Loh Kam v Gibson Engineering (S) Pte Ltd
[1999] SGHC 37
DC Suit 1446/1998, RA 300149/1998
Lim Teong Qwee JC
08 February 1999
Judgment:
GROUNDS OF JUDGMENT
1. This is an appeal from the decision of a district judge who gave the defendant unconditional leave to defend this action. I allowed the appeal and gave judgment for the plaintiff for the amount claimed in the summons for summary judgment with interest and costs. Counsel for the defendant then intimated that inquiries and searches for documents were being made with a view to adducing further evidence and in the circumstances I granted a stay of execution for a week. There has been no application to adduce further evidence but the defendant has given notice of appeal.
2. Part of the plaintiff’s claim is for balance of price for sanitary and plumbing installation works for the proposed condominium housing development at Lot 644 Pt of Mukim 27. This is the part comprised in the summons for summary judgment but for convenience I shall refer to it as the plaintiff’s claim. The main contractor for the development was Mitsui Construction Co Ltd ("Mitsui Construction"). The defendant was its sub-contractor for part of the works in the development and the plaintiff was the defendant’s sub-contractor for part of the sanitary and plumbing installation works. The sub-contract between the parties ("plaintiff’s sub-contract") is contained in or evidenced by the defendant’s letter of award dated 5 October 1995 which the plaintiff confirmed by an acknowledgment dated 15 February 1996.
3. The development was in two phases. Phase I comprised three blocks of housing units and phase II comprised four blocks. The scope of works under the plaintiff’s sub-contract related to one block of 227 housing units in phase II. The defendant also sub-contracted with the plaintiff in DC Suit No 50251 of 1998 for similar works in relation to 494 housing units in phase I and with another party for similar works in relation to two of the other blocks in phase II. The defendant itself undertook the works in relation to the remaining block in phase II.
4. The plaintiff’s sub-contract was for a lump sum price of $635,600 which was not "subject to any re-measurement, adjustment or alteration in any way whatsoever". Clause 2 provides:
"The Scope of Sub-Contract Works generally comprise of supply labour to install Sanitary and Plumbing System, installation of all sanitary wares, fittings and accessories (supplied by the owner/nominated supplier/main contractor), all as shown in the drawings and specifications, to the satisfaction of the Architects/Consulting Engineer.
(a) Take delivery, check, store and protect all sanitary wares and fittings supplied by the Nominated Supplier/The owner. All losses and damages of goods taken over by you shall be replaced at your own costs. (b) Clear all rubbish, crates, packing cases arising from your own Sub-Contractor’s work including Nominated Suppliers of sanitary wares and fittings from time to time to the designated locations as directed by our site representative."
Clause 15 provides:
"You shall submit your progress claim one (1) week before the end of each calender month. Payment shall be paid on the 12th & 28th of each calender month. Retention shall be as follows: Retention Sum : 10.0% Maximum Retention: 5.0% Release of Retention: 2.5% after obtaining Certificate of Completion issued by the Architect. 2.5% after Maintenance Period or Certificate of Making Good Defects issued by the Architect, whichever is the later."
Clause 9 provides:
"The maintenance period shall be 3 months commencing from the date of Completion Certificate issued by the Architect. On handing over, you shall provide free regular maintenance and servicing of the equipment and installation within Maintenance Period."
5. The plaintiff has received interim payments for the works and as appears from the certificate for the last progress claim issued on 24 February 1997 the total claim was $526,946 and the 10% retention sum was $52,694.60 leaving a balance of $474,251.40 of which the plaintiff had been paid $472,143.54 leaving $2,107.86 as the amount of the progress claim payable to the plaintiff when the certificate was issued. The certificate was issued by the defendant itself. In accordance with the payment terms under cl 15 the maximum retention was 5% so that if there were no more works to be executed under the sub-contract half of the 10% retention sum should have been paid. It was not. On 6 March 1997 the defendant paid the final progress claim of $2,107.86.
6. On 8 August 1997 the architect issued his certificate of completion for the works in phase I completed on 25 October 1996 and for the works in phase II completed on 20 December 1996. The sub-contract is only concerned with phase II works and in accordance with the terms of payment 2.5% ie one-quarter of the 10% retention sum became payable. This was also not paid. Nothing was paid at all.
7. The maintenance period of three months under cl 9 expired on 8 November 1997 and it is not the defendant’s case that the architect had not issued his certificate of making good defects or that such a certificate was going to be issued. In accordance with the payment terms the remaining one-quarter of the retention sum became payable. By this time the whole of the retention sum of $52,694.60 had become due and payable to the plaintiff.
8. Mr Foo Say Han the general manager of the defendant said in his affidavit of 14 July 1998:
"10.3 During the course of the Project, the main contractor had notified the defendants of various incomplete and defective works which the plaintiff was contractually obliged to carry out on behalf of the defendants. As a result of the plaintiff failing or refusing to carry out such incomplete and defective works, [Mitsui Construction] carried out these and charged the defendants for the same.
11.2 The defendants verily believe that the plaintiff is liable for the said sum of $17,177.00 which is worked out as follows:
a. Total number of defects and/or incomplete works which Mitsui has indicated, which is relevant for this present proceedings, in their ‘Grand Summary of Responsibility and Charge for day work (Done by MCC)’ is 1180. b. Total amount claimed by Mitsui is $227,708.93. c. Unit costs of defect and/or incomplete works = $227,708.93 / 1180 = $193.00. d. The plaintiff liability based on the defendants’ compilation is 89 items of defective and/or incomplete works. e. The plaintiff is therefore liable to the defendants as follows: $193.00 x 89 = $17,177.00."
He also referred to other claims for incomplete or defective works amounting to another $60,797.65.
9. The defendant’s case is that it has a counterclaim which exceeds the claim. It is alleged that the counterclaim arises out of incomplete or defective works. It was acknowledged at the hearing before me that there were no notices from the architect concerning any part of the works comprised in the plaintiff’s sub-contract. There were no notices in respect of any incomplete or defective works.
10. The plaintiff had received the certificate for the last progress claim by February 1997. As pointed out above it was issued by the defendant itself. The defendant paid all the progress claims for the works except the retention sum. It paid without any reservation. There was no more work to be done. The plaintiff would have substantially demobilised. He would have handed over the works upon the issue of the certificate of completion. He would have been out of possession of the site and would not have been in any position to exercise any control over the completed works.
11. The defendant seeks to counterclaim various sums for the alleged incomplete or defective works amounting to some $77,000 on the basis of the calculations it has made. These calculations were made in respect of claims which the defendant said had been made against it by Mitsui Construction. The claims were made between May and June 1997. There was no allegation that the defendant had paid these claims or that any amount had been deducted from sums due to it under its sub-contract with Mitsui Construction.
12. It was the plaintiff who uncovered and produced a copy of a letter from Mitsui Construction. The letter is dated 30 December 1997. It refers to a meeting on 30 December 1997 and continues:
"We would like to finalize that the remaining total deduction is S$100,000.00 and this amount will be deducted from your retention monies of Nominated Sub-Contract work. Therefore, this is to confirm that we have discharged and paid all outstanding balances on the above project except for the balance retention monies and variations which should be evaluated by the consultants and that no further claims exist between Gibson and Mitsui Construction ...."
An invoice for $100,000 was forwarded with the letter. The settlement was confirmed by Mr Foo the same day and he signed on the letter. Even if claims had been made by Mitsui Construction the defendant’s loss was limited to $100,000 but the $100,000 loss was arrived at on the basis of what appears to be an overall lump sum settlement. It is not possible on the materials before me to say if any and if so what part of the loss is attributable to any part of the works in the plaintiff’s sub-contract. Above all the defendant was itself executing works under its sub-contract with Mitsui Construction including works similar to those under the plaintiff’s sub-contract and the plaintiff was not at any time at all aware of the negotiations for the settlement and was not a party to it.
13. The defendant has not satisfied the court that there is any issue or question in dispute with respect to the plaintiff’s claim or any part of it. The plaintiff is entitled to payment under the terms of the sub-contract upon the expiry of the maintenance period. The evidence adduced by the defendant in support of the counterclaim does not satisfy the court that there ought for any reason at all to be a trial of any part of the plaintiff’s claim. In my judgment the plaintiff ought to have judgment. He has been kept out of his money and also out of the site long enough. I allowed the appeal and ordered accordingly.
Dated this 8th day of February 1999.
LIM TEONG QWEE
JUDICIAL COMMISSIONER