This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

IN THE SINGAPORE INTERNATIONAL COMMERCIAL COURT

OF
THE republic of singapore
[2024] SGHC(I) 8
Originating Application No 1 of 2023
Between
Reliance Infrastructure Limited
Claimant
And
Shanghai Electric Group Co Ltd
Defendant
JUDGMENT
[Civil Procedure — Costs — Principles — Principles on assessment of costs for proceedings in Singapore International Commercial Court — Reasonableness and proportionality of costs — Disparity between quantum of costs estimates of parties]
[Civil Procedure — Costs — Principles — Principles on assessment of costs for proceedings in Singapore International Commercial Court — Reasonableness and proportionality of costs — Factors relevant to assessment of reasonableness and proportionality of costs awarded pursuant to Order 22 rule 3(2) of Singapore International Commercial Court Rules 2021]

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Reliance Infrastructure Ltd

v

Shanghai Electric Group Co Ltd
[2024] SGHC(I) 8
Singapore International Commercial Court — Originating Application No 1 of 2023
Philip Jeyaretnam J, Sir Vivian Ramsey IJ and Anselmo Reyes IJ
6 March 2024
16 April 2024   Judgment reserved.
Philip Jeyaretnam J (delivering the judgment of the court):
Introduction
1 In Reliance Infrastructure Ltd v Shanghai Electric Group Co Ltd [2024] SGHC(I) 3 (“Reliance Infrastructure (Merits)”) at [143], we dismissed the application brought by the claimant, Reliance Infrastructure Limited (“Reliance Infrastructure”), in SIC/OA 1/2023 (“OA 1”), to set aside an arbitral award which had awarded damages to the defendant, Shanghai Electric Group Co Ltd (“Shanghai Electric”). Accordingly, we awarded costs to Shanghai Electric (see Reliance Infrastructure (Merits) at [143]).
2 However, Reliance Infrastructure and Shanghai Electric (“the Parties”) were unable to agree on the amount of costs. Having considered Parties’ submissions, we award costs to Shanghai Electric in the amount of US$734,660.02, for the reasons which follow.
Factual background
3 On 12 March 2023, Reliance Infrastructure applied in OA 1 to set aside an arbitral award rendered by a tribunal on 8 December 2022, following a Singapore-seated arbitration between Parties (“the Award”). The Award held that Reliance Infrastructure was liable to Shanghai Electric under the guarantee obligations found within a purported guarantee letter said to have been executed between the Parties on 26 June 2008 (“the Guarantee Letter”) (see the Award at [6]–[7], [9(a)] and [9(d)]) (see also Reliance Infrastructure (Merits) at [23] and [32]).
4 The Award ordered Reliance Infrastructure to pay over US$146.309 million to Shanghai Electric (not including the post-award interest and any reimbursement for the final costs of the arbitration that may be applicable) (see the Award at [9(d)], [9(f)], [9(i)]–[9(l)] and [1208(c)]–[1208(g)]).
5 In their OA 1, Reliance Infrastructure alleged that the signature of its former officer on the Guarantee Letter had been a forgery, and in the alternative, that its former officer had no authority to execute the arbitration agreement that was contained within the Guarantee Letter (see Reliance Infrastructure (Merits) at [38]–[39], [59] and [62]).
6 We dismissed OA 1 on 31 January 2024, following a 2-day hearing from 11–12 January 2024 (see Reliance Infrastructure (Merits) at [34]). We heard the evidence of three factual witnesses (two from Reliance Infrastructure and one from Shanghai Electric) and two handwriting experts (one from each party) (see Reliance Infrastructure (Merits) at [34(a)]–[34(e)]).
7 We awarded costs to Shanghai Electric and ordered that if Parties were unable to agree on the amount of costs within 14 days of our judgment, they were to file written submissions on costs within 7 days thereafter (see Reliance Infrastructure (Merits) at [143]). The deadline for Parties to file their costs submissions would have elapsed on 21 February 2024.
8 On 21 February 2024, Reliance Infrastructure wrote into court seeking an extension of time for Parties to agree on the amount of costs to 28 February 2024, and in the event of their being unable to agree, to file their submissions on costs by 6 March 2024. Shanghai Electric had no objections to that request.
9 Accordingly, on 22 February 2024, we allowed the extensions of time requested in Reliance Infrastructure’s letter (see O 1 r 5(10) of the Singapore International Commercial Court Rules 2021 (“SICC Rules 2021”)). Thus, Parties filed their written submissions on costs on 6 March 2024.
Costs are awarded to Shanghai Electric in the amount of US$734,660.02
Summary of Parties’ positions on costs
10 Reliance Infrastructure’s position is that Shanghai Electric should be awarded no more than S$225,000 in costs, this being the sum that the former had paid into court as security for the latter’s costs in OA 1 (see this court’s order dated 11 August 2023 on SIC/SUM 19/2023).
11 In contrast, Shanghai Electric argues that it is entitled to be reimbursed for all the costs and disbursements it incurred in defending OA 1, which amount to US$911,244.87 in total. Shanghai Electric also reserves their right to claim additional costs beyond that figure for reviewing Reliance Infrastructure’s submissions on costs and preparing any reply submissions thereon.
12 Having reviewed the costs incurred by Shanghai Electric, the details of which were particularised in their costs schedule, we find that they are generally reasonable and proportionate (see O 22 r 3(1), SICC Rules 2021), save that the costs claimed for Singapore counsel’s fees in the amount of US$726,584.85 should be moderated down to US$550,000. The other costs claimed by Shanghai Electric for foreign law counsel, expert’s fees, and all other disbursements, amounting to US$184,660.02 in total, are granted in full. Accordingly, we award, in total, costs to Shanghai Electric coming to US$734,660.02.
Breakdown of Parties’ respective costs estimates
13 It is helpful to start with the information provided by Parties concerning their own costs. Those costs, once broken down into four categories (Singapore counsel, foreign counsel, experts, and all other disbursements) show that the principal disparity between Parties’ costs estimates lies in the fees charged for Singapore counsel:
Categories
Shanghai Electric
Reliance Infrastructure
Singapore Counsel (Professional Fees)
US$726,584.85
(for six practitioners, 1,431.49 hours spent in total)
US$270,000
(for four practitioners, work described but no estimate of hours given)
Foreign Counsel (Professional Fees)
US$114,348.40 (Trilegal for Indian law; Fountain Court Chambers for English law)
US$146,693.79 (Mr Harish Salve KC for both Indian and English law)
Experts’ Fees
US$15,631.90
US$18,092.85
All Other Disbursements
US$54,679.72
US$51,482.34
The costs claimed by Shanghai Electric in respect of foreign counsel’s fees and all of their disbursements are granted in full
14 We hold that the costs incurred by Shanghai Electric in respect of its foreign counsel, expert, and other disbursements were reasonably incurred and grant them in full. They generally match Reliance Infrastructure’s estimates of their own costs for the same categories. This is an indication of reasonableness and proportionality. Comparing the costs of the Parties is a relevant and useful exercise: see, for example, Qilin World Capital Ltd v CPIT Investments Ltd and another appeal [2019] 1 SLR 1 at [32], where our Court of Appeal granted the costs claimed by Qilin with respect to the appeal in Civil Appeal No 145 of 2017 and assessed them to be reasonable, in the light of CPIT’s similar estimate in its own costs schedule.
The costs claimed by Shanghai Electric in respect of Singapore counsel’s fees are granted in part
15 We turn now to the costs incurred for Singapore counsel. There are two factors that we have considered, the first of which is, again, the comparison with Reliance Infrastructure’s own costs incurred in this category (see at [13] above), and the second is Shanghai Electric’s prior estimate of its own costs in respect of its application for security for costs of OA 1 in their SIC/SUM 19/2023 (“the SFC Application”).
16 Reliance Infrastructure has provided a figure of US$270,000 for its costs for Singapore counsel. It has relied on the disparity in costs incurred to argue that Shanghai Electric’s costs are not reasonable and proportionate within the meaning of O 22 r 3(1) of the SICC Rules 2021.
17 The question is whether the large disparity in costs for Singapore counsel between Parties – with costs for Shanghai Electric being more than 2.69 times that of Reliance Infrastructure for this category – justifies a reduction of the costs claimed by the former for Singapore counsel professional fees or if those costs should be granted in full as having been reasonably incurred.
18 The starting point is that Shanghai Electric, as the prevailing party in Reliance Infrastructure (Merits) at [96] and [141]–[143], is generally entitled to the costs that it subjectively incurred in defending OA 1: see O 22 r 3(1) of the SICC Rules 2021 and Senda International Capital Ltd v Kiri Industries Ltd [2023] 1 SLR 96 (“Senda v Kiri (Assessment of Costs)”) at [52]. However, this is tempered by the objective yardstick requiring the court to assess the reasonableness of both the manner in which costs were incurred and the quantum of those costs (see Senda v Kiri (Assessment of Costs) at [52]–[54]). For completeness, we observe that while Senda v Kiri (Assessment of Costs) was decided on the basis of the old O 110 r 46 of the Rules of Court (2014 Rev Ed), the principles articulated by the Court of Appeal in that case remain applicable to the assessment of costs in the Singapore International Commercial Court (“the SICC”) under the new O 22 of the SICC Rules 2021, having regard, in particular, to the wording of O 22 r 3(1), which provides that the prevailing party is “entitled to costs and the quantum of any costs award will generally reflect the costs incurred by the party entitled to costs, subject to the principles of proportionality and reasonableness” (see also Senda v Kiri (Assessment of Costs) at [56]–[57], which held to the same effect).
19 Considering the estimated hours provided by Shanghai Electric and the hourly rates of their practitioners in their costs schedule, they have given sufficient particulars of their costs for Singapore counsel for this court to assess their reasonableness (see Senda v Kiri (Assessment of Costs) at [73]). The figures provided are reasonable and the evidential burden then shifts onto Reliance Infrastructure to prove the unreasonableness of the costs claimed (see Senda v Kiri (Assessment of Costs) at [75]), notwithstanding that the legal burden remains on Shanghai Electric to prove the reasonableness thereof (see Senda v Kiri (Assessment of Costs) at [78]).
20 The extent of the disparity in quantum between the professional fees of Parties’ Singapore counsel does support the conclusion that the quantum of the costs claimed by Shanghai Electric therefor is unreasonable, even if the costs themselves (in terms of time and labour expended or hourly rates charged) were reasonably incurred. In assessing the objective reasonableness of the quantum, the court should consider “the nature and extent of the differences in the respective positions on costs taken by the parties” (see Senda v Kiri (Assessment of Costs) at [70]); “[h]ence, the best evidence that the unsuccessful party can adduce to discharge its evidential burden [of proving the objective unreasonableness of the costs claimed] will often be information as to the costs that it had correspondingly incurred for the matter, which might well be a sound proxy by which the trial court can determine what the appropriate level of costs in the particular case is” (see Senda v Kiri (Assessment of Costs) at [75]) (see also O 22 r 3(2)(j), SICC Rules 2021).
21 The large difference in costs for Singapore counsel between Parties is difficult to justify objectively given that the Parties here engaged with the same issues of fact and law and would have performed similar work in this proceeding (eg, reviewing and presenting the evidence of factual witnesses, reviewing the forensic reports of expert witnesses, etc). Moreover, the burden of proof was on Reliance Infrastructure to prove the grounds for its setting-aside application (ie, to prove forgery and/or absence of authority) and not on Shanghai Electric to disprove. Although Reliance Infrastructure has not provided a detailed breakdown of their professional fees with the hourly rates of their practitioners and the number of hours worked, that by itself does not render the quantum of the costs they actually incurred for Singapore counsel – US$270,000 – irrelevant in the ‘reasonableness’ assessment. The extent of the disparity supports the conclusion that the quantum claimed by Shanghai Electric in respect of Singapore counsel’s fees is objectively unreasonable for the purposes of O 22 r 3(1) of the SICC Rules 2021.
22 However, that does not mean that Shanghai Electric should be limited to claiming the quantum of the Singapore counsel’s fees incurred by Reliance Infrastructure in this case. There is no rule of law that one party’s costs are an upper limit on the costs claimable by the other party. The test remains what is reasonable. In any litigation, even if the work to be undertaken is broadly similar on both sides, there will naturally be variance. So long as the subjectively incurred legal fees fall within the spectrum of ‘reasonable’ costs, a successful party should be entitled to reimbursement. This follows from the principle in Senda v Kiri (Assessment of Costs) at [52] that the purpose behind the objective yardstick is to ensure that parties “pursue their proceedings in a reasonable and sensible manner”. There is logically no one exclusively reasonable and sensible manner of prosecuting the same claim even under the same circumstances. Case in point, Reliance Infrastructure hired four Singapore practitioners while Shanghai Electric hired six, which likely contributed to some extent to the difference in costs incurred. The decision of Shanghai Electric to engage a team of six Singapore practitioners was not an unreasonable or insensible manner of pursuing its claim just because Reliance Infrastructure chose to engage a team of four instead.
23 We would also take into account the fact that Shanghai Electric had estimated its own costs at S$250,000 in the SFC Application. That application was filed on 15 June 2023 and Shanghai Electric’s legal representative had estimated the total costs they would incur in defending OA 1 at S$250,000. Reliance Infrastructure now cites the great disparity between the initial estimate of S$250,000 in June 2023 and the costs Shanghai Electric is now claiming of US$911,244.87 to argue that Shanghai Electric’s current estimate cannot be reasonable and proportionate.
24 We agree that prior estimates given by a party of its own costs are relevant and should be considered. However, it is important to note that the sum of S$250,000 was only an estimate of the minimum amount Shanghai Electric might incur in the event of OA 1 proceeding to a full hearing on the merits. It was not an estimate of all costs that would be incurred by Shanghai Electric in that event. The supporting witness statement of Mr Tan Yi Fan thus stated at para 37 that “[t]he Defendant [Shanghai Electric] is therefore of the view that S$250,000 is a reasonable indication of the minimum amount of costs it would incur in defending OA 1 [emphasis added]”. Likewise, Shanghai Electric’s written submissions in the SFC Application similarly stated at para 55 that “the sum of S$250,000 is a very conservative estimate of the minimum costs that the Defendant [Shanghai Electric] would incur in OA 1. This quantum is entirely reasonable and not excessive”.
25 We accept that Shanghai Electric’s SFC Application was not intended to indemnify them fully for all costs they would incur in this proceeding. This was a reasonable position for Shanghai Electric to take at that stage, since asking for a higher sum to fully indemnify all of Shanghai Electric’s expected or reasonably anticipated costs would heighten the prospect of Reliance Infrastructure successfully arguing that the sum sought was unreasonable, excessive, oppressive and/or would otherwise stifle its application in OA 1. For these reasons, we would agree that the prior costs estimate of S$250,000 was given on a conservative basis. Nonetheless, there is a great disparity between it and what is now claimed, which is over 4.88 times their earlier estimate. This supports our moderating the quantum now claimed by Shanghai Electric for the component of its Singapore counsel’s costs.
26 We thus award to Shanghai Electric costs of US$550,000 for Singapore counsel, which represents a reduction from the amount they claimed therefor (US$726,584.85). This award is slightly more than twice the estimate given by Reliance Infrastructure for its own costs for the same – that is, US$270,000. Nonetheless, the quantum of US$550,000 for Singapore counsel is, in our view, reasonable and proportionate within the meaning of O 22 r 3(1), bearing in mind the following (see factors in O 22 rr 3(2)(a), 3(2)(b), 3(2)(c), 3(2)(e)(ii), 3(2)(f) and 3(2)(g)):
(a) the quantum of the amount at stake, viz, an arbitral award which had awarded more than US$146 million to Shanghai Electric (not including post-award interest thereon and any reimbursements for the final costs of the arbitration) (see at [4] above);
(b) the importance to Shanghai Electric of fully responding to and rebutting the very serious allegation of forgery (see at [5] above), and thus obtaining the vindication that it did;
(c) the voluminous factual record which had to be examined (ie, a Case Management Bundle spanning 14 volumes and over 7,000 pages);
(d) the relative legal complexity of the issues raised (here, Reliance Infrastructure tendered a bundle of 72 legal authorities in total while Shanghai Electric tendered 55 in total in its main and supplementary bundles);
(e) the extent of the time and effort expended by Shanghai Electric’s Singapore practitioners here (1,431.49 hours expended by six practitioners, with 83.83 hours on the low end and 532.33 hours on the high end), the quantity of which is not unreasonable given the complexity and volume of the legal authorities, facts, and evidence engaged here (see at [(c)]–[(d)] above); and
(f) the proceedings here lasted for nearly a year from March 2023 to January 2024 (see at [3] and [6] above), albeit that there were only two Case Management Conferences and a 2-day hearing on the merits (see at [6] above), and featured five interlocutory applications in the interregnum, notwithstanding that three of them were granted by consent.
27 Awarding Shanghai Electric US$550,000 in costs for its Singapore counsel’s fees would strike the proper balance between the principle of reinstating the successful party into the position it was legitimately entitled to be in all along by reimbursing them for the costs they subjectively incurred to obtain what it was always entitled to obtain (see Senda v Kiri (Assessment of Costs) at [52]) against the yardstick of objective reasonableness which tempers that subjective element by requiring costs to have been both reasonably incurred and reasonable in their quantum (see Senda v Kiri (Assessment of Costs) at [54]).
28 Finally, there is Reliance Infrastructure’s argument that the quantum of the costs claimed by Shanghai Electric here are significantly higher than costs awards in other SICC cases also involving setting-aside applications heard over two days or less, including the less than S$180,000 awarded in both DBX and another v DBZ [2024] SGHC(I) 5 (“DBX (Costs)”) at [18] and Asiana Airlines, Inc v Gate Gourmet Korea Co, Ltd [2022] 4 SLR 158 at [128], [130] and [132].
29 We certainly accept that prior SICC costs awards in cases with “common features” with the present case should be taken into consideration in assessing the ‘reasonableness’ of costs at the objective stage. To the extent that the case at hand shares “common features” with other SICC cases, the costs awarded in those other cases are a relevant factor to be considered (see Senda v Kiri (Assessment of Costs) at [79]). However, “[a]ny reliance placed on previous costs awards is not to determine the level of costs that should be awarded, but rather to provide a check as to whether the costs claimed by the successful party are reasonable or not [emphasis added]”: Senda v Kiri (Assessment of Costs) at [79].
30 The number of days spent on the hearing of these other setting-aside applications by the SICC is only one dimension in the comparison. Other dimensions, especially what was at stake in the litigation, both financially and non-financially, would have to be considered to assess what costs were reasonable to incur in the present case. The more that is at stake, the more parties will demand of counsel. For example, in the former case of DBX (Costs), the arbitral awards there had awarded less than HKD80 million (not including interest and costs) (see DBX and another v DBZ [2024] 3 SLR 141 at [1] and [23]), falling within the range of US$10–10.5 million (at prevailing exchange rates), far below the more than US$146 million award (not including post-award interest and any applicable reimbursements for the arbitration’s costs) at stake here. In addition, Reliance Infrastructure made a very serious accusation against Shanghai Electric, namely, that it had forged the signatures on the Guarantee Letter (see at [5] and [26(b)] above). Such an accusation strikes at the heart of a business party’s trustworthiness and, if proved, would have had a devastating impact on its international commercial reputation.
31 Given all these considerations, we find that the amount of US$550,000 in respect of Singapore counsel is a reasonable and proportionate quantum of costs under the circumstances (see O 22 rr 3(1) and 3(2), SICC Rules 2021).
Conclusion
32 For these reasons, we award costs in favour of Shanghai Electric in the following amounts:
(a) US$550,000 in respect of professional fees for Singapore counsel, a reduction from the US$726,584.85 claimed for this component; and
(b) US$184,660.02 in respect of foreign counsel, expert’s fees, and other disbursements, in the amounts claimed by Shanghai Electric therefor.
33 Consequently, we award to Shanghai Electric costs in the amount of US$734,660.02, a reduction from the costs claimed by them of US$911,244.87.
Philip Jeyaretnam
Judge of the High Court
Sir Vivian Ramsey
International Judge
Anselmo Reyes
International Judge
Vergis S Abraham SC, Asiyah binte Ahmad Arif, Ngo Wei Shing (Wu Weishen) and Liu Enning (Providence Law Asia LLC), Harish Salve KC (Blackstone Chambers) for the claimant;
Cavinder Bull SC, Foo Yuet Min, Tay Hong Zhi Gerald, Tan Yi Fan and Tan Pei Han (Drew & Napier LLC), Nicholas Emmet Graham Leslie (Fountain Court Chambers), Ketan Gaur and Aayush Mitruka (Trilegal) for the defendant.
SUPREME COURT OF SINGAPORE
16 April 2024
Case summary
Reliance Infrastructure Ltd v Shanghai Electric Group Co Ltd [2024] SGHC(I) 8
Singapore International Commercial Court Originating Application No 1 of 2023
--------------------------------------------------------------------------------------------------------------------------------------
Decision of Philip Jeyaretnam J, Sir Vivian Ramsey IJ and Anselmo Reyes IJ (delivered by Justice Jeyaretnam):
Outcome: SICC awarded costs to Shanghai Electric in the amount of US$734,660.02 as the successful party in defending the setting-aside application of Reliance Infrastructure
Background
1 The claimant (“Reliance Infrastructure”) sought to set aside an arbitral award which had awarded damages to the defendant (“Shanghai Electric”). The tribunal’s putative jurisdiction over the parties’ dispute was based on an arbitration clause found in a purported letter dated 26 June 2008 (“the Guarantee Letter”), in which Reliance Infrastructure had allegedly guaranteed the obligations of a related company owed to Shanghai Electric under a separate contract.
2 In its Originating Application, Reliance Infrastructure sought to set aside that award on the grounds that Shanghai Electric had forged the signature of its former officer on the Guarantee Letter and, in the alternative, that its former officer had no authority to execute agreements on its behalf.
3 The Court rejected Reliance Infrastructure’s setting-aside application and awarded costs in favour of Shanghai Electric. As Parties were unable to agree on the amount of costs, they filed written submissions on costs.
4 Shanghai Electric estimated the total amount of costs and disbursements it incurred to be US$911,244.87 and sought full reimbursement. Reliance Infrastructure argued that that sum was excessive and unreasonable. It argued that Shanghai Electric should be awarded no more than S$225,000 in costs.
The Court’s judgment
5 The Court held that Shanghai Electric had furnished sufficient information in its costs schedule to show that their costs were generally reasonable and proportionate (at [12] and [19]).
6 The Court then divided the Parties’ estimates of their own costs incurred into four categories – professional fees for local counsel; professional fees for foreign counsel; disbursements incurred for experts’ fees; and, lastly, all other disbursements (at [13]).
7 Having broken down the Parties’ costs estimates into these categories, the Court observed that Parties’ estimates were similar in quantum save only for their estimates for their respective local counsel’s professional fees (at [13]).
8 As the Parties’ estimates were similar in respect of foreign counsel’s fees and all disbursements incurred, the Court granted full reimbursement of Shanghai Electric’s costs for these categories, which amounted to US$184,660.02 in total (at [12], [14] and [32(b)]).
9 In respect of Parties’ local counsel’s fees, the Court noted that there was a significant disparity between the US$270,000 incurred by Reliance Infrastructure versus the sum of US$726,584.85 incurred by Shanghai Electric (at [13] and [20]). This large disparity in quantum justified a reduction in the costs claimed by Shanghai Electric for its local counsel as the sum was not objectively reasonable (at [17] and [21]).
10 Moreover, the Court recognised that Shanghai Electric had earlier estimated the costs it would incur in the proceedings at S$250,000 when applying for security for costs, whereas its present costs estimate was for a significantly higher sum, albeit that the figure of S$250,000 was only a conservative estimate of the minimum amount of costs they may incur (at [23] and [25]).
11 The Court calibrated the quantum claimed by Shanghai Electric for its local counsel’s fees from US$726,584.85 down to US$550,000 (at [12], [26], [31] and [32(a)]).
12 In arriving at the sum of US$550,000, the Court took into account such factors as the high amount of more than US$146 million at stake in the arbitral award which Reliance Infrastructure sought to set aside (at [26(a)]) as well as the severity of the allegation that Shanghai Electric had forged the signature of Reliance Infrastructure’s former officer on the Guarantee Letter (at [26(b)]). These factors increased the amount of costs that were reasonable for Shanghai Electric to have incurred to defend the setting-aside application (at [30]).
13 Thus, in the circumstances, the Court awarded a total of US$734,660.02 in costs to Shanghai Electric as the successful party in the setting-aside proceedings (at [12], [32] and [33]).
This summary is provided to assist in the understanding of the Court’s judgment. It is not intended to be a substitute for the reasons of the Court. All numbers in bold font and square brackets refer to the corresponding paragraph numbers in the Court’s judgment.
Back to Top

This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

Version No 1: 16 Apr 2024 (15:27 hrs)