In the High Court of the Republic of Singapore
[1999] SGHC 265
Suit 217/1999
Between
China Construction (South Pacific) Development Co Pte Ltd
… Plaintiff
And
Leisure Park (Singapore) Pte Ltd
… Defendant
grounds of decision
Building and Construction Law — Standard form contracts; Building and Construction Law — Standard form contracts

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
China Construction (South Pacific) Development Co Pte Ltd v Leisure Park (Singapore) Pte Ltd
[1999] SGHC 265
Suit 217/1999
Warren Khoo L H J
09 October 1999
1 :This is an appeal from a decision of the learned assistant registrar Miss Vivian Wong granting the plaintiffs summary judgment in the sum of $320,735.79 purportedly certified by the architect under a building contract.
2 The plaintiffs were the main contractors engaged by the defendant owners under a contract in the SIA standard form of contract for the building of a theme park on Sentosa Island at a lump sum of some S$8.146m. The provisions for the issue of interim certificates for payment for work executed by the plaintiffs under the contract were contained in cl 31 of the general conditions of contract as modified by the parties. This clause, read with the Appendix, provides for the certification of interim payments at monthly intervals on the 15th day of each month and for the honouring of the interim certificates by the employer within 21 days of their receipt.
3 Cl 31(2) of the general conditions provides that the interim certificates shall be based on aretrospective re-valuation of all the work carried out under up to a date not exceeding 7 days before the date of the certificate. It reads:
... such interim certificates shall ... be based on a retrospective re-valuation of all the work carried out under the contract up to a date (which shall be named in the certificate) not exceeding seven days before the date of issuing the certificate itself ...
4 However, by an addendum to the contract, a new cl 31(13) was added. It provided as follows:
Notwithstanding the foregoing provision, the issuance of each and every Interim Certificate by the Architect is conditional upon the Contractor having sent to the Quantity Surveyor a detailed statement and breakdown of the approximate value of the work executed and of unfixed materials on site, at least ten days before the date of each relevant Certificate.
5 As provided in the letter of award dated 31 May 1993, the commencement date of the contract was to be the date of issue by the relevant authority of the permit to commence work, and the contract period was 11 months. In the event, it appears that the commencement date was 13 July 1993 and the contract completion date was 12 June 1994. There is indication that the latter was extended to 15 January 1995. I do not know that for sure, but nothing turns on it. It seems not to be disputed that practical completion was certified on 15 January 1995.
6 Interim certificates were issued by the architect from time to time on progress claims submitted by the plaintiffs. On 7 October 1995, the plaintiffs submitted progress claim No 20, described as the `penultimate` claim, for the (cumulative) sum $6,568,910.27. The architect by right would in the normal course have issued one interim certificate in respect of the claim. However, he did not do so. Instead, he issued one (No 20) on 27 June 1996 for the cumulative sum of $4,621,575.75 and a net sum of $43,690 (after deducting the cumulative amount of $4,577,885.75 previously certified). He issued another document described as an interim certificate (No 21) on 13 January 1997 for a cumulative sum of $4,815,928.50 and a net sum of $194,352.75 (after deducting the $4,621,575.75 previously certified). Then, nearly two years later, on 10 December 1998, he issued interim certificate No 22 for the cumulative sum of $5,136,664.29 and a net sum of $320,735.79 (after deducting the $4,815,928.50 previously certified). This last certification was based on the quantity surveyor`s valuation made on 31 July 1997 contained in his valuation certificate No 22 dated 7 August 1997. The net certified sum of $320,735.79 is what the plaintiffs now claim from the defendants in these summary proceedings.
7 The reason why the plaintiffs` progress claim has been dealt with in this way has not been fully explained. It appears that the architect has explained to the defendants in a letter dated 7 January 1999 the reasons why he issued the interim certificate in question and why in his view the interim certificate was properly issued. The letter is no doubt in the possession of the defendants, but they have not produced it although they have had an opportunity to do so. Counsel for the defendants, however, tells me that the gist of the letter was that the interim certificate had been issued because of previous under-certification.
8 Defendants` contentions
9 The main contention for the defendants is that the architect has not certified interim certificate No 22 in accordance with the provisions of the contract. I hope I adequately summarise their counsel`s arguments as follows. First, counsel refers to cl 31(2), set out above. He raises points about the valuation date. He says that, contrary to this provision of the contract, the interim certificate does not show the valuation date. Note the words in parenthesis in the clause, set out above. The clause also requires the certification to be based on a valuation not more than seven days before the date of the certificate. Although he does not expressly say so, he seems to suggest that since the certificate was issued long after the date of valuation, it has not been issued in accordance with the contract. He also refers to the provision in cl 31(13) to the effect that the contractor has to submit a breakdown of the work `at least ten days before the date of the relevant certificate`. However, it is not absolutely clear what point he makes about this part of that sub-clause. Counsel refers to Tropicon Contractors Pte Ltd v Lojan Properties Pte Ltd [1989] SLR 610 [1989] 3 MLJ 216 in which interim certificates were struck down on the ground, inter alia, that it was issued long after the completion of the work and that they did not show the valuation date.
10 Secondly, counsel makes the general proposition that only one interim certificate can be issued on one progress claim. He says that this is implicit in cl 31(2) and it is also made clear in the added cl 31(13). The contract, counsel submits, does not allow more than one interim certificate to be issued in respect of one progress claim. But this is what the architect has done. There was no progress claim in respect of which the interim certificate in question could be issued.
11 Thirdly, counsel submits that interim certificates are intended to be issued during the progress of the works, and not after the contract has been completed. He points to the provision of cl 31(1), read with the Appendix, requiring the architect to issue interim certificates on the 15th day of every month. He points out that in this case, the works had been certified as having been completed on 15 January 1995. Progress claim No 20 (on the basis of which interim certificate No 22 was purportedly issued) had been presented as the penultimate claim. The previous certificate (No 21) had in fact been issued for the release of the full retention money, and the sum certified by that certificate ($194,352.75) had been paid to the plaintiffs on 13 January 1997. The plaintiffs had also submitted their final accounts. And now, counsel says, nearly four years after completion, the architect has purported to issue another interim certificate. This, counsel submits, is contrary to the scheme and provisions of the contract. Counsel refers to the Tropicon case, in which interim certificates were held to be invalid on account of having been issued more than two years after completion.
12 Whether valid as correction certificate
13 Clause 31(4) allows the architect to issue further interim certificates to correct earlier interim certificates. It reads as follows:
The Architect shall have power to issue a further Interim Certificate at any time, whether before or after completion, correcting any error in an earlier Interim Certificate (but not any Delay, Termination of Delay, Further Delay or any certificate other than an Interim Certificate) or dealing with any matter of which he was not aware, or which should have been dealt with, at the time of an earlier Interim Certificate, or revising any decision or opinion on which that Certificate was based.
14 Counsel for the plaintiffs relies largely on this clause, and contends that the interim certificate in question may be regarded as a certificate correcting the under-certification of progress claim No 20. Counsel for the defendants, on the other hand, submits that the certificate in question is not in form or in content a correction certificate properly issued under cl 31(4). Firstly, it does not state that it is a certificate issued under that sub-clause. Secondly, it is in exactly the same form as the earlier interim certificates No 20 and 21; it appears to be a continuation of those certificates, and it does not purport to correct anything in either of those certificates. Referring to the guidance notes issued by the SIA on the SIA articles and general conditions, counsel says that a proper correction certificate must
15 (i) identify the previous certificate it seeks to correct;
16 (ii) state the reasons for the correction; and
17 (iii) set out details of what is being corrected.
18 Instead, the certificate in question is in the form of an interim certificate, no different (except, of course, as to date, number and amounts) from the previous certificates. Counsel for the defendants refers to the Tropicon case, where LP Thean J [as he then was] held as invalid the alleged correction certificates for the reason that they did not contain the matters required to be set out.
19 A separate point: Interim certificate No 21: retention money
20 Clause 31(7) provides, so far as relevant, that one half of the retention money shall be certified as due to the contractor on the issue of the completion certificate. Clause 31(8) provides that the balance of the retention money shall be certified and paid to the contractor under a further interim certificate to be issued at the expiry of the maintenance period. By the addendum to the contract, a new cl 31(14) was added in the following terms:
Notwithstanding the provision of the sub-clause (7), the first release of the retention monies shall be subject to the submission by the Contractor of all as-built drawings, survey information/as-built survey plans, certificates/ guarantees of materials, equipment and/or workmanship, operation manuals of installation, maintenance instructions etc to the satisfaction of the Architect and the Employer.
21 In addition to contending that interim certificate No 22 is invalid for the above reasons, the defendants raise a separate point that the previous certificate, No 21, was also invalid. They say that the certificate was for the release of the retention money. But in breach of the added sub-cl (14), the plaintiffs had failed to provide the drawings and other things required to be provided. So, the defendants contend that the sum of $194,352.75 certified had been paid by mistake and they are entitled to have it back. They have instituted a separate suit (No 683 of 1999) to recover the payment.
22 Another separate point: GST payments
23 The letter of award provided that all goods and services tax on the value of the plaintiffs` works was to be borne by the plaintiffs except for the first $100,000. It is not disputed that, contrary to this provision, sums totalling $84,115.19 were included in the various invoices rendered by the plaintiffs on the value of the works certified. The defendants seek to recover this amount by way of a set-off against the amount of interim certificate No 22 in case that certificate is held to have been validly issued. They have also included this as a claim in Suit 683/99.
24 My views: conduct of the parties
25 It seems to me that when considering the question of the validity of interim certificate No 22, it is appropriate to take into account the conduct of the parties and the architect in the matter of certifications and payments. It is quite apparent that it is not in regard to interim certificate No 22 alone that the architect and the parties have not followed the provisions of the contract. The parties have, unfortunately, not produced all the progress claims that have been made and all the interim certificates that have been issued under this contract. But there are indications from the little that has been produced that the provisions of the contract have not always been followed. Indeed they have habitually been ignored. Take, first, the point about the form and contents of interim certificates. The defendants say that interim certificate No 21, the one issued before the interim certificate in dispute, was a certificate for the release of the retention sum under cll 31(7) and (8) of the conditions. I cannot for the life of me see that it is, in form, such a certificate. It is in exactly the same form as the ordinary interim certificate for payment for work done and materials delivered on site. Just like interim certificate No 20 and the disputed certificate No 22, it refers to cl 31(1) and (2) (relating to the issue of certificate and valuation of work and carried out and materials delivered). The sums included in the certificate run in a series between certificates No 20 and 22. The certificate does not refer to cl 31(7) and (8), (dealing with certification for the release of the retention). Neither was there anything to show that the sum certified was the amount of the retention to be returned; there was no mention of retention at all. So, if the defendants are right that this is an interim certificate for the release of the retention sum, the certificate does not show it. But the certificate was accepted as valid and the defendants paid on it without objection on the ground that it was not in proper form.
26 Next, take the point about the timing of certificates. The contract contemplated that a progress claim was to be submitted every month and an interim certificate was also to be issued every month. It was contemplated that on receipt of the progress claim, the quantity surveyor would proceed with his valuation, and the architect would then proceed with his certification on the basis of the quantity surveyor`s valuation. Clause 31(2) of the general conditions provides that the interim certification should be based on a valuation made not more than seven days before the certification. This was modified to `at least ten days before each relevant certificate`. There is no doubt that everything was to be done within a timeframe consistent with the scheme for monthly certification provided by the contract. But, we see from the way progress claim No 20 was dealt with how far the practice fell below the ideal. As stated above, the claim was made in October 1995. But interim certificate No 20 was not issued until towards the end of June 1996, more than eight months after the submission of the claim. But nothing was made of it. The employer paid the amount belatedly certified.
27 Then, in regard to interim certificate No 21, if the defendants are right that it was for the release of the `full` retention money, then it is quite evident that it, too, was not issued in accordance with the contract. According to cl 31(7), the first half of it should have been certified on the issue of the completion certificate, which I take to be 15 January 1995. According to cl 31(8), the balance should have been certified at the end of the maintenance period, ie 15 January 1996, according to the contract. But the certificate was not issued until 13 January 1997. So, the certification for release of the first half of the retention was delayed for a good two years, and for the release of the balance by nearly a whole year. Again, the defendants paid on the certificate without objection on ground that it was out of time.
28 Take, next, the point about valuation date. There are two points made by counsel for the defendants. First, he says that the interim certificate in question does not show the valuation date. On this point, it appears from the exhibits that it was not the practice of the architect to show the valuation date on the face of the certificate. It was not in his standard form of interim certificates. But it was his practice to attach the quantity surveyor`s valuation report to each interim certificate he issued. The valuation date was clearly shown there. Secondly, counsel makes the point about non-compliance with the stipulation that the interim certificate must be based on a re-valuation `not exceeding seven days` before the date of the interim certificate. In regard to this point, it seems to me, although I have not heard arguments about it, that this stipulation is intended for the benefit of the contractor. The certificate is to be issued on the basis of an up-to-date valuation, so that the contractor can be paid as much as practicable for the work he has done. Under this clause, if the valuation date is more than seven days before the date of issue of the certificate, it would be to the detriment of the contractor in that he would not be paid as much as he ought to be paid. It certainly would be odd for the employer to deny him payment on the ground that the valuation date is more than seven days before the certificate.
29 It seems to me that in view of these apparently habitual departures from the contract, all in relation to certifications of payments to the contractor, the defendants` criticisms about the form and timing of the certificates cannot be taken seriously. There has been a general waiver of the strict requirements of the contract, and it is inequitable for the employer to go back on it when it suits him.
30 Correction certificate point
31 I turn to the Tropicon case, in connection with the defence counsel`s point that interim certificate No 22 is not in form and content a correction certificate under cl 32(4). In that case, the architect purported to alter his earlier decisions on extension of time and purported to alter interim certificates which had been issued more than two years previously so as to `record` deductions for liquidated damages based on his revised decision on the time extension. It was held by LP Thean J (as he then was) that the purported revised interim certificates were not valid for the reason, among others, that they did not show the basis for the correction.
32 It seems to me that there were, basically, two main questions addressed by LP Thean J in his judgment in the case. The first had to do with the form and contents of the revised interim certificates, and the second, which in my view was far more important, had to do with the purported revision of the architect`s decision on time extension. In regard to the first question, his Honour found that the architect had in a letter to the employer avowedly revised the interim certificates to take account of certain matters which had been raised by the employer. However, the revised interim certificates did not reflect these matters. Secondly, his Honour noted that cl 31(2) of the SIA general conditions required that the date of the valuation of works in respect of which an interim certificate was issued should be stated in an interim certificate. He noted that in none of the revised interim certificates was such a date shown.
33 On the second main question, which, as I say, is far more important, LP Thean J held that no liquidated damages were payable or deductible unless and until a delay certificate had been issued in accordance with cl 24. The revised interim certificates bore the same dates as the interim certificates they purported to revise, but as of the dates of the original interim certificates, no delay certificate had been issued; the delay certificate relied on was not issued until more than two years later. Furthermore, LP Thean J held that the delay certificate purportedly issued was invalid because the architect`s revision of his decision on the extension of time, on the basis of which the delay certificate was purportedly issued, was flawed. Among other things, his Honour held that the decision to revise the extensions of time was made long after the time provided for in cl 23 (3). As the revised decision on extension of time was flawed, his Honour held that the delay certificate, purportedly based on that revision, was also flawed.
34 It seems to me that the gravamen of the criticism about the exercise of the architect`s certification powers in the Tropicon case was that he belatedly changed his decision on extension of time, belatedly issued a delay certificate based on that revised decision, and purportedly deducted liquidated damages from interim certificates previously issued on the basis of his revised decision on the time extension and the delay certificate based on it. The wrongful decision from which everything else flowed was the revised decision on the time extension, with drastic consequences to the contractor in the form of the liquidated damages which ensued. It so happened also that the architect`s decision was made belatedly, the form of the interim certificates he purported to issue did not conform to the requirement of the contract, eg for not showing the valuation date and not showing the basis for the correction. However, in my view, the Tropicon case is no authority for the proposition that an interim payment certificate is in all cases to be invalidated merely on the ground that such requirements are not met. I had occasion to say in a judgment delivered only a few days ago in Suit No 1432 of 1998 ( Lian Soon Construction Pte Ltd v Guan Qian Realty Pte Ltd [2000] 1 SLR 495 ) that as an architect`s decision on extension of time may have serious financial implications for the contractor, his decisions on such matters are more open to close scrutiny for compliance with the provisions of the contract and with principles governing the exercise of his power, than are his decisions on interim payments. In this connection, I pointed out that under cl 31(4) of the SIA general conditions, while interim certificates for payment were susceptible of correction, decisions on extensions of time (and the consequential decision on delay certificate and liquidated damages) are not.
35 Validity of certificate as a correction certificate
36 This leads me to the contentions in regard to interim certificate No 22 as a revision or correction certificate under cl 31(4) of the general conditions.
37 As Mr Duncan Wallace QC, the learned editor of Hudson`s Building and Engineering Contracts (11th Ed, at para 6-167) points out, correction in subsequent certificates of earlier mistakes of all kinds is an inherent element of nearly all systems of interim payments under building contracts based on periodical re-valuations of work done and materials delivered on site. I am sure this applies to the SIA form of contract, of which, incidentally, Mr Wallace was the author.
38 Clause 31(4) appears to have been included in the general conditions to give the architect the power at any time to correct any error he has made in any previous interim certificate or certificates, in addition to this automatic mechanism of correction resulting from a continuous re-valuations of work executed and materials delivered on site. The clause is worded widely, and I think deliberately so. A correction certificate may be issued at any time. It can be issued before completion of the contract; it can be issued afterwards. I am sure it can be issued in between two interim certificates; it can be issued notwithstanding that an interim certificate has already been issued on the same progress claim.
39 On my analysis of the Tropicon case and cl 31(4) above, it seems to me, therefore, that there is nothing in that case to support the view that a correction certificate, in the absence of vitiating factors such as those present in that case, should be invalidated merely on the ground that it was issued long after the completion date. That is particularly pertinent in a case, such as the present, where interim certificates have habitually been issued late. The delay in this case was probably consistent with a pattern of grudging and belated certifications, as manifested in the manner in which the previous two certificates I have referred to were issued. It seems evident that what happened was that the architect, having certified certain sums, did not consider that he had certified enough, and proceeded to issue a further certificate or certificates on the basis of the same progress claim made on 1 October 1995.
40 I think there is some force in the argument that the form of a correction certificate should follow the form proposed in the SIA guidance notes. However, in the instant case, the architect concerned did not seem to be very scrupulous about adhering to the form called for by the provisions of the contract. The form he used for interim certificate No 21 is a good example. I do not think that the contractor should be penalised for such lapses on the part of the architect. While strict compliance with the provisions of the contract in the matter of certifications should be the general norm, what happened in this case leads me to think that the rule should not be allowed to be applied in such a way as to enable the employer to rely on and take advantage of lapses on the part of the architect, particularly in respect of the form and timing of certifications of payments to the contractor, in the absence of substantial vitiating factors. Delays in the issue of interim certificates and failure to cast such certificates (indeed other certificates as well) in proper form seem to be not uncommon occurrences.
41 So, my view is that while it is desirable for an architect to adhere to the guidance notes when issuing a correction certificate, the failure to do so in this case was not fatal. An interim certificate for payment issued by the architect under the SIA form of contract, like other certificates issued by him, is prima facie to be honoured. It enjoys `temporary finality`, ie finality pending resolution of any underlying disputes between the parties by review in arbitration or court proceedings. Summary judgment is to be given in the meantime on the certificate unless it can be shown in a summary way that the certificate has not been issued in the proper exercise of the architect`s certification powers under the contract. All this is provided in cl 31(11) of the general conditions. The burden of showing that the power has not been properly exercised in respect of any certificate is on the party challenging its validity. On the facts of this case, I am not prepared to find that the architect has not acted properly in the exercise of his power under cl 31(4). The interim certificate in question must be honoured.
42 Retention money
43 As stated above, the defendants` claim for the return of the retention money is the subject of another suit. There is strictly no need for me to deal with it here. However, I cannot help noticing that the interim certificate concerned was issued and the money paid long ago, apparently without objection. Furthermore, there is a dispute as to whether and to what extent the drawings and other things in fact have been handed over. I do not think that any claim that the defendants may have for the return of the money or for the supply of the drawings and other things should be allowed to delay the payment of the sum claimed by the plaintiffs in these summary proceedings.
44 GST payments
45 The plaintiffs resist the defendants` claim for refund of the GST payments on the ground that payments under the contract, in the SIA standard form, are generally governed by certificates. Counsel cited dicta from the Tropicon case in support of this well accepted proposition. Counsel submits that since there has been no certification in respect of these payments, the defendants cannot make any claim in respect of them.
46 I do not think that these payments are payments within the scope of the contract. As to be expected, there are no provisions for certification of such payments. They were simply payments made by mistake. The defendants are entitled to have them back simply on the basis that these payments have been made by mistake.
47 Conclusion
48 I therefore hold that the plaintiffs are entitled to recover the sum of $320,735.79 claimed by the plaintiffs, and interest. I also hold that in diminution of that sum and interest, there shall be deducted the sum of $84,115.19 claimed by the defendants, and interest. The interest on each of these sums shall be at the rate of 6%, in the case of the sum due to the plaintiffs from the date of the writ, and, in the case of the sum due to the defendants from 17 March 1999, the date when the defendants first asserted their claim in these proceedings.
49 So far as costs are concerned, the defendants have failed on the major points in this appeal, and have succeeded only in respect of the GST point. They must bear the major portion of the costs of this appeal. I order that they pay 90% of the plaintiffs` costs.
50 Outcome:
51 Appeal dismissed.
Warren Khoo L H J
Tang King Kai (Tang & Partners) for the appellants/defendants
Michael Chia and Yap Pett Chin (Drew & Napier) for the respondents/ plaintiffs