This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.
Please delete where applicable –
1. This judgment DOES NOT need redaction.
2. Redaction HAS NOT been done.
DISTRICT JUDGE SAMUEL WEE CHOONG SIAN
1 OCTOBER 2025
In the state courts of the republic of singapore
[2025] SGDC 253
District Court Originating Claim No 248 of 2022
Between
(1)
Soh Chuan Swee
(2)
Tok Beng Kee
… Claimants
And
L.S. Construction Pte Ltd
… Defendant
judgment
Building And Construction Law — Construction torts — Negligence
Building And Construction Law — Construction torts — Torts affecting adjoining land
This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Soh Chuan Swee and another
v
L.S. Construction Pte Ltd
[2025] SGDC 253
District Court Originating Claim No 248 of 2022 District Judge Samuel Wee 6 May 2025, 3, 4 July 2025, 11 September 2025
1 October 2025 Judgment reserved.
District Judge Samuel Wee:
Introduction
1 The Defendant was constructing a residential development called “Affinity at Serangoon” comprising apartments and strata landed houses in Serangoon North Avenue 1 (“Construction Site”).
from the Construction Site and allege that the demolition works, concrete piling and I-beam extraction (“Vibration Causing Works”) performed at the Construction Site between November 2018 and April 2021 caused damage to their house (“Claimants’ House”).
2 After receiving complaints from the Claimants, the Defendant performed some minor repairs in January 2020 to patch up some cracks and address water seepage at the Claimants’ House (“Initial Repair Works”).
Foot Note 4
Claimants’ affidavit of evidence-in-chief (“AEIC”) of Soh Chuan Swee (“CMAEIC_Soh”)_[37]; Defendant’s AEIC of Tan Chia How (“DFAEIC_Tan”)_[12].
At the Claimants’ request, the Defendant later explored performing further repair works in 2021 (“Further Repair Works”),
Foot Note 5
SOC_[13]-[14].
but stopped doing so because it disputed the cause and extent of damage relied on by the Claimants.
Foot Note 6
DF_[12]-[17].
According to the Defendant, its offer to perform the Initial Repair Works or Further Repair Works was made on a goodwill basis, without admission of liability.
Foot Note 7
DFClosingSubs_[5]; DF_[12]-[14].
3 Dissatisfied, the Claimants commenced this action against the Defendant for performing the Vibration Causing Works and Initial Repair Works negligently.
Foot Note 8
DFClosingSubs_[2]; SOC_[6]-[8], [11].
The Claimants had originally relied on a claim for nuisance, but abandoned this after the affidavits of evidence-in-chief (“AEICs”) were filed.
Foot Note 9
1TRANS_PDF24:9-31. *[Day of Trial]TRANS_[PDF Page Number]:[Lines in Transcript].
Background facts
4 The Claimants’ House was built between 2017 and 2018, with the Certificate of Statutory Completion issued on 20 August 2018.
Foot Note 10
CMClosingSubs_[2]; CMAEIC_Soh_[5]-[6].
5 The Defendant was the main contractor at the Construction Site, which was across the road from the Claimants’ House, with a separating distance of around 12 metres.
Foot Note 11
CMAEIC_Soh_[7]-[8].
6 Before works commenced at the Construction Site,
Foot Note 12
CMAEIC_Soh_[9].
a pre-condition survey of the Claimants’ House was conducted (“Oct 2018 Pre-condition Survey”).
Foot Note 13
CMAEIC_Soh_[10]-[11].
The results of the Oct 2018 Pre-condition Survey are set out in a Pre-condition Photographic Survey Report dated 8 October 2018 (“Oct 2018 Survey Report”), which shows that the Claimants’ House was generally defect-free at the time, although there were various cracks observed in walls and tiles.
Foot Note 14
DFClosingSubs_[21]; CMAEIC_Soh_34-77.
7 The Vibration Causing Works commenced in November 2018.
(a) Demolition works were carried out from November 2018 to April 2019 to remove the existing buildings at the Construction Site (“Demolition Period”).
Foot Note 15
DF_[7]; Defendant’s AEIC of Lim Tse Wee (“DFAEIC_Lim”)_[8].
(b) Piling works were carried out from April 2019 to August 2019 (“Piling Period”).
Foot Note 16
DF_[7] ; DFAEIC_Lim_[9].
(c) I-beam installation and extraction works were carried out from sometime in 2020 to April 2021 (“I-beam Period”).
Foot Note 17
DF_[7]; DFAEIC_Lim_[10].
8 The Claimants first noticed damage to the Claimants’ House in October 2019
– around two months after the Piling Period and before the I-beam Period began (ie. no Vibration Causing Works were being performed at the time).
(a) The damage related to cracks in the common party wall, glass blocks and floor tiles at the front porch of the Claimants’ House, which resulted in water seeping through the cracks when it rained.
Foot Note 19
CMAEIC_Soh_[30].
(b) From WhatsApp message records, it is apparent that the Defendant offered to perform the Initial Repair Works after the Claimants’ House was inspected by its staff Mr Jason Tee
Foot Note 20
CMAEIC_Soh_[30]-[33], 175-176; DFAEIC_Tan_[6].
and Mr Tan Chia How (“Mr Tan”).
Foot Note 21
CMAEIC_Soh_[34]-[37], 181-187.
Based on a letter dated 7 January 2020 sent by the Defendant to the Claimants, the offer to perform the Initial Repair Works was made on a “without prejudice and without admission of liability basis”.
(c) Prior to this, there were no complaints from the Claimants about damage arising from the Vibration Causing Works. While the Claimants pointed to dust that flew into the Claimants’ House during the Demolition Period and possible inadequacies in the barriers and netting installed by the Defendant at the Construction Site,
Foot Note 23
CMAEIC_Soh_[14]-[27]; 1TRANS_PDF32:27-32.
these complaints had nothing to do with the alleged damage caused by the Vibration Causing Works.
9 In March 2020, the First Claimant experienced vibrations (“Mar 2020 Vibrations”) in the Claimants’ House that allegedly caused some cracks in the granite floor.
(a) The alleged vibrations happened when the Defendant was extracting I-beams from the ground.
Foot Note 25
CMAEIC_Soh_184, messages at 13.27 on 5 March 2020.
(b) The First Claimant testified that the vibrations were strong enough that one of the lighting fixtures in the Claimants’ House started swaying vigorously on 5, 6 and 16 March 2020.
Foot Note 26
CMAEIC_Soh_[38]; 1TRANS_PDF30:21-PDF31:6.
While he submitted video footage to support his view, the video footage was not helpful as it simply showed some swaying of the lighting fixture,
Foot Note 27
CMAEIC_Soh_208-211.
which could have happened for a variety of reasons given the dangling design of the lighting fixture.
(c) Further, based on the Monitoring Reports produced by the Defendant, the vibrations at the perimeter of the Construction Site were lower than 2mm/s and within the limit of 5mm/s.
Foot Note 29
DFAEIC_Lim_[11]-[12], 5226-5227; Defendant’s AEIC of Derek Richard Mills dated 23 July 2024 (“DFAEIC_Mills1”)_PDF19([5.26]).
10 Due to the Covid-19 Circuit Breaker, the Defendant did not inspect the alleged damage caused by the Mar 2020 Vibrations until September 2020.
Foot Note 30
CMAEIC_Soh_[42]-[43].
After some discussions, the Defendant’s Mr Tan indicated that the Defendant was prepared to perform the Further Repair Works to address the alleged damage caused by the Mar 2020 Vibrations, but suggested that they be done after the extraction of all I-beams.
Foot Note 31
CMAEIC_Soh_[44]-[49], 185.
11 In March 2021, the First Claimant again experienced vibrations in the Claimants’ House.
Foot Note 32
DFClosingSubs_[11(c)]; CMAEIC_Soh_[50], 186.
(a) The alleged vibrations happened on 29 March 2021, while the Defendant was extracting some I-beams from the ground.
Foot Note 33
CMAEIC_Soh_186, messages between 15.37 and 17.18 on 29 March 2021.
(b) Based on the Monitoring Reports produced by the Defendant, the vibrations at the perimeter of the Construction Site were lower than 2mm/s and within the limit of 5mm/s.
Foot Note 34
DFAEIC_Lim_[11]-[12], 5325-5326.
12 In April 2021, the Defendant’s Mr Tan provided the First Claimant with a draft method statement (“Apr 2021 Draft MS”).
The Apr 2021 Draft MS set out the scope of the proposed Further Repair Works, which included repairs to cracks, painting, and the application of waterproofing chemicals, but excluded works for cracks in the floor tiles. The First Claimant was not satisfied with and did not agree to the Apr 2021 Draft MS.
Foot Note 36
CMClosingSubs_[136].
13 Thereafter, the parties were unable to agree on the scope of the Further Repair Works, and the Defendant decided not to provide further assistance to the Claimants.
Foot Note 37
CMAEIC_Soh_[57]; DF_[12]-[17].
According to the Defendant, it was initially prepared to perform the Further Repair Works on a goodwill basis, but withdrew this offer because the Claimants were relying on damage that could not have been caused by the Vibration Causing Works.
Foot Note 38
DF_[12]-[17]; DFAEIC_Tan_[13]-[15].
Issues
14 There are two main issues:
(a) whether the Defendant performed the Vibration Causing Works negligently; and
(b) whether the Defendant performed the Initial Repair Works negligently.
Vibration Causing Works
Parties’ positions
15 The Claimants take the position that they have proven the following requisite elements of negligence: (a) the Defendant owed a duty of care in respect of the performance of the Vibration Causing Works;
(c) the Vibration Causing Works caused damage to the Claimants’ House;
Foot Note 41
CMClosingSubs_[80]-[83], [88]-[89].
and (d) the damage was not too remote.
Foot Note 42
CMClosingSubs_[86].
16 The Defendant contends that the Claimants have not established all four requisite elements.
Foot Note 43
DFClosingSubs_[8].
Its defence is two-fold:
Foot Note 44
DFClosingSubs_[5].
(a) The main defence is that the Claimants have not proven the elements of breach of duty and causation.
Foot Note 45
DFClosingSubs_[9].
This defence seeks to dispose of the Claimants’ claim without addressing the issue of whether a duty of care even exists.
(b) The alternative defence is that it did not owe a duty of care in respect of the performance of the Vibration Causing Works, which were undertaken by independent subcontractors.
Foot Note 46
DFClosingSubs_[58]-[65].
Breach of duty
17 The Claimants have failed to prove that the Defendant breached its duty of care by failing to act in accordance with industry practices when performing the Vibration Causing Works.
18 Vibrations are expected from the Vibration Causing Works.
Foot Note 48
DFClosingSubs_[32].
Indeed, the First Claimant, who has been a general contractor in the construction industry for more than 50 years,
Foot Note 49
CMAEIC_Soh_[4].
accepted during cross-examination that it is not unusual for such vibrations to be caused and clarified that his grievance lay with the alleged excessiveness of the vibrations.
Foot Note 50
1TRANS_PDF30:12-PDF31:4.
19 However, the evidence shows that the vibration levels caused by the Vibration Causing Works were within acceptable levels.
(a) The Defendant has produced Monitoring Reports showing that the vibrations caused by the Vibration Causing Works did not exceed 2mm/s and were well within the required limit of 5mm/s.
Foot Note 51
DFAEIC_Lim_[11]-[12], 412-10969.
(b) The Monitoring Reports were based on two vibration monitors (“VMs”): (i) VM-01 that was positioned at the north perimeter of the Construction Site; and (ii) VM-02 that was positioned at the south perimeter of the Construction Site, and just across the road from the Claimants’ House.
Foot Note 52
DFAEIC_Lim_5233.
The VMs provided continuous monitoring of vibrations
Foot Note 53
DFAEIC_Lim_5139.
and show that it is unlikely that the Claimants’ House experienced vibrations from the Vibration Causing Works in excess of 2mm/s, particularly since the Claimants’ House was located outside the perimeter of the Construction Site.
Foot Note 54
DFReplySubs_[14]; 2TRANS_PDF66:1-30.
(c) While the Claimants contend that the Monitoring Reports are not accurate,
they have produced no evidence to substantiate their assertion.
Foot Note 56
DFClosingSubs_[43]; DFReplySubs_[10]-[11].
In this regard, it is pertinent that the Claimants were informed by the Building and Construction Authority that it is “not in possession of any evidence that could suggest that the instrumentation data could have been adjusted or is in fact from [some] other work site”.
(d) The First Claimant’s oral testimony that he felt strong vibrations on 5, 6 and 16 March 2020 and 29 March 2021 (see [9] and [11] above) was of no assistance, as the Monitoring Reports show that the vibration levels were lower than 2mm/s on those days.
In this regard, the video footage the Claimants relied on does not support their assertion that the lighting fixture in the Claimants’ House was swaying vigorously on 5, 6 and 16 March 2020 (see [9(b)] above).
20 The following arguments raised by the Claimants are also untenable:
(a) The Claimants argue that the existence of damage to the Claimants’ House means that the Vibration Causing Works were not performed in accordance with industry practice.
Foot Note 59
CMClosingSubs_[60]-[63], [164].
However, the Claimants have not produced evidence of the alleged industry practice. Further, this argument seems to conflate the element of breach of duty with the element of causation (see [24(c)] below).
(b) The Claimants contend that the Defendant did not act in accordance with industry practice by failing to conduct a second pre-condition survey after the Oct 2018 Pre-condition Survey.
Foot Note 60
CMClosingSubs_[64], [166].
Again, the Claimants have not produced evidence of such an industry practice.
Foot Note 61
DFReplySubs_[15].
I also agree with the Defendant that the Claimants are not entitled to rely on this contention, which is not part of their pleaded case.
Foot Note 62
DFReplySubs_[15].
(c) The Claimants assert that the Defendant did not act in accordance with industry practice by failing to ensure an adequate number of vibration sensors.
Foot Note 63
CMClosingSubs_[65], [167].
Once more, the Claimants have not produced evidence of such an industry practice, and are not entitled to rely on this unpleaded point.
Foot Note 64
DFReplySubs_[16].
21 Moreover, contrary to the Claimants’ assertion, the Defendant did not admit liability for performing the Vibration Causing Works negligently.
Foot Note 65
CMClosingSubs_[128]-[157]; CMReplySubs-[52].
I agree with the Defendant that there was no unequivocal admission of liability (Qingdao Bohai Construction Group Co, Ltd and others v Goh Teck Beng and another [2016] 4 SLR 977 at [87]), given that:
Foot Note 66
DFClosingSubs_[51]-[57].
(a) the First Claimant confirmed during cross-examination that there is no “black and white” documentation of the Defendant admitting to fault;
Foot Note 67
1TRANS_PDF77:2-17, PDF83:14-21, PDF85:10-24.
and (b) the documents show that the Defendant’s offer to perform the Initial Repair Works or Further Repair Works was on a goodwill basis, without admission of liability.
Foot Note 68
CMAEIC_Soh_189, 399-400.
Causation
22 The Claimants have failed to prove that the Vibration Causing Works caused the alleged damage to the Claimants’ House.
23 The Claimants’ evidence on causation is premised on the testimony of the First Claimant and their expert Mr Loggie Bruce Jamieson (“Mr Loggie”).
Foot Note 69
CMClosingSubs_[88]-[89].
However, their evidence does not assist the Claimants’ position.
(a) The First Claimant’s evidence was speculative and lacked objectivity.
Foot Note 70
DFClosingSubs_[17]-[22].
Based on his experience in the construction industry,
Foot Note 71
CMAEIC_Soh_[4].
the First Claimant was aware that “shrinkage cracks from expansion and contraction from a new construction and/or weather conditions are normal”,
Foot Note 72
CMAEIC_Soh_[31].
which is why there is typically a defects liability period and accompanying warranties for new construction projects to deal with such issues.
Foot Note 73
1TRANS_PDF26:9-24, PDF28:7-13.
Despite this, the First Claimant was quick to assume that the alleged damage was caused by the Vibration Causing Works rather than by inherent defects in the recent construction of the Claimants’ House, and did not conduct any investigations to substantiate his view objectively.
Foot Note 74
1TRANS_PDF34:1-PDF35:8.
(b) Mr Loggie’s evidence was also unhelpful.
(i) Mr Loggie was tasked to “investigate and report on the condition of the [Claimants’ House]”
Foot Note 75
Claimants’ AEIC of Loggie Bruce Jamieson (“CMAEIC_Loggie”)_PDF3([8]).
and “advise on the appropriate corrective action”
Foot Note 76
CMAEIC_Loggie_PDF3([9]).
(that encompassed identifying and detailing the damage observed and quantifying the rectification costs)
Mr Loggie also confirmed at trial that he did not review the Monitoring Reports and suggested that the Claimants seek assistance from someone with expertise on the effects of vibrations and ground movements.
(iii) Consequently, Mr Loggie was not able to assist the Court in explaining how the alleged damage could have arisen when the vibrations detected were lower than 2mm/s,
Foot Note 82
2TRANS_PDF18:1-7.
and I do not find his evidence on the issue of causation to be of assistance.
24 In contrast, the Defendant’s evidence and arguments show that it is likely that the damage was not caused by the Vibration Causing Works.
Foot Note 83
DFClosingSubs_[24]-[41].
(a) The Defendant’s expert, Mr Derek Richard Mills (“Mr Mills”) reviewed the Monitoring Reports and testified that the Claimants’ House “was not exposed to a magnitude of vibrations that would ordinarily affect the building or induce damage”
Foot Note 84
DFAEIC_Mills1_PDF19([5.27]).
and that the alleged damage to the Claimants’ House was not caused by the Vibration Causing Works.
(i) Mr Mills described the damage in question as cosmetic (rather than structural) in nature,
Foot Note 86
DFAEIC_Mills1_PDF22([5.46]-[5.48]).
pointed out that cosmetic damage is caused by vibrations between 8mm/s and 20mm/s,
Foot Note 87
DFAEIC_Mills1_PDF22([5.49]).
and concluded that the vibrations of less than 2mm/s detected for the Vibration Causing Works mean that they did not cause the damage to the Claimants’ House.
(ii) I accept Mr Mills’ view for two main reasons. First, I am satisfied that he has the requisite expertise to provide expert evidence on the effect of the vibrations on the Claimants’ House.
Foot Note 89
DFClosingSubs_[26]-[28]; DFReplySubs_[28]-[29]; DFAEIC_Mills1_PDF9([1.2]), PDF148-162; 3TRANS_PDF10:1-PDF17:8. Suffice to say that I disagree with the arguments raised by the Claimants at CMClosingSubs_[90], [171] and CMReplySubs_[69]-[86].
Second, his view is well reasoned and coherent – it was reached after he considered various technical papers
Foot Note 90
DFAEIC_Mills1_PDF11([3.6]-[3.9]).
and standards
Foot Note 91
DFAEIC_Mills1_PDF11([3.11]-[3.13]).
relating to ground vibrations from construction works, and also the ground settlement markers and tilt meter readings in the Monitoring Reports, which revealed that there were no significant ground movements around the Claimants’ House.
(b) There were no complaints from the owners of houses neighbouring the Claimants’ House regarding damage arising from the Vibration Causing Works.
Foot Note 93
DFAEIC_Lim_[20].
The absence of such damage suggests that the damage to the Claimants’ House may have arisen from some other cause, such as inherent defects in the Claimants’ House that had been recently constructed. In this regard, the Oct 2018 Pre-condition Survey shows that cracks had already manifested in the Claimants’ House in September 2018 (ie. one month after the Certificate of Statutory Completion was issued on 20 August 2018) (see [4] and [6] above).
Foot Note 94
1TRANS_PDF35:30-PDF38:21.
(c) To this end, I agree with the Defendant that the mere fact that the Claimants’ House may have exhibited damage which was not specified in the Oct 2018 Survey Report does not mean that the damage must have been caused by the Vibration Causing Works.
Foot Note 95
DFClosingSubs_[18]-[19]; CMReplySubs_[36]-[39].
Conclusion on the Vibration Causing Works
25 The Claimants have not proven that the Defendant breached its duty of care, or that the Vibration Causing Works caused the alleged damage to the Claimants’ House. Their claim that the Defendant performed the Vibration Causing Works negligently therefore fails, since they cannot establish at least two of the four requisite elements of negligence.
26 Consequently, it is not necessary for me to consider the Defendant’s alternative defence that it did not owe a duty of care in respect of the performance of the Vibration Causing Works, which were undertaken by independent subcontractors.
Initial Repair Works
27 The Claimants contend that the Defendant performed the Initial Repair Works negligently.
Foot Note 96
CMClosingSubs_[126].
28 The Defendant denies that it was negligent. It takes the position that it did not owe a duty of care because the Initial Repair Works were done on a goodwill basis
Foot Note 97
DFClosingSubs_[68].
and that the Claimants have in any event not proven a breach of duty.
Foot Note 98
DFClosingSubs_[69].
29 While the Defendant may have performed the Initial Repair Works on a goodwill basis, its choice to perform the works means that it owed a duty of care to the Claimants.
30 However, the Claimants have failed to prove that the Defendant breached its duty of care. As the Defendant points out, the Claimants have not specified the standard of care to be met for the Initial Repair Works or how the Defendant fell short of that standard.
Foot Note 99
DFClosingSubs_[69].
It is insufficient for the Claimants to merely opine that the Initial Repair Works were done badly as “all the patched-up areas were very uneven and ugly” and produce photographs that do not clearly demonstrate their position.
Foot Note 100
CMAEIC_Soh_[37(c)], 191-208.
31 The Claimants’ claim that the Defendant performed the Initial Repair Works negligently therefore fails.
Conclusion
32 I dismiss the Claimants’ claim. They have not proven that the Defendant performed the Vibration Causing Works or Initial Repair Works negligently.
33 The parties are to file and exchange written submissions on the issue of costs (limited to 7 pages) within 14 days from the date of this judgment.
Samuel Wee District Judge
Anil Murkoth Changaroth (ChangAroth Chambers LLC) for the Claimants;
Tan Yiting Gina, Tan Yun Hao, Alson and Brenda Kylie Tay Kai Lin (Terra Law LLC) for the Defendant.
This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.