In the High Court of the Republic of Singapore
[1999] SGHC 24
Suit 1727/1997
Between
Eltraco Internatioal Pte Ltd
… Plaintiff
And
Uniontic Piling Construction Pte Ltd
… Defendant
grounds of decision

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Eltraco Internatioal Pte Ltd v Uniontic Piling Construction Pte Ltd
[1999] SGHC 24
Suit 1727/1997
Lai Siu Chiu J
25 January 1999
1 Judgment :
2 Cur Adv Vult
3 The background
4 The plaintiffs were the main contractors in the construction of a 4-storey residential block at Balmoral Road with two (2) basements and a swimming pool. The defendants were engaged as the sub-contractors in respect of the piling works at a sum of $330,566.40. Both parties entered into a written contract dated 29 July 1996 (the written contract). Piling works commenced on 8 August 1996 and physical piling works were completed on 23 September 1996 while the test for pile driven analysis (PDA) was completed on 3 October 1996.
5 The claim
6 On 17 September 1997 the plaintiffs commenced proceedings against the defendants. The relevant portions of the statement of claim are as follows :
"3. It was implied in the terms of the agreement between the Plaintiffs and Defendants that :-
a) the Defendants would use reasonable care and skill in carrying out the works; b) that the piling works would be carried out in a workmanlike or professional manner with proper materials. 4. Further or in the alternative the Defendants owed a duty of care to the Plaintiffs in carrying out the said works. 5. Negligently and in breach of their contractual and or duty of care owed to the Plaintiffs the Defendants’ works were defective and or unsatisfactory and delayed. PARTICULARS a) the Defendants failed to complete the works by the 6th day of September 1996; b) the pile eccentricities were deviated; c) failure to provide as-built ECC Drawings. 7. The best particulars the Plaintiffs can provide at the present moment are as follows :- PARTICULARS a) Cost of carrying out remedial work $215,420.22 b) Liquidated damages for a delay of 21 days at $4000.00 per day $84,000.00 c) Liquidated damages for delays owing to carrying out of remedial works $224,000.00 d) Management and Administrative Costs $11,160.94 e) Cost of preliminaries $59,290.00 $593,691.16
8. From the Plaintiffs’ calculation at the time of the issuance of this Writ, the value of the works carried out by the Defendants is $76,420.12 which sum the Plaintiffs intend to deduct from the sums due by the Defendants to the Plaintiffs.
11. AND THE PLAINTIFFS CLAIMS : (i) the sum of $517,271.04 under paragraphs 7 and 8; (ii) damages for breach of contract and or breach of duty and or in negligence; (iii) a declaration that the Plaintiffs are entitled to be indemnified by the Defendants in respect of all loss, expense and liability by way of Third Party’s claims or otherwise that the Plaintiffs have incurred and or have been exposed to by reason of the Defendants’ breach of contract and or duty and or in negligence; (iv) all necessary accounts, inquiries and consequential orders; (v) orders for payment by the Defendants to the Plaintiffs of such amounts as may be found due to the Plaintiffs from the Defendants upon the taking of such accounts and inquiries; (vi) interest; (vii) costs."
7 I will only determine the issue of liability as the quantum of damages, depending on my findings, should be assessed by the Registrar. Essentially the plaintiffs alleged that the defendants are liable in respect of the following: Firstly, for the delay in completing the piling works; secondly, for defective work in respect of the deviation from the pile eccentricities (ECC); and lastly, that the defendants were liable for failure to provide as-built ECC drawings.
8 Delay in piling works
9 In their statement of claim the plaintiffs alleged that the defendants failed to complete the piling works by 6 September 1996 as contracted. Under the written contract the piling works were supposed to commence on 1 August 1996 and be completed on 31 August 1996. Due to a delay by the employer of the plaintiffs in obtaining the permit to commence works, the commencement date of the piling works was postponed to 8 August 1996. The affidavits of both Louis Ee (Ee), the plaintiffs’ manager (Construction and Contracts Department), and Ng Chee Wah (Ng), the managing-director of the defendants, confirmed that the piling contract required the defendants to start work on 8 August 1996 and for the work to be completed 4 weeks later (on 8 September 1996). The date for completion was subsequently extended to 12 September 1996 to compensate for the fact that the defendants were not allowed by the Building Control Division (BCD) to pile on Saturdays, Sundays and public holidays. This directive from the BCD was conveyed to the defendants on 28 August 1996 by which date the defendants should have made substantial progress in piling for 20 days (8-28 August 1996). However, this was not the case as would appear from a letter dated 15 August 1996 (1AB 45) from the plaintiffs to the defendants expressing dissatisfaction over the slow progress of the latter’s work:
You commence [sic] work on 6/8/96 and today is 15/8/96, you have only accomplished piling 9 piles (total 9 days).
10 The defendants did not dispute that the physical piling works were completed only on 23 September 1996 and that the PDA test was only completed on 3 October 1996. Their defence and closing submission was, that there was an implied term in the written contract that the plaintiffs shall give the defendants timely possession of the site and that the delay was due to the failure of the plaintiffs to provide the same such that it was free of obstruction and prepared in such a way that the defendants’ surveyor could set out the piling points and the defendants’ machinery could move about safely.
11 However, timely possession of the site does not mean sole possession of the entire site; this was acknowledged by counsel for the defendants. Instead, what is required is that the plaintiffs as main contractors, give an adequate degree of undisturbed possession of the site. The degree of undisturbed possession required varies with the nature and circumstances of the work. It has been stated in Hudson on Building and Engineering Contracts (11 ed. vol. 1 at p 575) that:
In the case of sub-contracts, or cases where the contract contemplates that other contractors of the owner will be on the site at the same time, however, it is obvious that depending on the facts, different considerations may apply, and it is doubtful if any general rule can be established as to the degree of permissible disturbance, which will vary greatly. This makes detailed express provision an essential commercial precaution, which is usually well understood by main and sub-contractors.
12 Besides the issue of timely possession, the defendants also alleged in their defence that the delay was due to the plaintiffs’ breach of an express term of the written contract to prepare the access and piling ground. Yong Kee Hock (Yong) the defendants’ project manager, testified that the plaintiffs failed to provide timely possession of the site and to prepare the access and piling ground. I found him to be a witness whose evidence was suspect for the following reasons:
a. under cross-examination he initially said that sheet piling was a similar type of work to excavation [NE 315B], later however he admitted that sheet piling and excavation were not the same type of works [NE 316C];
b. cross-examined, he initially said that his only excavation work experience was a single project in Tuas in December 1997 [NE 314D]. Questioned further, he claimed that he had more than a year’s experience in excavation work, having handled excavation work for Orchard Towers in 1989/1990 [NE 316E]. He subsequently revealed that all he did was to stay on after sheet piling and observe the excavation work until it was done [NE 316C]. In effect Yong claimed to have "handled excavation work for more than one year" when all he did was to observe excavation work;
c. under cross-examination he mentioned Golden Village Yishun Cinema Multiplex as another example of other excavation projects he had undertaken [NE 317B]. Questioned further, he revealed that all that he did was sheet piling and that the excavation work was done by somebody else [NE 317D];
d. he had to be admonished (NE 414C/D) for making a sweeping comment that none of the registered surveyors (numbering 22-25) in Singapore carry out physical survey on site, his tendency being always to answer questions beyond what he had been asked.
13 I also found Ng the defendants’ managing director, to be an unreliable witness; the following factors contributed to this finding:
a. in his evidence-in-chief he said that the plaintiffs did not complain of any delay [NE 171F]. However under cross-examination, when he was shown four letters from the plaintiffs he admitted that there were complaints of delay and that his earlier evidence was untrue [NE 173D-E].
b. under cross-examination he admitted that his earlier evidence that there was obstruction at the front of the site was untrue [NE 254E-F].
c. cross-examined, he claimed that he saw the letters of complaints only in court [NE 270B]. Upon further questioning he admitted that his evidence was untrue and that he had received the letters prior to coming to court [NE 270F].
14 Indeed, Ng’s testimony was so inconsistent at one stage that I had to take the unprecedented step of warning him of the possibility of imprisonment for the commission of perjury (NE 251D).
15 The defendants alleged that they were delayed in their work because the plaintiffs were late in cutting the slope at the rear of the site to a profile which would enable the defendants to set out piling points and to begin physical piling. I am unable to accept this allegation which was wholly unsubstantiated; instead I believe Ee’s evidence that the slope cutting work had already been done by the plaintiffs by 18 or 19 July 1996. Unlike Ng and Yong, Ee testified in a forthright and candid manner, and his testimony was entirely consistent with that of a witness of truth; neither was he shaken under cross-examination.
16 The defendants also alleged that because the plaintiffs were carrying out capping beam works at the rear of the site from 14 to 29 August 1996 and laying granular materials behind the retaining wall from 30 August to 9 September 1996, the defendants were impeded from carrying out the piling works in an efficient sequence and had no choice but to work around the interference caused by the plaintiffs. As noted above, the principle is that in a situation where there are sub-contracts the degree of permissible disturbance must take into account the fact that there are other parties working at the same time on the site. On the facts before me, I am unable to say that the other works carried out by the plaintiffs created such an interference as to provide the defendants with a valid defence for their delay. This finding is strengthened by three points: Firstly, the daily site reports maintained by the clerk of works of the employer, showed that much time was spent by the defendants in assembling the piling rigs or that the rigs had broken down. Secondly, at no point was any complaint of interference made to the plaintiffs during the period when the piling works were carried out. This silence on the part of the defendants on matters which before me they sought to plead as a defence, was in marked contrast to the four complaints made by the plaintiffs to the defendants about the slowness of their piling work. Thirdly, Ng admitted in cross-examination that the letters of complaint of delay from the plaintiffs were true and that the defendants had delayed the piling works.
17 Examining the evidence as a whole I found that the defendants had failed to establish that the delay in the completion works was caused by or indeed attributed by the failure of the plaintiffs to provide timely possession of the site or to prepare the access and piling ground. Accordingly, I hold that the defendants are solely liable for the delay in the physical piling works, starting from 13 September 1996.
18 An issue related to the delay in piling works is whether PDA testing was part of the work to be completed within the four week period for piling. If so, the defendants’ liability for delay would extend to 3 October 1996, when the PDA testing was finally completed. PDA testing involved the random selection of piles by C & V Consultants (the employer’s consultants) for testing by ABV Technology Pte Ltd (ABV) to determine whether the defendants had driven the piles in accordance with specifications laid down by the former. It was admitted by Yong that PDA test was part of the defendants’ calculations for their contractual period. The defendants however claimed that they should not be liable for the delay in the PDA testing because the plaintiffs took an unduly long time to select the piles for testing.
19 However, the evidence was that the physical piling was completed on 23 September 1996 and the piles were selected four days later on 27 September 1996 by C & V Consultants on which same day the plaintiffs informed the defendants of the selection.
20 I am of the view that the defendants’ attempt to escape liability for the delay in PDA testing is spurious. They are in effect claiming that they were not at fault for the delay simply because the plaintiffs should have anticipated when the defendants would finish physical piling! In so contending, the defendants overlooked the fact that they were the party who were doing the physical piling and therefore, would have the most accurate knowledge of when they would complete the work. Knowing that it was part of their contractual obligations to do the PDA test, the simplest and most reasonable thing for the defendants to do was to have informed the plaintiffs in advance when the physical piling was likely to be completed and similarly to alert ABV. The unreasonableness of their stand was clear from the double standards they sought to raise in their defence. While they claimed that four days for the plaintiffs to select piles for PDA testing were too long, they themselves took six days to carry out the tests after being informed by the plaintiffs! Cross-examined, Yong remained adamant that this was not unfair to the plaintiffs [NE 374E]. Yong also claimed that there was no obligation on the part of the defendants to predict when the tests would be conducted, even though the defendants themselves expected the plaintiffs to anticipate when the defendants would complete the physical piling [NE 375E].
21 Even if I disregarded such a tenuous defence, the facts do not support the defendants’ position. When ABV went to the site on 2 October 1996, the defendants were not ready for the PDA test and the test had to be postponed to the following day. In view of the overwhelming evidence of the defendants’ unreasonable and irresponsible conduct and the haphazard manner in which they carried out the piling works, I find that the defendants are also solely liable for the delay in PDA testing. Coupled with the delay in completion of piling, the defendants are liable for delay up to 3 October 1996. Indeed, Ng went further to admit (NE 370C) that he completed the works on the day he demobilised his equipment, which was on 5 October 1996.
22 Defective piling works
23 The plaintiffs also claimed that the defendants were liable for defective piling works in that the pile eccentricities were deviated. There was a dispute as to the type of specifications which would apply. The plaintiffs contended that C & V Consultants’ specifications applied while the defendants contended that the Public Works Department’s (PWD) specifications applied.
24 The plaintiffs’ stand was based on cl 2 of the written contract which provided:
"all work to be carried out in accordance to drawings, specifications and contract documents issued by the Consultants".
25 The plaintiffs submitted that this term made it clear that the piling works must abide by the specifications issued by the Consultants. They also argued that the defendants’ conduct after C & V Consultants rejected many of the piles made it reasonable to infer that the defendants had accepted C & V Consultants’ specifications. Out of 191 piles driven, 182 were rejected by C & V Consultants as being out of eccentricity [see plan no. 9 at 11 AB]. The defendants did not dispute the rejections and even employed Tan Bin Keong (Tan), a professional engineer (initially from Poly & Partnership and subsequently from B K Tan Consultants) to carry out remedial works. During cross-examination, Ng acknowledged that the piles were out of ECC, that Tan was employed to redesign and recalculate the ECC and that he paid Tan for these calculations without disputing any of his calculations [NE 164D-165C]. Ng also admitted that the defendants were withdrawing their claim for the sum of $15,000 which they paid to Tan for the re-design calculations [NE 163B]. With regard to this particular aspect of Ng’s evidence, I take a dim view of his later attempt (during re-examination) to renege on his earlier testimony, with the excuse that his statement about withdrawing the claim for $15,000 was given while he was suffering from hypertension.
26 The defendants’ case on the other hand, was that the plaintiffs had not provided them with any specifications either at the time of entering into the written contract or during the piling works itself. They relied on the evidence of their expert witness, Kog Yue Choong (Kog), a civil engineer, that in situations like the present case, it was reasonable to adopt PWD’s specifications if no other specifications were furnished to the defendants. Dr Kog opined on the probable causes for the pile eccentricities and these included workmanship, soil movements and the presence of soft/weak soil. As his findings were not conclusive, I do not find Kog’s testimony particularly helpful.
27 The defendants’ case that PWD’s specifications apply is premised upon an omission in the written contract to provide for specifications. Although the written contract did not expressly stipulate that C & V Consultants’ specifications apply, I am of the view that cl 2 is clear, unambiguous and wide enough in its ambit to cover the plaintiffs’ contention that C & V Consultants’ specifications, not PWD’s, apply to the piling works. Taking this view of cl 2 together with Ng’s admission that the piling works were defective and remedial works were carried out by the plaintiffs’ subcontractor Yee Ping Corporation Pte Ltd (Yee Ping) (NE 161F), the logical conclusion must be that the defendants are liable for defective piling in respect of the deviations from the pile eccentricities. My view is reinforced by the evidence of Yee Ping’s managing director Goh Kiam Seng (Goh) who testified that his company was delayed in their construction of the two levels of basement due to the defendants’ late completion of piling works many of which were also out of eccentricity; I have no reason to disbelieve Goh’s testimony.
28 Following upon my above finding, I dismiss the defendants’ counterclaim for the costs of engaging Poly & Partnership/B K Tan Consultants for re-designing the pilecaps. It was not disputed that C & V Consultants’ specifications were stricter than PWD’s, and it was quite clear that the defendants’ arguments were but a weak attempt to shirk liability for something which had been specifically provided in the contract.
29 Failure to provide as-built drawings
30 Lastly, the plaintiffs also claimed that the defendants were liable for their failure to provide as-built ECC drawings. According to cl 13 of the Consultants’ letter of award, the plaintiffs are required to submit the as-built ECC drawings to the Consultants. In taking on these works, this duty fell on the defendants. I am of the view that the terms of this principal contract would be imported into the sub-contract between the plaintiffs and the defendants. This meant that the Consultants’ letter of award was part of the sub-contract. The clause relied on by the plaintiffs is cl 2 which states that
31 all work is to be carried out in accordance to drawings, specifications and contract documents issued by the Consultants
32 (see 1AB 34). A reading of cl 2 would import an obligation on the part of the defendants to submit as-built ECC drawings. This was not challenged by the defendants before me nor in their correspondence with the plaintiffs. In fact, the defendants had failed to respond to the plaintiffs’ request for a full set of as-built ECC drawings and to the plaintiffs’ debit note for the cost of obtaining a set of drawings from B K Tan Consultants. I accordingly find that the defendants are liable to the plaintiffs for failing to provide as-built ECC drawings.
33 Defendants’ counterclaim for cost of third rig
34 The defendants had counter-claimed for the cost of hiring a third piling rig. At para 11 of the defence and counterclaim they pleaded:
"The Defendants aver that delay was also caused to the rest of the works under the Contract (apart from the piling works) due to the Plaintiffs’ breach of the terms of the Contract and the Plaintiffs’ carrying out of the excavation works in a haphazard, intermittent and sporadic manner. The delay to the piling works as well as the delay to the rest of the works under the Contract have resulted in the Defendants having to mobilise a third piling rig and also resulted in disruption and/or prolongation of the Contract, thereby causing the Defendants to suffer loss and expense."
35 The essence of the defendants’ counterclaim is that the plaintiffs caused delay to the piling works resulting in the defendants having to mobilise a third piling rig. I do not believe Yong’s evidence that it was Ee who, towards the end of August or early September 1996, requested the defendants to bring on-site a third piling rig with a hanging leader in anticipation that the plaintiffs would be cutting the slope. I am however, satisfied with the plaintiffs’ explanation (as given by Ee) that the third (smaller) piling rig was requested because the two existing rigs of the defendants were too big for the 175 x 175mm piles which the defendants were required to drive under the written contract. Taking that into consideration together with my earlier finding that the defendants not the plaintiffs, are solely responsible for the delay in piling, I dismiss the defendants’ counterclaim for the cost of the third rig.
36 Defendants’ counterclaim for additional fees paid to surveyor
37 The defendants also counterclaimed for the additional fees paid to the surveyor for the increased number of times he had to visit the site. The defendants claimed that the increase in fees was due to the plaintiffs’ failure to provide uninterrupted possession of the site. I am of the view that there is no merit to this counterclaim. As I have held earlier, there was no need for the plaintiffs to provide uninterrupted possession of the site but an adequate degree of undisturbed possession which on the evidence, I am satisfied the plaintiffs did provide. Further, the defendants did not at any time claim the extra charges from the plaintiffs, on the inexplicable basis of wanting to maintain a good relationship with the latter [NE 202F-203C]. There is no basis for the defendants’ counterclaim for additional survey fees and accordingly I dismissed it.
38 25. Some mention must be made of the evidence called by the defendants in support of their claim for additional survey fees paid to one Quek Kai Hock (Quek), who is the sole-proprietor of Polymax Survey & Associates (Polymax) which he registered on 28 October 1996. Back in July 1996, Quek worked freelance for Alpha Survey Consultants (Alpha). The defendants engaged Alpha in July 1996 to set out the piling points on the site and also to carry out ECC checks. According to Quek (who has 20 years’ experience but is not qualified, in land surveying), he undertook the work for the defendants under the supervision of Ang Kim Tee (Ang) of Alpha (a registered surveyor) who endorsed Quek’s plans even though Ang never visited the site according to Ee and admitted by Quek, contrary to the claim of Yong; Quek continued and completed the task after he set up Polymax; Polymax not Alpha, billed the defendants $8,400 for 10 trips which Quek made to the site to set out piling pegs and for 11 trips to check pile ECC (see Polymax’s invoice at 1AB 227). Quek explained that he charged the defendants $400 per trip instead of $12 per peg as initially agreed with Yong, after he had made 4-5 trips and found obstructions such as excavations which inconvenienced his work; Yong had agreed to his request to be compensated and to his charge of $400 per trip. I find Quek’s evidence highly unsatisfactory on many counts; in particular he did not explain let alone satisfactorily, why only Polymax billed the defendants for survey services when the assignment was first given to him under the auspices of Alpha and why Ang Kim Tee did not charge him or Polymax if indeed Ang supervised Quek’s survey work and or endorsed his plans. In any event, Quek not being a registered surveyor, as required by the terms of the contract between the parties which fact was known to Yong (NE 379B and NE 384F)), the defendants are precluded from claiming his additional fees from the plaintiffs. A lump sum ($5,760) was also provided in the written contract (item d) for surveyor setting out and checking ECC. Quek’s claim of being obstructed by the plaintiffs in carrying out his surveys was also effectively demolished under cross-examination; I reject Quek’s testimony as unreliable.
39 Defendants’ counterclaim for additional pay length for piles
40 26. Finally, the defendants counter-claimed for the additional pay length for the piles. In a letter dated 19 June 1996 [1AB 6], it was stated that :
"Paylength measured from toe of driven pile to the existing ground level."
41 By virtue of cl 1, this letter formed part of the written contract. Subsequently the defendants wrote a letter dated 2 July 1996 [at 1AB 12] to revise the pay length term to state that:
"Paylength is to be measured from toe of driven pile to the cut-off level and using of steel follower would be allowed up till the depth of 3 meter below the existing ground level."
42 This subsequent letter also formed part of the written contract by virtue of cl 1. The defendants claimed that the intention of the parties was that the defendants would not have to suffer any loss due to wastage and that the defendants were therefore claiming for the actual additional pay length which is the actual wastage of piles due to the actual cut-off level being deeper than the agreed cut-off level of 3m as assured by the plaintiffs.
43 27. In reply, the plaintiffs contended that they never agreed with the defendants that the cut-off level will be 3m below ground level. Examining the provision in the letter dated 2 July 1996, I am of the view that it does not constitute an agreement on the part of the plaintiffs to pay for the actual length of piles driven. In addition the written contract [1AB 34] stated :
"Paylength shall be measured from toe of driven pile to cut-off level and subject to Consultant’s/Quantity Surveyor’s measurement and certification in accordance to the main contract."
44 It was clear that the written contract provided that the pay length has to be subject to the Consultants’/Quantity Surveyor’s certification. Under cross-examination, Ng agreed that if the consultant Quantity Surveyor did not allow an excess of 3 or 5m the defendants were not entitled to it. He further agreed that the consultant did not certify that additional 3 or 5m in his certification [1AB 237]. I also took into account the defendants’ conduct in not claiming for the additional pay length in their first five claims; this was inconsistent with their contended interpretation of the written contract. I therefore dismiss the defendants’ counterclaim for additional pay length for the piles.
45 Conclusion
46 28. Accordingly, I award interlocutory judgment to the plaintiffs on their claim with costs and dismiss the defendants’ counterclaim with costs. The Registrar shall assess the plaintiffs’ claim for damages for the defendants’ delay in completing the piling works and for the rectification works undertaken as a consequence. A sum should also be assessed for the defendants’ omission to provide a set of as-built drawings. For purposes of assessment, as I had indicated at the trial, whatever evidence that was adduced before me shall be accepted without challenge, but with liberty to the parties to adduce additional evidence on the issue of quantum; costs of the assessment shall be reserved to the Registrar. For the avoidance of doubt, I rule that the plaintiffs are not entitled as of right to direct reimbursement from the defendants of the sum of $4,000 per day claimed as liquidated damages under para 7(b) of the statement of claim -- there is no provision for liquidated damages in the written contract and, the main contract between the plaintiffs and the employer with the clause for liquidated damages was not shown or made known to the defendants as at 29 July 1996. However, in the event I am wrong in this conclusion, the plaintiffs are not precluded from adducing evidence at the assessment hearing to prove that liquidated damages were not too remote but, were within the contemplation of both parties at the time they contracted, as the probable result if there was a breach and should therefore form part of general damages (under the Hadley v Baxendale (1854) 9 Exch 341 principle as refined by Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528). It is then for the Registrar to decide whether $4,000 per day is a reasonable figure for liquidated damages (should he uphold the plaintiffs’ claim) or as the defendants’ counsel submitted, is a penalty rather than a genuine pre-estimate of loss. The damages when assessed, should be reduced by the sum of $78,420.12 which the plaintiffs still owe to the defendants for the piling works, as admitted under para 8 of the amended statement of claim.
47 29. Finally, I was informed by counsel for the plaintiffs by letter on 15 January 1999 (upon my inquiry of both parties) that the defendants had served two Offers To Settle on the plaintiffs’ solicitors pursuant to O22A of the Rules of Court 1996; this was on 19 August 1998 a week before trial first commenced. In respect of the plaintiffs’ claim, the defendants offered to pay $70,000 in full and final settlement, inclusive of interest and costs. In respect of their own counterclaim, the defendants offered to accept $127,000 from the plaintiffs inclusive of interest and costs, in full and final settlement.
48 30. Dealing first with the counterclaim, I had dismissed it and as the sum I ordered to be paid to the defendants is much less than $127,000, the award to the defendants of $78,420.12 is less favourable than their Offer to Settle. As for the plaintiffs’ claim, granted the damages due to them have yet to be assessed but I doubt that the eventual sum awarded to them would be less than $70,000 as, the defendants’ offer includes costs, which for a eleven (11) day trial may well exceed $70,000.
49 31. Accordingly, as the plaintiffs have obtained judgment on terms more favourable than both Offers to Settle, the same do not alter my orders for costs on a standard basis in their favour.
50 LAI SIU CHIU
51 JUDGE
Lai Siu Chiu J
Pavan Kumar Ratty (P K Ratty & Partners) for the plaintiffs
Tan Lay Pheng (Tan & Lim) for the defendants