In the High Court of the Republic of Singapore
[1999] SGHC 282
Suit 1764/1998
Between
Graham Taylor Designs (S) Pte Ltd
… Plaintiff
And
Grande Studio East Pte Ltd (fka Grande Star East Pte Ltd)
… Defendant
grounds of decision
Building and Construction Law — Building and construction contracts; Building and Construction Law — Building and construction contracts

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Graham Taylor Designs (S) Pte Ltd v Grande Studio East Pte Ltd (fka Grande Star East Pte Ltd)
[1999] SGHC 282
Suit 1764/1998
Lim Teong Qwee JC
27 October 1999
1 : This is a claim for balance of fees payable for consultancy services under a contract evidenced by a memorandum of understanding dated 16 March 1998 and for balance of price of construction works executed under an oral agreement made on or about 4 May 1998 and several letters of award issued pursuant to the oral agreement and orders for additions and variations. On 26 August 1999 I gave judgment for the plaintiff as claimed less deductions for defects and dismissed the counterclaim. On 4 September 1999 I assessed the defects and gave judgment accordingly. Having regard to all the circumstances including the issue of defects I awarded the plaintiff only part of the costs. The defendant has given notice of appeal and these are my written grounds. [The appeal was withdrawn - Ed.]
2 The plaintiff (`Graham Taylor`) is a company incorporated in Singapore and as its company profile says it `offers a professional consultancy service in space planning, environment and interior design`. In January 1998 the defendant (`Grande Studio`) was minded to operate a theme entertainment centre at the 9th storey of the building at Grange Rd known as Cineleisure Orchard and for that purpose to take a lease of the premises and fit it out accordingly. Graham Taylor was approached and following several discussions a memorandum of understanding (`memorandum`) contained in a letter dated 16 March 1998 was signed for Graham Taylor by Mr Linwood its managing director and for Grande Studio (then known as Grande Star East Pte Ltd) by its executive director Mr Law.
3 The memorandum provides:
1.1 [Grande Studio] agrees to appoint [Graham Taylor] as Full Service Consultants and Project Managers for the above project.
1.2 The design and completion of the project is to be carried out in accordance with the attached Budget Estimate and Fee Proposal (Appendix A), and Programme of Works (Appendix B).
1.3 No changes to the Budget or Programme of Works will be allowed without written approval of [Grande Studio].
1.4 [Grande Studio] agrees to pay [Graham Taylor] a lump sum fee of $333,000.00 for the Consultancy services stated therein and further specified on the attached Scope of Services (Appendix C) and itemised hereafter:
Interior Design; Project Management; M&E Design; Graphic Design; Architectural Submissions; Structural Engineer; Clerk of Works; Acoustic Engineer.
4 I have added the numbering. Payment terms are then set out in para 2 and it appears that the services are divided into five phases described as planning, design development, specification, tender, and site supervision. Paragraph 3 provides that a full service agreement will be prepared by Graham Taylor for signature by Grande Studio before the commencement of phase 2. Paragraph 4 of the memorandum provides:
Following completion of [tender phase] of the above services the successful Contractor will be appointed by [Graham Taylor] under a separate agreement.`
5 The annexed budget estimate provides for interior and M&E works, catering equipment, professional fees and a 2.25% contingency sum. The interior and M&E works were estimated over 14 locations of the entertainment centre on a cost per square metre basis giving a total of $2,049,250. The estimate for catering equipment was $125,000 and that for professional fees was $370,000. The programme of works allowed 12 weeks from the appointment of Graham Taylor as consultant to handover of the works to Grande Studio. More significantly it allowed five and a half weeks for construction on site.
6 In accordance with para 3 of the memorandum Graham Taylor sent two copies of its full service agreement to Grande Studio with its letter of 25 March 1998. These have not been signed and it is not disputed that the parties were bound by the agreement evidenced by the memorandum and that nothing in the full service agreement has been incorporated in the agreement. The letter of 25 March 1998 also said:
The Scope of Works excludes Graphic Design and the total fee is therefore reduced to $333,000.00 (excluding GST) as agreed. Phase 4 of our services has been renamed `Cost Control` since, as directed, tenders will not be issued but a pricing exercise will be held instead.
7 Paragraph 1.4 of the memorandum already mentions the reduced fee as reflected in the budget estimate.
8 Grande Studio admits the agreement evidenced by the memorandum as amended by the letter of 25 March 1998. It alleges in para 2 of its defence that the memorandum did not constitute the entire contract and that:
[Graham Taylor`s] obligation was to design and build an exclusive and up-market night entertainment club comprising, inter alia, a discotheque (also known as the Main Hall), a wine bar (also known as the Cafe Bar) and karaoke rooms (also known as KTV Rooms/Section) which were to operate in close proximity on the same floor of the premises at level 9 Cineleisure Orchard.
9 It further alleges in para 9 that:
It was an express or implied term of the [memorandum] that [Graham Taylor] would undertake the project on a design and build basis.
10 Mr Law said in his affidavit:
In the minutes of meeting held on 9 March 1998 ... para 1 stated `[Graham Taylor] was appointed by Mr Paul Law to be the Interior Designer/Project Management & Builder for Star East`.
Accordingly, when the [memorandum] was signed, it was understood, and [Grande Studio] is advised it was an express or implied term that [Graham Taylor] would be responsible and liable to [Grande Studio] for all aspects of the Project, including the construction aspect.
11 A copy of the minutes was annexed to the affidavit. It appears on the face of it to contain minutes recorded by a Mr Wee of a meeting on 9 March 1998 between Mr Law and Mr Wee representing Grande Studio and Mr Linwood representing Graham Taylor. Mr Wee did not give any evidence. Mr Linwood did not give any evidence about the alleged meeting on 9 March 1998 and he was not cross-examined on what the minutes recorded.
12 On 10 March 1998 Graham Taylor wrote to Grande Studio and para 1 (appointment of Graham Taylor as full service consultants and project managers) was in material respects identical with para 1.1 of the memorandum. The letter that was produced had these words written in the margin against this paragraph: `No mention of builder`. Under cross-examination Mr Law admitted that Mr Wee faxed this letter to him with these words which Mr Wee had written. On 16 March 1998 another meeting took place and following that the letter containing the memorandum was sent.
13 Item 1 of the minutes of the meeting on 9 March 1998 states that Graham Taylor was appointed to be the `Interior Designer/Project Management & Builder`. It goes on to state that the agreed lump sum fee was $250,000 for design and project management and $120,000 for all other related professional services. Nothing was recorded in the minutes as regards the construction cost but item 4 states:
[Graham Taylor] will also be preparing a Design Build Contract for [Grande Studio] to review as soon as [Graham Taylor] has finalised the contract sum for the project.
14 It is not disputed that no `design build` or `design and build` contract was ever prepared whether by Graham Taylor or by Grande Studio.
15 On 22 April 1998 Graham Taylor wrote to Grande Studio to advise that it had awarded a contract for preliminary works to DH Decor Pte Ltd and forwarded a letter of award expressed to be from Graham Taylor on behalf of Grande Studio and addressed to DH Decor with a request that it be signed by Grande Studio as confirmation. The letter of award when signed would show that it was Grande Studio contracting as owner with DH Decor as contractor. This letter was returned to Graham Taylor with a note written on it to the effect that Grande Studio would not sign it. The note continues:
As you are aware that this is a turn key project we will only sign with your company.
16 On 27 April 1998 there was a meeting of consultants and following that Mr Linwood had a discussion with Mr Law and Mr Wee. On 29 April 1998 Graham Taylor wrote to Grande Studio. The relevant part of the letter states:
As already explained a `turn key` approach to this project is not possible as an itemised budget has not been agreed and we are providing comparative quotations, which of course is the best way for you to control costs. We must reiterate that if we follow standard consultancy procedure (as outlined in our Design Agreement and the Project Organisation sheet), [Graham Taylor] will still act as the conduit through which all communication flows; yet [Grande Studio] retains ultimate direct financial control.
If you wish us to act as a main contractor then we will do so and apply a profit and attendance sum to each sub-contractor and supplier.
You proposed a meeting with Paul Law to resolve this issue however he is not available until 4 May 1998. This will hinder commencement of works. Please arrange the meeting at your convenience.
17 There was a meeting on 4 May 1998 and following that meeting all the letters of award and variation orders were signed. These documents show that Grande Studio contracted with Graham Taylor for the construction works. Graham Taylor did not execute the works itself but sub-contracted out the works to DH Decor and others. As Mr Linwood explained the letters of award between Graham Taylor and the sub-contractors and suppliers were sent out upon Grande Studio signing the letters of award between Grande Studio and Graham Taylor.
18 Grande Studio`s case is that at the meeting on 9 March 1998 a `design and build` contract was made. I find that no such contract was made at all. The minutes of the meeting are inconsistent with any such contract having been made notwithstanding the inclusion of `builder` in item 1. A design had not been developed yet. It would have been impossible to determine a price for it. A design and build contract was to be prepared but this had never been done. The letter of 10 March 1998 made no mention of Graham Taylor being the builder as Mr Wee quite rightly pointed out and this remained unchanged when the memorandum was prepared and signed by both parties. I think Grande Studio preferred entering into such a `design and build` contract but Graham Taylor was quite unwilling to do so but it was willing to be the main contractor on certain terms. Its letter of 29 April 1998 explained its position. I find that the memorandum contains the entire contract between the parties at the point of time it was signed and that this contract was amended by the terms of Graham Taylor`s letter of 25 March 1998.
19 Grande Studio`s alternative case is that Graham Taylor`s obligation under the memorandum was to design and build the entertainment centre. Mr Chia referred to paras 1.2, 1.3 and 4 and submitted that upon a true construction of the memorandum Graham Taylor had undertaken the obligation to build. His argument is that the `design and completion of the project` was to be carried out in accordance with a budget estimate and a programme of works which could not be changed without Grande Studio`s written approval and a contractor would be appointed by Graham Taylor. The memorandum does not say that the appointment would be made on behalf of Grande Studio . All this so counsel`s argument goes pointed to an obligation to build.
20 Paragraph 1.1 provides for the appointment of Graham Taylor `as full service consultants and project managers` for the project and para 1.2 provides for the manner in which `the design and completion of the project` is to be carried out. I think the expression `the design and completion of the project` refers to the services to be provided by Graham Taylor under its appointment. The services are as para 1.4 of the memorandum says `stated therein [ie in Appendix A and Appendix B] and further specified ... [in Appendix C] and itemised hereafter [ie under the eight heads following]`.
21 The memorandum has to be read as a whole and read in this way it does not say and cannot be understood to say that Graham Taylor is also to build the entertainment centre or otherwise to be the main contractor. The description of phase 4 of the services contained in Appendix C (renamed `Cost Control`) makes it clear that it is Grande Studio that is to employ a contractor and not Graham Taylor. There is no express term that Graham Taylor would undertake the project on a design and build basis. The memorandum expressly provides for the services defined in it and in particular in the appendices to be given by Graham Taylor and no term can be implied for Graham Taylor to build the entertainment centre as such a term would be unreasonable in the circumstances and is inconsistent with the memorandum.
22 Paragraphs 35 and 36 of the defence state:
35 Further, [Grande Studio] avers that [Graham Taylor] has, in breach of contract and/or its fiduciary or professional duty to [Grande Studio] and without the knowledge or consent of [Grande Studio], made secret profits from its contracts with its sub-contractors/suppliers.
36 In particular, [Graham Taylor] has made secret profits of $69,136.27 from four of its contracts with its sub-contractor DH Decor Pte Ltd ...
23 The particulars allege secret profits of $49,291.73 from 75 of the contracts with suppliers. It is not disputed that the contract price between Grande Studio as supplier and Graham Taylor as contractor exceeded the contract price between Graham Taylor as main contractor and DH Decor as sub-contractor and between Graham Taylor and the suppliers by the sums alleged as secret profits. It is also not disputed that Mr Taylor a director of Graham Taylor is and has since a date prior to 16 March 1998 (the date of the memorandum) been a director and shareholder of DH Decor.
24 Mr Chia submitted that Graham Taylor owed a fiduciary duty to Grande Studio and could not take secret profits. He referred to Hudson`s Building & Engineering Contracts (11th Ed) at para 2-233 which has this statement:
Whenever a secret commission or bribe is given to an agent, whether directly in connection with the particular transaction or in such relation to it as to affect it, the consideration is corrupt and the transaction invalidated so far as the principal is concerned.
25 He also referred to Thornton Hall v Wembley Electrical Appliances Ltd [1947] 2 All ER 630. At p 634 Scott LJ said:
No authority is required to establish or emphasise the strictness with which these courts insist that a man must not put himself in a position where his interest and his duty conflict.
26 Grande Studio`s case as pleaded is not that any of Graham Taylor`s sub-contractors or suppliers had paid or agreed to pay Graham Taylor a secret commission or a bribe. Its case stated quite simply is that what it had to pay Graham Taylor as main contractor exceeded what Graham Taylor had to pay to DH Decor as sub-contractor and to the suppliers. The excess was about 5% in respect of three of the contracts for works and about 14% in the fourth contract. In the case of the materials and equipment the excess was about 11% to 14% in most cases.
27 In Thornton Hall a surveyor was engaged by the owner of a factory to prepare a specification of the repairs to be done to the factory and subsequently to supervise the work of repair done by the building company and to check its accounts. After the specification had been prepared but before the repairs had begun the surveyor became managing director of the building company. Scott LJ said at p 633:
It is next necessary to determine what, so far as relevant to the present claim, was the nature of the duties owed by Mr Thornton Hall in carrying out his work. On this question counsel for Mr Thornton Hall conceded (and, in our judgment, rightly conceded) that Mr Thornton Hall owed a duty by virtue of his engagement as quantity surveyor to the [factory owner] ... to see that the work specified in the schedule was not more extensive than the occasion required and also to see, in the course of supervising the work and checking the accounts, that the charges of the [building company] were in no way inflated. If this formulation is correct, then it seems to us too plain for argument that acceptance by Mr Thornton Hall of the post of managing director of the [building company] was as wholly inconsistent with his contractual obligations as it was with professional propriety ...
28 The surveyor`s interest as managing director of the building company was in conflict with his duty to the factory owner to supervise the repair works and to check the accounts submitted by the building company.
29 The facts before me are materially different. In March 1998 Graham Taylor was engaged to provide the services of consultants and project managers. In May 1998 it agreed to be employed as the main contractor and from that point of time letters of award were from time to time signed between Grande Studio as employer and Graham Taylor as contractor. Every letter of award stated the agreed price with a breakdown for the works to be executed or for the materials or equipment to be supplied and installed. In each case complained of the letters of award even disclosed that DH Decor was the sub-contractor for the works and identified the suppliers for the materials and equipment.
30 A contractor owes no duty to the employer not to make a profit whether secret or otherwise by sub-contracting out the works he has undertaken to execute. Unless the contract otherwise provides he is free to sub-contract out the works in whole or in part but he remains answerable to the employer and is entitled to be paid in accordance with the terms of the main contract.
31 The contractor`s interest in the sub-contractor or supplier however substantial is irrelevant and no question of conflict between his interest and his duty under the contract can arise. He can choose to execute the works or supply the materials and equipment himself which is what the contract with his employer often contemplates or he can sub-contract with others and if he does so at a lesser price he is under no obligation to account to the employer for the `profit` or difference.
32 In the case before me the main contract in each case discloses the identity of the sub-contractor or supplier and it must be clear that Graham Taylor was entitled to sub-contract out the works to the named sub-contractor and to purchase the materials and equipment from the named suppliers. The fact that Mr Taylor is a director of both Graham Taylor and DH Decor is irrelevant. Graham Taylor has made a profit and in my judgment it is not liable to account to Grande Studio for such profit.
33 Paragraph 39 of the defence states:
... [Grande Studio] further avers that [Graham Taylor] is not entitled to recover or retain its professional fees or the fees for the works undertaken by DH Decor Pte Ltd.
34 Graham Taylor`s reply in para 26 states:
[Grande Studio`s] Simon Wee was aware of the relationship of Mr Graham Taylor to DH Decor Pte Ltd. [Graham Taylor] had also by a letter dated 4 May 1998 to [Grande Studio] informed [Grande Studio] of Mr Graham Taylor`s directorship in DH Decor Pte Ltd and [Grande Studio] acquiesced to the appointment of DH Decor Pte Ltd as a sub-contractor for the project.
35 The letter of 4 May 1998 was admitted except that as Mr Chia said Grande Studio`s case is that it was received `about the time of commencement of proceedings` but he was unable to say whether it was before or after. He corrected himself to say it ` should be after `.
36 Mr Taylor said in his affidavit:
I had personally explained to [Grande Studio`s] Paul Law and Simon Wee that [Graham Taylor] were interior designers and consultants and not turnkey contractors and therefore a turnkey approach between [Graham Taylor] and [Grande Studio] was not possible. I also pointed out that an itemised budget had not been agreed upon and in any event, if [Graham Taylor] were to act as a main contractor, then a profit and attendance sum would be applied to each sub-contractor and supplier and payable by [Grande Studio].
37 He referred to Graham Taylor`s letter dated 29 April 1998 which has been earlier referred to. He then said:
Prior to the appointment of DH Decor Pte Ltd [as Graham Taylor`s sub-contractor], I had verbally informed Simon Wee that I was a director and shareholder of DH Decor Pte Ltd and that for this reason it would be preferable to use DH Decor Pte Ltd as the sub-contractor for the project wherever possible. Further, Simon Wee has social contacts with me and Henry Choo Chin Beng, the other director and shareholder of DH Decor Pte Ltd, and was well aware of my relationship with DH Decor Pte Ltd
.In any event, [Graham Taylor] did on 4 May 1998 write to formally inform [Grande Studio] of my relationship with DH Decor Pte Ltd.
38 The letter he referred to is the letter referred to in para 26 of Graham Taylor`s reply.
39 Under cross-examination Mr Taylor said:
Q: Taylor (1). Para 15. Sentence 3. If Simon Wee well aware why you had to tell him?
A: My company policy to always make disclosure my interests in contractor if contractor used in our projects.
Q: Social contacts?
A: Socialised with him at his bar he was running at East Coast. Met him socially for golf together with Henry Choo and another of the suppliers for the project.
40 Mr Linwood said in his affidavit:
As [Grande Studio] wished to run the project similar to one on a turnkey basis, [Graham Taylor] did on 4 May 1998 (before any of the letters of award were signed by [Grande Studio]) write to inform [Grande Studio] that DH Decor Pte Ltd would be the preferred sub-contractor where possible. This was because Graham Taylor was a director of DH Decor Pte Ltd and this would provide [Graham Taylor] with a large degree of control during the works.
41 He referred to the letter dated 4 May 1998 also which is the letter referred to in para 26 of Graham Taylor`s reply. It was not put to him that the letter was not sent until after these proceedings had commenced. No evidence was given by any of Grande Studio`s witnesses as to this letter.
42 On the evidence before me I find that Mr Taylor did inform Mr Wee that he was a director and shareholder of DH Decor and that he did so before DH Decor was appointed Graham Taylor`s sub-contractor. I further find that Graham Taylor`s letter of 4 May 1998 was sent before any of the letters of award was signed by Grande Studio by which Graham Taylor was employed as the main contractor. The letter states:
Further to my letter of 29 April 1998 and our subsequent telephone call, if you insist the project is run on a `turnkey` basis then we would prefer to use DH Decor Pte Ltd as our sub-contractor where possible.
Graham Taylor is a director of the company (although he is not involved in the day-to-day running of the business) and this should provide us with a large degree of control during the works.
43 The letter was written by Mr Linwood and addressed to Grande Studio for the attention of Mr Wee. Grande Studio was informed by Mr Taylor and by letter and it was aware of Mr Taylor`s interest in DH Decor when it employed Graham Taylor on terms that DH Decor would be the sub-contractor.
44 In Thornton Hall Scott LJ said at p 634:
It is, however, equally well established that breach of fiduciary obligations such as the present contract imports may be waived by the other party to the contract who has full knowledge of the circumstances. If at the time of Mr Thornton Hall`s appointment as agent for the [factory owner] at the beginning of Aug 1944, Mr Thornton Hall had been managing director of the [building company], and that fact had been known to the [factory owner], the latter company could not thereafter have complained of the conflict of Mr Thornton Hall`s duty with his interest. On the footing that the contract of agency was one and indivisible, is the position different where the agent assumed his equivocal position, with the knowledge of, and without any objection from, the principal, in the middle and not at the beginning of the engagement? ... In our judgment, the correct inference is that the [factory owner] must be taken to have acquiesced in his continuing as its quantity surveyor, notwithstanding the conflict of his duty and his interest.
45 I think the position would not be any different if before the building company was employed to execute the repair works the surveyor was its managing director and that fact had been known to the factory owner.
46 I return to the facts of this case. It was Graham Taylor which was appointed and which was Grande Studio`s agent. It was Graham Taylor the corporation which owed a duty to Grande Studio but a corporation can only act by its servants and agents. It was Mr Taylor who had an interest. Assuming for the present purpose that it can be said that Mr Taylor was in a position where his interest and his duty were in conflict or alternatively that Graham Taylor was in a position where its interest (through Mr Taylor) and its duty were in conflict then given that Grande Studio had knowledge of that interest the inference must be that Grande Studio has acquiesced in the employment of DH Decor as sub-contractor by Graham Taylor as main contractor. But in my opinion the principle in Thornton Hall cannot apply to the facts of this case. Graham Taylor was employed as the main contractor after it had been employed as consultant and while it was so employed but this is not what Grande Studio is complaining of. As I have pointed out above Graham Taylor as the main contractor could have executed the works itself and if it could do so it could also have sub-contracted the works out to DH Decor (as it has done) whether or not it had or any of its directors had any interest in DH Decor and whether or not Grande Studio knew about the interest.
47 Paragraphs 18 and 19 of the defence state:
18 .... it was an express term of the contract that the works would be completed by 31 May 1998 as stipulated in Appendix B of the [memorandum], which is the Programme of Works. Further or alternatively, [Graham Taylor] negligently represented that the works would be capable of completion by 31 May 1998.
19 In breach of contract and negligently, the works were not completed by 31 May 1998.
48 As to the alleged representation I should observe that no particulars of any representation are supplied and there is no allegation that the representation was false. It is also not clear what fact is alleged to have been represented if this is a claim in misrepresentation unless it is intended as a claim in negligence. However no particulars of any negligence are supplied. Counsel has not in any case made any submission on the alleged negligent representation or negligence or on misrepresentation.
49 I turn now to the alleged breach of contract. The contract referred to is clearly the contract contained in the memorandum dated 16 March 1998 as amended by the terms of Graham Taylor`s letter of 25 March 1998. Under this contract Graham Taylor did not undertake to execute any works much less to complete the works by 31 May 1998. It was only on 4 May 1998 that Graham Taylor agreed to be the main contractor and following that between 5 May 1998 and 18 July 1998 nine letters of award for the works were signed between the parties but Grande Studio is not referring to this agreement made on 4 May 1998 or any of the agreements evidenced by or contained in the letters of award. In any case one of the letters of award dated 18 July 1998 provides for completion by 27 July 1998 in relation to partitions and shell works and by 15 August 1998 in relation to the other works. The grounds of defence alleging breach of contract and negligence or negligent misrepresentation have not been proved and I find accordingly.
50 Paragraph 8 of the statement of claim states:
The interior and M & E works for the project (excluding those for the KTV rooms) were completed and handed over to [Grande Studio] by [Graham Taylor] on 14 August 1998 and [Grande Studio] commenced business on 14 August 1998. The interior and M & E works for the KTV rooms were completed and ready to be handed over to [Grande Studio] on 17 August 1998 but the handover was postponed at [Grande Studio`s] request to 21 August 1998 when the handover took place.
51 Grande Studio admits that the works excluding those for the KTV rooms (`KTV works`) were handed over and Grande Studio commenced partial operations on 14 August 1998 but denies that the works were completed. It also admits that the KTV works were handed over but says that it was on 16 September 1998.
52 Grande Studio alleges that it took over the works on 14 August 1998 and 16 September 1998 subject to outstanding works and defects and further that it took over the KTV works in order to mitigate its loss and to expedite the completion of the works and rectification of the defects. Finally it alleges that Graham Taylor failed to complete the outstanding works or rectification of the defects. The alleged outstanding works and defects are set out in Annex 1 containing 138 items and Annex 2 containing 26 items for the works (other than KTV works) and in Annex 3 containing 108 items for KTV works.
53 As to the works (other than the KTV works) Graham Taylor denies that they were not completed (except for an item relating to general cleaning before handing over) and says that all the other items in Annex 1 and Annex 2 were defects to be rectified upon practical completion. As to the KTV works Graham Taylor denies that they were not completed and says that all the items in Annex 3 were defects to be rectified upon practical completion. Graham Taylor further says that a large number of items had been rectified and that on or about 12 September 1998 Grande Studio refused to allow further access to the premises for rectification works to be executed.
54 On 13 August 1998 Graham Taylor wrote:
As previously agreed our representatives were on site at 5pm on Tuesday 11 August 1998 for the handover of the Main Hall Works.
You informed us that you are unable to accept handover as you required your quantity surveyor to sign off the works.
Despite your refusal to accept handover, we documented numerous Grande Star East staff occupying the premises.
Once again, this represents defacto practical completion and we therefore enclose our practical completion certificate and defect list to this effect.
55 The practical completion certificate stated that practical completion was achieved on 10 August 1998.
56 Mr Linwood said in his affidavit that on 14 August 1998 when the works (other than the KTV works) were handed over the whole of the works were practically completed. One of the items of defects related to the epoxy paint to be applied to parts of the floor. Under cross-examination he agreed that part of the floor to be painted had not been painted. He said:
A: ... By this date [13/8/98] client already occupied this space. Also client`s sub-contractor AV Suppliers also carrying out extensive work in this area. Would therefore have been extremely difficult to paint floor. I discussed with Simon Wee and would wait until after opening. When AV Suppliers had finished. During daylight hours disco empty.
Q: At 13/8/98 floor adjacent to dance floor sufficiently dry for epoxy paint to be applied?
A: I couldn`t be sure at the time.
57 It was also admitted that part of the paint work had flaked off.
58 It is not disputed that epoxy paint could only be applied when the floor was sufficiently dry. This would have taken some time. Mr Linwood said he could not be sure the floor was sufficiently dry even though the moisture level was measured seven to ten days earlier. There were other trades in possession of the premises and this interfered with Graham Taylor`s work. Grande Studio`s staff were already in occupation. After the handover of the works the areas to be painted were carpeted instead by Grande Studio and in the circumstances I have treated the items relating to painting of parts of the floor as having been varied or omitted and disallowed this part of the price of the works.
59 Mr Lim Kah Soo, a quantity surveyor, said in his affidavit that he inspected the premises on 12, 13, 14 and 18 August 1998. He prepared a preliminary report dated 14 August 1998 and a detailed report dated 18 August 1998 for works other than the KTV works and another detailed report also dated 18 August 1998 for the KTV works. He said in his affidavit:
From my inspection, I am of the opinion that the works (within the scope of my appointment) were not ready for handing over because of the items listed in my reports.
60 Mr Lim Kah Soo identified what he called the main items which have a bearing on the operations of the entertainment centre. Some of these items were:
C) The Wine Bar
b) Wall leading to kitchen: Painting not properly done, to be repainted.
D) Artists Changing Rooms
b) Some cracked floor tile to one toilet needs replacement.
F) The Store Next To Office
a) The wall cracks have to be patched up.
H) The Fire Escape Passage At Goods Lift Lobby
a) The walls are not painted.
I) Fire Escape Behind KTV Rooms
a) Painting to wall and ceiling in progress.
61 I am not sure what bearing these items would have on the operations of the entertainment centre.
62 Mr Lim Kah Soo also included works which were not within Graham Taylor`s scope of works. Under cross-examination he said:
Q: Aware some of items not in plaintiff`s scope of works?
A: Yes. Aware.
Q: Yet listed as part of plaintiff`s works?
A: When I made report I was not fully informed of plaintiff`s scope of works. This qualification stated in my report. Lim (1). Page 66. Item 4.2.
Q: Lim (1). Para 7(a). State of completion of these works would also have bearing on operation of club?
A: Yes.
63 Paragraph 7(a) related to mechanical installations, audio/video equipment, sound and stage lightings, kitchen equipment and the operator`s [Grande Studio`s] equipment.
64 I have referred to the omission and failure of the epoxy painting and I have also referred to Mr Lim Kah Soo`s evidence. The real issue as pleaded however is not whether the works were ready for handing or were completed. Grande Studio did take over the works and it did so subject to outstanding works and defects (as it alleges) and Mr Chia conceded (in my opinion quite properly so) that at 14 August 1998 (when the works other than the KTV works were taken over) and at 16 September 1998 (when as Grande Studio alleges it took over the KTV works) the contract between the parties was still in force and not terminated. If the works were not completed or were defective Graham Taylor was bound to complete or to rectify.
65 On 12 September 1998 Grande Studio wrote to Graham Taylor:
I understand that you have made arrangements for the carpenters to rectify the table tops today at 11am.
As we have informed you, no further access to our premises for rectification works or otherwise will be granted to [Graham Taylor] and/or their contractors.
All rights are reserved herein.
66 The contract was still in force and Graham Taylor was bound to carry out rectification works and as alleged by Grande Studio other works as well to complete the contract works but access to the site has been denied.
67 In my judgment Graham Taylor is entitled to be paid the balance of its fees under the memorandum and the balance of the price of the works executed under the agreement made on 4 May 1998 and the letters of award and the orders for additions and variations. There were variations as regards the epoxy paint and defects which ought to have been rectified and there were some omissions. I considered the evidence and with the assistance of counsel assessed these variations, defects and omissions at $76,036 and gave judgment accordingly.
68 Outcome:
69 Plaintiffs` claim allowed.
Lim Teong Qwee JC
Felicia Ng and Yeo Piah Chuan (Piah Tan & Partners) for the Plaintiffs
Chia Ho Choon and Rowena Chew (Bih Li & Lee) for the Defendants