S A Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd
[1999] SGHC 245
Suit 658/1999, SIC 3257/1999
Lee Seiu Kin JC
16 September 1999
1 JUDGMENT:
2 GROUNDS OF DECISION
3 The Defendant company is the developer of a multi-storey flatted factory at Kaki Bukit Road 3 ("the Project"). The Plaintiff company is a building contractor engaged by the Defendant to build part of the Project. In this suit, the Plaintiff claims payment in respect of five architect's certificates plus interest and costs. The Defendant took out this Summons, SIC 3257/99, to stay the proceedings pursuant to section 7 of the Arbitration Act. After hearing counsel for the parties on 21 June 1999, I stayed the proceedings and ordered the Plaintiff to pay the Defendant's costs in respect of this application. The Plaintiff has since appealed and I now give my grounds of decision.
4 The Pleadings
5 The Plaintiff’s claim, as set out in its Statement of Claim, is as follows. By a written contract ("the Contract") dated 8 March 1998, the Plaintiff engaged the Defendant to carry out certain works in respect of the Project. The Contract incorporated the Singapore Institute of Architects’ Conditions of Contract ("the SIA"). As the works progressed, the Plaintiff obtained interim certificates from the architect and various payments from the Defendant pursuant to those certificates. However the Defendant had failed to make full payment in respect of five interim certificates. The amount outstanding under these five certificates totals $5,469,137.04.
6 In its Defence, the Defendant admitted the fact of the certificates but denied that it was liable to the Plaintiff for that sum for two reasons. The first was that the Defendant had paid $2 million to the Plaintiff’s director, Chwee Meng Chong ("Chwee"). The Defence states that the Plaintiff had agreed that this sum would go towards reducing the amount owed under the interim certificates. As regards the balance sum of $3,469,137.04, the Plaintiff had agreed that this need not be paid until a sum of $9.46 million was paid to the Defendant by the Plaintiff’s associated company, How Hwa Investment Pte Ltd ("How Hwa"). The background to that agreement is as follows. The Plaintiff was part of a group of companies ("the CHT group") that owned shares in the Defendant. There was an agreement for the CHT group to transfer their shares in the Defendant to Straits International Resources Pte Ltd, a related company of the Defendant, for the sum of $92,155,991. It was a term of that agreement that members of the CHT group would purchase certain units in the Project and pay half the purchase price in cash up front. Pursuant to this agreement a cheque for $9.46 million was issued by How Hwa to the Defendant but it was dishonoured on 23 October 1998. After this, the Defendant agreed to forbear suing on the cheque in return for the Plaintiff not requiring the outstanding sum of $3,469,137.04 under the interim certificates in question to be paid until such time as the $9.46 million could be paid by the CHT group.
7 The Defendants’ Version
8 According to the Defendant, the background to this matter is as follows. In 1994, Ho Mun Fei ("HMF") who is the Defendant’s general manager, tendered for the URA industrial site at Kaki Bukit jointly with one Chng Heng Tiu ("Chng"). When they succeeded, they incorporated the Defendant company and assigned to it the tender award. The shares in the Defendant company were divided up as follows: on HMF's side, 36% was held by him and his brother; on Chng's side, a total of 64% was held by his company, Chng Heng Tiu Pte Ltd ("CHTPL"), and by his associates Chwee and one Yeo Siew Hang ("Yeo"). It should be noted that Chwee himself held 5% of the shares in the Defendant company at the material time.
9 The Defendant proceeded with the development of the Project. However in late 1997, as a result of disputes between the two groups, HMF and his brother decided to buy over the Chng group’s 64% shareholdings in the Defendant through their company, Straits International Resources Pte Ltd ("SIR"). An agreement was entered into on 1 December 1997 between Chwee, Yeo and CHTPL as vendors and SIR as purchaser in which the vendors would sell their shares in the Defendant to SIR for $123,155,991, payable in instalments according to a prescribed schedule. SIR made payments in accordance with this schedule until February 1998. These payments totalled $92 million. SIR stopped payment because a dispute had arisen between the parties in respect of a condition of the 1 December 1997agreement. The parties have commenced a number of actions in respect of this matter.
10 Meanwhile on 8 March 1998 the Defendant awarded the Contract to the Plaintiff, which was a company in which Chwee is the majority shareholder and a director. The Plaintiff’s main sub-contractor for the works under the Contract was Boonan Construction Pte Ltd, in which Yeo was the chairman and a substantial shareholder. Yeo held 2.5% of the shares in the Defendant company at the material time
11 The two groups held a meeting around 20 October 1998 and agreed to settle their dispute in the following manner. Firstly, SIR would proceed with the purchase of the shares but at a reduced price of $92,155,991. Secondly, Chng and his associates would purchase all the units in Plot A of the Project from the Defendant, for which the former would immediately pay 50% of the price although according to the normal sale and purchase agreement only 30% was payable up front. Pursuant to this settlement, various cheques were given to the Ho group, drawn on accounts of three companies controlled by the Chng group. Payments representing 30% of the sale price were cleared. As regards the remaining 20%, a cheque for the sum of $9.46 million was given but it was dishonoured on 23 October 1998. Chng's representatives explained that they did not have sufficient funds at the time and assured HMT's representatives that such funds would be available in due course. Consequently the parties agreed that the Plaintiff would not insist on payments under the interim certificates until the Chng group could make payment on the cheque.
12 On 11 February 1999, the Plaintiff sent a letter to the Defendant giving it notice under clause 33(1)(b) of the SIA. This provision entitles the contractor, where the employer does not pay any certificate within the prescribed period, to give a Notice of Termination if the employer does not pay within 14 days after the contractor has given written notice of his intention to do so. This was followed two days later by a further letter, dated 13 February, in which the Plaintiff referred to the 11 February letter and, invoking clause 33(1)(b), gave the Defendant Notice of Termination of the Contract. Thereafter on 22 February the parties held a meeting in which the architects and quantity surveyors also attended. The Defendant claims that at this meeting the Plaintiff agreed on a "mutual termination" of the Contract. This termination agreement provided for the architects and quantity surveyors to measure and certify the value of work done up to 22 February 1999 and the value of work and materials on site for the purpose of payment. The Defendant would pay the Plaintiff such certified sum and the outstanding sums under the interim certificates by 31 March 1999 and the Plaintiff would vacate the site on that date. However the Defendant claimed that the Plaintiff did not abide by this agreement and continued to insist that the termination was effected under clause 33(1)(b). I note that there is at least one advantage in taking this position and it is the provision under clause 33(3) of the SIA for right of the contractor to recover his loss of profit on the remaining part of the Works and any costs arising from the termination. The Plaintiff continued to remain in occupation of the site after 31 March although joint inspection had been completed. By a letter dated 8 April 1999 the Defendant rescinded the termination agreement and reserved its right to claim damages against the Plaintiff. The Defendant also gave notice to the Plaintiff to vacate the site by 15 April. The Plaintiff did not comply with this request and by its letter dated 22 April 1999, the Defendant accepted the Plaintiff’s repudiation of the Contract and reserved its right to claim damages arising from this.
13 The Plaintiffs’ Version
14 Chwee denies any arrangement to set-off the $2 million paid to him. He also denies that money was paid to him for such purpose. He agreed that his solicitors received $1 million from a company known as Chng Heng Tiu Pte Ltd for a separate purpose. But that purpose failed and this money was returned by his solicitors. As regards the second $1 million, Chwee claims that this money was part payment for the sale of shares in the Defendant company by Chwee, Yeo and CHTPL to SIR.
15 The Plaintiff denies that it is linked to the Defendant by virtue of Chwee. The Plaintiff says that Chwee's position as a shareholder in the Defendant company has nothing to do with his position as a director and majority shareholder in the Plaintiff company. The Plaintiff also says that it is not linked to the CHT group. However the Plaintiff admits that there was an agreement that the CHT group would pay the $9.46 million to the Defendant in order to assist the Defendant to make progress payments. But the Plaintiff denies that it had agreed to make payment of its interim certificates contingent upon the receipt of the $9.46 million.
16 The Litigation
17 By its solicitors’ letter dated 21 April 1999, the Defendant gave notice of arbitration to the Plaintiff’s solicitors pursuant to clause 37(1) of the SIA. On 3 May 1999, the Plaintiff took out the Writ of Summons in this action. On 19 May the Defendant took out this application to stay the proceedings. On 28 May the Plaintiff took out SIC 3480/99 for summary judgment on their claim. Both applications came up before me. In view of my order staying the proceedings, it became unnecessary for me to decide on the Plaintiff’s application for summary judgment.
18 Counsel for the Plaintiff, Mr Coomaraswamy, contended that the interim certificates of the architect were conclusive and that the Plaintiff was entitled to summary judgment irrespective of whether there was any dispute in respect of the Contract. He said that this position obtains in the SIA under clauses 31(1) and 31(11), and clause 37(3)(h). These provide as follows:
"31(1) On the dates or at the stages for issuing Interim Certificates named in the Appendix hereto the Architect shall … issue Interim Certificates for payment to the Contractor, who shall be entitled to payment of any sum stated therein as due to the Contractor within the Period for Honouring Certificates stated in the Appendix following receipt of the Certificate or a copy of the Certificate by the Employer."
"31(11) No certificate of the Architect under this Contract shall be final and binding in any dispute between the Employer and the Contractor, whether before an arbitrator or in the Courts, save only that, in the absence of fraud or improper pressure or interference by either party, full effect by way of Summary Judgment or Interim Award or otherwise shall, in the absence of express provision, be given to all decisions and certificates of the Architect (other than a Cost of Termination Certificate or Termination Delay Certificate under clause 32(8) of these Conditions), whether for payment or otherwise, until final judgment or award, as the case may be, and until such final judgment or award such decision or certificates shall (save as aforesaid and subject to sub-clause (4) of this condition) be binding on the Employer and the Contractor in relation to any matter which, under the terms of the Contract, the Architect has [as] a fact taken into account or allowed or disallowed, or any disputed matter upon which under the terms of the Contract he has as a fact ruled, in his certificates or otherwise. The Architect shall in all matters certify strictly in accordance with the terms of the Contract. In any case of doubt the Architect shall, at the request of either party, state in writing within 28 days whether he has as a fact taken account of or allowed or disallowed or ruled upon any matter in his certificates, if so identifying any certificate and indicating the amount (if any) taken into account or allowed or disallowed, or the nature of any ruling made by him, as the case may be."
"37(3)(h) Pursuant to clause 31(11) of these Conditions, temporary effect shall be given to all certificates (other than a Cost of Termination or Termination Delay Certificate under clause 32(8) of these Conditions), whether for payment or otherwise, granted (or refused) by the Architect, and to all rulings and decisions required of him for the purpose of issuing certificates under the terms of the Contract, until final award (or, where the courts may for any reason be seised of a dispute, until final judgment), save only that in cases where no ruling or decision has been made or certificate given or refused by the Architect (as to which an arbitrator or the Courts may if necessary receive evidence from the Architect) or in the case of a Cost of Termination or Termination Delay Certificate, or of any matter in relation to which the Architect has no power to decide or certify under the terms of the Contract, an arbitrator or the Courts, as the case may be, may deal with a matter whether in interlocutory proceedings or by way of Interim Award or in any other way, before final award or judgment."
19 Mr Coomaraswamy argued that the purpose of this provision was to ensure that contractors received payment on such certificates within the period prescribed in the contract In accordance with the scheme of the SIA, the Plaintiff was entitled to summary judgment on its claim. It was still open to the arbitrator to decide in the arbitration whether the certificates were correctly issued and whether the Defendant’s counterclaim was valid, and if so to rule on the quantum. This sum can be consolidated in any award the arbitrator may make. Accordingly there is no question of staying this action pending arbitration.
20 In support of his contention, Mr Coomaraswamy cited the Court of Appeal decision in Lojan Properties Pte Ltd v Tropicon Contractors Pte Ltd [1991] 2 MLJ 70. That case dealt with facts similar to the present case, but with one exception on which I shall elaborate in due course. Lojan Properties also concerned a contract on SIA terms in which the plaintiffs claimed payment on interim certificates and the defendants applied to stay the proceeding pending arbitration. The defendants there had counterclaimed against the plaintiffs for cost of rectification of defective works which the defendants alleged the plaintiffs had failed to rectify. Had the defendants succeeded in proving the fact of the defective works and the sum incurred by them, they would have been entitled under the contract to recover such sum from the plaintiffs. But this sum was not certified by the architect at the time of the action. The Court of Appeal held that even though there was a bona fide counterclaim by the defendants, such sum could not be deducted from the payment due to the contractor under the interim certificates. The court said at p 74:
"… The scheme of the contract is clear. As we have premised earlier the intention clearly expressed in the contract is to exclude the right of set-off. See the House of Lords decision in Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1973] 3 All ER 195, where the right of set-off was contractually excluded. … [Under] cl 31(11) of the conditions of contract … only amounts expressly deductible under the contract may be set off against the amounts due under the interim certificates. In our opinion the scheme of the contract is equally clear that cross-claims or counterclaims, not the subject of the architects’ certification giving the right of immediate payment or deduction, are to be separately litigated or arbitrated."
21 However the situation in the present case is quite different in that I am not concerned with a counterclaim by the Defendant in respect of the Contract. What the Defendant alleges is firstly that it has made payment in respect of the $2 million. Secondly, in respect of the balance, the Defendant says that it has a collateral agreement with the Plaintiff which is separate from the Contract. This provides that the Plaintiff would refrain from any action to enforce its right to payment under the interim certificates until the Defendant receives payment of the $9.46 million. In resisting this action the Defendant is seeking to enforce that agreement. If there is such an agreement, and it is legally binding, then the Plaintiff’s action is bound to fail. I cannot see any impediment in the SIA to the formation of such an agreement. The SIA deals with the relationship between the parties under the Contract. Insofar as payments under the interim certificates are concerned, the SIA provides that it shall be paid without any deduction for any counterclaim that the employer may have under the Contract. That is the ratio of the decision in Lojan Properties and the Court of Appeal had certainly not extended it to situations such as the present case. There is no express provision for this in the SIA and neither is there any reason why the parties should be prevented from making a collateral contract in this manner if they see it fit to do so.
22 Therefore the questions that I have to determine are, on the basis of the affidavit evidence before me:
(i) whether there are triable issues in respect of the alleged payment of the $2 million and the existence and effect of the collateral agreement, as would entitle the Defendant to unconditional leave to defend the action; and if so
(ii) whether those issues form part of the reference to arbitration as would constitute sufficient grounds to stay the proceedings under section 7 of the Arbitration Act.
23 Before I embark on these questions, it is useful to give my reasons for this formulation because it is not immediately apparent how the two applications, for stay and for summary judgment, are related. This suit relates to a claim for payment on interim certificates. The SIA provides that in the absence of fraud, etc, the court should give full and immediate effect to such certificates leaving any dispute between the parties to be determined by arbitration. Therefore if the Defendant is unable to show that there is any triable issue, the Plaintiff would be entitled to summary judgment. However if the Defendant is able to do so, and the court accordingly grants unconditional leave to defend, the next inquiry would then relate to whether the triable issues raised by the Defendant have been included in the reference to arbitration. If they have, a stay would be ordered; if not, the action would proceed to trial.
24 (i) Whether there are triable issues
25 The Plaintiff has denied that there was any payment of $2 million. However the Defendant has alleged that such payment was made in the course of the myriad dealings the parties had with one another in various capacities. The parties have also joined issue on the existence of any agreement on the part of the Plaintiff not to insist on payment on the interim certificates until the Defendant received the payment of the $9.46 million. However the background facts are admitted, i.e. the agreement by Chng's group to sell their shares in the Defendant and to buy Plot A and pay 50% of the price up front. They also agree on the fact of the dishonour of the cheque for $9.46 million, although not on the grounds for it. The complicated inter-relationship between the actors, individual and corporate, in the entire drama is also not disputed. I have no hesitation in holding that these are matters that ought to be determined at a trial. However I need to examine also whether the agreement alleged by the Defendant, i.e. that Chwee undertook on behalf of the Plaintiff that it would not insist on payment of the interim certificates until the Defendant was paid the $9.46 million, was supported by consideration. I cannot say that there is none as the promise by the Defendant not to sue on the $9.46 million cheque could constitute good consideration. The Defendant would obviously have to pierce the corporate veil and show that Chwee was the principal behind the Plaintiff. Given the complex relationships in this matter, I have no doubt that these are triable issues that would have entitled the Defendant to unconditional leave to defend in an application for summary judgment.
26 (ii) Whether a stay ought to be granted
27 The Defendant had referred the dispute to arbitration on 21 April 1999. In their letter, the Defendant’s solicitors said, inter alia, as follows:
"…
We are further instructed that disputes have now arisen between our respective clients, arising from your clients' purported termination of their employment under your clients' Notice of Termination dated 13 February 1999, which termination our clients maintain was unlawful and in breach of clause 33(1)(b) of the Conditions of Contract.
Pursuant to clause 37(1) of the Conditions of Contract, we are instructed by our clients to give your clients Notice to refer the said dispute to arbitration.
…"
28 The Plaintiff’s position is that the Contract was validly terminated by its letter of 13 February 1999. This was pursuant to clause 33(1)(b) of the SIA. The Defendant’s position is that the 14-day period was not over when the Plaintiff sent that letter - only two days had elapsed from the 11 February letter. The parties had mutually agreed to terminate the Contract on 22 February 1999 and one of the terms of that agreement was that the Plaintiff was to vacate the site by 31 March. But the Plaintiff failed to vacate the site on that date and on 8 April the Defendant rescinded the mutual termination agreement. The Defendant further says that on 22 April it accepted the Plaintiff’s repudiation of the Contract and reserved its right as to damages.
29 The parties are substantially not in dispute that there is a valid reference to arbitration pursuant to clause 37(1) of the SIA, which provides as follows:
"Any dispute between the Employer and the Contractor as to any matter arising under or out of or in connection with this Contract or under or out of or in connection with the carrying out of the Works and whether in contract or tort, or as to any direction or instruction or certificate of the Architect or as to the contents of or granting or refusal of or reasons for any such direction, instruction or certificate shall be referred to the arbitration and final decision of a person to be agreed by the parties …" (emphasis added)
30 The Plaintiff’s purported termination on 13 February 1999 under clause 33(1)(b) arose out of the failure of the Defendant to pay on the interim certificates in question. Whether the Plaintiff is entitled to invoke this clause will depend on a finding whether the Defendant was justified in not paying the Plaintiff on those interim certificates. Therefore the two issues, (i) the alleged $2 million payment and (ii) the existence or otherwise of the collateral contract, would be matters arising "in connection with" the Contract which has been referred to arbitration.
31 I turn next to the question of the stay. Section 7 of the Arbitration Act provides as follows:
"(1) If any party to an arbitration agreement … commences any legal proceedings against any other party to the arbitration agreement … in respect of any matter agreed to be referred, any party to the legal proceedings may at any time after appearance, and before delivering any pleadings or taking any other steps in the proceedings, apply to the court to stay the proceedings.
(2) The court or a judge thereof, if satisfied that there is no sufficient reason why the matter should not be referred in accordance with the arbitration agreement, and that the applicant was, at the time when the proceedings were commenced, and still remains, ready and willing to do all things necessary to the proper conduct of the arbitration, may make an order staying the proceedings."
32 As the matter has been referred to arbitration and the issue is one which is within the arbitrator's jurisdiction to decide under the reference, the Defendant has satisfied sub-section (1). The only question is whether a stay ought to be granted under sub-section (2).
33 In JDC Corporation v Lightweight Concrete Pte Ltd [1999] 1 SLR 615, the Court of Appeal held (at paragraph 10) that once the court finds that a party is entitled to a stay under section 7(1), the inquiry then turns to a consideration of section 7(2) and "the burden of showing that there was a sufficient reason for not referring the matter in dispute to arbitration fell on the party opposing the application for a stay". In the present case Mr Coomaraswamy was unable to satisfy me that there were such reasons nor could I see any. It would be just and convenient for the dispute between the parties on the question of whether there was payment of $2 million and whether there was a collateral contract in respect of the balance to be heard and determined by the arbitrator pursuant to the arbitration agreement along with all other disputes arising from the Contract. Accordingly I granted the Defendant's application and ordered that the proceedings be stayed.
34 LEE SEIU KIN
35 JUDICIAL COMMISSIONER
Vinod Coomaraswamy (Shook Lin & Bok) for the plaintiffs
Howard Cashin (Lim Hua Yong) & Raymond Chan (Chan Tan & Pnrs) for the defendants