This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

IN THE SINGAPORE INTERNATIONAL COMMERCIAL COURT

OF THE
REPUBLIC OF SINGAPORE
[2024] SGHC(I) 3
Originating Application No 1 of 2023
Between
Reliance Infrastructure Limited
Claimant
And
Shanghai Electric Group Co Ltd
Defendant
JUDGMENT
[Arbitration — Award — Recourse against award — Setting aside]
[Arbitration — Agreement — Separability]
[Arbitration — Conduct of arbitration — Waiver of objections]

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Reliance Infrastructure Ltd

v

Shanghai Electric Group Co Ltd
[2024] SGHC(I) 3
Singapore International Commercial Court — Originating Application No 1 of 2023
Philip Jeyaretnam J, Sir Vivian Ramsey IJ and Anselmo Reyes IJ
11–12 January 2024
31 January 2024  Judgment reserved.
Philip Jeyaretnam J (delivering the judgment of the court):
Introduction
1 When a company receives a claim on a contract of which it has no record and where its purported signatory has ceased to be its employee, does it waive any jurisdictional objection to the arbitration based on forgery of the arbitration agreement if it unsuccessfully defends the arbitration without alleging forgery? If it contests the claim on its merits with the defence that the contract was entered into by its employee without authority, but without specifically alleging that the arbitration agreement contained in the contract was itself made without authority, can it after the award is given against it raise a jurisdictional challenge that the arbitration agreement was made without authority? These were the principal questions that arose in this challenge to an arbitration award.
2 The claimant in this application seeks to set aside an award of an arbitral tribunal (“the Tribunal”) dated 8 December 2022 (“the Award”), which awarded damages in favour of the defendant. The Tribunal’s putative jurisdiction was based upon an alleged arbitration agreement between the Parties contained in a letter dated 26 June 2008 (“the Guarantee Letter”) within which the claimant had purportedly guaranteed the sums owed to the defendant in another related contract. The claimant had disputed the legal validity of the Guarantee Letter during the arbitration, but the Tribunal was unconvinced by that submission.
3 Upon challenge of that Award before this court, our task is to determine whether the claimant has waived its rights to adduce the following challenges before us – (1) that the defendant had forged the signatures of its former officer, Mr Rajesh Agrawal, on the Guarantee Letter; and (2) in the alternative, if he did sign it, that Mr Agrawal had no authority to bind the claimant to an agreement to arbitrate with the defendant.
Background
Factual background of the dispute
The parties
4 The claimant seeking to set aside the Award is Reliance Infrastructure Limited (“Reliance Infrastructure”), a company incorporated in the Republic of India, and the defendant, Shanghai Electric Group Co Ltd (“Shanghai Electric”), was incorporated in the People’s Republic of China.
5 Both Parties had been involved in a major construction project for an electricity generating power plant in Sasan Village, India (“the Sasan Project”), and it is from the Sasan Project that this dispute between the Parties arose.
The Supply Contract between Reliance (UK) and Shanghai Electric
6 On 24 June 2008, the owner of the Sasan Project, an Indian company known as Sasan Power Limited (“Sasan Power”), entered into a contract with an English company, Reliance Infra Projects (UK) Limited (“Reliance (UK)”), that is related to Reliance Infrastructure (“the Sasan Project Contract”). Under the Sasan Project Contract, Reliance (UK) was to procure for Sasan Power the supply of equipment and services needed for the Sasan Project.
7 On 26 June 2008, Reliance (UK) and Shanghai Electric then entered into a contract that provided for Shanghai Electric to supply the requisite equipment and services for the Sasan Project (“the Supply Contract”). It was Mr Agrawal, Reliance Infrastructure’s Additional Vice–President at the material time, who signed the Supply Contract on behalf of Reliance (UK).
8 Although Reliance (UK)’s board of directors had provided express authorisation for Mr Agrawal to execute the Supply Contract with Shanghai Electric by passing a board resolution to that effect, there is no evidence in the record indicating that that board resolution had ever been furnished to Shanghai Electric as the grounds of Mr Agrawal’s authority to do so. The validity of the Supply Contract is not a matter of dispute between the Parties.
9 The final version of the Supply Contract did not contain any ‘parent company guarantee’ clause, owing to a request from Mr Agrawal to Shanghai Electric on 25 May 2008 seeking the deletion of such a clause.
10 It is undisputed that Mr Agrawal had been involved in the negotiations over the Supply Contract, although the nature of his involvement is disputed. While Reliance Infrastructure characterises his role as a purely facilitative one of coordinating the negotiations between the Parties’ senior managements, Shanghai Electric argues instead that he led the negotiations between them and all entities within the wider Reliance Group (including Reliance Infrastructure) in relation to multiple power plant projects they were both involved in, inclusive of the Sasan Project.
The events surrounding the disputed Guarantee Letter between Reliance Infrastructure and Shanghai Electric
11 Unlike with the Supply Contract, the validity of the Guarantee Letter was put in issue in the underlying arbitration, and remains a matter of dispute before us. We summarise here the relevant facts that surrounded the execution – or alleged execution – of the Guarantee Letter between the Parties.
12 On 9 February 2007, Reliance Infrastructure, under its previous name: Reliance Energy Limited, agreed to indemnify Shanghai Electric in relation to claims that the owner of another power plant project in Hisar, India may institute against Shanghai Electric for any matters relating to that project (“the Hisar Indemnity”).
13 Paragraph 6(b) of the Hisar Indemnity contained an agreement to arbitrate disputes between the Parties, and it was Mr Agrawal who signed the Hisar Indemnity on behalf of Reliance Infrastructure (as Reliance Energy Limited).
14 On 20 May 2008, the Parties entered into a Framework Agreement that established that “[t]he Purchaser shall provide suitable guarantee letter from its parent company acceptable to the Contractor”. Ex facie, that “Purchaser” was defined as referring to Reliance Infra Projects International Limited (“RIPIL”), while “Contractor” was defined as a reference to Shanghai Electric. At that time, Reliance (UK) was the wholly–owned subsidiary of RIPIL while Reliance Infrastructure held 10% of the shareholding of RIPIL (with the remaining shares being held by other Reliance Group entities).
15 While Mr Agrawal did not sign the Framework Agreement for Reliance Infrastructure, he did initial at the bottom of every page thereof. Paragraph 3.7 also contained an agreement to arbitrate disputes between the Parties.
16 On 23 June 2008, another officer of Reliance Infrastructure sent an email to Shanghai Electric, copying Mr Agrawal, with an attached draft of a guarantee letter dated 25 June 2008. Under that draft guarantee, Reliance Infrastructure would have guaranteed the performance of Reliance (UK)’s obligations owed to Shanghai Electric under another contract, which related to a different power plant project in India that was owned by the Damodar Valley Corporation (“the DVC Draft Guarantee”).
17 Paragraph 10 of the DVC Draft Guarantee contained an agreement to arbitrate disputes between the Parties, but the draft was never executed by the Parties.
18 On 26 June 2008, the Guarantee Letter was allegedly signed by Mr Agrawal on behalf of Reliance Infrastructure at a signing ceremony in Shanghai, China. According to Ms Yu Liwen, who was Shanghai Electric’s sales and business development manager at the time, she printed out the Guarantee Letter, delivered it to Mr Agrawal, and then witnessed him sign it.
19 According to Ms Yu, Mr Agrawal attended that ceremony on behalf of the senior management of the Reliance Group, as said to be demonstrated by the contents of Mr Agrawal’s speech which he delivered thereat.
20 In the Guarantee Letter, Reliance Infrastructure guaranteed (or is alleged to have guaranteed) the performance of Reliance (UK)’s obligations owed to Shanghai Electric in the Supply Contract. Paragraph 10 contained a putative agreement to submit all disputes between the Parties to arbitration, seated in Singapore, and administered by the Singapore International Arbitration Centre (“SIAC”).
21 On 4 July 2008, Mr Agrawal sent an email to Shanghai Electric’s Vice–President, with an enclosed letter relaying various requests made by the Damodar Valley Corporation and proposing a contractual assignment for Shanghai Electric’s acceptance. That letter was signed by Mr Agrawal, who was described therein as an “Authorized Signatory” for Reliance Infrastructure.
22 On 26 August 2008, Mr Agrawal sent an email to Shanghai Electric, in which he discussed two other power plant projects in India, viz, the Butibori and Krishnapattnam Projects. In relation to both projects, he wrote, “RIL Guarantee Letter similar to Sasan would be given for Reliance Infra behalf”.
Procedural background of the dispute
SIAC arbitration proceedings
23 The underlying SIAC–administered arbitration arose out of outstanding payments alleged by Shanghai Electric to be owed to it by Reliance (UK), that went unpaid and in alleged breach of the Supply Contract. Shanghai Electric invoked the arbitration agreement in Paragraph 10 of the Guarantee Letter and sought enforcement of Reliance Infrastructure’s guarantee of Reliance (UK)’s liabilities under the Supply Contract.
24 In response, Reliance Infrastructure pleaded that the Guarantee Letter was invalid, because it was not aware of its existence, and Mr Agrawal had no authority to execute it. However, Reliance Infrastructure did not expressly put in issue that Mr Agrawal’s signature on the Guarantee Letter was a forgery, nor did it expressly plead that the Tribunal lacked jurisdiction over the dispute.
25 In opening submissions to the Tribunal on 6 September 2021, Reliance Infrastructure made clear that it was not alleging that the Guarantee Letter was a forgery. Reliance Infrastructure never adduced any witness statements of Mr Agrawal nor any handwriting expert evidence during the arbitration to show that the Guarantee Letter was a forgery.
26 Then, on the last day of oral closing submissions, 21 January 2022, the Tribunal asked Shanghai Electric if the letterhead of Reliance Infrastructure on the original Guarantee Letter was embossed or computer-–generated. Shanghai Electric’s counsel clarified in an email to the Tribunal dated 30 January 2022 that the original Guarantee Letter, inclusive of the letterhead, had been printed in black–and-–white.
27 In light of that development, Reliance Infrastructure’s counsel sent an email to the Tribunal on 4 February 2022 alleging that these fresh facts as to how the Guarantee Letter had been printed meant that it “would prima facie constitute the making of a ‘false instrument’” and “appears to be a nullity (as all forgeries are nullities)”.
28 In response to the Tribunal’s query as to the “specific findings” Parties wished for the Tribunal to make in respect of the Guarantee Letter, Reliance Infrastructure took the position that the newly disclosed facts meant “[t]hat the provenance of the purported Guarantee Letter … is in serious question” and prayed for “a declaration that the purported Guarantee Letter is invalid and unenforceable”.
29 Reliance Infrastructure’s updated Schedule of Issues did put in issue the general question “[w]hether the purported Guarantee Letter is valid, enforceable and binding”, but it did not expressly put into issue the question whether the signatures on the Guarantee Letter were forgeries, nor did it expressly object to the jurisdiction of the Tribunal or the validity of the arbitration agreement.
30 Hence, the Tribunal held that Reliance Infrastructure did not put in issue whether the Guarantee Letter was a forgery and must be taken to have conceded that the Guarantee Letter existed.
31 In contrast, Mr Agrawal’s authority to sign the Guarantee Letter was put in issue, and on this point, the Tribunal found that Mr Agrawal had apparent authority to sign the Guarantee Letter on Reliance Infrastructure’s behalf.
32 Ultimately, the Tribunal’s Award ordered Reliance Infrastructure to pay damages to Shanghai Electric for outstanding payments that were due under the Supply Contract. The Award affirmed some of Reliance Infrastructure’s set–offs against the sums owed to Shanghai Electric while disallowing others.
Setting aside proceedings
33 Now that Reliance Infrastructure is attempting to set aside that Award, it wishes to rely upon fresh evidence which was never put before the Tribunal, viz, the evidence of Mr Agrawal averring that he did not sign the Guarantee Letter, and the report of a handwriting expert, Mr Manas Mishra, who opines that the initials and signature of Mr Agrawal found on the Guarantee Letter are all forgeries.
34 By consent of the Parties, we allowed the following five witnesses to be cross–examined before us on 11–12 January 2024 (see this Court’s order dated 6 October 2023 on SIC/SUM 42/2023) –
(a) Mr Neeraj Parakh, Reliance Infrastructure’s Senior Executive Vice–President, who gave evidence on the claimant’s knowledge and its basis for believing the Guarantee Letter to be a forgery;
(b) Mr Agrawal, who testified that he never signed the Guarantee Letter;
(c) Ms Yu, who gave evidence that she saw Mr Agrawal sign the Guarantee Letter;
(d) Mr Manas, who gave his expert opinion that the signatures on the Guarantee Letter were forgeries; and
(e) Ms Lee Gek Kwee, who gave her expert opinion to the contrary – ie, that those signatures were genuine.
35 There was initially a sealing order preventing the disclosure of Parties’ identities in this proceeding (see this Court’s order in SIC/ORC 34/2023 dated 16 June 2023), this being the default position for all proceedings under the International Arbitration Act 1994 (“IAA 1994”) (see s 22(1) of IAA and The Republic of India v Deutsche Telekom AG [2023] 2 SLR 77 (“Deutsche Telekom (Confidentiality of Arbitration)”) at [16]).
36 However, upon considering the Parties’ cases before us, especially Reliance Infrastructure’s serious allegations of forgery that it levelled against Shanghai Electric, we considered that a compelling public interest may be said to exist in respect of the Parties’ identities. In this Court, Reliance Infrastructure has alleged forgery against Shanghai Electric. If true, this is conduct of a kind that the international business community should know about. Conversely, if allegations of forgery are made without proper basis, those too should be known about. In addition, there has been litigation in India that is publicly known: see the proceedings between Parties before the Delhi High Court (Shanghai Electric Group Co Ltd v Reliance Infrastructure Ltd on 19 July 2022, O.M.P. (I) (Comm.) 433 of 2020). It could be said that the confidentiality of the underlying arbitration has already been lost, potentially rendering our sealing order “an empty exercise to protect confidentiality when there is nothing left to protect” (see Deutsche Telekom (Confidentiality of Arbitration) at [28]).
37 We expressed our preliminary views to Parties on the second day of the hearing, 12 January 2024, and sought their responses. After consideration, both Parties agreed to this judgment being published unredacted. Accordingly, we lifted our sealing order by consent to this extent (see s 23(3)(a), IAA 1994).
The parties’ cases
Reliance Infrastructure’s case
38 Reliance Infrastructure now seeks the setting aside of the Tribunal’s Award on the grounds that the Tribunal lacked jurisdiction due to the invalidity of the arbitration agreement (Art 34(2)(a)(i), UNCITRAL Model Law on International Commercial Arbitration (adopted on 21 June 1985) (“Model Law”)), that the Award was affected by Shanghai Electric’s fraud (s 24(a), IAA 1994), and being affected by such fraud, the Award is contrary to the public policy of Singapore (Art 34(2)(b)(ii), Model Law).
39 The factual basis for Reliance Infrastructure’s legal grounds to set aside the Award are its allegations that Shanghai Electric forged the Guarantee Letter or that, if his signature was not forged, Mr Agrawal nonetheless lacked authority to execute it.
Non–waiver of Reliance Infrastructure’s jurisdictional objections
40 According to Reliance Infrastructure, it has not waived its objections to the Tribunal’s jurisdiction, on the grounds of forgery and absence of authority, within the meaning of Art 16(2) of the Model Law. It did not waive its right to allege forgery because it lacked actual knowledge of the facts required to plead its case of forgery. It only learnt from Mr Agrawal that he had never signed the Guarantee Letter in early 2023, after the Award had already been published. Before that point, Reliance Infrastructure could not obtain the co–operation of Mr Agrawal because he was working for its competitor, Adani Group, and he feared that divulging any information would render him in breach of contractual obligations owed to his new employer. After it learnt of the forgery for the first time, it made a timely application to set aside the Award on that ground.
41 Turning to lack of authority, Reliance Infrastructure argues that it did not waive its right to object to jurisdiction on the ground of Mr Agrawal’s want of authority, since it did put in issue that Mr Agrawal was never authorised to sign the Guarantee Letter during the arbitration proceeding, and it was not necessary to expressly frame that argument as an objection to jurisdiction since its arguments that Mr Agrawal lacked authority to make the Guarantee Letter were co–extensive with its arguments that he lacked authority to make the arbitration agreement which was contained therein.
Allegation that the Guarantee Letter was forged
42 To support its allegation of forgery made before this court and not in the arbitration, Reliance Infrastructure relies on two items of fresh evidence. The first is the testimony of Mr Agrawal that he never signed the Guarantee Letter, which it regards as credible direct evidence of such forgery from a neutral witness.
43 The second item of fresh evidence is the forensic report of its handwriting expert, Mr Manas. His opinion is that the signature was forged. Reliance Infrastructure characterises it as a detailed report employing a thorough methodology, with clear explanations of how Mr Manas arrived at his expert opinion that the disputed signatures on the Guarantee Letter were forgeries, when compared to his admitted signatures on other documents.
44 In addition, Reliance Infrastructure points to other external circumstances to support its claim of forgery, including non–compliance with internal company procedures, non–compliance with regulatory requirements in Indian law, the absence of contemporaneous documentation, the removal of a ‘parent company guarantee’ clause from the Supply Contract, and the high amount that is at stake in the purported Guarantee Letter.
Submissions on Mr Agrawal’s want of authority to sign the Guarantee Letter
45 Reliance Infrastructure further submits that Mr Agrawal lacked any authority, be it express, implied, or apparent, to make the Guarantee Letter on its behalf.
46 In its view, Mr Agrawal was never ‘held out’ as having any authority to bind Reliance Infrastructure, given his junior role as Additional Vice–President and the fact that his involvement in negotiations was limited to the facilitative role of coordinating discussions between the senior management of Parties.
47 Even if Mr Agrawal did play a leading role in the negotiations, Reliance Infrastructure draws a distinction between having the authority to negotiate on behalf of the principal versus having the authority to commit the principal to any binding legal obligation on their behalf.
48 Reliance Infrastructure distinguished other instances when Mr Agrawal did sign agreements with Shanghai Electric. He did so either with the express authorisation of a separate legal entity entirely, such as his signing of the Supply Contract on Reliance (UK)’s behalf, or under entirely different commercial circumstances which did not concern a ‘parent company guarantee’, such as his signing of the Hisar Indemnity by which Reliance Infrastructure (under its previous name) indemnified Shanghai Electric from claims arising out of a joint deed of undertaking made by Parties in favour of the project owner. Consequently, at no point did it ever represent or ‘hold out’ that Mr Agrawal had any authority to execute ‘parent company guarantees’ on its behalf.
Shanghai Electric’s case
49 Shanghai Electric broadly agrees on the applicable legal principles relating to a setting aside application under Singapore law, and under Art 34 of the Model Law and s 24 of the IAA 1994 more particularly. However, it argues that Reliance Infrastructure has waived any right to contest jurisdiction and that in any event its claims of forgery and lack of authority are without merit.
Reliance Infrastructure’s waiver of its jurisdictional objections
50 First, Reliance Infrastructure has already waived its right to object to the Tribunal’s jurisdiction on the grounds of forgery and want of authority, as it had every opportunity to make these objections in the arbitration itself, and having failed to do so, it is deemed to have waived its rights under Art 16(2) of the Model Law.
51 On the point of forgery, Reliance Infrastructure had all the information it needed to form its view that the Guarantee Letter was forged. It asserted to the Tribunal that the Guarantee Letter was a “false instrument” in its email of 4 February 2022 and expressed concerns over its authenticity yet never sought a positive finding from the Tribunal that the Guarantee Letter was forged.
52 Moreover, Reliance Infrastructure had all of the documents it needed to procure a forensic report of a handwriting expert to ascertain if the signatures on the Guarantee Letter were genuine or forged, but simply chose not to do so.
53 Likewise, Reliance Infrastructure also waived its right to object to the Tribunal’s jurisdiction on the ground of Mr Agrawal’s want of authority, since it never mounted any objection to the Tribunal’s jurisdiction nor sought a ruling from the Tribunal that it had no jurisdiction over their dispute. The principle of separability means that it was insufficient for Reliance Infrastructure to only put in issue the validity of the Guarantee Letter without also putting in issue the validity of the arbitration agreement contained therein.
Response to Reliance Infrastructure’s allegation of forgery
54 In any event, even if Reliance Infrastructure had not waived its right to mount its jurisdictional objection based on forgery, Shanghai Electric submits that the external circumstances prove that the Guarantee Letter is genuine, based on the entire course of conduct between the Parties before and after its execution, including, among other things, the terms of the Framework Agreement, Mr Agrawal’s email on 26 August 2008 which acknowledged the existence of the Guarantee Letter and the eye-–witness evidence of Ms Yu.
55 Moreover, the expert evidence of its handwriting expert, Ms Lee, to the effect that Mr Agrawal’s initials and signature on the Guarantee Letter are all genuine when compared to his admitted signatures on other documents, should be preferred over the contrary evidence of Reliance Infrastructure’s handwriting expert, Mr Manas, which it characterises as biased, partisan, and tailored in service of the conclusion that the signatures were forgeries.
Mr Agrawal’s authority to make an arbitration agreement
56 Shanghai Electric argues that, under the separability doctrine, Reliance Infrastructure’s attacks on the authority of Mr Agrawal must fail since they are not directed at his want of authority to bind Reliance Infrastructure into an agreement to arbitrate specifically, as opposed to guarantees generally.
57 Hence, it argues that the arbitration clauses contained in the Framework Agreement, Hisar Indemnity, and DVC Draft Guarantee, and the involvement of Mr Agrawal’s in signing or negotiating such documents, meant that Reliance Infrastructure had ‘held out’ Mr Agrawal as having the apparent authority to make arbitration agreements with Shanghai Electric on its behalf.
58 Shanghai Electric further contends that Mr Agrawal had apparent authority to bind Reliance Infrastructure and relies on the evidence that supported the Tribunal’s finding of apparent authority.
Issues to be determined
59 We observe that Reliance Infrastructure has asserted three grounds to set aside the Award, viz, want of jurisdiction, fraud, and public policy. The success of these grounds all hinge upon showing that Mr Agrawal’s signature on the Guarantee Letter was forged or that he signed without authority.
60 The ground of fraud is not, upon analysis, a distinct ground for setting aside. It is only if Shanghai Electric forged the Guarantee Letter that Shanghai Electric’s officer, Ms Yu, adduced false evidence to the Tribunal by testifying that Mr Agrawal signed the Guarantee Letter.
61 The ground that the Award is contrary to the public policy of the lex fori (i.e., Singapore) in turn depends on showing that the Award was procured by fraud, which is contrary to Singaporean public policy.
62 Thus, the premise of Reliance Infrastructure’s case remains that the arbitration agreement was invalid either because the Guarantee Letter is the product of forgery or that Mr Agrawal had no authority to execute it.
63 Hence, we proceed to consider the following questions:
(a) Whether Reliance Infrastructure waived its right to challenge the Award on the grounds of forgery and want of authority; and
(b) If not, whether Reliance Infrastructure proved that –
(i) the Guarantee Letter was forged; or
(ii) Mr Agrawal lacked authority to make agreements to arbitrate with Shanghai Electric.
Issue 1: Whether Reliance Infrastructure is precluded by waiver from raising its grounds to set aside the Award
64 Our starting point is Art 16(2) of the Model Law – having the force of law in Singapore (as the lex loci arbitri) under s 3(1) of the IAA 1994 – which provides that “[a] plea that the arbitral tribunal does not have jurisdiction shall be raised not later than the submission of the statement of defence”. If raised later in the arbitral process, then the tribunal must be persuaded that the delay in raising the plea was a “justified” one.
65 The fundamental purpose behind Art 16(2) is to require parties to raise objections to the jurisdiction of an arbitral tribunal at the earliest possible time: Hunan Xiangzhong Mining Group Ltd v Oilive Pte Ltd [2022] 5 SLR 239 (“Hunan Xiangzhong”) at [42]. A party should be treated as having waived its right to raise a jurisdictional objection in a setting aside proceeding if it had made a decision not to raise it during the arbitration when it ought to have done so at that juncture: BAZ v BBA and others and other matters [2020] 5 SLR 266 (“BAZ v BBA”) at [64] (see also Rakna Arakshaka Lanka Ltd v Avant Garde Maritime Services (Pte) Ltd [2019] 2 SLR 131 at [50]–[51] and [61]–[62]).
66 However, a party will only be deemed to have waived its rights if the objection was clear to the party and they knew of the objection: BAZ v BBA at [59]. Crucially, the question is whether the party had knowledge of the “matters underlying the jurisdictional objection so that it could have objected in a timely fashion during the arbitration [emphasis added]” itself: per the Singapore International Commercial Court (“SICC”) decision in Deutsche Telekom AG v The Republic of India [2023] SGHC(I) 7 (“Deutsche Telekom v India”) at [165] (affirmed on appeal by our Court of Appeal in The Republic of India v Deutsche Telekom AG [2023] SGCA(I) 10).
67 The SICC also considered whether “India had good reason for holding back on the three allegations due to lack of evidence and still–ongoing investigations [emphasis added]” and whether its “failure to raise the three illegality allegations in the Arbitration was justified or excusable [emphasis added]” (Deutsche Telekom v India at [169] and [171]). Thus, once a party subjectively knows of facts that ground the jurisdictional objection, failure to raise it is only justified or excused for good reason which is a matter for objective evaluation.
Reliance Infrastructure waived its right to challenge the Award based on forgery
68 We consider the state of Reliance Infrastructure’s actual knowledge of the facts underlying its right to object to the Tribunal’s jurisdiction, based on the alleged forgery of the Guarantee Letter at two stages. First, when the claim was originally made and it could find no mention or documentation thereof within its internal company records. Secondly, after the hearing when it was told that the original Guarantee Letter was not printed on its original letterhead.
69 First, it is Reliance Infrastructure’s own case that it only learnt of the existence of the Guarantee Letter, for the very first time, when Shanghai Electric raised it in its Notice of Dispute, and that it saw a copy of that document – again, for the first time – when Shanghai Electric appended that copy to its Notice of Arbitration. According to Mr Parakh, when Reliance Infrastructure received a copy “for the first time” on or around 13 December 2019, it checked its internal records and could find no “evidence of the existence of the purported Guarantee Letter in its records”. It could not find copies of it, nor any correspondence referring to it, nor any proof that its board ever knew and approved of it nor any recordation of that liability in its financial statements, which, on Reliance Infrastructure’s own evidence, were marked departures from its established internal company processes.
70 It is obvious that, when a company receives a claim on a document of which it has no record and that none of its current employees recall, one possible explanation would be that the document was forged. Another is that it was signed without authority.
71 Indeed, Reliance Infrastructure relies upon the absence of records as strong circumstantial evidence that the Guarantee Letter is a forgery. Reliance Infrastructure invoked the fact that “there is not a single piece of documentary evidence to prove or even suggest that the parties had negotiated, let alone agreed to the terms of the Guarantee Letter. No drafts of the Guarantee Letter were ever exchanged between the parties. There are no contemporaneous records of discussions between the parties regarding the terms of any such guarantee [emphasis in original]”, and describes that “complete dearth of documentation” as “especially astonishing when juxtaposed against” various pieces of correspondence between Parties on the Supply Contract. They contend that the “suspicious nature of the circumstances leading up to the alleged execution of the Guarantee Letter is amplified” by the absence of record, that it “defies logic” that there is no “document trail or drafts of the Guarantee Letter” in Parties’ internal records, and “it is scarcely believable that there would not be any evidence that the Guarantee Letter was reviewed by the parties’ in–house or external lawyers”.
72 All these matters raised in submissions to argue for the inference that the Guarantee Letter was forged were known to Reliance Infrastructure from the start. Indeed, in its Statement of Defence of 13 August 2020, Reliance Infrastructure asserted back then that it “has no record of issuing such purported Guarantee Letter to the Claimant [ie, Shanghai Electric]”. Yet, Reliance Infrastructure argues that it had “no reason … to suspect” and “no basis … to think” that the Guarantee Letter was forged.
73 Indeed, when the hearing commenced before the Tribunal the possibility of forgery was sufficiently in the air for Reliance Infrastructure’s counsel to disavow it specifically in opening the defence.
74 Reliance Infrastructure contends that it had good reason not to raise any jurisdictional objection because it had contacted Mr Agrawal via his mobile phone and he had in effect declined to say anything, because he felt he was working for a business competitor and should not become involved in a dispute on behalf of his former employer. He was not asked whether he signed the Guarantee Letter and hence he did not then tell them that he had not signed it.
75 In our view, if there was no record of the Guarantee Letter and Mr Agrawal had not told them that he had signed the letter, it was not reasonable for Reliance Infrastructure to assume that he had signed it, albeit without authority. It would have been a basic step to ask him the question directly. This was not done.
76 In short, subjectively knowing that the absence of record meant that the Guarantee Letter might be forged, Reliance Infrastructure did not have good reason for not raising the jurisdictional objection. It could and should have taken steps such as requesting the original Guarantee Letter from Shanghai Electric so that it could engage an expert to analyse the signature.
77 The position became even clearer in early 2022. The Tribunal had asked for a description of the original at the close of the hearing of 21 January 2022. An inaccurate answer was proffered by Shanghai Electric’s counsel that was corrected soon after by email dated 30 January 2022. This email explained that the letterhead on the Guarantee Letter had been printed in black–and–white (with Mr Agrawal’s signature appearing in blue ink). In response, Reliance Infrastructure’s lawyers sent an email to the Tribunal dated 4 February 2022, arguing that the revelation rendered the Guarantee Letter a “false instrument”. They said that “[i]f this was done by Mr Rajesh Agrawal”, it would constitute forgery, and “[e]ven if Mr Rajesh Agrawal participated in this misadventure, he would be a conspirator”. It added that the Guarantee Letter “appears to be a nullity (as all forgeries are nullities) … created by the Claimant [Shanghai Electric] (with or without the connivance of Mr Rajesh Agrawal) [emphasis added]”.
78 Thus, at the time of its email of 4 February 2022, Reliance Infrastructure openly aired the possibility of a forgery. Yet it did not pursue that issue further before the Tribunal. Its own Schedule of Issues, updated on 11 February 2022, did not include as a specific issue whether the Guarantee Letter was a forgery. There was only the general question (in S/N 1) “[w]hether the purported Guarantee Letter is valid, enforceable and binding upon the Respondent [ie, Reliance Infrastructure]”.
79 Moreover, the Tribunal then asked the Parties to indicate the “specific findings” sought on the issue of the Guarantee Letter. Reliance Infrastructure, in its reply dated 18 February 2022, did not seek any finding that Mr Agrawal had not signed the Guarantee Letter. It only alluded to its “serious concerns” that “the provenance of the purported Guarantee Letter … is in serious question” and sought “a declaration that the purported Guarantee Letter is invalid and unenforceable”.
80 The picture that emerges from the emails dated 4 February 2022 and 18 February 2022 is that, by that point in time, Reliance Infrastructure subjectively believed that the Guarantee Letter had been forged. At the hearing before us, it became clear that it consciously chose not to raise a jurisdictional objection because it was content to rest on its defences already run in the proceedings. Such was the oral evidence of Mr Parakh. When asked in cross–examination whether Reliance Infrastructure asked Mr Agrawal if he signed the Guarantee Letter after Reliance Infrastructure “learnt of the possibility of forgery”, Mr Parakh’s reply was “I don’t think that was a requirement because it was so clear during the oral submissions before the honourable tribunal. We were … very confident that this would come through in the award, whenever the tribunal gives the award. … It’s only the award which came other way [sic]”.
81 In other words, Reliance Infrastructure had made a conscious choice not to pursue its allegation of forgery because it was very confident that, under the circumstances, its other challenges to the validity of the Guarantee Letter would prevail in any event. It only wishes to revive that argument now because the outcome differed from its expectation.
82 Accordingly, Reliance Infrastructure has waived its right to raise forgery as a jurisdictional objection before us.
Reliance Infrastructure waived its right to challenge the Award based on want of authority
83 Reliance Infrastructure similarly waived its right to raise its objection to the Tribunal’s jurisdiction, based on Mr Agrawal’s alleged want of authority, when it failed to put in issue the Tribunal’s jurisdiction over the dispute, on the basis of Mr Agrawal’s want of authority to execute an agreement to arbitrate, more specifically, whilst clearly having had actual knowledge of all the relevant facts to mount that objection, at the time of the SIAC arbitral proceedings.
84 That actual knowledge is clear from the fact that Reliance Infrastructure did put in issue, at the outset of the proceedings, the validity of the Guarantee Letter, based on Mr Agrawal’s lack of authority to execute that agreement. Yet it did not at any time seek a ruling from the Tribunal that it had no jurisdiction to rule on the Parties’ dispute, based on Mr Agrawal’s absence of authority to execute an arbitration agreement on its behalf. It now seeks to make before us the latter objection based on substantially the same facts upon which it pleaded the former objection – this it cannot do. Having been “aware of the matters underlying the jurisdictional objection so that it could have objected in a timely fashion during the arbitration” (see Deustche Telekom v India at [165]), and failing to do so then, it is precluded by waiver from raising that objection now.
85 Reliance Infrastructure makes several attempts to rebut this argument. First, it suggests that it did put the validity of the arbitration agreement in issue because it put the validity of the Guarantee Letter in issue, within which that agreement is contained. That submission is squarely against the principle of separability as described, for example, in Fiona Trust & Holding Corporation and others v Privalov and others [2007] UKHL 40 (“Fiona Trust”) at [17]–[18]. An agreement to arbitrate is a separate contract that survives the destruction or rescission of the underlying contract in which it is contained. The separability doctrine is also found in Art 16(1) of the Model Law, which has the force of law in the lex loci arbitri (see s 3(1), IAA 1994), which provides that “[a] decision by the arbitral tribunal that the contract is null and void shall not entail ipso jure the invalidity of the arbitration clause”.
86 Accordingly, to put in issue that the Guarantee Letter was invalid does not impliedly put in issue that the arbitration agreement was also invalid. This is confirmed by the heads of relief sought in the arbitration itself. Reliance Infrastructure never sought a finding from the Tribunal that it lacked jurisdiction to arbitrate the Parties’ dispute. Instead, it sought “[a] declaration that the purported Guarantee Letter is invalid and not enforceable”, as noted by the Tribunal in its Award at [130(a)].
87 When considered against the fact that Reliance Infrastructure never put in issue the invalidity of the arbitration agreement based on Mr Agrawal’s want of authority, this declaratory relief can only be construed as substantive relief rather than an objection to jurisdiction. It sought the dismissal of Shanghai Electric’s claims on the basis that it was not bound by the substantive contractual obligations found in the Guarantee Letter. It did not attack the validity of the arbitration agreement or the jurisdiction of the Tribunal.
88 Secondly, Reliance Infrastructure argues that if the main contract fails on a set of facts which would of themselves also entail the failure of any arbitration agreement therein, there is no requirement that a party expressly state that it is attacking both the main contract and the arbitration agreement to put both of those challenges in issue.
89 It relies on portions of the reasoning of both the English House of Lords in Fiona Trust and our Court of Appeal in Founder Group (Hong Kong) Ltd (in liquidation) v Singapore JHC Co Pte Ltd [2023] SGCA 40 (“Founder Group”) in support of this argument.
90 We do not agree with the interpretation of these authorities that Reliance Infrastructure propounds. Reliance Infrastructure relies on the paragraph in Founder Group at [58], where it was explained that:
The principle of separability cannot guarantee the survival of the arbitration clause in all circumstances. Instead, where a challenge to the validity of the underlying contract is raised, it will be crucial to determine if this is also an attack on the arbitration agreement. This will necessarily be a fact–sensitive exercise, and much will depend on the nature of the challenge mounted against the underlying contract. … if the allegation is that the entire contract was entered into without authority, this may well be an attack on both the underlying contract and the arbitration agreement, as the implication would be that every clause in the contract including the arbitration agreement was entered into without authority. On the other hand, where the challenge is that the underlying contract is void or voidable for misrepresentation, the arbitration agreement may survive because the parties’ intention to arbitrate may not be affected by the misrepresentation. …
[emphasis in original]
91 Indeed, that the whole agreement was entered into without authority “may well be an attack” on the arbitration agreement, but it may not always be. The distinction is important on the facts of this case. Mr Agrawal had previously signed an indemnity on behalf of Reliance Infrastructure in favour of Shanghai Electric: Reliance Infrastructure distinguished this on the basis that it was an indemnity and not a parent company guarantee. But both contained arbitration agreements. This illustrates the point that the person signing an agreement may have authority to enter into arbitration agreements but not to enter into the contract which contains it.
92 Thus, an attack on the main contract remains conceptually separate, in law, from an attack on the arbitration agreement within it. The learned Lord Hoffmann gave the example in Fiona Trust at [17] that “if the main agreement and the arbitration agreement are contained in the same document and one of the parties claims that he never agreed to anything in the document and that his signature was forged, that will be an attack on the validity of the arbitration agreement. But the ground of attack is not that the main agreement was invalid. It is that the signature to the arbitration agreement, as a ‘distinct agreement’, was forged. Similarly, if a party alleges that someone who purported to sign as agent on his behalf had no authority whatever to conclude any agreement on his behalf, that is an attack on both the main agreement and the arbitration agreement”.
93 We do not read the decision in Founder Group as erasing the distinction between an attack on an arbitration agreement and an attack on the main contract in which it is found. While there may be an overlap – if not an outright identity, in some cases – of the facts and evidence used to invalidate both agreements, they remain distinct agreements nevertheless. The question to be asked is whether the ground for invalidation being pleaded would affect the arbitration agreement as a separate agreement. Thus, in Fiona Trust at [18], the mere fact that an agent was shown to have exceeded his authority in making the main contract did not automatically mean that he also exceeded his authority in making the arbitration agreement found therein.
94 It is also important to keep in mind that the question we are concerned with is whether Reliance Infrastructure is precluded by waiver from raising the objection now. For the purpose of deciding that issue, the relevant question is whether Reliance Infrastructure did or did not pursue its jurisdictional objection, on the grounds of Mr Agrawal’s want of authority to make an arbitration agreement, during the arbitral process itself. It plainly did not do so. Instead, it was content for the question of authority to be decided by the Tribunal.
95 Having failed in its defence of lack of authority on the merits, Reliance Infrastructure cannot now recast its merits defence as a jurisdictional objection for which it seeks de novo review before us.
Issue 2: Reliance Infrastructure failed to show that the Guarantee Letter was forged
96 As we find that Reliance Infrastructure has waived its rights to challenge the Award on the basis of forgery and want of authority, its application to set aside the Award must be dismissed. We will not delve in detail into the merits of these challenges, given that Reliance Infrastructure is precluded by waiver from raising them before us now. However, even if those challenges had not been waived, we are not persuaded of their merits in any event. We shall now briefly canvass our reasons for coming to that view on the evidence before us.
The external evidence clearly showed that the Guarantee Letter is genuine
97 First of all, the objective evidence proved the existence of the executed Guarantee Letter. The most compelling evidence was the email sent by Mr Agrawal to officers of Shanghai Electric on 26 August 2008. In that email, he wrote concerning two other power plant projects in India that for those contemplated projects “RIL Guarantee Letter similar to Sasan would be given for Reliance Infra behalf”. “RIL” is an acronym for Reliance Infrastructure Limited, with “Reliance Infra” being an abbreviation of the same.
98 In our view, the language used must refer to a guarantee letter that is already executed and in existence in respect of the Sasan Project. There can only be similarity to something that exists. Moreover, the words are capitalised.
99 Mr Agrawal’s testimony was that he could not remember sending the email, which in his witness statement he referred to as “an email purportedly sent by me”. Notwithstanding that he could not remember it, he gave evidence that he must have meant a “draft” and not an executed version. He testified that subsequently it was decided not to give such a guarantee. First, if Mr Agrawal could not remember the email, he could not reliably give evidence of what he meant when sending that email. Secondly, his explanation is unconvincing and does not match the words he in fact used, as described above.
100 The inference to be drawn from the 26 August 2008 email is that, by that point in time, the Guarantee Letter had been executed by Mr Agrawal in favour of Shanghai Electric for the Sasan Project. That inference is only further strengthened upon reference to the Term Sheet of the Framework Agreement concluded between the Parties on 20 May 2008. This contained a provision that “[t]he Purchaser shall provide suitable guarantee letter from its parent company acceptable to the Contractor with in [sic] one week of signing of contract”. The Purchaser is defined as RIPIL, the sole holding company of Reliance (UK). The Contractor is also defined therein as Shanghai Electric. As for what “contract” is being referred to, it must be the Supply Contract concluded between Shanghai Electric and Reliance (UK), since the “Owner” is defined in the same section of the Term Sheet as Sasan Power; hence, that “contract” must be a contract with Shanghai Electric involving the Sasan Project.
101 The reasonable inference to be drawn from the Framework Agreement is that, on 20 May 2008, there was a common understanding between the Parties that Shanghai Electric would receive a guarantee letter from a parent company of RIPIL in relation to the Sasan Project. This supports the interpretation that the 26 August 2008 email was referring to a Sasan guarantee letter that was in existence, and not one which might or might not be agreed upon in future.
102 Reliance Infrastructure proffers unconvincing alternative explanations for this term in the Framework Agreement’s Term Sheet. First, its witness Mr Parakh suggested that Reliance Infrastructure could not be the “parent company” referred to in the Framework Agreement since it only held 10% of the shareholding of RIPIL. But this merely puts in question which company in the group should eventually give the guarantee, not that there should be a guarantee from the appropriate entity.
103 On that question of the intended guarantor there is ample material indicating that that was Reliance Infrastructure. First, there is the DVC Draft Guarantee, sent in an email dated 23 June 2008 from an officer of Reliance Infrastructure to the officers of Shanghai Electric (whilst copying Mr Agrawal). Paragraph B of its recitals states that “RELINFRA [ie, Reliance Infrastructure] has assigned the BTG Contract to Reliance Infra Projects UK Limited … which is a subsidiary of RELINFRA [emphasis in bold and italics]”. Although that DVC Draft Guarantee may not have been executed in the end, the contents of that draft, which were sent by Reliance Infrastructure to Shanghai Electric, show that, whatever the internal corporate structure of the Reliance Group may have been, as far as Shanghai Electric was aware, the Parties were content to deal with each other on the understanding that Reliance (UK) was, for all intents and purposes, in fact a subsidiary of Reliance Infrastructure. This is reinforced by the Supply Contract, which contains a similar description of Reliance (UK) as “a subsidiary of Reliance Infrastructure Limited for the procurement of equipments [sic] & services from outside India for the projects of the group companies of Reliance Infrastructure Limited” in its recitals.
104 It follows that the “parent company” of RIPIL (sole holding company of Reliance (UK)) which was to provide a guarantee letter to Shanghai Electric under the Framework Agreement would have been Reliance Infrastructure. This would make sense as Reliance Infrastructure was also the only member of the Reliance Group that was a party to the Framework Agreement in the first place.
105 However, Reliance Infrastructure also argues that, even if it was agreed in the Framework Agreement that a guarantee letter would be given to Shanghai Electric, that understanding ended when Mr Agrawal sought to amend the Supply Contract to remove a ‘parent company guarantee’ clause on 25 May 2008, which was acceded to by Shanghai Electric.
106 In our view, that does not follow. The effect of the clause was to include an undertaking to provide the guarantee within a week after the signing of the Supply Contract. The clause was no longer needed once it was agreed that the Guarantee Letter was to be provided, as it later was, at the same time or prior to the signing of the Supply Contract. This is consistent with the words used by Mr Agrawal at the time, namely, “we request deletion from here”. The “here” was the Supply Contract. It was not a change of heart over whether the parent company letter would be given.
The evidence of Ms Yu should be preferred over the evidence of Mr Agrawal
107 The fact that the objective documentary and circumstantial evidence support the inference that the Guarantee Letter is genuine provides independent corroboration of Ms Yu’s evidence that she saw Mr Agrawal sign the Guarantee Letter at the signing ceremony of 26 June 2008, and for the same reason, it undermines the credibility of Mr Agrawal and his evidence that he did not sign the Guarantee Letter. Separately, we also find Ms Yu’s testimony convincing. It was given matter–of–factly and clearly. Conversely, we do not find Mr Agrawal’s testimony to be reliable.
108 Mr Agrawal’s evidence on the 26 August 2008 email was unconvincing. In his witness statement, he first stated that that it was an email purportedly sent by him and that he had no memory of that email at all. He did not offer any explanation of the contents of that email – to the contrary, he claimed to have no memory of the “context in which this email was sent [emphasis added]”. He added that as he never signed the Guarantee Letter “there was no reason why I would have referred to any such Guarantee Letter for the Sasan UMPP”. This stands in stark contrast with his oral evidence, under cross–examination, where for the first time he proffered an explanation of the contents of an email that he maintained he still had no memory of, as follows: “the intent of my mail, if it appears to be that whatever the decision will happen on Sasan, we will follow the same one for Butibori. That was the intent”.
109 That explanation, that a reference to a Sasan guarantee letter meant only a potential guarantee letter that was still being discussed between the Parties at the time, contradicts Mr Agrawal’s earlier claim that there was “no reason” he would be referring to a Sasan guarantee letter at all in his 26 August 2008 email. It also cannot be squared with his claim that he has no memory of sending that email or the “context in which” it was sent. In addition to these difficulties with his testimony, the explanation given cannot be squared with the plain language he used within the email itself. The statement that a guarantee letter “similar to Sasan would be given [emphasis added]” is clearly not provisional or conditional on some future event that may or may not materialise, but can only be a reference to a guarantee letter already in existence at that point in time. Indeed, he later said that the “RIL Guarantee Letter” was a reference to a draft in existence. As a result of such internal and external difficulties, we find that Mr Agrawal is not a credible witness and we accord little weight to his evidence.
110 In contrast, we find Ms Yu to be a credible witness, as her testimony that Mr Agrawal had signed the Guarantee Letter coheres with the external evidence pointing to the existence of that Guarantee Letter, including the 26 August 2008 email considered together with the Term Sheet of the Framework Agreement. Her explanation for the removal of the ‘parent company guarantee’ clause from the Supply Contract – that Reliance Infrastructure had already agreed to provide the guarantee letter at the same time as the Supply Contract would be signed, making such a clause unnecessary – was logical and made commercial sense. There was no need to bind Reliance (UK) under the Supply Contract to obtain a ‘parent company guarantee’ when that very company, Reliance Infrastructure, had already agreed to provide one together with the signing of that Supply Contract.
111 Additionally, the attacks which Reliance Infrastructure level against her credibility strike us as unfair, generally resting on minor immaterial inconsistencies which are readily explained as mere lapses of memory from the long passage of time.
112 For example, much was made of the fact that Ms Yu appeared unsure of where precisely the Guarantee Letter was signed, when she was sure that the Supply Contract was signed in the front of the room as part of the ceremony. The suggestion that this was a conveniently selective loss of memory on her part seems unwarranted to us. It is not unreasonable given the passage of time that Ms Yu may not be able to remember precisely where the Guarantee Letter was signed while remembering that it was, in fact, signed at the relevant time.
113 Moreover, the argument that Ms Yu vacillated in her evidence concerning whether the signing of the Guarantee Letter was part of the signing ceremony or not rested on interpretation of what Ms Yu meant by her evidence that the signing of the Guarantee Letter was part of the ceremony. As Ms Yu explained, “[a]t the ceremony, he did not go onto the stage to sign the document, but in my view that’s still an official signing”. When Ms Yu testified that Mr Agrawal signed the Guarantee Letter at the signing ceremony, as “part of” that ceremony, she was not saying – as Reliance Infrastructure interpreted it to mean – that the Guarantee Letter was signed at precisely the same time and location as the Supply Contract, with identical fanfare and formalities for both. It could just as easily mean – as she explained – that the Guarantee Letter was signed on the day of the signing ceremony, but not necessarily at exactly the same time as the Supply Contract. Moreover, her explanation for why the Guarantee Letter was signed before the Supply Contract accords with commercial commonsense, viz, that Shanghai Electric would naturally want that protection in hand before it bound itself to a contract with Reliance (UK) without a guarantee from its parent company being in force at that point in time.
114 Accordingly, we accept Ms Yu’s evidence and reject that of Mr Agrawal.
The expert evidence of Mr Manas failed to show that the signatures on the Guarantee Letter were forgeries
115 Finally, we briefly canvass our views on the contrary evidence of the handwriting experts, Mr Manas and Ms Lee, whose reports arrived at competing conclusions as to whether the signatures on the Guarantee Letter were forgeries.
116 The two experts employed differing methodologies for their appraisals. Ms Lee did not detect line quality defects in the disputed signatures when comparing them against Mr Agrawal’s admitted signatures under a stereo microscope, and identified similar characteristics in terms of pen pressure, line quality, and stroke fluency between the disputed and admitted signatures. She found no signs of tracing in the disputed signatures when examining them under oblique lighting, including the re–touching of strokes, unusual pen lifts, unusual pen pressure or stroke hesitation.
117 In contrast, Dr Manas’s methodology involved among other things superimposing the disputed signatures upon the admitted signatures under transmitted light to detect suspicious similarities and indicators of manual tracing, using oblique light to detect indentations as a sign of unusually high pen pressure as indicative of slower execution in a forgery, and the ‘ruled square’ method of examining the admitted and disputed signatures under a transparent sheet bearing ruled squares of the same scale, to compare them for suspicious similarities. Based on these methods, he concluded that all five initials and signatures on the Guarantee Letter were the product of forgery.
118 We do not accept the criticisms of Mr Manas as an expert pressed by counsel for Shanghai Electric. We consider that he attempted a thorough examination of the material before him. He was not biased or partial. However, we are not able to accept his conclusion that the signature and initials were forged. In our view, Mr Manas’s interpretation of the evidence was not sufficiently compelling, especially when Ms Lee’s interpretation was considered.
119 For example, Mr Manas detected the presence and absence of striations in several of the disputed signatures, which he chalked up to the deliberate re–tracing or re–touching of strokes, which is indicative of forgery. In contrast, Ms Lee did not interpret these striations as indicative of forgery, and was of the view that they could be attributable to the uneven ink flow of a ballpoint pen.
120 Likewise, Mr Manas detected what he regarded as line quality defects in the disputed signatures, which he interpreted as being indicative of hesitation, slow execution, re–tracing of strokes, and unnatural pen pauses and pen lifts, all signs of forgery in his view. In contrast, Ms Lee was of the view that they were attributable to striations from a ballpoint pen or an unsteadiness in pen movement also seen in Mr Agrawal’s admitted signatures.
121 While Mr Manas had concluded from his superimposition of the signatures under transmitted light that, among other things, the long form signature on the Guarantee Letter had suspicious similarities with one of Mr Agrawal’s admitted signatures, suggesting that the latter was used to trace the former, Ms Lee was of the view that the signatures were not suspiciously similar, and there were marked and significant departures in their sizes, formations, and relative alignments.
122 We do not propose to set out exhaustively the differences between the expert opinions of Ms Lee and Mr Manas. It suffices for us to state that we consider these to be attributable to reasonable differences of interpretation by two handwriting experts. They have both drawn broadly logical inferences from the same set of primary data but reach differing secondary conclusions. Hence, for this reason, taking their evidence on its own, we would not prefer the expert conclusions of Mr Manas over Ms Lee. Thus, even on the conflicting expert evidence alone, Reliance Infrastructure would have failed to discharge its burden of proving forgery of the Guarantee Letter.
123 We do not, however, assess the conflicting expert evidence in isolation. We consider that evidence in conjunction with the totality of the direct evidence of Ms Yu and Mr Agrawal together with the circumstantial evidence concerning the execution of the Guarantee Letter. Such circumstantial evidence, as we have explained, strongly supports the inference that the Guarantee Letter is genuine and was signed by Mr Agrawal. Hence, even if Reliance Infrastructure had not waived its forgery claim, we would have rejected it on its merits, based on the totality of the evidence before us.
Issue 3: Reliance Infrastructure failed to show that Mr Agrawal lacked the apparent authority to commit it to agreements to arbitrate with Shanghai Electric
124 Finally, we find that Mr Agrawal had the apparent authority to commit Reliance Infrastructure into agreements to arbitrate with Shanghai Electric, and would have dismissed its jurisdictional objection on this ground even if it had not been waived.
125 As a preliminary point, we note for completeness that although Reliance Infrastructure had made submissions on Mr Agrawal’s absence of express actual authority, implied actual authority, and apparent authority, while Shanghai Electric submitted on Mr Agrawal’s implied authority and apparent authority, the central point in issue is Mr Agrawal’s apparent authority. If he had apparent authority, the issues of express and implied actual authority are moot.
126 We also note that the Parties’ written submissions were at odds as to the governing law to be applied to the agreement to arbitrate in the Guarantee Letter. Reliance Infrastructure’s position was that the applicable law was Indian law, and in the alternative, Singapore law, whereas Shanghai Electric’s view was that the governing law of the arbitration agreement was English law. By the time of the second day of the hearing before us, 12 January 2024, however, the Parties indicated that they were prepared to agree that the law which governs the formation of the arbitration agreement (based on Mr Agrawal’s apparent authority) is English law. This accords with the view of the Tribunal, which held in its Award that the governing law of the arbitration agreement was English law.
127 Hence, we apply English law to determine whether Mr Agrawal had the apparent authority to conclude an arbitration agreement on behalf of Reliance Infrastructure. The locus classicus is the English Court of Appeal decision of Freeman and Lockyer (a firm) v Buckhurst Park Properties (Mangal) Ltd and another [1964] 2 QB 480 (“Freeman & Lockyer”). This held that the most common means by which a principal may represent or ‘hold out’ that an agent has ostensible authority to contract on its behalf is the conduct of permitting or acquiescing in the agent conducting the business of the principal with third parties, cloaking that agent with apparent authority to make contracts in the ordinary course of such business: Freeman & Lockyer at 505.
128 On that ground, we find that Reliance Infrastructure had ‘held out’ Mr Agrawal as having the apparent authority to make arbitration agreements with Shanghai Electric on its behalf, for the reasons that follow.
Signing the Hisar Indemnity
129 In our view, the clearest representation that Mr Agrawal had apparent authority to make arbitration agreements with Shanghai Electric on Reliance Infrastructure’s behalf was their having him sign the Hisar Indemnity. This indemnity contained an arbitration agreement in Paragraph 6(b). It was signed by Mr Agrawal on behalf of Reliance Energy Limited, the previous name of Reliance Infrastructure. That agreement had been executed on 9 February 2007, before the signing of the Guarantee Letter on 26 June 2008. Similar to the Guarantee Letter, it concerned a power plant project in India which both Parties were involved in.
130 While there are differences between the arbitral processes provided in Paragraph 6(b) of the Hisar Indemnity and Paragraph 10 of the Guarantee Letter – eg, the former provides for one arbitrator, the latter provides for three; the former selects SIAC arbitration rules as the procedural regime, the latter selects UNCITRAL arbitration rules, etc – these do not affect the salient point that Reliance Infrastructure effectively ‘held out’ Mr Agrawal as having the authority to commit it into agreements to arbitrate disputes with Shanghai Electric. The differences are minor and immaterial to the question of authority to bind Reliance Infrastructure to arbitration agreements.
131 Reliance Infrastructure invokes differences in the commercial context surrounding the two agreements to argue that Mr Agrawal’s authority to execute the Hisar Indemnity did not amount to a representation that he could execute the Guarantee Letter. In particular, it argues that the indemnity in the Hisar Indemnity was for a joint deed of undertaking (JDU) executed by both Parties to the project owner, whereas the Guarantee Letter concerned a ‘parent company guarantee’, which it says Mr Agrawal had no authority to make.
132 That argument is at odds with the principle that agreements to arbitrate are separate and distinct agreements from the underlying contract. Even if it is assumed that Mr Agrawal’s signing of the Hisar Indemnity would not amount to a reasonable representation that he could sign ‘parent company guarantees’ on behalf of Reliance Infrastructure, it would nonetheless amount to a representation that he could sign arbitration agreements on their behalf. It is not enough to point to commercial differences between the Guarantee Letter’s and Hisar Indemnity’s substantive terms; instead, “[i]t would have to be shown that whatever the terms of the main agreement or the reasons for which the agent concluded it, he would have had no authority to enter into an arbitration agreement”: Fiona Trust at [18].
133 Hence, the fact that Reliance Infrastructure permitted or acquiesced in Mr Agrawal signing an arbitration agreement on its behalf within the Hisar Indemnity, thereby committing it to arbitrate its disputes with Shanghai Electric, was a clear representation that he had authority to make arbitration agreements with Shanghai Electric on its behalf. We consider that that representation is even clearer when considered together with two other events –
(a) First, while he did not sign the agreement itself, on 20 May 2008, Mr Agrawal initialled at the bottom–left of every page of the Framework Agreement on Reliance Infrastructure’s behalf, including the page for Paragraph 3.7, which also contained an agreement to arbitrate disputes with Shanghai Electric; and
(b) On 23 June 2008, Mr Devinder Batta, who is described by Mr Agrawal as his “junior”, sent an email to Shanghai Electric’s officers, copying Mr Agrawal, proposing a draft of the DVC Draft Guarantee to be reviewed and “finalised in today’s meeting”, Paragraph 10 of which contained an agreement to arbitrate disputes with Shanghai Electric. This draft was similarly worded to Paragraph 10 of the Guarantee Letter.
134 We find that a reasonable person placed in Shanghai Electric’s shoes, considering the totality of Reliance Infrastructure’s conduct, would conclude that Mr Agrawal had authority to make arbitration agreements with Shanghai Electric on Reliance Infrastructure’s behalf. Thus, the making of the arbitration agreement found in Paragraph 10 of the Guarantee Letter fell squarely within the scope of Mr Agrawal’s ostensible authority. This is regardless of whatever may be said about Mr Agrawal’s apparent authority (or lack thereof) to make ‘parent company guarantees’ or to execute other commercial agreements between the Parties.
135 Indeed, the differences in nature between the Hisar Indemnity and the Guarantee Letter were not so great that his previously signing the Hisar Indemnity on behalf of Reliance Infrastructure would not amount to a representation that he had authority to sign the Guarantee Letter. Both were commercial contracts. An objective observer would not have come to the view that his authority was limited only to indemnities and not to parent company guarantees.
The external circumstances reinforced that Reliance Infrastructure ‘held out’ Mr Agrawal as having the authority to make agreements with Shanghai Electric on its behalf
136 In any event, our finding that Mr Agrawal had apparent authority is only reinforced when one broadens the scope of analysis beyond Mr Agrawal’s prior making, signing or proposing of arbitration agreements with Shanghai Electric to consider the wider pattern of Mr Agrawal’s involvement in the negotiations between Parties on various power plant projects they were both involved in.
137 That conduct of Mr Agrawal included –
(a) Leading the negotiations between the Reliance Group entities and Shanghai Electric, as averred by Reliance Infrastructure’s witness, Mr Parakh, who confirmed that while Mr Agrawal was a ‘liaison’, he also led the negotiations, while not having decision–making authority;
(b) Signing the Hisar Indemnity on Reliance Infrastructure’s behalf (as Reliance Energy Limited) on 9 February 2007;
(c) Sending an email to the officers of Shanghai Electric on 30 July 2007 conveying that he and two members of Reliance Group’s senior management would like to visit Shanghai Electric’s office “as soon as possible to discuss the frame work and strategy for the Sasan as well as for Shahapur projects”;
(d) Sending other emails to Shanghai Electric relaying relevant draft contractual documents on 8 October 2007, arranging for discussions to finalise the signing of contracts on 16 February 2008, and relaying comments and changes on the terms of draft contractual documents on 29 February 2008, 14 March 2008, and 9 May 2008;
(e) Initialling at the bottom-–left of every page of the Framework Agreement between the Parties on behalf of Reliance Infrastructure on 20 May 2008;
(f) Proposing contractual changes such as in the email dated 25 May 2008 seeking the deletion of the ‘parent company guarantee’ clause from the Supply Contract;
(g) Attending the signing ceremony on 26 June 2008 when members of Reliance Group’s senior management could not be present, delivering a speech which conveyed various sentiments “on behalf of” the Reliance Group;
(h) Signing the Supply Contract at the signing ceremony on 26 June 2008 on behalf of Reliance (UK), subsidiary of Reliance Infrastructure (as described in the Supply Contract and the DVC Draft Guarantee);
(i) As we regard Ms Yu to be a credible witness and would prefer her evidence over Mr Agrawal’s, we would add to the above list that Mr Agrawal negotiated the terms of the Guarantee Letter with an officer of Shanghai Electric’s legal department on 25 June 2008, and was sent by the Reliance Group to sign both the Supply Contract and Guarantee Letter at the signing ceremony on 26 June 2008; and
(j) Finally, his conduct post–dating the Guarantee Letter of 26 June 2008 may bear relevance in corroborating the course of conduct between the Parties prior to that date. Such conduct would include Mr Agrawal sending an email dated 4 July 2008 with a letter to Shanghai Electric’s Vice–President proposing the assignment of a contract to Reliance (UK) for Shanghai Electric’s acceptance, signed by Mr Agrawal, in which he is described as Reliance Infrastructure’s “Authorized Signatory”, and him sending an email dated 26 August 2008 communicating to Shanghai Electric that guarantee letters would be furnished for a number of power plant projects on Reliance Infrastructure’s “behalf”.
138 While the representations of the apparent authority of the agent must emanate from the principal and not the agent, and Mr Agrawal’s conduct alone cannot cloak himself with ostensible authority to act for Reliance Infrastructure, apparent authority can arise from the principal’s representations by conduct, the most common form of which involves its acquiescence in the agent’s consistent course of dealings with third parties (Freeman & Lockyer at 498). Here, the length of time and frequency of Mr Agrawal’s dealings with Shanghai Electric support the inference that Reliance Infrastructure must have known of and acquiesced in Mr Agrawal dealing with Shanghai Electric on its behalf on matters relating to the power plant projects they were both involved in. Thus, Reliance Infrastructure impliedly represented that he had their authority to do so (Freeman & Lockyer at 498).
139 Of course, if each of the above acts are taken strictly in isolation, various arguments may be made attacking the strength of the individual representations. Distinctions may be drawn between negotiating contracts and concluding contracts or between signing a contract for Reliance (UK) versus Reliance Infrastructure. The critical point, however, is to assess the representations in the round and not as discrete acts. The overall impression given by Reliance Infrastructure was that Mr Agrawal was heavily involved in the business dealings between Shanghai Electric and Reliance Group entities and handled many relevant arrangements and negotiations for the conclusion of contracts relating to the power plant projects that the Parties were engaged in, including the Sasan Project. Thus, he was cloaked with apparent authority to enter into any contracts in the ordinary course of such business dealings (Freeman & Lockyer at 505). There was nothing unusual about the Guarantee Letter, and it was conceded by Reliance Infrastructure’s own witness, Mr Agrawal, that it had been contemplated by Parties.
140 Looked at in its totality, we find that this consistent course of conduct gave rise to the representation that Mr Agrawal had authority to sign the Guarantee Letter and to make the arbitration agreement.
Conclusion
141 We conclude that Reliance Infrastructure, having had knowledge of the underlying facts to mount its objections to the jurisdiction of the Tribunal, on the grounds of both forgery and want of authority, and lacking good reason not to do so, must now be deemed to have waived its rights to make those arguments here by its failure to pursue those objections to jurisdiction in the SIAC arbitration.
142 This finding is, of course, fatal to Reliance Infrastructure’s setting aside application; however, for completeness, we find that, in any event, the objections raised were without merit. We would have dismissed them even if Reliance Infrastructure had not waived its right to pursue them.
143 Consequently, we dismiss Reliance Infrastructure’s application to set aside the Award in SIC/OA 1/2023. We also award costs to Shanghai Electric. If parties are unable to agree on the amount of costs within 14 days of the date of this judgment, they are to file within 7 days thereafter submissions on costs limited to ten pages each, excluding any tables of time spent or work done.
Philip Jeyaretnam
Judge of the High Court
Sir Vivian Ramsey
International Judge
Anselmo Reyes
International Judge
Vergis S Abraham SC, Asiyah binte Ahmad Arif, Ngo Wei Shing (Wu Weishen) and Liu Enning (Providence Law Asia LLC), Harish Salve KC (Blackstone Chambers) for the claimant;
Cavinder Bull SC, Foo Yuet Min, Tay Hong Zhi, Gerald, Tan Yi Fan and Tan Pei Han (Drew & Napier LLC), Nicholas Emmet Graham Leslie (Fountain Court Chambers), Ketan Gaur and Aayush Mitruka (Trilegal) for the defendant.
SUPREME COURT OF SINGAPORE
31 January 2024
Case summary
Reliance Infrastructure Limited v Shanghai Electric Group Co Ltd [2024] SGHC(I) [3]
Singapore International Commercial Court Originating Application No 1 of 2023
--------------------------------------------------------------------------------------------------------------------------------------
Decision of Philip Jeyaretnam J, Anselmo Reyes IJ and Sir Vivian Ramsey IJ (delivered by Justice Jeyaretnam):
Outcome: SICC dismissed Reliance Infrastructure Limited’s application to set aside an SIAC arbitral award which had awarded damages in favour of Shanghai Electric Group Co Ltd
Background
1 The claimant (“Reliance Infrastructure”) sought to set aside an SIAC arbitral award dated 8 December 2022 (“the Award”) which had awarded damages to the defendant (“Shanghai Electric”). The Tribunal’s putative jurisdiction over the Parties’ dispute was based on an arbitration clause found in a purported letter dated 26 June 2008 (“the Guarantee Letter”), in which Reliance Infrastructure had allegedly guaranteed the obligations of a related company owed to Shanghai Electric under a separate contract.
2 In its Originating Application, Reliance Infrastructure sought to set aside the Award on the grounds that the Tribunal lacked jurisdiction over the dispute, that the Award was affected by Shanghai Electric’s fraud, and being affected by such fraud, it was contrary to Singapore’s public policy.
3 Reliance Infrastructure made two arguments in support of the above grounds – (1) it alleged that Shanghai Electric had forged the signature of its former officer (Mr Agrawal”) on the Guarantee Letter; and (2) that Mr Agrawal had no authority to make agreements on its behalf.
The material facts
4 The Parties were involved in a construction project for a power plant in Sasan Village, India (“the Sasan Project”). On 26 June 2008, an English company related to Reliance Infrastructure – Reliance Infra Projects (UK) Limited (“Reliance (UK)”) – entered into a contract for Shanghai Electric to supply equipment and services for the Sasan Project (“the Supply Contract”).
5 The validity of the Supply Contract was not in dispute between the Parties. What was disputed was whether the Guarantee Letter had also been executed on that same day. On Shanghai Electric’s case, Mr Agrawal signed the Guarantee Letter on Reliance Infrastructure’s behalf, guaranteeing Reliance (UK)’s obligations to Shanghai Electric under the Supply Contract and agreeing to submit disputes in the Guarantee Letter to SIAC arbitration. Reliance Infrastructure denied this, claiming that Mr Agrawal’s signature was forged and, alternatively, that he lacked authority to make that agreement on its behalf.
6 Shanghai Electric then commenced an SIAC arbitration against Reliance Infrastructure, claiming that Reliance (UK) failed to make progress payments owed to it under the Supply Contract, and seeking to enforce Reliance Infrastructure’s guarantee thereof.
7 In the SIAC arbitration, Reliance Infrastructure denied the existence of the Guarantee Letter and contested Mr Agrawal’s authority to sign it. However, it never objected to the Tribunal’s jurisdiction. It never put in issue that Mr Agrawal’s signature had been forged nor that he lacked authority to make an arbitration agreement (as distinguished from his authority to make the Guarantee Letter).
8 After Reliance Infrastructure filed its setting–aside application, it raised for the first time its allegation of forgery. It adduced fresh evidence in support of that allegation, in the form of Mr Agrawal’s evidence that he never signed the Guarantee Letter, and the report of a handwriting expert to that effect. It also raised an objection to the Tribunal’s jurisdiction based on Mr Agrawal’s lack of authority to make agreements on its behalf.
The Court’s judgment
9 In the circumstances, the Court found that Reliance Infrastructure had waived its rights to pursue these challenges against the Award (at [82] and [95]). On its own case, it allegedly could find no contemporaneous documentation corroborating the existence of the Guarantee Letter in its internal records near the outset of the arbitration (at [69]).
10 Despite this, Reliance Infrastructure never asked Mr Agrawal if he had signed the Guarantee Letter or not throughout the arbitration (at [74] and [75]). Moreover, it never engaged an expert to examine the authenticity of his signature when it could have done so (at [76]).
11 Thus, the Court found that Reliance Infrastructure had adequate knowledge of the necessary facts to pursue its forgery allegation when it could find no proof of the Guarantee Letter in its company records or, alternatively, when it sent an email to the Tribunal on 4 February 2022, showing that it subjectively believed that the Guarantee Letter had been forged (at [68], [76] and [80]). By failing to take steps to pursue its forgery allegation before the Tribunal without good reason, it waived its right to raise the same challenge against the Award before the Court (at [81] and [82]).
12 The Court also found that Reliance Infrastructure could have raised Mr Agrawal’s lack of authority to make an arbitration agreement on its behalf as an objection to the Tribunal’s jurisdiction during the SIAC arbitration (at [83]). Therefore, its failure to do so constituted a waiver of its right to challenge the Award on that ground (at [95]).
13 It was not enough for Reliance Infrastructure to challenge Mr Agrawal’s authority to make the Guarantee Letter during the arbitration, since an agreement to arbitrate is a separate and distinct agreement from the main contract which contains it (at [85], [86] and [92]). Hence, challenging Mr Agrawal’s authority to sign the Guarantee Letter was not the same as challenging his authority to make the arbitration agreement therein (at [87] and [94]).
14 Thus, the Court found that Reliance Infrastructure had waived its rights to challenge the Award on the grounds that the Guarantee Letter was forged and that Mr Agrawal lacked authority to make an arbitration agreement on its behalf (at [141]).
15 In any event, the Court held that Reliance Infrastructure’s allegations were without merit and it would have dismissed them even if they had not been waived (at [96] and [142]). The evidence showed that Mr Agrawal had signed the Guarantee Letter (at [97], [107] and [123]) and that Reliance Infrastructure had ‘held him out’ as having the apparent authority to make arbitration agreements with Shanghai Electric on its behalf (at [134], [137] and [140]).
16 For these reasons, the Court dismissed Reliance Infrastructure’s application to set aside the Award (at [143]).
This summary is provided to assist in the understanding of the Court’s judgment. It is not intended to be a substitute for the reasons of the Court. All numbers in bold font and square brackets refer to the corresponding paragraph numbers in the Court’s judgment.
Back to Top

This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

Version No 2: 13 Feb 2024 (15:05 hrs)