L & M Equipment Pte Ltd (formerly known as L & M Engineering Logistic Pte Ltd) v Hyundai Engineering & Construction Co Ltd and Others
[1999] SGHC 182
Suit 651/1998
Chao Hick Tin J
08 July 1999
JUDGMENT:
GROUNDS OF JUDGMENT
Introduction
1 The plaintiffs, L&M Equipment Pte Ltd (L&M), are formwork specialist contractors. They tendered for the provision of formwork required for the reinforced concrete (RC) works of Suntec City complex project (Suntec project), including office towers Nos 1 and 5 (OT1 and OT5). The first defendants (Hyundai) were the main contractors for the Suntec project and they, in turn, appointed Ngee Lian, the second defendants, as the sub-contractors for the RC works of OT5. L&M were to be the nominated sub-contractors of Ngee Lian in relation to the required formwork for OT5.
2 L&M were also the nominated sub-contractors of (i) Kim Seng Heng Engineering Construction (Pte) Ltd (KSH), the third defendants, who were awarded the RC works for the Convention Centre, spiral truck ramp and sub-station, part retail podium and related basement works (hereinafter referred to collectively as the "Convention Centre") and (ii) of Eng Keong Pte Ltd who were awarded the RC works for OT1. The present action does not concern the Convention Centre or OT1.
3 The dispute in this action relates to a claim by L&M for a reasonable amount, or, if there is no contract, in quantum meruit, for the formwork provided to cast the transfer girder on the 4th level of OT5. Transfer girder is a huge beam which has to be constructed before the superstructure can be erected. Such a girder is necessary as the floor space below the transfer girder level would be column free. The width of the girder is 2 metres, and depth 4.2 metres. The span of the transfer girder support is about 45 metres apart. Its height is between 18 metres to 20 metres (approximately 6 storeys) above ground level. It is a gigantic structure. Its construction was a huge task and required heavy duty shoring.
4 Among the defences raised by Hyundai are: (i) the rates payable for formwork required to cast the transfer girder should be no different from the rates for ordinary beams as provided for in the bills of quantities (B/Q) of OT5 and as L&M had already been paid for that, L&M are not entitled to make any further claim for that work; and (ii), if L&M are entitled to make such a claim then the party liable to pay L&M is either Ngee Lian, L&M being the sub-contractor of Ngee Lian, or KSH, having taken over from Ngee Lian.
5 On their part Ngee Lian deny that they are liable to L&M for the additional payment which L&M are claiming on account of the transfer girder. As regards KSH, they said that when they took over the RC works of OT5 from Ngee Lian in January 1993, the construction of the transfer girder had already been completed. They, at no time, agreed to take over the liabilities of Ngee Lian or of Hyundai.
6 In view of the stand taken by the three defendants, L&M were obliged to cite all of them as parties hereto. At the commencement of the trial, the parties agreed, with the approval of this court, that the question of liability be determined first. The question of quantum, if it arises for consideration, could be taken up later.
Background
7 On 4 May 1992, L&M submitted to Hyundai a revised quotation in respect of the formwork of OT5 for a sum of $2,102,897.30. Also set out in the same letter was, inter alia, a quotation for a sum of $1,820.086 in respect of the formwork for OT1. The letter stated that –
"Formwork to transfer beams (another term for transfer girders) between 5th and 6th floor of OT1 at S$135.00 per metre square. This shall exclude stagings and props from basement to 1st storey."
It was clear that the quotation was submitted on the basis that L&M would be the nominated sub-contractor to the RC contractor.
8 Earlier, on 25 September 1991, L&M had submitted a quotation to Hyundai in relation to the same formwork for OT5. Nothing in that quotation is relevant to the present dispute.
9 At a meeting on 21 May 1992, Hyundai asked L&M to start work on OT5 and also to submit, by 28 May 1992, a detailed method statement on pre-stressing and post-tensioning work. L&M were also asked by Hyundai to include as many technical details as possible in their method statement.
10 On 25 May 1992, Hyundai instructed L&M that there would be a change of sequence of work: L&M would have to start with the formwork for the 4th level of OT5 first, including the transfer girder of that level. This caused the price quoted by L&M to be raised to $2.3 million. It will be noted that all these occurred before L&M were formally informed by Hyundai that the former’s quotation for OT5 had been accepted.
11 On 28 May 1992, Hyundai wrote to inform Ngee Lian of Hyundai’s intention to award the RC sub-contract to Ngee Lian. Included in that sub-contract was the formwork to be carried out by L&M. A further sum of $236,000 was also provided, being attendance fees for Ngee Lian in relation to the formwork and post-tensioning work to be undertaken by L&M. Ngee Lian was also informed by Hyundai that the latter would be nominating L&M to be Ngee Lian’s formwork sub-contractors and that Ngee Lian would be "fully responsible for the management coordination, planning and supervision of the works" of the nominated sub-contractors.
12 On the same day, Hyundai also informed L&M of the former’s intention to nominate the latter to undertake the formwork for the Convention Centre (the RC sub-contractor being KSH) and OT5 (the RC sub-contractor being Ngee Lian) and that each of the RC sub-contractors would "in turn … be instructed to enter into sub-contract with (L&M) for the formwork." Hyundai further stated in the letter:-
"With regard to payment we confirm that specific clauses will be included within both of the reinforced sub-contracts such as to reasonably protect your rights to payment through those respective sub-contracts.
……
Upon receipt of your aforesaid letter of acceptance, instruction of nomination will then be issued to each of the two reinforced concrete sub-contractors who shall forthwith enter into sub-contract with you for the execution of the formwork……"
13 On 3 June 1992, L&M wrote to accept the offer in Hyundai’s letter of 28 May 1992. On the same day, L&M received a letter dated 2 June 1999 from Hyundai instructing L&M to proceed with the fabrication of the formwork for OT5. L&M replied also on the same day agreeing to the same.
14 On 19 June 1992, L&M forwarded to Hyundai certain terms which the former would like to see incorporated into the sub-sub-contract to be entered into between L&M and Ngee Lian. At the time Hyundai were preparing the documentation for the sub-sub-contract.
15 On 23 June 1992, Hyundai gave instructions (addressed to Ngee Lian and copied to L&M) that the casting of the transfer girder on the 4th level of OT5 was to be carried out by a continuous pour. The relevant part of the letter reads:-
"Notwithstanding previous discussions and regardless of any previous submissions, we confirm that the transfer girder casting at the 4th storey of OT5 will be carried out in a continuous pour. In this situation we must ask that you submit forthwith your method statement together with formwork propping and back propping design to take into account this method of construction."
16 Unlike the position for OT1, in the B/Q of OT5 while rates were specified for normal beams, there were no separate item(s) or rate(s) for the transfer girder. Thus, on 9 July 1992, there was a discussion between L&M and Hyundai where the question of the appropriate rates for transfer girder of OT5 was brought up by L&M. Ngee Lian was not involved in that discussion. The next day, L&M wrote to confirm that discussion and stated, "as discussed we shall apply the rate (for) this item used in OT1 to OT5 claims." This letter was not copied to Ngee Lian.
17 On 25 August 1992, L&M wrote to Hyundai (which was copied to Ngee Lian) on the question of the rates for transfer girder for OT5 as follows:-
"For avoidance of doubt and prior to signing of the Nominated Sub-contract, we hereby state firmly on our forming rates for the following works:-
Transfer girder
for strutting not exceeding 3.50m high $158/sqm
for strutting 18.50m – 20.00m high $253/sqm
Transfer girder (off form)
for strutting not exceeding 3.50m high $165/sqm
for strutting 18.50m – 20.00m high $264/sqm
These rates are applicable for both the soffit as well as the sides of the transfer girder beam.
Back propping rates for transfer girder is $75.00/sqm."
18 In the meantime a draft sub-sub-contract was prepared and forwarded by Hyundai to Ngee Lian, who, in turn, conveyed it to L&M. L&M did not accept it. By end August 1992 the contemplated sub-sub-contract between Ngee Lian and L&M on OT5 had yet to be finalized and executed. There appears to be some problems with certain terms. One of the matters was on "instructions" and what L&M proposed to Ngee Lian was "We (L&M) shall take instructions from only yourselves and not Hyundai, the Architect or any other party (which will lead to horrendous confusion from our experience of this type of job)."
19 On 31 August 1992, Hyundai orally instructed L&M to proceed with the formwork fabrication for the transfer girder on the 4th storey at OT5. L&M notified Ngee Lian of the instruction of Hyundai. No objection was taken by Hyundai as to the rates set out in L&M’s letter of 25 August 1992.
20 It was only on 24 October 1992 that the sub-contract agreement between Hyundai and Ngee Lian was executed.
21 The formwork for the transfer girder at OT5 was completed by L&M by November 1992. From late 1992 through 1993 Hyundai had certified progress payments for transfer girder formwork on the basis of the rates (i.e., $158/m2) applicable to OT1. It seems to me that this certification by Hyundai bears two significance. First, Hyundai accepted that the rates for the transfer girder should be different from those for the ordinary beams. Second, that the rates specified in the B/Q of OT1 should mutatis mutandis apply.
22 Sometime towards the end of 1992, by agreement with Hyundai, Ngee Lian withdrew from OT5 as the RC sub-contractor. Up to that point the contemplated sub-sub-contract between L&M and Ngee Lian had yet to be executed. There were apparently differences. Sometime at the end of December 1992/early 1993, in place of Ngee Lian, Hyundai appointed KSH as the sub-contractor to carry out the remaining RC works of OT5. Ngee Lian left the site on 5 January 1993. KSH confirmed the terms of appointment by their letter of 15 January 1993 to Hyundai.
23 On 29 January 1993, L&M wrote to KSH (copied to Hyundai) making a claim for the transfer girder of OT5 at $677.52 per square metre, stating that that was the actual cost they incurred in providing the formwork for the transfer girder. L&M pointed out again that in the B/Q of OT5 no rates for transfer girder were specified.
24 On 20 February 1993, by a letter addressed to KSH, Hyundai stated, inter alia,:-
"… subject to any quantity changes which become evident upon final measurement … we believe that the relevant tendered rates, together with the lump sum previously mentioned, provide full and proper recompense for the work carried out."
25 On 25 February 1993, Hyundai wrote to the project Architects setting out their case why the transfer girder should be paid at rates different from the rates specified for ordinary beams. It is necessary for me to set out their arguments in extenso:-
"Now that S4 has been built, it will be apparent to all that the transfer girder, whilst perhaps not being unique in its field, is certainly a large and none too commonplace a structure; indeed it embodies a type and standard of construction necessitating specific ‘tailor-made’ considerations and procedures, which are not in any sense ‘run-of-the-mill’. The sheer size of the transfer girder demanded a precisely executed concrete pour schedule, curing regime and stress management procedure. The concomitant mass of the structure compelled the implementation of an extensive support system as equally extraordinary as the other dictates of the transfer girder.
In the instance of similar work in P4 (namely OT1) the Quantity Surveyor apparently considered the transfer girder formwork to be sufficiently ‘different’ to justify measurement under separately described items in the Bills. This is an example of the Quantity Surveyor adopting ‘special methods’ to accurately represent the work to be carried out.
However, and unlike P4, the P3B Bills (relating to OT5) contains no items of formwork specifically described as relating to the transfer girder. By this omission, we contend that the formwork items in said Bills are deficient and inadequate.
.
.
It is our opinion, therefore, that the P3B items of formwork do not sufficiently and accurately describe the work to be carried out, and the decision not to provide more detailed information has denied us the opportunity to provide estimating which would accurately represent the work executed.
.
.
In view of all the foregoing, we would request that the final measurement of formwork to OT5 transfer girder must be described as such and priced accordingly. In the absence of appropriate pricing information in P3B, we would suggest that reference to P4 transfer girder formwork rates would provide an equitable solution."
26 There is another significant aspect to this letter. It shows that Hyundai had been certifying in favour of L&M using the OT1 transfer girder rates for the transfer girder of OT5, even before the Architects/consultants had agreed to certify the same.
27 On 11 September 1993, Hyundai reached a full settlement with Ngee Lian following Ngee Lian’s withdrawal as the RC sub-contractor of OT5 at end 1992. The settlement agreement provides for a certain payment to Ngee Lian and their respective rights and liabilities vis--vis third parties and sub-sub-contractors. More will be said about this settlement agreement later.
28 In March 1994 Hyundai unilaterally changed the rates for transfer girder they would pay to L&M from $158/m2 to about $58/m2 as provided in the B/Q of OT5 for ordinary beams. Hyundai sought to place the blame for this on the project quantity surveyor, saying the latter reverted to rates for ordinary beams. That is not true. Hyundai’s witness Mr Eun-Sik Park, the Project Manager, had to admit that they took that stand because they were upset with L&M for claiming a rate of $677/m2 for the transfer girder formwork.
29 On 9 December 1996, Hyundai reached a settlement with L&M which expressly excludes from the scope of that settlement the claim of L&M in respect of the formwork for the OT5 transfer girder.
30 In early 1997, L&M continued to be in contact with Hyundai on the transfer girder claim. On 6 March 1997, L&M were asked by Hyundai to wait while Hyundai were sorting out with the project quantity surveyor. There is evidence indicating that Hyundai were claiming against the owners in respect of the transfer girder of OT5 at the rates of $400.09/m2 to $579.39/m2. It would appear that no specific rate(s) were eventually certified by the project consultants as it was subsumed under a global settlement between Hyundai and the owners. However, Hyundai chose not to place any of the relevant documents relating to that global settlement before the court.
Basis of L&M’s claim against defendants
31 L&M say that they tendered for the formwork on the basis of two pours for the transfer girder. The change to a single pour occurred after L&M’s tender had been accepted and it involved additional financial cost. In any case there were no agreed rates for transfer girder. L&M contend that Hyundai are liable because the latter had requested L&M to proceed with the works for the transfer girder (before any sub-sub-contract was entered into between L&M and Ngee Lian) and pursuant to that request, L&M did carry out the works. On Hyundai’s part, they deny liability on three main grounds:-
(i) The rates for formwork for beams in general as specified in the B/Q apply equally to that for the transfer girder and as L&M have been paid in accordance with those rates, L&M are not entitled to any further claims.
(ii) There was no change in the method of casting of the transfer girder. It was always the understanding of the parties that the transfer girder would be cast in one pour.
(iii) If the court should hold that L&M are entitled to reasonable remuneration or be paid on quantum meruit, the additional sum that is payable should be borne by either Ngee Lian or KSH, as L&M were in fact the nominated sub-contractors of Ngee Lian and later of KSH..
Should transfer girder be separately priced?
32 It is not in dispute that in the B/Q for OT1 there were separate items and rates for the transfer girder; not so for OT5. In the light of the arguments which Hyundai themselves advanced so eloquently to the project architect/owners, I do not see how Hyundai could be heard to say that the rates for ordinary beams as set out in the B/Q should apply to transfer girder. Even Mr Park admitted in cross-examination that the transfer girder should be separately identified and that their rates are different from the rates for normal beams. I set out hereunder his relevant evidence:-
"Q: See B/Q at 1AB22, the items on transfer girder – these were for transfer girder of OT1?
A: Yes.
Q: On 1AB23 there are also items on beams simpliciter where the rates are about $25/-. They are for ordinary beams of OT1?
A: Yes.
Q: See 1AB24 B/Q for OT5, the rates for beams are from $26/- to $56/-. Is it first defendant’s case that transfer girder is also included in those items on beams?
A: Yes, that was what I mean agreed rates.
Q: Why in 1AB24 there was no mention of "beam/girder"?
A: Different quantity surveyors prepared the B/Qs and they have different ways.
Q: Wouldn’t you agree this was an oversight by the person who prepared the B/Q? Transfer girder should be separately described?
A: Agreed.
Q: Reason it should be separately described is because the rate is different from a normal beam?
A: Yes."
33 So we have here a situation where works that were required to be carried out were not priced.
Change of construction method
34 The second main point of dispute is, was there a change of construction method? Hyundai have asserted that it was common knowledge of all the parties that casting of the transfer girder was to be by one continuous pour. They relied upon a tender questionaire of 16 August 1991 where in answer to a written query as to whether "the horizontal construction joint to cast concrete for transfer girder located on 5th and 6th floors of 45 storey office (OT1) can be allowed," the project architects replied that "no horizontal construction joints will be permitted in the transfer girder." There is no evidence that this questionaire was ever communicated to L&M. L&M deny having seen this. I do not see how I can find otherwise.
35 Hyundai next relied on the fact that L&M were, on 25 May 1992, required to cast the 4th storey of OT5 first, including the transfer girder of that level, to contend that such a sequence of construction necessarily involved casting the transfer girder in one continuous pour; it could not have been done in stages. However, in cross-examination Park agreed that the change in the casting sequence (to construct the 4th floor slab first) had nothing to do with the casting of the transfer girder in one continuous pour.
36 In any case, the evidence do not appear to support the alleged common knowledge of all parties of one continuous pour for the casting of the transfer girder.
(i) In a method statement which L&M submitted to Hyundai on 28 May 1992 it was stated that casting of the transfer girder would be in two pours.
(ii) In a work programme which L&M received from Ngee Lian on 2 June 1992 (1AB208-9) it was indicated thereon that the transfer beam (namely transfer girder) would be cast in two stages (first half 2m).
(iii) At a meeting on 18 June 1992, Hyundai merely "suggested" that the transfer girder be cast in one operation. The minutes (1AB292) of the meeting did not record that it had always been the common understanding of all parties that it should be cast in one continuous pour.
(iv) At a separate meeting also on 18 June 1992 (2AB341) Hyundai advised project architects that Hyundai intended casting the transfer girder in "two lifts of 2.0 m each instead of 1.5 m and 2.5 m as stated in the submission in order to be able to use Doka D2 load towers."
(v) On 23 June 1992 (2AB334) Hyundai wrote to Ngee Lian, copied to L&M, stating that "Notwithstanding previous discussions and regardless of any previous submission, we confirm that the transfer girder casting at the 4th storey of OT5 will be carried out in a continuous pour." Mr Park tried to explain (though he was not the author of that letter) that this meant the pouring should be done continuously so that there would be no cold joints, not that there was to be a change from a two-pour to a one-pour method. Having regard to what had transpired before as mentioned in the preceding sub-paragraphs the interpretation of Park could not be correct. All previous discussions did not touch on the question of cold joints.
37 Accordingly, I find that there was indeed a change of casting method for the transfer girder from two pours to one pour. As I understand it, the change would entail, inter alia, more work and materials and the materials required to do the transfer girder formwork were not of the run-of-the-mill types. They were required to be specially fabricated.
Quantum Meruit
38 A party can claim a quantum meruit for work done under a contract which does not expressly provide how much he is to be paid (The Gregos [1985] 2QB 348 or 357 and Way v Latilla [1937] 3 All ER 759) or which only provides for some provision for payment, not full provision (Sir Lindsay Parkson & Co Ltd v Commissioner of Works [1949] 2 KB 632). A quantum meruit may also be awarded where work is done in the belief that there is a concluded contract when, in fact, there is none or where one party does work at the request of the other during negotiations which are expected to lead to a contract but which negotiations eventually do not succeed.
39 On the facts of this case, whichever way one looks at it, L&M are entitled to be paid a reasonable sum for the formwork for the transfer girder. If there was a contract between L&M and any of the defendants, then, as no rates were prescribed in respect of the transfer girder formwork, L&M should be entitled to be paid a reasonable sum by that agreement. On the other hand, if there was no contract, then as the works were performed at the request of Hyundai, and for whose benefit the works were executed, there would be a claim in quantum meruit.
Is there a contract?
40 So the question is, on the facts as I have outlined, had a contract come into existence between L&M and any of the defendants. From the documentary evidence, there can be no doubt that it was intended that L&M would be the nominated sub-contractors of Ngee Lian. Ngee Lian was to have entered into a written contract with L&M. According to the letter of 28 May 1992 from Hyundai to L&M, Hyundai would instruct Ngee Lian to enter into a contract with L&M. Hyundai was preparing the draft Agreement which Ngee Lian were to sign with L&M. However, in the meantime, instructions were issued by Hyundai to L&M to proceed with the work while the terms of the written agreement were being negotiated. As mentioned before, the written agreement between Ngee Lian and L&M was never executed though most of the main terms which were to form the written agreement had been agreed upon.
41 So was there, nevertheless, a binding contract between Ngee Lian and L&M notwithstanding the absence of a written agreement? I must confess I find great difficulty in this question. Was the written agreement truly a matter of formality or was it a condition precedent before a binding contract would come into being? My inclination is to hold that there was no binding contract in existence between L&M and Ngee Lian, because (i) all negotiations with L&M were done by Hyundai; (ii) as late as in August 1992 L&M were still discussing with Hyundai and Ngee Lian as to the terms of the written agreement; and, (iii) among the terms yet to be sorted out, were those on safeguarding payment to L&M and valuation of work for interim payments. It seems to me what we have here is a situation where works commenced in the belief that eventually an agreement on all the terms would be reached between L&M and Ngee Lian. As no agreement was reached, L&M are entitled to reasonable payment on a quantum meruit against the ultimate beneficiary, Hyundai.
42 In any case, I do not think the answer to that question is really that critical. Let me elaborate. Assuming there was in law a contract between Ngee Lian and L&M because the entering into the written agreement was only a formality, then L&M would be entitled to make their claim on the transfer girder to Ngee Lian, who would, in turn, and for the same reasons (it being basically a back-to-back arrangement), be entitled to claim the same from Hyundai. However, if the correct construction is that there is no binding contract between L&M and Ngee Lian, then L&M would be able to claim in quantum meruit against Ngee Lian, who would in turn be entitled to claim reimbursement/indemnity from Hyundai as the latter were the ultimate beneficiary of the transfer girder formwork carried out by L&M.
43 However, I must at this juncture add that the position as between Hyundai and Ngee Lian is further complicated by the fact that on 11 September 1993 they entered into a settlement agreement. On the basis of that settlement agreement, Hyundai seek indemnity from Ngee Lian. In the preamble it was stated that the agreement was to be a "full and final … of all matters between them in relation to the sub-contract, other than any matters expressly excluded" by the terms thereof. The relevant provision is clause 3.1 and it reads:-
"3.1 The parties agree that the Final Account and the Settlement Sum excludes any outstanding sums claimed by or owed to NGEE LIAN’s Sub-sub-contractors and that NGEE LIAN is liable for and indemnifies HYUNDAI in respect of any claims by or payments due to the Sub-sub-contractors or third parties in connection with the Sub-Contract, including without limitation, L&M Systems Pte Ltd, L&M Prestressing Pte Ltd, Brani Readymixed Pte Ltd, Legend Building Supplies (Pte) Ltd, and claims for dayworks by the Nominated Sub-Contractors."
44 There appears to be an inherent contradiction in this clause 3.1. On the one hand it excludes from the settlement "any outstanding sums claimed by or owed to Ngee Lian’s sub-sub-contractors." However, the second part of that clause provides that Ngee Lian are liable for and shall indemnify Hyundai in respect of "any claims by or payment due to the sub-sub-contractors", including L&M. I find this a difficult clause to construe. Be that as it may, at the time of the settlement agreement, L&M’s enhanced claim (at $677.52 m2) for the transfer girder formwork was not known to Ngee Lian. The 29 January 1993 letter from L&M was addressed to KSH who forwarded it to Hyundai. Ngee Lian did not see or know of it. By that time, Ngee Lian had completely left the project. While Ngee Lian were with the project, whatever sum Hyundai had certified as due to L&M for the transfer girder formwork was paid over by Ngee Lian to L&M. At the time of the settlement agreement, there was no way Ngee Lian could have known that Hyundai would be making a complete about turn and would only be paying L&M for the transfer girder formwork at the rates as if it were an ordinary beam.
45 In the light of the inherent contradiction in clause 3.1 and of the facts I have highlighted in the last paragraph, I hold that Ngee Lian are not liable under the settlement agreement to indemnify Hyundai in respect of the enhanced claim of L&M. The indemnity clause (even if it was clear) must be construed fairly in the light of the factual matrix known to both parties. It would be unjust and unconscionable to construe that clause and other related clauses in the settlement agreement literally so as even to impose liability on Ngee Lian which liability was brought about by actions taken by Hyundai subsequently and of which Ngee Lian had no knowledge.
Position of the third defendant
46 KSH commenced work on OT5 sometime during the second week of January 1993. By then the formwork for the transfer girder had long been completed. Dismantling of the transfer girder formwork was carried out in early January 1993. At the time, KSH were mobilising their labour to commence work. The instruction for the dismantling was not given by KSH but by Hyundai’s Engineer, Mr S Lee.
47 The scope of work of KSH on OT5 was from the 6th storey up. This is evidenced by KSH’s letter of 15 January 1993 to Hyundai. Under this letter the responsibility for the works completed by Ngee Lian, including any responsibility for defects in the transfer girder, was specifically excluded. The evidence of witnesses in court also confirmed that.
48 The basis upon which Hyundai seek to make KSH liable for L&M’s claim is, in my view, tenuous. Hyundai say that their liability to L&M on the formwork of OT5 was novated to KSH by virtue of (i) a written instruction of 26 November 1993 from Hyundai to KSH and (ii) L&M’s letter of 24 August 1994 to KSH. I do not see how this averment could stand as KSH were only instructed to carry out the remainder of the RC works on OT5, which did not include the transfer girder on the 4th level. It is true that the written instruction stated that L&M would be KSH’s nominated sub-contractor. But the instruction excluded from KSH’s scope of work "the works which had been carried out by the previous sub-contractor." There was no novation agreement that KSH would take over the rights and liabilities of Hyundai/Ngee Lian. Nothing was mentioned on that in the instruction. At the time the written instruction was issued (on 26 November 1993) the RC works on OT5 were completed by KSH. The instruction seems to be issued for record purposes. As for the letter of 24 August 1994, it was no more than an attempt on the part of L&M to make KSH liable. It cannot form the basis of liability.
49 Similarly, in the settlement agreement of 9 December 1996 between Hyundai and L&M it was stated that L&M were the nominated sub-contractor of KSH for, inter alia, "the remaining works to Office Tower 5". Mr Lim Thian Fatt, the then contracts manager of L&M, told this court that Hyundai never informed L&M that L&M’s claim in respect of the transfer girder would be transferred to KSH. More significantly, if KSH’s responsibility covered the works for the transfer girder, would Hyundai have requested KSH to quote for the cost for rectification of the transfer girder?
Pleading issue
50 Finally, I ought to refer to a point on pleadings raised by Hyundai, namely, that it was not L&M’s case that there were no agreed rates for transfer girder; this action is based wholly on the alleged change from a two-pour to a one pour method for the casting of the transfer girder. While on a reading of the statement of claim, one could obtain the impression that the trigger-point giving rise to the action was the change from two pours to one pour, it seems to me that in paragraph 9 of the statement of claim L&M have alluded to the fact that there were no agreed rates for the transfer girder:-
"9. In the absence of any written sub-contract between the plaintiffs and the second defendants and notwithstanding the lack of any final agreement on the rates to be used for the construction of the transfer girder, the plaintiffs commenced the works on the basis that they would be properly remunerated for the works, including inter alia the extra cost resulting from the change to the single pour method." (emphasis added).
While I agree that this paragraph could have been more clearly drafted, what L&M are saying is that as there are no agreed rates for the transfer girder, they should be paid reasonably, including the extra cost brought about by the change to a single pour.
51 That paragraph of the statement of claim ought to be viewed in the light of the relevant correspondence. As early as on 9 July 1992, L&M had raised the question that there were no rates specified in the B/Q for the transfer girder as such. L&M have always taken the stand that the rates specified in the B/Q for ordinary beams cannot apply to a transfer girder, which is a huge and out of the ordinary structure. This issue has always been a live one. Hyundai were and are well aware of it. In L&M’s letter of 25 August 1992 to Hyundai they made proposals on the appropriate rates for the transfer girder. There was no response or objection from Hyundai. The reference to "final agreement" in paragraph 9 of the statement of claim must be in relation to that.
52 There is another reference in paragraph 9 of the statement of claim which is also pertinent: "they would be properly remunerated for the works, including inter alia the extra cost resulting from the change to the single pour method". From this, it is clear that L&M are claiming for reasonable remuneration for the transfer girder and also reasonable costs for the extra efforts/materials caused by the change in pouring method.
53 I do not think Hyundai could have been in any sense unclear as to what L&M are claiming. Indeed, Hyundai have responded to this point when they averred in paragraph 9 of their defence that "there was clearly final agreement as to the rates to be used for the transfer girder" and referred to L&M’s letter of 4th and 27th May 1992 and Hyundai’s letter of 28 May 1992 expressing their intention to appoint L&M as the nominated sub-contractors of Ngee Lian. If it were necessary that the statement of claim should have been amended to more clearly bring out the point, I would have granted leave to amend.
Identity of the main contractor
54 In their defence, Hyundai aver that the main contractors for the Suntec City project were the Hyundai-Ssangyong Consortium. But the "Consortium" is not a separate legal entity. It was only a convenient description of what was really a joint venture between Hyundai and Ssangyong. Hyundai say they should not be sued solely. Obviously contribution is a matter between Hyundai and Ssangyong which L&M need not be concerned with.
Judgment
55 In the premises I hold that Hyundai are liable to pay L&M at a reasonable rate in respect of the transfer girder formwork of OT5. Whether the change of casting method from two pours to one pour involved any additional expenses is a matter of proof. I order that the assessment of the proper rate or rates be carried out by the Registrar. L&M’s claims against Ngee Lian and KSH are accordingly dismissed.
56 In the circumstances of this case, I think the proper order to make on costs is that Hyundai should pay not only the costs of L&M but also of Ngee
Lian and KSH. However, there shall be liberty to apply on the question of costs within two weeks.
Chao Hick Tin
Judge
Alvin Yeo with Lawrence Tan (Wong Partnership) for the plaintiffs
M Sivakumar with Akramjeet Singh (Azman Soh & Murugaiyan) for the 1st defendants
James Ponniah with C P Lee (C P Lee & Co) for the 2nd defendants
Raymond Chan with Tan Teck Hian (Chan Tan & Partners) for 3rd defendants