institution for commercial studies.
5 For the conversion, the Contractor was invited to tender for the additions and alterations (‘the works’) to the Building in accordance with the tender documents. One of the items of Preliminaries in the tender documents stated:
"On the acceptance of his tender, the Contractor shall deposit with the Employer an amount equal to 10% of the Tender sum in cash or provided[sic] by an approved Banker’s/Insurer’s Guarantee in strict accordance with the sample in Appendix C."
6 The tender submitted by the Contractor was accepted by the Plaintiff by a Letter of Award dated 14 August 1995 for a lump sum of $13,695,000.00.
7 Condition 9 of the Letter of Award stated:
"Within ten (10) days from the date of this Letter of Award, you shall deposit with the Employer a Performance Bond by way of a Banker’s Insurance Guarantee in an amount equals[sic] to ten percent (10%) of the Contract Sum in strict accordance with the form of Performance Guarantee annexed to the Tender Documents."
8 Pursuant to condition 9 of the Letter of Award, the Contractor procured the Bond issued by Defendant as ‘the Guarantor’ in favor of the Plaintiff described therein as ‘the Employer’. The relevant provisions of the Bond read:
"
WHEREAS This Deed is supplemental to an agreement (hereinafter called "Contract") made between MESSRS. INTE'CON PTE LTD of 24A Sam Leong Road Singapore 0820 (hereinafter called "the Contractor") of the one part and the Employer of the other part, whereby the Contractor agreed to carry out the works included in the contract for PROPOSED ADDITIONS AND ALTERATIONS TO THE EXISTING 6 STOREY TUAN MONG HIGH SCHOOL AT 97 TANK ROAD FOR NGEE ANN KONGSI – FOR The MAIN BUILDING CONTRACT for the sum of Singapore Dollars Thirteen Million Six Hundred And Ninety Five Thousand Only (S$13,695,000.00) AND WHEREAS THE Guarantor has agreed to guarantee the due performance of the Contract in the manner specified therein.
NOW THE GUARANTOR HEREBY AGREES with the Employer as follows:-
1. In consideration of the Employer not insisting on the Contractor paying ten (10) per cent of the total value of the Contract including Prime Cost and Provisional Sums as a security deposit for the said Contract, the Guarantor hereby guarantees the Employer the sum of SINGAPORE DOLLARS ONE MILLION THREE HUNDRED AND SIXTY NINE THOUSAND AND FIVE HUNDRED ONLY (S$1,369,500.00) being the total value of the Security Deposit required for the due and faithful performance of the said Contract.
2. In the event of the Contractor failing to fulfil any of the terms and conditions of the said Contract, the Guarantor shall indemnify the Employer against all losses, damages, costs, expenses or otherwise sustained by the Employer thereby up to the aforementioned sum. The Guaranteed Sum shall be payable to the Employer immediately upon demand for payment in writing notwithstanding the existence of any dispute between the Employer and the Contractor in relation to the Contract or any amount payable thereunder.
…
5. This guarantee is conditional upon a claim being made by the Employer by notice in writing to us and a claim hereunder must be made within six (6) months from the expiry of this guarantee.
"
9 On 22 November 1995, the formal contract incorporating the current SIA Articles and Conditions of Contract was entered into between the Plaintiff and the Contractor.
10 By the Appendix to Condition 25 of the Conditions of Contract, the works were to be completed in four phases as follows:
" (a) Phase I – Renovation Works 21 March 1996 (b) Phase II – PUB Substation 21 November 1996 (c) Phase III – Lift Shafts and Motor Room 5 January 1997
(d) Phase IV – All Remaining
Works 21 May 1997
"
11 Phase I was completed on time. Phases II was completed on 26 March 1997. Phase III was completed on 20 March 1997. Phase IV which comprised the bulk of the works saw substantial delay. On 6 February 1998, the Architect issued the Delay Certificate under cl 24(1) of the Conditions of Contract giving an extension of 80 days. 13 September 1997 was thus the extended date of completion. The Architect accordingly certified that the Contractor had been in default in not having completed the works by the said date.
12 On 16 October 1997, as the works had still not been completed, the Plaintiff, by letter, made a call on the Bond demanding from the Defendant payment of the guaranteed sum. The letter read:
"As the Contractor, M/s Inte’con Pte Ltd, has failed to complete the works by the Contract completion date/extended completion date, we hereby demand payment by you of the guaranteed amount of S$1,369,500.00 under the above mentioned Bond No. DGBPSP0027929500 issued by you."
13 A reminder dated 21 October 1997 was sent by the Plaintiff to the Defendant.
14 The Defendant refused to comply with the demand unless there was proof of default and the amount of loss. Its letter of 28 October 1997 stated:
" …the first sentence of clause 2 of the bond, clearly contemplates a situation where the contractor fails to fulfil the terms of the contract and our obligation is to indemnify you against ‘all losses, damage, costs, expenses or otherwise sustained by the Employer thereby upto the aforementioned sum’.
… "
The proceedings
15 On 2 December 1997, the Plaintiff commenced these proceedings for the guaranteed sum on the ground that it was payable on demand under cl 2 of the Bond.
16 On 13 March 1998, a winding-up order was made against the Contractor. By cl 32(7) of the Conditions of Contract, the employment of the Contractor was automatically terminated. The outstanding works were eventually completed and defects rectified by another contractor at additional costs to the Plaintiff.
17 On 14 April 1999, the Plaintiff by its Amended Statement of Claim included an alternative claim with particulars of its losses due to the default of the Contractor as follows:
"Losses, Damages, Costs and Expenses
Sustained by the Plaintiff
Amount
(a) Increased costs incurred in completing outstanding works and defects rectification works
S$1,683,251.37
(b) Liquidated and Ascertained Damages
(i) 14 September 1997 to 3 December 1997
S$240,000.00
(ii) 23 December 1997 to 1 November 1998
S$942,000.00
c) Costs of Utilities Paid on Behalf of Inte'con by Plaintiff
S$35,390.00
TOTAL S$2,900,641.37
(d) Claim by Mayban Finance (S) Ltd against Plaintiff in Suit No. 901 of 1998 [for amount of invoice already paid to but allegedly assigned by Contractor]
S$1,677,251.73
TOTAL S$4,577,893.10 "
18 When the matter came before me for hearing on 26 April 1999, counsel for the Defendant applied for the dates of hearing to be vacated on the ground that they required time to look into the Plaintiff’s alternative claim. As the action might be deposed of purely on the construction of the Bond, I proceeded with the hearing on the Plaintiff’s original claim deferring the hearing, if necessary, on the alternative claim to a later date.
My decision
19 The Bond, as appears from cl 1 thereof, was furnished in consideration of the Plaintiff not insisting on the Contractor paying a cash deposit of 10% of the contract sum. It must therefore have been clear that the Plaintiff required a bond which was as good as cash in hand. The ‘cash in hand principle’ is consistent with the desire for commercial efficacy and certainty in the use of performance bond. See Bocotra Construction Pte Ltd v A-G (No. 2) [1995] 2 SLR 733 at 744 where the Court of Appeal stated:
" The respondent undertook a comprehensive and judicious survey of the relevant case law on restraint of calls or payment on bonds from a variety of common law jurisdictions. Of the various propositions of law suggested by the respondent, four principles may be extracted:
(a) The ‘autonomy’ principle – the guarantee constitutes a separate contract from the underlying transaction. …
(b) The ‘cash in hand’ principle – reflecting the importance of promoting commercial efficacy and certainty in the use of letters [of credit], guarantees and bonds. This ties in with the ‘autonomy’ principle.
(c) The ‘fraud’ exception – the sole exception to the ‘autonomy’ and ‘cash in hand’ principles arises where the plaintiff can establish fraud in the circumstances of the call or payment…
(d) …
Principles (a) to (c) were all alluded to and supported by the judge below. The weight of authority suggests that these principles are well entrenched. "
20 The Defendant however contended that by virtue of cl 2 of the Bond, its liability was established only upon proof of the Contractor’s ‘failing to fulfil any of the terms and conditions of the said Contract’ (‘words relied on by Defendant’) which by the recital the Bond was said to be supplemental to. In other words, there must be proof of failure of due performance by the Contractor and that the Plaintiff had suffered loss before the Defendant’s liability to pay under the Bond could arise. It is clear in my view that the recital read with words relied on by the Defendant only serve to identify the contract, the due performance of which was guaranteed by the Bond. It did not require proof of failure of due performance and loss as a condition precedent to liability. See Hudson’s Building and Engineering Contracts, 11th Ed Vol 2 para 17-056:
"(b) Nature of unconditional or ‘on demand’ undertaking
The essence of an on demand bond or guarantee derives from express wording which "triggers" the surety's liability upon some event, document or certificate, or more often a mere demand or "call" by the creditor (provided the call is expressed in accordance with any requirements of form which are to be inferred from the wording of the bond). In such cases the occurrences of the event or document or the making of the demand in appropriate form will override any need to establish the accuracy or justification of any facts or alleged facts, such as failure of due performance, under the principal contract on which the bond or guarantee may have been nominally conditioned. In the case of construction contracts the nominal or cosmetic basis for the creditor’s calling of such an unconditional bond is usually stated to be failure of "due performance" of the contractor’s obligations (although "guarantees" or bonds for due payment by construction owners, where the contractor is in a position to require them, are now not infrequently required to be expressed unconditionally as well)…"
21 In Bocotra Construction Pte Ltd v A-G (No. 2) supra, the recital to the bond stated ‘…whereas by cl 9 of the conditions of contract, the contractor must provide a bank guarantee for a sum equal to ten per cent (10%) of the contract sum, for the due performance of the contract.’ It was similarly contended there that proof of default was a pre-condition for a call to be made on the bond. The Court of Appeal at 740 dismissed the contention:
"We are quite unable to see how the passing reference to cl 9 in the recital could support the appellants' arguments that the contract itself had qualified the right of the respondent to make a demand on the guarantee."
22 Cl 2 of the Bond also did not support the Defendant’s position. It stated that the ‘Guaranteed Sum shall be payable to the Employer immediately upon demand for payment in writing notwithstanding the existence of any dispute between the Employer and the Contractor in relation to the contract or any amount payable thereunder.’ This quite clearly embodied the ‘autonomy’ principle of the Bond.
23 Accordingly the Defendant's liability to pay arose upon demand being made, save in the case of fraud (see Bocotra Construction Pte Ltd v A-G (No. 2) supra).
24 That the Bond so worded is a demand bond is consistent with banking practice, otherwise banks will have the unenviable task of deciding whether payment when demanded has to be made. See Esal (Commodities) Ltd & Anor v Oriental Credit Ltd & Anor [1985] Lloyd’s Report 546. The performance bond there stated:
"We undertake to pay the said amount on your written demand in the event that the supplier fails to execute the contract in perfect performance…"
In holding it to be a demand bond, Ackner LJ said at 549:
"OCL contend that on the true construction of the performance bond, either: (a) There was no liability under the performance bond unless and until there had been a breach of the underlying contract of sale, and this was never established. Alternatively (b) that the beneficiary of the performance bond not only had to make a written demand for payment under and pursuant to the performance bond, but he must in the making of the demand assert that the demand was made because the supplier had failed properly to execute the contract.
Mr Tugendhat supports both constructions by relying upon the words in the undertaking immediately following ‘written demand’ –
‘ … in the event that the supplier fails to execute the contract in perfect performance.’
As regards the first interpretation, Mr Tugendhat is obliged to accept that if he is right, the bank, by entering into the performance bond, is taking upon itself the obligation of deciding the merits of a dispute under a contract of sale, a function for which it is virtually common ground the bank is wholly unfitted and which the parties could not sensibly have intended. … If the performance bond was so conditional, then unless there was clear evidence that the seller admitted that he was in breach of the contract of sale, payment could never safely be made by the bank except on a judgment of a competent court of jurisdiction and this result would be wholly inconsistent with the entire object of the transaction, namely, to enable the beneficiary to obtain prompt and certain payment."
25 It must have been to spare themselves the unenviable task of having to decide on the merits of a dispute between the Plaintiff and the Contractor that the Defendant obtained an indemnity from the Contractor which provided as follows:
"I/we INTE’CON PTE LTD and the undermentioned guarantors, jointly and severally agree and undertake to keep you indemnified in respect of any sums up to the limit of your liability under the Bond paid by you to NGEE ANN KONGSI on demand appearing or purporting to be made by or on behalf of NGEE ANN KONGSI under the Bond, which payments may be made by you without reference to or any necessity for confirmation or verification on my/our part. …
It is hereby expressly DECLARED and AGREED that any demand as aforesaid shall, as between me/us and you, be conclusive evidence that the sum stated herein is properly due and payable. I/We hereby further agree that you may at your absolute discretion compromise any demand as aforesaid and/or any consequent proceedings and to accept the receipts, vouchers or other evidence of payment(s) made by you as conclusive evidence against me/us of the fact and extent of our liability herein to you."
26 I was therefore of the view that the Bond is a demand bond. The Defendant's liability was ‘triggered’ by the Plaintiff’s call thereon. The amount of the Bond demanded must be paid in full. It will then be left to the Contractor (or the Liquidator) and the Plaintiff to do an ‘accounting’ thereafter. If the Plaintiff has suffered no loss, the money received by it must be paid over to the Contractor (or the Liquidator). See Cargill International SA and Anor v Bangladesh Sugar & Food Industries Corp [1996] 4 All ER 563.
In that case, the plaintiff companies successfully tendered for the supply of sugar to the defendant governmental organisation. The tender was accepted subject to the receipt of a banker’s performance bond covering 10% of the total cost and freight value and was subsequently confirmed in writing by a contract dated 16 June 1994. The contract stipulated that the cargo would be transported in a vessel which was not more than 20 years old and would be delivered before 15 September 1994. Clause 13 provided that the plaintiffs’ performance bond was liable to be forfeited if they failed to fulfil any of the terms and conditions of the contract and also if they were responsible for any loss or damage suffered by the defendant. In the event, the vessel used was over 20 years old and arrived some days late. The defendant therefore rejected the shipment and made a call on the bond under cl 13. The plaintiffs thereafter applied to the Commercial Court for, inter alia, an injunction restraining the defendants from drawing on the bond and a declaration that the defendant was not entitled to make any call on the bond or to retain any money so received on the ground that it had suffered no loss since the market for sugar had fallen, and the defendants had replaced the rejected sugar at less than the contract price. Further, the plaintiffs themselves had paid the extra insurance required for the over-age vessel.
It was held that the defendant was entitled to make a call for the full amount of the performance bond, even if the breach of contract had caused it no loss, since the bond was not intended to represent an ‘estimate’ of the amount of damages to which it might be entitled for such breach but was a ‘guarantee’ of due performance. However, it was implicit in the nature of a bond that, in the absence of clear words to a different effect, when the bond was called there would at some stage in the future be an ‘accounting’ between the parties to determine their rights and obligations. Accordingly, if the defendant had suffered no damage as a result of the plaintiffs’ breach, any money received by it under the bond was recoverable by the plaintiffs.
At 569-570, Morison J stated:
"Support may also be found in two Australian cases. In the first, Australasian Conference Association Ltd v Mainline Constructions Pty Ltd (in liq) (1978) 141 CLR 335, the question before the court was whether the employer under a building contract made with a builder (Mainline) which subsequently went into liquidation was entitled to pay sub-contractors out of the performance bond moneys which it had called, and been paid by the builder’s bank. It was the bank’s position, inter alia, that the employer was obliged to account to it for any surplus after the sub-contractors had been paid off. The employer conceded that it was not entitled to retain any surplus, and the court clearly believed that to be correct, as did the other two parties. The court’s conclusion was that the issue had to be determined by reference to the contract between the employer and Mainline; it concluded that the surplus should be released to Mainline and not to the bank. In a subsequent building case (an injunction case), Wood Hall Ltd v Pipeline Authority (1979) 141 CLR 443, the court held that the beneficiary was entitled to call the bond but that once paid, the ‘money must be held as security for the contractor’s due and faithful performance of the work’ (see 141 CLR 443 at 454 per Gibbs J).
Both these cases lend (limited) support for the proposition that moneys paid under a performance bond are designed to be used in accordance with the provisions of the contract and that any surplus is for the account of the party which provided the bond."
27 Accordingly, I entered judgment for the Plaintiff for the full amount of the guaranteed sum, that is $1,369,500.00 with interest at 6% per annum from 16 October 1997 when the Plaintiff made the demand for payment under the Bond. I also awarded Plaintiff costs.
GOH JOON SENG
JUDGE
Goh Joon Seng J
Ho Chien Mien / Earl Allan Trevor (Allen & Gledhill) for the plaintiff
Brij Raj Rai / Gavin Khoo / Nagaraja Maniam (Rajah & Tann) for the defendant